Home / AIG Australia Limited / Determination 991799

Determination 991799

Insurer limited its liability for storm damage, stock loss and business interruption after storm and flood events

FirmAIG Australia Limited
Decided2024-03-28
ProductGeneral Insurance · Business / commercial
OutcomeFor the complainant
Amount awarded$84,284
Non-financial loss—
Amount claimed$159,352
SourceAFCA PDF

Summary

A grocery store was inundated by stormwater and then floodwater; the insurer covered only part of the storm damage, stock and BI. AFCA found the insurer's assessment unfair and ordered increased property, stock and 38 weeks of BI settlement with interest.

The storm and flood were independent events, and the insurer failed to show a fair methodology separating storm damage, so the complainant's more persuasive evidence was accepted.

Issues

Subjects and remedies

business interruptionhome or building damagenatural disastersmall businesspay claimpay interest

Related

All AIG Australia Limited determinations · Find similar determinations

Text of the determination

Determination Case number 991799 Financial firm AIG Australia Limited Determination | Case number: 991799 Page 1 of 8 Case number: 991799 28 March 2024 1 Determination overview 1.1 Complaint The complainant holds a business insurance policy (policy) with the financial firm (insurer). The policy provides cover for property damage and business interruption (BI). The policy insures a retail grocery store (store). The complainant lodged a claim for property damage and BI after t he store was inundated with water on 27 February 2022 (stormwater) and again on 28 February 2022 (floodwater). Based on its hydrology report the insurer accepted stormwater damage to equipment, furnishings and stock up to 100mm above floor level. The insurer has offered to pay $84,121.25 for property damaged, $18,144 for damaged stock and $437 for BI, less the $250 policy excess. The insurer has already issued the complainant with a $45,000 cash settlement earlier in the claim. The complainant disputes the insurer’s offer. The complainant wants the insurer to increase cover to $129,250.08 for property damage and pay a further $15,102 for damaged stock. The complaint wants the insurer to accept 38 weeks of BI cover. 1.2 Issues and key findings Is the insurer ’s assessment of its liability under the policy fair ? No. There is no dispute the store was inundated by stormwater before the floodwater arrived, these being two independent events under the policy. The insurer has not established the assessment of its liability is fair in the circumstances. Therefore:  the insurer is to increase the settlement amount for property damage to $129,250.08 (less the $45,000 already paid to the complainant and applicable policy deductions such as the excess)  the insurer is to accept liability for the damaged timber step in the amount of $5,155.30  the insurer is to increase its settlement for the lost stock because it is most likely that the stormwater was responsible for the tripping and loss of power resulting in stock loss. The insurer is required to increase its settlement for damaged stock by a further $15,425. Is the insurer required to increase its offer for BI? Yes. The policy provides cover for BI and the evidence shows the stormwater ingress event most likely resulted in BI related loss independent of the flood event. The insurer is required to settle the complainant for 38 weeks of BI, this being a reasonable representation of the interruption caused by the storm event. Why is the outcome fair? The outcome is fair because the complainant has established a higher entitlement for claimable loss or damage due to the storm event. The insurer has not shown the assessment of its liability is fair, consistent with the policy and the available information. Determination | Case number: 991799 Page 2 of 8 1.3 Determination This determination is in favour of the complainant. Within 21 days of receiving notice of the complainant’s acceptance of this determination, the insurer is to:  increase its settlement for the property damage to $129,250.08 (less the $45,000 already paid to the complainant and applicable policy deductions)  the insurer is to accept liability for the damaged timber step in the amount of $5,155.30  increase its settlement for damaged stock by a further $15,425  settle the complainant for 38 weeks of BI related losses  is required to pay interest in accordance with section 57 of the Insurance Contracts Act 1984 (Cth) for the increased settlement amount from 29 November 2022 (when the insurer made its claim decision) until payment is made. Determination | Case number: 991799 Page 3 of 8 2 Reasons for determination 2.1 Is the insurer ’s assessment of its liability fair ? No. There is no dispute the store was inundated by stormwater before floodwater. The insurer has not established the assessment of its liability and therefore cash settlement offer is fair in the circumstances. The policy covers the insured property against accidental loss or damage The insurer provided the complainant with the relevant policy documentation including the product disclosure statement (PDS) and certificate of insurance (COI). The panel accepts the insurer is entitled to rely on the policy provisions to assess its liability under the claim. The policy covers the insured property against accidental loss or damage. Cover under the policy is subject to the conditions, limitations and exclusions specified in the PDS. Complainant has the onus of showing loss/damage that triggers cover The complainant is first required to show, it is more likely than not, that the loss or damage claimed triggers cover under the policy. Only if the complainant can do this, will the duty shift to the insurer to show, on balance, it is entitled to decline cover in line with the policy wording or otherwise. The panel is satisfied:  there is no dispute the insured property was first inundated by storm water up to approximately 100mm commencing around 1.00pm 27 February 2022  there is no dispute the property remained inundated with storm water for approximately 19hrs before the flood waters arrived around 8.00am on 28 February 2022 pushing the flooding up to 300mm-350mm  there is no dispute the insurer has accepted to cover the complainant for loss or damage arising from the initial storm water inundation, but has declined cover for loss or damage caused by the subsequent flood water inundation  the complainant accepts this and confirms cover being sought under the policy is limited to the initial 100mm storm event and not flood related loss or damage. Given the above, the panel accepts the complainant has established a claim for loss or damage caused by the storm event. The onus rests with the insurer to show, on balance, it is entitled to limit or refuse indemnity in line with the policy provisions or otherwise. Complainant says insurer should increase settlement amount The complainant requested the insurer to settle the claim for property damage in the amount of $124,094.78 based on his preferred repair quote from ‘Q’ dated 22 July 2022 as well as accept Q’s quote for the damaged timber step in the amount of $5,155.30 , these amounts being exclusive of GST. The complainant says this only includes damage up to 100mm from the storm event. The complainant has provided an email from Q dated 22 June 2022. In the email Q explains, given the construction of the stores fit out, it cannot remove and replace damaged sections without damaging the entire fit out. Therefore, necessitating complete replacement of most areas of the fit out. Determination | Case number: 991799 Page 4 of 8 The complainant seeks a further $15,102 for damaged stock, this being in addition to the $18,534 the insurer has accepted to cover under the policy. The complainant expects this because he says water entered a power point located under 100mm and which short-circuited power in the entire shop. The complainant says this spoilt stock in the all the fridges and freezers. The complainant has provided a photograph of the power point which shows this to be low to the ground and likely under 100mm. The complainant has provided an invoice from refrigeration specialist ‘ ER ’ dated 18 April 2022. The invoice says ER attended the shop on 28 February 2022 following the storm and flood events and where it found multiple power points circuits tripping. Insurer says it has correctly settled claim The insurer says the complainant’s quotation from Q does not separate damage caused by the covered storm event and the excluded flood event. The insurer relies on a report from M to assess its liability and associated claim settlement offers. M says its quantity surveyor reviewed Q’s quote and calculates the estimated cost of reinstating up to the point of 100mm to be $84,121.25. M says the estimate includes steel racking, POS and café counter glued and allowance for the lowest timber shelf and cupboards on the shelving unit. Further, regarding the stocks damage, M says the cost to reinstate damaged stock up to 100mm is $18,534. Insurer required to increase its settlement amount The issue in dispute is whether the insurer is entitled to limit its liability based on its assessment of the claimed property damage. The complainant says the quotes from Q for $129,250.08 is only for damage up to 100mm. The insurer says the quotes do not separate damage caused by the storm and damage caused by the flood. The complainant provided an email from Q explaining the scope of works quoted and the reasons why these works are necessary given the 100mm stormwater ingress event. The panel has also considered the insurer’s information. However, the panel finds the information from the complainant and Q to be more persuasive and consistent with the circumstances resulting in the claimed loss and damage. The insurer’s information is limited and does not provide a reasonable explanation/methodology for separating the storm damage and flood damage. There is no dispute the insured property remained inundated by stormwater for close to 19 hours before the floodwaters arrived. The panel accepts this is a substantial period for the contents, furnishings, equipment and power point(s) to be exposed to and damaged by the stormwater. The panel accepts it is more likely this long period of inundation did cause significant damage and impacted the power supply to the fridges and freezers within the store. There is no persuasive information from the insurer or M in response to Q’s evidence relating to the required scope of works and requirement to replace as opposed to repair sections of the store fit out. The available information shows M appears to have reached out to building consultants seeking expert opinion on the damage and associated repair methodology. However, given delays in receiving a response, M abandons its request for expert opinion and recommends the insurer accept and base the assessment its liability on the loss Determination | Case number: 991799 Page 5 of 8 adjuster’s (M) opinion. M, not a building consultant, says it referred and relied on the rates in place in 2016, when the shop was initially fit-out by Q. The insurer has not provided any persuasive information in support o f its concerns about Q’s quotes to show they are incorrect, excessive or are inconsistent with accepted industry practices. The insurer has not provided any persuasive information as to the methodology it used in preparing its scope of works, repair costs or the separation of damage caused by the storm or flood events. Without compelling information to the contrary and accepting the advice of the more appropriately qualified consultants Q, the panel accepts it more likely the damaged fit out needs to be r eplaced as opposed to being repaired in sections. The panel accepts Q’s proposed scope of works and repair quotes are not only more compelling but that they are actionable quotes. In the absence of an actionable quote to support the insurer’s position, th e panel is not satisfied the insurer’s proposed settlement can be accepted as being fair, reasonable or capable of covering the cost to complete the works to be accepted under the policy. For these reasons, the panel is satisfied it is fair and consistent with the policy that the insurer increases its settlement for property damage to $129,250.08. Insurer to increase cover for damaged stock The complainant says during the storm event water entered a power point and short-circuited the power causing all the fridge and freezers to shut down damaging stock. The complainant has provided a report and invoice from ER which confirms multiple power points were water affected causing them to trip the power in the shop. The complainant has provided a photograph showing a power point that appears most likely to be under the 100mm. The panel acknowledges the insurer’s position that the complainant bears the onus to provide reasonable evidence that it was the stormwater and not the subsequent floodwater that caused the power tripping and associated damage to stocks in all the fridges and freezers in the shop. However, given the timing of the two events, the panel accepts it would be practically impossible to obtain such information. The complainant has provided a report from a specialist confirming the impact of water ingress to the electricals, photographic evidence of power points below 100mm. There is no dispute the stormwater ingress event occurred first and remained in place for close to 19 hours before the arrival of the floodwater. Neither the insurer or M has provided any persuasive information contrary to the complainant’s position or showing stormwater did not enter the power point(s) below 100mm resulting in tripping and short circuiting of power. Give the above, the panel is satisfied it is fair to accept stormwater will have entered the power point(s) causing the power to trip before the floodwater arrived. Further, that the complainant has provided reasonable information in support of his position in circumstances where sourcing such information it unlikely or difficult. It would be unfair to permit the insurer to reduce its liability as proposed in these circumstances. Accordingly, the insurer is to increase its settlement for the damaged to stock by $15,425 consistent M’s assessment and the insurer’s obligations under the policy. Determination | Case number: 991799 Page 6 of 8 2.2 Is the insurer required to increase its offer for BI? Yes. The policy provides cover for BI and the evidence shows the storm event most likely resulted in BI related loss independent of the flood event. The insurer is required to settle the complainant for 38 weeks of BI. Insurer says it is only required to pay BI up until arrival of the floodwaters There is no dispute there exists a loss that triggers cover under the pol icy’s BI benefits. The parties, however, differ significantly in their views on the amount of the BI settlement to be paid under the claim. The insurer has made extensive submissions regarding BI. In summary, the insurer says its liability in terms of BI cover is limited from initial storm event to the arrival of the floodwaters. The insurer says the proximate cause of the BI is the flood event and not the storm event. The insurer is of the view that because of the more significant flooding caused by the flood event, any loss due to the storm event becomes irrelevant. The insurer says its offer of $437 for BI related loss from the storm event is fair and reasonable, considering the facts relative to the terms and conditions of the policy and legal jurisprud ence. In the insurer’s opinion the BI caused by the storm event is limited to three hours. It says the stormwater ingress occurred around three before closing time (4.00pm) on 27 January 2022 and the floodwater arrived before the store was meant to open on 28 January 2022, this means an interruption of just three hours. The insurer also says the complainant failed to mitigate the loss. Complainant says insurer should cover 38 weeks of BI The complainant says the insurer should settle its BI claim based on the time it would take to reinstate the business back to its pre-trading revenue. The complainant has calculated this as follows:  twelve weeks to receive the final repair quote  four weeks to review quote, accept and sign the contracts and order materials  sixteen weeks to complete works  six weeks to return to the pre-loss revenue. The complainant says the 12-week timeframe to receive the final quote is based off the actual time it took to receive a quote from Q given the challenges in finding repairers and materials etc due to the significant event and the impact this had on sourcing assistance and materials. The complainant has provided an email from Q estimating the repair timeframe to be 14-16 weeks. The complainant says as the business is a health food store and is subject to codes, compliances and standards, it could not partially reopen without repairing all the damage. The panel notes the insurer has not provided any information to show these timeframes are incorrect or excessive in the circumstances. The panel accepts the impact of a significant weather does extend to finding experts, availability and costs of material as well as repair timeframes. Insurer is required to increase its BI offer It is accepted that when there are two concurrent proximate causes of damage, and the policy covers one cause and excludes the other, the insurer can rely on the exclusion to deny the Determination | Case number: 991799 Page 7 of 8 entire claim. However, when there are two independent proximate causes, the losses are treated separately. The panel agrees the insurer is not liable for any BI caused by the flood event, however the insurer is liable for BI caused by the storm event. The insurer accepts the storm and flood are two independent events which have caused loss and damage covered under the policy. The insurer accepts the storm event caused damage independent of the subsequent flood event. The panel notes the insurer’s substantial communications and documenta tion in support of its position to limit its liability to three hours based on the flood event excusing the insurer of its liability arising from the earlier storm event. However, the panel is not persuaded and is not satisfied this position to be fair, consistent with policy, the commercial intention of providing insurance cover or consistent with a common-sense approach. The panel accepts the storm event has independently and prior to the arrival of floodwaters caused significant property damage that is covered under the policy. Further, that this damage is sufficient to cause the store to cease operation pending repairs and reinstatement to its pre-event condition plus return to pre-loss revenue. Insurer to cover the complainant for 38 weeks of BI The panel is satisfied the insurer is obliged to cover the complainant under the BI policy benefit equal to the period it would take to repair the damage caused by the storm event. The complainant estimates the storm event resulted in 38 weeks of BI. The insurer has had multiple opportunities to calculate what BI the storm event would have caused independent of the flood event, however it has chosen not to do so. The insurer has not provided any information indicating the complainant’s proposed timeframes are unreasonable or incorrect. The complainant’s calculation for 38 weeks accounts for actual timeframes or delays experienced in being able to source scopes of works and repair quotes. The panel accepts it is not uncommon to experience difficulty and delays in locating assistance and materials after significant weather events and associated wide spread damage. In the absence of any other information, the panel considers it fair in the circumstances the insurer accepts the complainant’s claimed cover for 38 weeks of BI. The complainant is to co-operate with the insurer and make available any necessary and reasonable documentation/information, so to allow the insurer to calculate its liability in this regard. The insurer is to ensure this process and its claim settlement payments are to be made within 21 days of receiving notice of the complai nant’s acceptance of this determination. 2.3 Why is the outcome fair? The outcome is fair because the complainant has established a higher entitlement for claimable loss or damage due to the stormwater ingress event. The insurer has not established its assessment of its liability under the policy is fair or consistent with the policy and available information. Determination | Case number: 991799 Page 8 of 8 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. A panel determined this matter Due to the nature of this complaint, we referred it to a panel for determination. The panel includes:  an ombudsman  a member with significant experience in consumer and small business advocacy  a member with extensive experience as an industry representative. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. Other matters The panel notes the insurer’s assertion that the complainant has failed to mitigate its loss. However, on the available information, the panel accepts the complainant has remained reasonably active and there is no persuasive information to show a failure to or the extent of such failure to mitigate loss.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.