Summary

Following a water leak claim, the complainants disputed the insurer's contractor's flooring repairs. AFCA found the flooring matched acceptably, required only caulking of a residual stain, and accepted the insurer's offer to reimburse legal costs for delay.

The complainants provided no expert evidence contradicting the insurer's flooring specialist report, so it was preferred, and the insurer's offer to reimburse legal costs for delay was fair.

Issues

Subjects and remedies

home or building damagepay compensationrepair or rectify

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination Case number 992445 Financial firm Insurance Manufacturers of Australia Pty Ltd Determination | Case number: 992445 Page 1 of 7 Case number: 992445 30 November 2023 1 Determination overview 1.1 Complaint The complainants hold a Home Buildings and Contents Insurance policy (the policy) issued by the financial firm (the insurer). Following an escape of water event (a leak) in the insured property on 25 November 2018, the complainants lodged a claim for damages which was accepted. Company B was engaged by the insurer to complete the repairs. The complainants say during the repairs to the property, Company B:  left a lounge set and a free-standing oven exposed to the elements, causing damage  made faulty repairs in respect of poor painting and caulking work and  failed to match floorboard materials to existing materials and did not repair the flooring correctly. The insurer engaged an assessor to inspect the property on 3 July 2023 and, as a result of the assessor’s report, on 14 July 2023 has:  accepted liability for replacing the lounge set and oven and  acknowledged the poor workmanship relating to the painting and caulking. However, it says it engaged a timber flooring specialist, Company T, on 22 November 2022 to complete an onsite assessment of the floorboards and Company T found the material used to repair the floorboards was consistent and was, due to natural variations in wood, considered an acceptable match. In addition, Company T found some of the issues attributed to the Company B repairs were pre-existing issues not caused by the insured event. The complainants would like AFCA to determine the issue of liability for the flooring work, and to require the insurer to pay their legal costs. 1.2 Issues and key findings Is the insurer liable for the flooring? Partially. As recommended by Company T, the insurer should arrange for the application of an appropriate coloured caulking to detail the slight line of residual stain in front of the fire place. Did the insurer cause undue delays in the handling of the claim? Yes. The insurer accepts it took too long to resolve the claim and has offered fair compensation as a result. Why is the outcome fair? In the absence of any supporting evidence from the complainant, it is appropriate to rely on the Company T expert report. On this basis, there is no further liability for the insurer beyond that which has already been accepted. 1.3 Determination This determination is substantially in favour of the insurer. Determination | Case number: 992445 Page 2 of 7 2 Reasons for determination 2.1 Is the insurer liable for the flooring? Partially. As recommended by Company T, the insurer should arrange for the application of an appropriate coloured caulking to detail the slight line of residual stain in front of the fire place. The insurer’s liability is se t out in the policy wording The policy is an insurance contract set out in a Product Disclosure Statement (PDS). I am satisfied the PDS contains the rights and responsibilities applicable to this claim which the parties have agreed to. Relevant sections of the PDS are set out in section 3.2 of this determination. The insurer says there is no defect in the flooring The insurer relies on the Company T report and, in summary in its letter of 14 July 2023, said: I refer you to the above policy wording located on page 76 of the PDS which outlines that [the insurer] does not pay to match materials to create a uniform appearance. The expert reporting provided by [Company T] determines that the floorboards squeaking is not a result of the repairs completed by [Company B] and the colour variant is not considered a defect. As such, [the insurer] maintains that the floorboards will not be rectified as no poor workmanship has been established. The insurer has declined to pay for rectification works relating to the floorboards on this basis. The complainants say there are issues with the flooring The complainants have engaged a solicitor to assist them with this complaint. In a letter to AFCA dated 19 September 2023, the complainants’ solicitor, Mr S, relevantly said : The insurer seeks to rely upon the policy wording on page 76 of the policy when it says it does not pay to match materials to create a uniform appearance. […] The floorboards were damaged and the repairs effected by the insurer’s repairer. The insurer did not pay our client or settle with our client in respect of the repair of the floorboards. It undertook to repair the floorboards itself. The policy does not say that if the insurer repairs the damage itself, that it will not try and match as best as it can. It has not done so. For the insurer to suggest that these clauses allow the insurer’s contractor to not match the floorboards through staining is simply not correct. It is illogical to suggest that a floorboard contractor should not, as a professional, attempt to match the colour of the floorboards surrounding the damaged area. Determination | Case number: 992445 Page 3 of 7 If we are to accept the insurer’s explanation of what this clause means, then the insurer’s contractor could put any type of wood and any type of colour in floor boards and it would rely on the policy to state it were allowed to do so. In fact, this is not correct. The insurer has said that it tried to source wood that was close match to that in the home, but that its supplier didn’t have it. It did not go to an alternate supplier with the correct wood type. Our client should not be limited to the insurer’s supplier’s availability only. The wood should have been matched and the stain on that matched wood should have been painted to match the remaining floorboards. Any reasonable and competent contractor would have done so. To not do so is poor workmanship and it does not return the insured into the position it would have been in had the insured event not occurred. The wood floorboards in question are not of a rare type that is irreplaceable and the staining of the wood is a simple process for a floorboards contractor to match. It is an implied clause that when works are being completed to floorboards under a policy that if it is a partial repair to one room, that the partial repairs will be matched as best as possible. It would be illogical and non-commercial to suggest otherwise. For example, what if cedar wood was used with a black tint? If we were to accept the insurer’s position, this scenario would be acceptable under the policy. The complainants’ position is the policy should be interpreted to require the insurer, when making repairs, to match both the type, and colour (through staining) of the undamaged floorboards. The insurer does not say it is entitled to provide mis-matching materials As can be seen in the policy wording extract in section 3.2 of this determination, the policy wording on this point is clear and unambiguous. The policy states the insurer will not pay for materials to match the undamaged parts of the home to create a uniform appearance within the part of the home that was damaged. However, I am satisfied there is an implied obligation, when engaging in rectification works, to take reasonable steps to restore the home to its pre-event condition. This is the purpose of the insurance policy. While I accept the complainant’s argument in respect of this implied condition of the policy, Mr S misinterprets the insurer’s position on this issue. The insurer does not say it is entitled to use any materials it wishes to conduct the repairs. Its position is the repairs have been carried out with materials which are an acceptable match to the existing flooring, despite being slightly different. Company T provided an expert assessment of the match Company T relevantly says: VARIATION IN COLOUR: Determination | Case number: 992445 Page 4 of 7 Timber is a natural product that will have variation of colour throughout a floor. The timber installed is an Oak species, the material being from a different feed stock will not always have the same colour and grain structure. Reference is given to AS 2796.2 – 2006 Timber – Hardwood – Sawn and milled products. This standard covers natural feature in timber and grading of timber. It does not cover the colour variation in timber, timber from different feed stock generally produces different grain structure and colour variation. The species in the floor is an Oak species, this colour variation being a natural aspect of timber is considered acceptable. No defect recorded. RESIDUAL STAIN: […] The slight line of residual stain in front of the fire place is considered minimal, this can be detailed by the application of an appropriate coloured caulking to detail this issue. It is not recommended to re-sand the floor to detail this minor issue. Company T’s report is the only expert report provided by the parties on this issue. In the absence of any contradictory reports about the colour of the timber used in the replacements not meeting the Australian Standard, on balance, I accept the material s used have ‘matched’ the pre-existing floorboards to an acceptable standard. I am satisfied however Company T recommended the application of an appropriate coloured caulking to detail the slight line of residual stain and this should be done. The complainants also raise additional damage to the floorboards Mr S’ letter of 19 September 2023 also raised issues of damage to the floorboards which have not been rectified: In respect of the squeaky floors and gaps in the floorboards, these were as a result of the insured event and the report at Appendix E is very poor and has no explanation as to how it comes to its conclusions that this was pre-existing. It is not pre-existing and the insurer has failed to show how it is so. The insured has stated how the property was prior to the insured event, and how it was afterward. There is no evidence to the contrary so the insured’s position must be accepted. Further, the report at Appendix E notes that there is a residual stain on the flooring in front of the fireplace, yet, the insurer has failed to address this or offer to repair it. Determination | Case number: 992445 Page 5 of 7 In summary, the insurer should repair the floor board to ensure a full colour match, or as close as possible. The insured has the burden of establishing a claimable loss When bringing a complaint to AFCA, the complainant is required initially to show it is more likely than not there is a claimable loss under the policy. This means demonstrating the loss or damage was caused by a risk that is covered under the policy. Once the complainant proves there is a claimable loss, the insurer is liable for the loss unless it shows an exclusion or limiting condition applies. The insurer has the responsibility to show it is more likely than not the exclusion or condition applies. As a result, Mr S is i ncorrect when he asserts it is the insurer’s responsibility to establish the squeaky floors and gaps were pre- existing. It is the complainants’ responsibility to establish they were caused by the claimed event. As the complainants have not provided any substantive evidence to support their statements these issues were caused by the escape of water event (or by Company B subsequently) or offered any expert evidence to contradict the Company T expert report, on balance, I accept Company T’s expert report con clusion. The insurer is not required to pay for these repairs to the flooring. 2.2 Did the insurer cause undue delays in the handling of the claim? Yes. The insurer accepts it took too long to resolve the claim and has offered fair compensation as a result. The insurer acknowledged the delays In its letter of 14 July 2023, the insurer acknowledged the delays in its claim handling process and the time taken to resolve the issues which arose from Company B’s poor workmanship. As part of this acknowledgement, it offered to pay for the legal fees the complainants have incurred on receipt of a full and final invoice of those costs. It also accepts these fees are likely to exceed AFCA’s cap on the compensation which can be awarded for legal costs. Nevertheless, it reconfirmed its willingness to reimburse the complainants on 21 August 2023. I am satisfied this is a fair offer of compensation for the delays and the expense the complainants have been put to as a result. 2.3 Why is the outcome fair? In the absence of any supporting evidence from the complainant, it is appropriate to rely on the Company T expert report. On this basis, there is no further liability for the insurer beyond that which has already been accepted. Determination | Case number: 992445 Page 6 of 7 3 Supporting information 3.1 The AFCA process AFCA’s a pproach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 Relevant policy terms Product Disclosure Statement – page 76 How we settle certain things When we pay your claim, we settle certain things in line with the information shown in this section. Matching materials Under Buildings Insurance Determination | Case number: 992445 Page 7 of 7  we only repair the damaged parts of your home. We don't pay for materials to match the undamaged parts of your home to create a uniform appearance. Carpet, vinyl, tiles or floorboards Under Buildings Insurance and Contents Insurance  we only repair or replace the carpet, vinyl, tiles or floorboards in the part of your home that was damaged  we don’t pay for any adjoining rooms, or your entire home.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.