Home / Hollard / Determination 996346

Determination 996346

Partial decline of storm damage claim for roof, garage door and pool fence, plus claim handling delays

FirmHollard
Decided2024-04-02
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$500
Amount claimed—
SourceAFCA PDF

Summary

The complainant's home insurance claim for storm damage was partly declined for the roof, garage door and pool fence. AFCA upheld the decline for roof and garage door but required the insurer to cover the pool fence with section 57 interest and pay $500 for non-financial loss.

The complainant did not prove storm caused the roof and garage door damage, but the insurer did not establish an exclusion for the pool fence and delayed handling the claim.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interestpay non financial loss

Related

All Hollard determinations · Find similar determinations

Text of the determination

Determination Case number 996346 Financial firm The Hollard Insurance Company Pty Ltd Determination | Case number: 996346 Page 2 of 10 Case number: 996346 29 February 2024 Determination overview 1.1. Complaint The complainant held a home insurance policy with the financial firm (insurer). In October 2022, the complainant made a claim for damage to the property which allegedly occurred during storms in February and July 2022. The insurer has accepted the claim for internal damages, but declined to cover the cost of repairing the roof, pool fence and garage door. The insurer says these parts of the property were not damaged by the storm but due to gradual deterioration and wear and tear, which are excluded under the policy. The insurer says further that these maintenance works need to be completed prior to the internal repairs and offered to cash settle the internal damage. The complainant disputes the insurer’s decision and has raised concerns about how the insure r handled the claim and the qualifications of the insurer’s expert. The complainant wants the insurer to cover the claim in full and pay compensation. 1.2. Issues and key findings Is the insurer entitled to partially decline the claim? Yes. The complainant has not established that the damage to the roof and garage door was caused by storm and the insurer is entitled to deny that part of the claim. However, the insurer has not established that the damage to the pool fence is excluded and the insurer is required to pay that part of the claim. Is the insurer required to pay compensation? Yes. The insurer did not handle the claim as well as it could have and there were delays. It is fair for the insurer to pay the complainant $500 compensation for non-financial loss. Why is the outcome fair? The outcome is fair because the terms, conditions and exclusions of the insurance policy have been correctly applied to determine the extent of coverage. The insurer has shown that the damage to the roof and garage door was not caused by the storm and it is fair for the insurer to decline that part of the claim. It is fair for the insurer to pay for the pool fence and $500 compensation due to delays handling the claim. 1.3. Determination The determination is substantially in favour of the insurer. The insurer is not required to cover the damage to the roof and garage door, but is required to cover the damage to the pool fence together with section 57 interest. The insurer is required to pay $500 compensation for non-financial loss. Determination | Case number: 996346 Page 3 of 10 Reasons for determination 2.1 Is the insurer entitled to partially decline the claim? Yes. The complainant has not established that the damage to the roof and garage door was caused by storm and the insurer is entitled to deny that part of the claim. However, the insurer has not established that the damage to the pool fence is excluded and the insurer is required to pay that part of the claim. Complainant bears the onus of establishing a claimable loss It is accepted insurance law that an insured has the initial onus to show, on the balance of probabilities (that it is more likely than not), that the loss or damage claimed falls within the terms of the policy. Where this is established, the onus then shifts to the insurer to prove that an exclusion applies if it seeks to deny or limit its liability for the loss. There is no dispute that the complainant received the policy documents including the Product Disclosure Statement and Certificate of Insurance. The policy covers several insured events subject to limits, conditions and exclusions as set out in the policy . Page 14 states that the policy covers loss or damage caused by ‘storm, rainwater and flood’. There is no dispute that a storm occurred in July 2022 and rainwater entered the property. The insurer has accepted the claim for internal damage, but says the damage to the roof, pool fence and garage door (the disputed damage) was not caused by the storm event. The question for determination is whether the proximate cause of the disputed damage was a storm or whether it was caused by gradual deterioration, wear and tear or faulty workmanship (which are excluded from cover under the policy). The proximate cause is the real, dominant, or effective cause; it is not necessarily the cause that most immediately prec eded the damage. History of the claim The claim was made on 31 October 2022. The complainant says they noticed water leaking into the home during a storm on 4 July 2022. They had the roof restored a year before the storm event and installed solar panels on the roof a few months later. Following this, roof leaks occurred. The complainant delayed making a claim due to an overseas trip. The insurer engaged AC to assess the claim. AC inspected the property on 1 November 2022 and engaged a roof specialist who attended the property on 7 November 2022 and prepared a report. In December 2022, the insurer sent a partial decline letter advising that it would accept the resultant internal damage, but the roof damage would be excluded from cover as it was not directly caused by the storm event. The complainant disputed the insurer’s decision regar ding the roof and requested confirmation of AC’s qualifications. They were advised that an HBCF Certified builder was used for the assessment. The complainant requested a new builder/assessor with suitable qualifications be engaged to reinspect the property. Determination | Case number: 996346 Page 4 of 10 The insurer complied with the complainant’s request and appointed a new builder/assessor, CC, and another roof specialist, AS. CC inspected the property on 16 March 2023 and prepared a report and scope of works. AS also inspected the property and prepared a roof report dated 22 March 2023. The insurer reviewed the expert material and sent a further partial decline letter on 4 May 2023 which stated that the following damage was not covered:  Roof repairs  Garage door  External – left side elevation / pool fence Expert reports say the roof and door were not damaged by storm The expert evidence is summarised in section 3.2 below. The insurer’s experts broadly conclude that the disputed damage did not occur due to a single storm event and was caused by gradual deterioration, ongoing weather exposure and wear and tear. They have also identified design defects and faulty workmanship. The two roof experts identified the same or similar problems with the roof including:  the mortar to the ridge capping has cracked and water is entering behind the mortar  the omission of weep holes which allowed water to enter through cracks and led to overflow into the roof cavity as water was unable to escape. In relation to the garage door, CC reported that the damage is not due to a single storm event but deterioration over time (as evidenced by severe rot and weathering). The door is also hollow and should be a solid door with relevant finishing to prevent weathering. T he complainant has questioned the qualifications of the insurer’s experts to determine the cause of the damage. In particular, the complainant submits that a licenced builder/roofer cannot determine what has caused damage to a roof, the impacts of weather events on roofs or comment on what has caused deterioration. I am not persuaded by the complainant’s submissions regarding the suitability of the insurer’s experts. The insurer’s exper ts are all qualified builders and roofing specialists. Their reports are detailed, well-reasoned and include supporting photographs. I acknowledge they are not engineers but have no reason to doubt their expertise and ability to assess the cause of the damage. In any event, the complainant bears the onus of proving that the damage claimed was caused by an insured event, not the insurer. Complainant has not established roof and door were damaged by storm The insurer has provided multiple expert opinions (at the complainant’s request) and the complainant has not provided any expert evidence to refute the insurer’s expert reports. All experts have provided the same explanation for the roof damage. The expert evidence regarding the garage door is also compelling as it discusses the level of deterioration and the presence of mould and rot. This is not consistent with a single storm event and could not have happened with 72 hours from the event. In the circumstances, I am not persuaded that the damage to the roof and garage door was caused by a storm event. It follows that the complainant has not established a claimable loss under the policy and the insurer is not required to pay the cost of repairing this damage. Determination | Case number: 996346 Page 5 of 10 Given the complainant has not shown the damage to the roof and garage door is a claimable loss, there is no requirement to consider/discuss the policy exclusions and conditions argued in the alternate by the insurer for this damage. C omplainant’s arguments do not advance their position The complainant has made a number of submissions to AFCA. While this determination does not refer to them all, I have taken each submission into account in reaching my decision. The complainant says that the installation of solar panels and/or a leak underneath may have contributed to the damage. I acknowledge the insurer has not fully explored the cause of the leak under the solar panels. However, the solar panels were installed prior to the storms and the complainant says the roof has only leaked since then. Any issues were therefore pre- existing and there is no evidence that a storm event caused damage to that part of the roof. It is possible that the roof may have been damaged during installation of the solar panels, but this does not assist the complainant’s position. The complainant bears the onus of proving the damage is claimable under the policy and has failed to do so. Further, the insurer cannot be held responsible for any defective works by the complainant’s tradespeople. The insurer therefore has no liability to repair the roof and it is unnecessary to establish the precise cause of the leak. The insurer has acted in good faith and agreed to cover the resultant stormwater ingress damage, which I consider a fair outcome. Insurer is to pay the cost of repairing the pool fence AC initially reported that the timber pool fence had blown over in the storm and recommended that the pool fence is be repaired as resultant damage. The AC report does not raise any maintenance concerns with the fence or provide any evidence to refute the insured’s statement that it blew over during the storm. AC arranged a make safe of this area. CC later inspected the property and reported that the timber pool fence posts had been removed, but the remaining posts showed signs of wear and tear/gradual deterioration. CC also stated that the pool fence gate is out of alignment due to wear and tear. There is minimal evidence regarding the cause of the damage to the pool fence. Based on the complainant’s version and the report by AC, I am satisfied the pool fence blew over during a storm. I am therefore satisfied that the complainant has established a claimable loss under the policy and the onus shifts to the insurer to establish the application of a policy exclusion. CC has reported that the pool fence pickets displayed wear and tear and says it is unlikely the damage would have been caused by winds on the reported incident date if the posts were in good condition. However, CC has not provided a detailed explanation regarding the nature of the wear and tear to the posts or how this caused or contributed to the fence falling down. In the circumstances, I am not satisfied the insurer has established that the damage was caused by an excluded peril under the policy and I consider it fair for the insurer to pay for the cost of replacing the pool fence. The insurer is to settle this part of the claim by either arranging for the fence to be reinstated or cash settling the fair and reasonable cost of repairs in accordance with the terms of the policy. The insurer is also to pay interest under section 57 of the Insurance Contracts Act 1984 from 4 May 2023 when the damage to the pool fence was declined. Determination | Case number: 996346 Page 6 of 10 2.2 Is the complainant entitled to compensation? Yes. The insurer did not handle the claim as well as it could have and there were delays. It is fair for the insurer to pay the complainant $500 compensation for non-financial loss. AFCA can award compensation for non-financial loss Under AFCA’s Rules, AFCA may award compensation for non -financial loss where there has been an unusual amount of physical inconvenience, time taken to resolve a situation, or interference with the complainant’s expectation of enjoyment or peace of mind. In assessing whether to award compensation, AFCA expects complainants to be moderately robust, bear the normal degree of inconvenience experienced when a problem occurs, and take reasonable steps to minimise the inconvenience suffered. AFCA considers the severity and impact of the insurer’s conduct on the particular complainant. Insurer caused delays during its complaints process The General Insurance Code of Practice (the Code) sets out timeframes insurers are required to comply with when handling claims. The Code states that the insurer will:  decide whether to accept or deny a claim within ten business days of receiving all relevant information and completing all inquiries  make a decision within four months of receiving the claim unless an exception applies  make a decision within 30 calendar days of a complaint being lodged. The claim was made on 31 October 2022 and AC assessed the damage on 1 November 2022. AC engaged a roof specialist who attended the property on 7 November 2022 and provided a report to the insurer on 16 November 2022. The insurer sent a partial decline letter in early December 2022. The complainant disputed the insurer’s decision regarding the roof and qu estioned AC’s qualifications. He made a complaint to the insurer by email on 19 December 2022 and by telephone on 5 January 2023. His complainant was closed on 17 January 2023. The complainant followed up on 27 February 2023 and requested a new builder/assessor, which the insurer arranged. The new builder and roof specialist inspected the property in March 2023 and an updated decline letter was sent on 4 May 2023. The complainant lodged a further complaint with the insurer on 16 May 2023 and the insurer sent a final decision letter on 27 June 2023. Having considered all relevant information, I am satisfied that the insurer handled the claim appropriately in the first instance and communicated its initial decision promptly. However, there were delays during the complaints process and a complaint was incorrectly closed with no response provided. The complainant was also provided with an incorrect telephone number and experienced frustration attempting to contact the insurer to discuss the claim. In the circumstances, I am satisfied that the insurer caused unreasonable delays which warrant compensation for non-financial loss in the amount of $500. 1.4. Why is the outcome fair? The outcome is fair because the terms, conditions and exclusions of the insurance policy have been correctly applied to determine the extent of coverage. The insurer has shown that the damage to the roof and garage door was not caused by the storm and it is fair for the Determination | Case number: 996346 Page 7 of 10 insurer to decline that part of the claim. It is fair for the insurer to pay for the pool fence and $500 compensation due to delays handling the claim. Determination | Case number: 996346 Page 8 of 10 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: the legal principles applicable industry codes or guidance good industry practice previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: available documents the recollections of the parties all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. Determination | Case number: 996346 Page 9 of 10 3.2 Summary of expert evidence Record Key points Insurer’s builder (AC) Asse ssment Report 1 November 2022  Complainant noticed water ingress on 4 July after heavy rain  Complainant advised they had the roof restored about 12 months ago and solar panels installed about 11 months ago . Prior to these works the roof has never leaked.  A digital level was placed on the concrete tiled roof and the reading was 9.7°. This is below the standard pitch for roof tiles.  A timber picket fenc e surrounding the inground pool has blown over in the storm. Currently there is no fence around the pool area, which is a safety issue. Will arrange temporary fenc e.  Maintenance and Building Defects: > Re - mort ar the cracked ridge capping and install weep holes . > Have the Solar panels disconnected by Electrician and removed and stored so cracked tiles underneath the panels can be replaced. Re - instate Solar panels and commission. Insurer’s roofer (A R ) Roof Report 7 November 2022  Over the affected areas there is a top ridge. Mortar to the ridge capping has cracked and water is entering behind the mortar.  There has been no weep holes installed into the mortar which is allowing any water that enters through the cracks to not be able to escape and overflow int o the roof cavity. The wat er is also tracking down the rafters in the roof to multiple leak spots.  Under the solar panels there is also a leak - most likely a broken tile or deteriorated seal. The solar panels will need to be removed to locate the leaks and repair. Second builder (CC) Asse ssment Report 16 - 03 - 2023  insured advised they restored the roof a year before the storm event. A few months later they installed solar panels onto the roof. Following this, the roof leaks occurred.  the resultant damage has been caused by deteriorated roof pointing, ongoing weather expos ure, deteriorat ed pool fencing posts and heavy rain caus ing the sustained damages noted  engaged roof specialist to attend and determine the cause and extent of damages (discussed below)  there was a large volume of rain around the reported incident date, but pre - existing issues to the roof were not present it is unlikely water ingress would have occurred  t imber garage entry door i s heavily rotted and deteriorated from ongoing weathering  t he door is also a hollow core door and should be a solid timber door finis hed to avoid damage from weather exposure.  t he timber pool fenc e posts had been removed, but remaining posts showed signs o f wear and tear/gradual deterioration. If the posts were in good condition it is unlikely the damage would have been caused by winds on the reported incident dat e. MAINTENANCE There are maint enance repairs to be carried out at the Determination | Case number: 996346 Page 10 of 10 Record Key points property (as per scope) at the owner’s expense and the insured has been informed of the maintenance repairs to be carried out on the property. The maintenance and/or pre - existing conditions are described below: Insured to hire qualified trades for the following works prior to any internal repairs commencing: Re - bed and point top ridge capping with weep holes - 25 l/m. Rear tiled roof with flat pitch to be converted to metal roof sheets to comply with pitch. Stink pipe to have dektite flashing installed - to be completed prior to an y insurable works. Second Roof Specialist (AS) Roof Report 22 - 03 - 2023  Top ridge capping has cracks throughout and no weepholes. This is directly above the leak in the front bedroom and kitchen down lights.  The leaks in the rear sunroom, this area has a rake ceiling and a flat pitch roof off 8 degrees with concrete tiles on it.  Solar panels on this area need to be removed to inspect. Roof tiles shouldn’t be on this area, pitch is too flat, 17 degrees minimum required for tiles, with 100 mm lap.  Mould around the air ducts for the air conditioning, very minor, no broken tiles above this area .