Insurer declined roof replacement as pre-existing gradual deterioration and disputed other repairs and mould remediation after storm damage

FirmSuncorp Group
Decided2024-04-29
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$13,057
Non-financial loss$2,000
Amount claimed—
SourceAFCA PDF

Summary

After a storm, the insurer accepted internal damage but declined roof replacement as pre-existing deterioration. AFCA upheld the roof decline but ordered $13,057 for additional repairs, a mould remediation cash settlement (excluding the ensuite) and $2,000 non-financial loss.

Expert evidence showed the roof damage pre-dated the storm and was excluded as gradual deterioration, but the insurer had not properly dealt with other accepted items and handled the claim poorly.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay compensationpay non financial loss

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 998708 Financial firm AAI Limited Determination | Case number: 998708 Page 1 of 13 Case number: 998708 26 April 2024 1 Determination overview 1.1 Complaint The complainant lodged a claim under his home and contents insurance policy with the financial firm (insurer) following a storm that caused damage to the property. The insurer partially accepted the claim and has settled most of the internal damage and contents. However, the insurer declined damage to the roof on the basis that it was pre- existing and caused by gradual deterioration, which is not covered under the policy. A dispute has arisen about the insurer‟s decision and extent of liability under the policy. The complainant has replaced the roof and wants the insurer to reimburse him for this and settle other items including asbestos removal, mould remediation and floor repairs. As a gesture of goodwill, the insurer agreed to contribute 5% towards the cost of replacing the broken roof tiles caused by foot traffic and has paid $2,264.97. 1.2 Issues and key findings Is the insurer entitled to deny the roof replacement claim? Yes. The complainant has not established the damage to the roof is a claimable loss. The damage is also excluded under the policy as it was caused by gradual deterioration. Is complainant entitled to additional amounts for repairs? Yes. The insurer is to pay $13,057 for repairs to the window hoods, timber floors and removal of roof tarps/sandbags. The insurer is not required to pay for mould remediation to the ensuite but is required to pay for mould remediation to other parts of the property. Is the complainant entitled to non-financial loss compensation? Yes. The insurer‟s claims handling and delays have been un reasonable and have caused the complainant significant stress and inconvenience. The insurer is to pay $2,000 compensation. Why is the outcome fair? The outcome is fair because the terms, conditions and exclusions of the insurance policy have been correctly applied to determine the extent of coverage. The insurer has shown that the damage to the roof was not caused by the storm and is excluded from cover. It is fair for the insurer to decline that part of the claim, but pay for the additional items in paragraph 2.2. 1.3 Determination This determination is partially in favour of the complainant. The insurer is required to:  pay the complainant $13,057 for the additional repairs (as set out in section 2.2)  obtain an actionable quote from RS (or another qualified mould remediator) based on the scope of works dated 24 February 2023 and pay the complainant the amount quoted  pay the complainant $2,000 compensation for non-financial loss. Determination | Case number: 998708 Page 2 of 13 2 Reasons for determination 2.1 Is the insurer entitled to deny the roof replacement claim? Yes. The complainant has not established the damage to the roof is a claimable loss. The damage is also excluded under the policy as it was caused by gradual deterioration. Complainant bears the onus of establishing a claimable loss It is accepted insurance law that an insured has the initial onus to show, on the balance of probabilities (that it is more likely than not), that the loss or damage claimed falls within the terms of the policy. Where this is established, the onus then shifts to the insurer to prove that an exclusion applies if it seeks to deny or limit its liability for the loss. There is no dispute that the complainant received the policy documents including the Product Disclosure Statement and Certificate of Insurance. The policy covers „loss or damage to the building at the insured address caused by an insured event in the period of insurance‟ . The policy lists the specific insured events that are covered subject to limits, conditions and exclusions as set out in the policy. Page 42 states that the policy covers loss or damage caused by a storm. There is no dispute that a storm occurred in February 2022 and rain water entered the property. The insurer has partially accepted the claim for resultant water damage to the property and contents, but says the damage to the roof was not caused by the storm event. Insurer bears the onus of establishing an exclusion applies The insurer also says the damage is excluded from cover and relies on the following General Exclusions (see pages 30 to 33 of the policy): Home, unit or contents that are not in good condition any part of the home, unit or contents not being in good condition, such as, but not limited to: — the roof leaks when it rains; Wear, tear and gradual deterioration any part of the home, unit or contents that has wear, tear, rust, fading, rising damp, corrosion, rot, action of light, atmospheric or climatic conditions or gradual deterioration such as, but not limited to: … — weathering of roof tiles or roof ridge capping; Defects, faults, workmanship Determination | Case number: 998708 Page 3 of 13 — any loss or damage to the part of the home or contents with an inherent defect, faulty design, structural defect or faulty/poor workmanship, whether or not you knew or should reasonably have known about it. The insurer bears the onus of establishing that one or more of these exclusions applies. The question for determination is whether the damage to the roof was caused by storm (which is covered), or whether it was caused by an excluded cause. It is therefore necessary to identify the proximate cause (that is the operative, dominant or effective cause) of the roof damage. Expert evidence regarding the cause of roof damage The insurer relies on expert reports by two builders (CM and JL), a roof specialist (LC) and an engineer (CR). The expert evidence is summarised in section 3.2 below. CM attended the property for make safe and found multiple leaks to all ceilings and internal water damage. CM reported that the roof is in poor condition with many cracked, brittle and loose tiles and this is causing water leaks. The roof also does not have suitable flashing. CM reported at least 50% of the roof is damaged and recommended full replacement. The insurer engaged another builder, JL who inspected the roof from a ladder and reported multiple broken tiles which cause leaks. JL observed that the tarp was ripped but could not rectify this as the complainant was concerned about JL causing further damage to the roof. CM engaged a roof specialist, LC, who inspected the property and found approximately 80% of the roof is damaged. LC reported that the roof is in poor condition with many cracked tiles and it feels springy and saggy. The age of the cracks varies and there is evidence of pre- existing damage and repairs, but no storm damage to the roof. Approximately 10% of the tiles have been replaced, but many of these have also cracked. LC believes the cracked tiles are due to foot traffic combined with the springy and uneven roof frame. LC also reported that the window awnings on the western side have what appears to be maybe hail damage. Finally, the insurer appointed an engineer, CR, who reported that the roof tiles are 109 years old and have been porous for an extended period of time. CR identified multiple issues with the roof and timber frames and trims (including advanced wood rot) and noted the roof is unsafe to walk on. CR also reported that a major renovation was undertaken in 2005 and the roof is non-compliant. The engineer concluded that the roof issues predate the complainant‟s occupancy of the property in 2017 and sagging is due to pre-existing condition and how the rafters and beams have been installed. Complainant has not established a claimable loss I am satisfied the complainant has established a claimable loss under the policy for water damage to the property from the storm. However, I am not persuaded the damage to the roof was caused by the storm or any other insured event. I acknowledge t he complainant‟s submission that the damage all started in February 2022. However, the expert evidence clearly establishes that the roof was in a deteriorated state with broken tiles and other issues unrelated to the storm. It does not establish that the proximate cause of the roof damage was a single storm event. The complainant has not provided any expert evidence and I accept the findings in the insurer‟s expert reports. The engineer has provided a detailed report which explains the Determination | Case number: 998708 Page 4 of 13 nature, cause and timing of the roof damage. I am satisfied, on balance, that this damage pre-dates the claimed storm event in February 2022 and has been ongoing for a long time. The complainant therefore has not established that the roof damage is a claimable loss under the policy and the insurer is not required to pay the cost of replacing the roof. Insurer has established roof damage is excluded Given the complainant has not shown the damage to the roof is a claimable loss, there is no requirement to consider/discuss the policy exclusions and conditions relied on by the insurer. For the sake of completeness though, I am satisfied based on the expert evidence that the damage to the roof was caused by wear, tear and gradual deterioration. It follows that the insurer is entitled to rely on the policy exclusion on page 33 as an alternative basis to decline the roof damage. It is unnecessary to consider the other policy exclusions. Complainant’s arguments do not advance his position The complainant provided numerous submissions to AFCA. While this determination does not refer to them all, I have taken each submission into account in reaching my decision. The complainant wants the insurer to pay $56,000 for the roof replacement based on his invoice from BQ. He says that due to the fact 50% of the roof was deemed damaged on first inspection and 80% on second inspection this meets the threshold for full replacement. He says further that the first roof report states no maintenance is needed. CM reported that „at least 50% of the roof is damaged‟. LC reported that approximately 80% of the roof is damaged. These are approximations only and I am not persuaded that any significant additional damage occurred between the first inspection and second inspection. In any event, the roof damage was not caused by the storm or any other insured event. CM observed that the roof had damage during their initial inspection and this is confirmed in the causation report. I acknowledge the report dated 12 August 2022 states “No maintenance issues” but the remainder of the report indicates there were significant age-related issues. The insurer issued maintenance notices for the roof on 19 September 2022 and 29 November 2022. The insurer has acted in good faith and agreed to cover the resultant storm damage, which I consider a fair outcome. CM noted the make safe was challenging due to the deteriorated condition of the roof. While the complainant says the engineer‟s assessment was limited, I accept it would have been unsafe for the engineer to walk on the roof given its fragile state and the complainant has not provided any expert evidence to refute the e ngineer‟s findings. I accept the engineer‟s evidence that the roof was in poor condition prior to 2017 and 5% of the roof was affected by foot traffic. The engineer does not state that all the foot traffic damage was caused by the insurer‟s trades; however, the insurer has o ffered to pay 5% of the total roof replacement costs (based on the CM quotation). The BQ and CM quotes also include replacing battens and there is no evidence the insurer‟s trades damaged the battens. In the circumstances, I consider the insurer‟s payment of $2,264.97 to be fair and reasonable. The insurer is entitled to decline the remainder of the roof damage. Determination | Case number: 998708 Page 5 of 13 2.2 Is complainant entitled to additional amounts for repairs? Yes. The insurer is to pay $13,057 for repairs to the window hoods, timber floors and removal of roof tarps/sandbags. The insurer is not required to pay for mould remediation to the ensuite but is required to pay for mould remediation to other parts of the property. Parties disagree on certain repairs and settlement As noted above, the insurer partially accepted the claim for storm damage to the building and contents (excluding the roof). The insurer completed a make safe which included tarping the roof. However, further water ingress occurred due to strong winds and rain after the subject storm event. A further make safe was performed by the insurer on 8 June 2022. The damp condition inside the property resulted in mould growth and further damage. CM has provided several scopes of works (SOW) and quotes as additional damage has been identified over time. There has been ongoing debate between the parties as to the extent of repairs required, adequacy of some of the repairs undertaken by the insurer‟s trades and adequacy of SOW and cash settlements. The situation has been exacerbated by miscommunication between the parties and the insurer‟s trades, additional items being added over time and periodic lack of clarity on the status of the work. The relationship between the parties has broken down and the complainant is unwilling to allow the insurer to reattend the site. On 18 October 2023, the complainant submitted a list of unresolved items. Based on this list and subsequent communications, the remaining areas of dispute appear limited to four items. The disputed items and my determination on them is set out below. Window hoods The insurer has accepted liability for storm damage to three windows hoods and provided a quote for them to be replaced with fibre cement sheeting. The complainant does not object the replacement material and estimated cost, but says the window hoods contain asbestos and the quote does not include asbestos testing and removal. The complainant says the property has five window hoods. In 2020, he had two of the window hoods on the east side replaced with Colorbond when the yard was being upgraded. He said these window hoods were tested and found to contain asbestos and has provided a laboratory analysis dated 7 October 2020. The complainant has provided a quote of $2,700 for the testing and removal of asbestos from the three damaged windows hoods. The insurer has offered to send its trades to the property to carry out asbestos testing, but the complainant refused to allow them further access. I accept the complainant‟s position that the insurer has had ample opportunity to complete asbestos testing since the claim was lodged. I am satisfied the 2020 laboratory analysis provided by the complainant is sufficient to establish on the balance of probabilities that the damaged window hoods contain asbestos. While this testing was on the other side, photos show the remaining window hoods have a very distinctive appearance and I am satisfied on balance that the five original window hoods were made of the same material. I consider it fair for the insurer to add $2,700 to its cash settlement for the window hoods. Mould remediation Determination | Case number: 998708 Page 6 of 13 The insurer engaged a mould specialist, RS, who attended the property on 10 February 2023 and found mould growth and water staining to the ensuite ceiling. RS also noted that the complainant painted the ceiling around October 2022 (after the storm event). RS recommended the ensuite ceiling and roof lining be stripped and remediated by sanding and vacuuming exposed timber and sanitising the cavity with anti-microbial solution. On 21 February 2023, the insurer‟s assessor reported that removing the ensuite ceiling due to mould was not required. This report followed an inspection in relation to unrelated damage. On 24 February 2023, RS reattended the property. RS noted that roof leaks were still ongoing and further damages are likely to occur before the roof is repaired. RS recommended further mould remediation work to the living room, hallway/stairs, bathroom 2/toilet and laundry. On 7 August 2023, the insurer‟s assessor reported that:  the ensuite ceiling has been extended with an existing FC ceiling lining put in place below the old plastered ceiling lining. The clearance space of this void is unknown.  photos taken by RS show that the mould has attached itself to this existing old ceiling lining which has been encapsulated with the new false ceiling. There is no evidence this has occurred since the new false FC ceiling lining was installed.  photos taken by RS show no water staining to the old ceiling and it is impossible to determine if the claimed mould growth was from water ingress from the storm event or from numerous wetting events due to the condition of the roof prior to the event  there is new mould along with old mould staining, suggesting this appears to be an issue pre-event and quite possibly a pre-existing issue due to poor preparation of the ceiling  the inhabitable ceiling space could be remediated by fogging. On 11 October 2023, RS advised the complainant by email that they had been allocated to complete a scope of works in the ensuite which included stripping the ceiling and roof lining. The complainant says he telephoned RS to find out whether they could provide a quote and RS indicated this was possible, but it would need to be provided to the insurer. On 24 October 2023, the insurer emailed the complainant to book in a further assessment, but the complainant has not allowed the insurer access to the property. To date, no mould remediation works have been completed. The insurer‟s submissions to AFCA focus on the ensuite, but I am satisfied based on the RS reports that there is mould damage to other areas of the property. The insurer says that further assessments are required to address the mould concerns and the complainant has not allowed this which is a contravention of his responsibilities when making a claim (see page 88 of the policy). The complainant says he allowed the insurer and its contractors to inspect the mould issues on multiple occasions in February 2023 and he has therefore complied with his policy obligations. He says RS has provided two detailed scopes of work that can be used for quoting purposes. The policy contains the following relevant exclusion on page 31: Mould or mildew mould or mildew at the insured address unless it was directly caused by an incident covered by your policy and there is no evidence of pre-existing mould in the home or unit. Determination | Case number: 998708 Page 7 of 13 Based on exchanged information, I am not satisfied the mould damage in the ensuite was caused directly by the claimed storm in February 2022. RS rely on statements made by the complainant and have not adequately considered the cause of the mould damage. It is not in dispute that there is a false ceiling in the ensuite and I consider the analysis provided by the in surer‟s assessor regarding the ceiling construction and evidence of pre-existing mould damage compelling. Although the storm event in February 2022 likely contributed to mould growth in the ensuite ceiling cavity, I am not persuaded that it was the proximate cause of that damage. I consider it more likely that the mould growth was pre-existing and/or occurred due to repeated water ingress due to the poor condition of the roof. It follows that the mould damage to the ensuite is not a claimable loss under the policy and the mould exclusion also applies. The insurer is not required to pay for mould damage to the ensuite. However, RS have also identified mould damage to other parts of the property. The insurer has accepted liability for internal damage to the property and had ample time to assess the mould damage and make submissions to AFCA. The RS reports were provided in February 2023 and the insurer did not request a further assessment until October 2023 (8 months later). The insurer also has not adequately explained why a further assessment is required. I acknowledge that roof leaks were ongoing when RS attended and the poor condition of the roof would have contributed to mould growth. However, RS is the insurer‟s expert and the insurer has not given this aspect of the claim due attention - in fact it appears to have been overlooked. In the circumstances, I consider it fair for the insurer to pay for the mould remediation work identified to the living room, hallway/stairs, bathroom 2/toilet and laundry. The insurer is to obtain an actionable quote from RS (or another qualified mould remediator) based on the scope of works dated 24 February 2023 and issue a cash settlement on that basis. If a desktop quote cannot be provided, the complainant is to allow a further inspection of the property to determine the cost of the mould remediation works (excluding the ensuite). Make safe removal cost The complainant seeks the insurer to reimburse him $2,250 being the cost he incurred hiring trades to remove the tarps and sandbags from the roof in May 2023. He has provided an invoice from BQ which states: Clean up: Remove tarps and debris from roof Clean out gutters due to sand bags breaking filling gutters [sic] The insurer submitted on 18 October 2023 that:  it instructed CM to remove the tarps and sandbags from the roof  it will seek clarification from CM why it did not remove the tarps and sandbags  once CM have provided clarification why the tarps and sandbags were not removed, it would then determine if the complainant‟s invoice of $2,250 for the removal is reasonable. The insurer has not provided any further information and I consider the complainant‟s invoice of $2,250 for the removal of the tarps and sandbags fair and reasonable. The insurer is to reimburse the complainant this amount. Determination | Case number: 998708 Page 8 of 13 Damaged Flooring RS reported during its assessment on 24 February 2023, its technicians ladder collapsed and caused damage to the timber floor in the living room. The insurer has accepted liability. The complainant has provided a repair quote from PF for $8,107 which states: Due to damages on timber floors from sub-contractors, the timber floors will need to be rejuvenated from scratch. We have to incorporate the 4 main rooms that lead off the main lounge room and office into the quotation. This is the only option, if we just rectify the open plan lounge room there will be substantial differences in colour of timber and also different in finished sheens i.e. our finish maybe glosser than the existing finish and will not blend in as a whole. The insurer says due to insufficient information and lack of photographs of the damaged area, it proposed to engage a flooring specialist to review the damaged floor and validate the complainant‟s quote and repair method. However, on 26 October 2023, the complainant did not consent further attendance to the property for assessment. The insurer has not provided further information after it became aware of the complainant‟s refusal for further attendance and assessment to the property. The policy states that the insurer will pay extra costs to repair certain undamaged parts of the home to achieve a uniform appearance, including continuously joined undamaged floor coverings in the same room or area (page 74). The policy also includes a lifetime guarantee on repairs (page 95). As the damage to the floor was not caused by the storm, the insurer is not bound by the matching materials provision. However, I am satisfied the insurer is liable to repair the damage floor under the lifetime guarantee on repairs and common law. The insurer has had ample time to assess the damage to the timber flooring caused by RS and I consider it fair for the insurer to pay the complainant $8,107 as quoted. Insurer is to pay for some additional repairs In light of the matters set out above, the insurer is to cash settle the complainant the total amount of $13,057 broken down as follows:  $2,700 for testing and removal of asbestos  $2,250 for removal of the tarps and sandbags on the roof  $8,107 for timber floor damage The insurer is also to cash settle mould remediation to the property (excluding the ensuite) based on the RS scope of works dated 24 February 2023. 2.3 Is the complainant entitled to compensation? Yes. The insurer‟s claims handling and delays have been unreasonable and have caused the complainant significant stress and inconvenience. The insurer is to pay the complainant $2,000 compensation for non-financial loss. Determination | Case number: 998708 Page 9 of 13 AFCA may award non-financial loss compensation in certain circumstances Under paragraph D.3 of the AFCA Rules, we may award compensation for non-financial loss where t he insurer‟s actions have caused an unusual amount of:  physical inconvenience  time taken to resolve the situation  interference with the complainant‟s expectation of enjoyment or peace of mind. The complainant says the insurer‟s poor claims handling, de lays and miscommunication have caused him and his family significant stress and inconvenience. Amongst other things, he highlights the difficulties experienced communicating with the insurer during the claim process. The exchanged material confirms that the insurer has apologised to the complainant for his experience (including delays) and acknowledges that information provided to the complainant has not always been correct or complete. The insurer has offered the complainant $1,000 compensation for non-financial loss, but it does not appear this amount has been paid. I consider it fair in the circumstances for the insurer to pay the complainant $2,000 compensation for non-financial loss. 2.4 Why is the outcome fair? The outcome is fair because the terms, conditions and exclusions of the insurance policy have been correctly applied to determine the extent of coverage. The insurer has shown that the damage to the roof was not caused by the storm and is excluded from cover. It is fair for the insurer to decline that part of the claim, but pay for the additional items in paragraph 2.2. Determination | Case number: 998708 Page 10 of 13 3 Supporting information 3.1 The AFCA processes AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 Summary of expert evidence Record Key points Determination | Case number: 998708 Page 11 of 13 Record Key points Insurer’s expert ( CM ) Builder  CM a ttended property on 18 - 19 May 2022 for make safe and found multiple leaks to all ceilings throughout the property, paint peeling, water stains, water damage to the bamboo flooring  First make safe report states the roof is in poor condition with many cracked, brittle and loose tiles. It found evidence of tiles with pre - existing sikaflex fixed to the tiles over the years. It says cause of water leak through the roof is due to the old, loose cracked tiles. CM says the make safe was challenging due to the fragile condition of the roof, coupled with the height and pitch.  CM re - attended on 8 June 2022 to complete a further make safe after high winds dislodged the sandbags causing the tarp to become loose.  CM roof report dated 1 2 August 2022 s ays : I found mud broken away from ridge tiles, 20 plus broken tiles all over the roof, the stability of the roof felt concerning with the age of the tiles, and the number of broken around made it hard t o move around safely on the roof. I would suggest to have a reroof done simply for safety and age of the roof. There was leaks at the transition of tile to metal roofing, from what I could find simply doesn't have the flashing suitable for this area. Brak es in the window tiles which may be from hail also. Valleys on the roof seemed to be leaking from inside inspection though couldn't find the problem on outer area. [sic]  CM roof report says a t least 50% of the roof is damaged; and due to the poor and deteriorated condition of the roof, a full replacement of the roof is recommended. Insurer’s expert (JL ) Builder 13 - 10 - 2022  JL inspected the property on 13 October 202 2 and reported: - Roofer attended site and carried out the following. Trades have attended the site. Inspected internal ceiling, finding signs of water ingress. Trades have Inspected the roof from a ladder, finding multiple broken tiles and the tarp was ripped and shifted. Trades noted that the exposed broken tiles will cause a leak if any rain event occurs. Trades did not attend to the roof works due to insured concerned about liability for damages due to the condition of the roof. Trades have contacted JL and was told to hold off awaiting further instructions. Insurer’s expert (LC ) Roof Specialist 15 - 11 - 2022  LC attended the property on 15 November 2022 and found: > approximately 80% of the roof is damaged > evidence of pre - existing damage > evidence of previous attempted repairs of silicone over many cracked tiles > no evidence of storm created openings > no evidence of hail impact damage.  In addressing causation, LC says: I found the roof to be in poor condition. There are many cracked and broken tiles covering all sections of the Determination | Case number: 998708 Page 12 of 13 Record Key points roof. The age of the cracks varies from quite old, siliconed over cracks, to new cracks with fresh dust and shards present along with damage that is harder to date but lies within this ti meframe. The ridge and hip pointing appears to have been replaced recently however the application is messy and not correct. Roughly 10% of the roof has been replaced with fresh tile but many of these have cracked also. The roof feels “springy” underfoot a nd and the tiles are sagging down in many areas which indicates the battens and trusses likely have issues also. I believe that most of the cracked and broken tile are a result of foot traffic combined with the weakened, springy and uneven roof frame. The window awnings on the western side have what appears to maybe be hail damage but also has general deterioration for the elements. Insurer ’s expert ( CR ) Structural Engineer 03 - 02 - 2023  Engineer inspected property and reported that: > the terracotta roof tiles are 109 years old > evidence of porous for an extended period of time > signs of efflorescence indicating salts in the clay leeching calcium carbonate which shows as white stains on the underside of the tile > evidence of delignification on some roofing timbers that has been occurring over a period > approximately 5% of the roof were affected by foot traffic > a major renovation to the property in 2005 which would have needed certification and engineering > the roof is non - compliant with 2005 roof regulations > the comp lainant confirmed no maintenance has been carried out to the roof since purchase in 2017 > evidence of aged rot to tim ber rafters and battens over front veranda > the roof tiles have shifted from their original position on the 45mm x 25mm timber battens > moveme nt and rot visible in the timber lap eaves adjacent the telstra connection to the fascia board > visible rot to the external timber and trims to the front veranda, as well as staining to the timber ceiling lining, indicating water entry through the roof to t he roof space inside of the front veranda > visible rot to the timber balustrading of the front stairs > the observed rots are quite advanced and appears to have been happening for a considerable time period.  E ngineer noted the roof is not safe to walk on and concluded that: … the issue with the tiles being porous and in poor position on the roof battens, predates the occupancy of the insured, pre - 2017 … The described sagging to the roof is a combination of a pre - existing condition where a Rafter has been cleated between two beams and Determination | Case number: 998708 Page 13 of 13 Record Key points bolted in support and the position of the tiles on the battens opposed to those sitting correctly would give the illusion of sagging areas to the roof tiles. Insurer’s expert (RS) Mould Remediation 10 - 02 - 2023  Damage had occurred to the ceiling of the ensuite bathroom with it having mould and water staining.  Customer has since painted the ceiling in October.  1X AFD to be installed during duration of works.  Electrician to provide disconnect of bathroom lights pri or to works.  Ensuite ceiling to be stripped out in ensuite.  Roof lining plasterboard to also be stripped out.  Technicians to remediate ceiling cavity: > Denail and deglue exposed Timbers > sand exposed Timbers to IICRC standards. > Hepa Vacuum exposed Timbers > Sanitise cavity with anti microbial solution wet wash. Insurer’s expert (RS) Mould Remediation 24 - 02 - 2023  Non invasive moisture readings were conducted throughout property.  All readings returned within acceptable levels, however moisture is still likely present in ceiling cavity.  Roof to be repaired before any works commence.  Roof leaks are ongoing, further damages are likely to occur before roof is repaired. A re attendance for a final scope may be required.  Scope of works includes structural and remedia tion works to open plan area, hallway/stairs, bathroom 2/toilet and laundry/storage  Ceilings to be removed and back of wall linings assessed for damage  A ll exposed framework to be hepa vacuumed, sanded and treated with an anti microbial solution.  During works ladder technician was using collapsed and caused damage to timber floor. Effected area was photographed.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.