Home / Auto & General / Determination 990033

Determination 990033

Scope and cost of repairs after sewage inundation, further remediation, accommodation and compensation for delay

FirmAuto & General
Decided2024-03-14
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$188,831
Non-financial loss$2,000
Amount claimed—
SourceAFCA PDF

Summary

The complainant's home was inundated with sewage and he disputed the scope of remediation, repair costs and delay. AFCA rejected further remediation and most extra repair items but ordered $188,830.86 plus interest, accommodation to 14 June 2024 and $2,000 non-financial loss.

The insurer's itemised quote was the most reliable estimate of repair cost, adjusted for omitted items and contingency, and the insurer was responsible for seven months of delay from failed remediation.

Issues

Subjects and remedies

home or building damagepay claimpay compensationpay interestpay non financial loss

Related

All Auto & General determinations · Find similar determinations

Text of the determination

Determination Case number 990033 Financial firm Auto & General Services Pty Ltd Determination | Case number: 990033 Page 2 of 12 Case number: 990033 21 February 2024 1 Determination overview 1.1 Complaint The complainant holds a home insurance policy with the financial firm (the insurer). He lodged a claim when his home was inundated with sewage on 14 November 2022. The insurer has:  stripped out and cleaned the home in preparation for repairs  obtained a quo te for $ 164,489.16 to repair the home  agreed to pay for the complainant’s accommodation to May 2024. The complainant says the insurer should pay for:  further stripping out and testing for contamination  further repairs (he has provided repairs quotes for $420,977 and $452,782.72)  accommodation for eight months after this determination is issued, to allow time for repairs  compensation for stress it caused by delaying and mismanaging the claim. 1.2 Issues and key findings Should the insurer cover further stripping out and testing? Tests by both parties’ experts show the home now has a normal microbial environment. The insurer is not required to cover further stripping out or testing. Should the insurer pay more for repairs? The insurer’s repair quote is the best available estimate of the cost of repairs. Therefore, the claim settlement should be based on this quote. However, the insurer should pay extra for:  external painting ($5,580.26)  replacement of the garden shed ($1,595)  contingency for potential variations (10% of the estimated repair costs). The insurer should settle the claim for building damage by paying $188,830.86, plus interest from 24 October 2023 (the date of the insurer’s repair quote). Should the insurer pay other compensation? The insurer was responsible for a delay of about seven months. The insurer should pay:  the cost of the complainant’s accommodation for seven months after the policy limit for accommodation is exhausted (i.e. to 14 June 2024)  $2,000 compensation for non-financial loss. Why is the outcome fair? The insurer is liable for the cost of repairing the complainant’s home. With the available information, the best estimate of the cost of repairs is $188,830.86. The panel is satisfied that this determination provides the fairest possible outcome, based on the available information. Determination | Case number: 990033 Page 3 of 12 1.3 Determination The determination is mostly in favour of the insurer. Within 14 days of being informed of the complainant’s acceptance of this determination, the insurer must pay the complainant:  $188,830.86, plus interest at the rate determined under section 57 of the Insurance Contracts Act 1984 (Cth) from 24 October 2023, in settlement of the claim for building damage  the cost of the complainant’s accommodation to 14 June 2024  $2,000 compensation for non-financial loss. Determination | Case number: 990033 Page 4 of 12 2 Reasons for determination 2.1 Should the insurer cover further stripping out and testing? Tests by both parties’ experts show the home now has a normal microbial environment. The insurer is not required to cover further stripping out or testing. First round of remediation was incomplete On 14 November 2022, the complainant’s home was inundated with sewage. The same day, he lodged a claim with the insurer. The insurer arranged a strip out, drying, and mould remediation. The insurer appointed a hygienist (EHS), who inspected the home on 21 February 2023. EHS concluded the mould had ‘ returned to a pre-event condition ’. The insurer appointed another hygienist (VAS), who inspected the home on 10 March 2023. VAS found evidence o f ‘abnormal’ microbial growth in the kitchen and one of the bedrooms. VAS recommended further remediation, followed by post-remediation verification. The complainant appointed a hygienist (MS), who inspected the home on 31 March 2023. MS produced a report saying: ‘ bacteria and Mould swabs returned with elevated numbers ’. The report did not say what the elevated numbers were, or where they were found. The complainant provided a lab report dated 2 April 2023 saying fungal growth was detected on a sample from the bathroom door jamb, but not on any other samples. Subsequent remediation was successful The insurer arranged further remediation. VAS returned to the home on 4 September 2023 for post-remediation verification. VAS said: Unfortunately we cannot pass the job at this stage however only need some very minor additional works to obtain clearance. The insurer arranged the additional work (a wipe-down clean of the timber base plates in the bathroom), which was done on 12 September 2023. VAS returned to the home on 22 September 2023 for post-remediation verification. VAS concluded the home had a ‘ normal microbial ecological environment ’, and no further remediation was needed. VAS issued a post-remediation verification certificate on 27 September 2023. Insurer not liable for further remediation The complainant said mould could have contaminated the plaster and roof truss frame. He said VAS did not test these areas. He said all plaster and insulation in the home (including the ceiling) should be stripped out and the home should be retested. MS returned to the home on 7 October 2023. MS took samples from several areas, including from plaster and timber in the ceiling void. MS said all samples were ‘condition 1’, which indicates ‘normal fungal ecology’. MS said they ‘w ould recommend the removal of all insulation ’, and the test results ‘ may be enough to justify the removal of the ceiling ’. This makes no sense . MS did not explain why Determination | Case number: 990033 Page 5 of 12 they would recommend these or any other remediation measures when all tests showed the home had normal fungal ecology. The complainant has not provided any other information indicating VAS’ findings should not be accepted. The complainant’s home was inundated with sewage , which can cause abnormal and dangerous microbial activity . T he complainant was understandably concerned about this. However, the insurer arranged several rounds of remediation. Both parties’ experts tested samples from the home, and all tests indicate the home now has normal microbial activity. In the circumstances , it would not be reasonable to require the insurer to arrange or pay for further remediation or testing. 2.2 Should the insurer pay more for repairs? The insurer’s repair quote is the best available estimate of the cost of repairs. Therefore, the claim settlement should be based on this quote. However, the insurer should pay extra for:  external painting ($5,580.26)  replacement of the garden shed ($1,595)  contingency for potential variations (10% of the estimated repair costs). The insurer should settle the claim for building damage by paying $188,830.86, plus interest at the rate determined under section 57 of the Insurance Contracts Act 1984 (Cth) from 24 October 2023 (the date of the insurer’s repair quote) . Claim to be cash settled The policy says the insurer can settle a claim by repairing damage or by paying the reasonable cost of repairs. The insurer offered to appoint a builder to repair the property. However, the complainant says he wants a cash settlement because he does not trust the insurer or its contractors. The insurer cannot repair the property without the complainant’s consent. Therefore, the insurer must settle the claim by paying the reasonable cost of repairs. Both parties obtained repair quotes The insurer has provide d quotes for the following amounts (including 20% builder’s margin and 10% GST):  $113,257.77, builder BBS, 4 April 2023  $164,489.16, builder JPF, 24 October 2023. The insurer says JPF’s quote is fair and reasonable. The complainant said he wanted the insurer to pay for a full demolition and rebuild of his home. He provided the following estimates for a full demolition and rebuild:  $481,157.16, building consultant CB, 21 November 2022  $880,349.80, builder TC, 8 May 2023. The complainant is no longer insisting on a full demolition and rebuild. The complainant has provided the following estimates for repairs (including 15% builder’s margin and 10% GST):  $452,782.72, builder TC, 13 October 2023  $420,977, builder RM, 27 October 2023. Determination | Case number: 990033 Page 6 of 12 Insurer not required to pay more for pool JPF’s quote allows $9,688.80 (including 20% builder’s margin and 10% GST) for the following work to the pool:  pool cleaning and drainage  acid clean and flush plumbing system  remove and replace sand to pool filter  remove and replace solar matting  remove and re-level uplifted pavers. The complainant’s quotes allow approximately $100,000 for the removal and replacement of the pool’s inner surface, and the demolition and reconstruction of all landscaping around pool. The complainant has provided a quote from a pool technician (LP) dated 14 January 2023. The quote says the pool surface has to be replaced because ‘ the waste has now been absorbed into the render ’. It does not say how LP determined the render was damaged. It does not say whether LP inspected the pool. The complainant appointed an engineer (DS), who inspected the property on 9 May 2023. DS said: [The pool] appears to be still structurally sound but needs proper cleaning and should be stripped back to the shell to inspect if any cracks are developing. Also, near and around the pool coping, some of the pavers seem to have dropped, relative to the pool. The insurer appointed a pool technician (BPS), who inspected the pool in or about October 2023. BPS provided an undated report, which said:  they could not inspect the pool’s inner surface because the pool was full of dark green water. They ‘ would not expect contaminated water to damage a pool surface ’. If the pool had contaminated water, they would recommend draining, pressure washing, and acid washing  the pool equipment was working. However, if contaminated water was pumped into the filter, the pool filter and solar matting should be replaced  some pavers around the pool appear to have shifted, but they could not tell whether this was because of the sewage leak. The complainant says BPS was at the property for less than seven minutes, and had no testing equipment. LP said waste had been absorbed into the pool surface, but did not say what evidence indicated this. DS did not find any damage to the pool surface. BPS said they could not inspect the pool surface, but they would not expect contaminated water to damage it. Having considered the information provided by both parties, the panel is not satisfied the pool surface needs anything other than cleaning. JPF’s quote includes cleaning. The available information indicates the only damage to landscaping around pool is the movement of some pavers, and it is not clear whether the sewage leak caused this. JPF’s quote includes re-levelling of the pavers. The available information does not show the pool area needs repairs not included in JPF’s quote. Therefore, the insurer is not required to pay for more for repairs to the pool area. Determination | Case number: 990033 Page 7 of 12 Insurer not required to pay for slab cracks DS, who inspected the property on 9 May 2023, took photographs showing cracks in the concrete slab. DS said the slab had moved ‘ due to the extensive and localised flood event ’, and the cracks were ‘ mainly due to shrinkage and heaving from the water drying effect ’. The insurer appointed an engineer (ECE), who inspected the property on 11 July 2023. ECE said:  the slab cracks had chipped and rounded edges. This meant they had existed ‘ for an extended period of time ’  some cracks appeared continuous, but closer inspection revealed they were discontinuous (i.e. what appeared to be a single crack was actually multiple cracks in the same direction). This is characteristic of shrinkage cracks that develop as concrete cures. ECE concluded the slab cracks were not caused by the sewage leak, but occurred soon after the concrete was poured. DS did not say what evidence supported their conclusion that the slab cracks were caused by the sewage leak. ECE gave reasons for their conclusion that the slab cracks occurred soon a fter the concrete was poured. Because of this, the panel finds ECE’s report more persuasive. The available information does not show the sewage leak damaged the slab. Therefore, the insurer is not required to pay for repairs to the slab. Insurer not required to pay for external wall cracks The complainant says cracks formed in the external walls of his home because of the drying equipment used by the insurer. ECE said the external wall cracks had chipped and rounded edges, and were full of cobwebs. ECE concluded the cracks were not related to the sewage leak. The complainant has not provided any information to refute ECE’s findings. The available information does not show the sewage leak caused the external wall cracks. Therefore, the insurer is not required to pay for repairs to the cracks. Insurer must pay $5,580.26 for external painting JPF’s quote allows $18,000.84 (including builder’s margin and GST) for internal painting, but nothing for external painting. The complainant says the outside of the house was damaged by the sewage leak, and needs to be painted. CB ’s report said the exterior of the house was ‘engulfed in sewage’. BBS’ quote said the external doors needed to be painted on both sides. The insurer has not provided any information indicating the exterior was not damaged. In the circumstances, the panel considers it fair for the insurer to pay for external painting. TC’s quote allows $31,625 (including builder’s margin and GST) for internal and external painting. It does not say how much of this is for external painting. RM’s quote allows $29,221.50 (including builder’s margin and GST) for internal and external painting. It does not say how much of this is for external painting. CB’s scope of works estimates internal painting will cost $12,556.20 ($ 11,414.73 plus GST) external painting will cost $3,850 ($3,500 plus GST). This indicates the external painting will Determination | Case number: 990033 Page 8 of 12 cost about 31% of the cost of the internal painting. JPF’s quote allows $18,000.84 for internal painting. The insurer should pay 31% of this amount ($5,580.26) for external painting. Insurer must pay $1,595 for shed The complainant says the insurer refused to replace the garden shed ‘ after it has been scoped previously’. None of t he insurer’s scopes of work included the shed. When the complainant lodged the claim, he said the shed had been inundated to 300mm. The insurer has not provided information indicating it inspected the shed. It does not dispute that the shed was inundated with sewage. It has not explained why it had not offered to pay for it. In the circumstances, the panel considers it fair for the insurer to pay for the shed. The complainant’s repair quotes include replacement of the shed, but do not say how much it will cost. CB’s scope of works estimates it will cost $1,595 ($1,450 plus GST). The insurer should pay $1,595 for the shed. Insurer not required to pay for other items The complainant says JPF’s quote allows for the reinstatement of ‘contaminated’ doors and bathroom fixtures. However, the available information does not show these items are contaminated. Furthermore, the complainant’s repair quotes also allow for the reinstatement of existing doors and bathroom fixtures. The complainant says JPF’s quote allows for the supply of ‘inferior’ air conditioning. JPF’s quote allows for the replacement of two air conditioning condenser units. This would repair the existing air conditioning system, not replace it with an inferior one. The complainant says the insurer should pay for other items, including:  misalignment of the entire boundary fence (JPF’s quote only includes the cost of replacing the bottom plinth)  termite damage to timber base plates  compressed sheeting in the studio damaged during restoration  sisilation paper loosened during restoration. The available information does not show these items are damaged. Insurer’s quote more reliable than complainant’s quotes The complainant ’s quotes are much higher than the insurer’s. The complainant’s quotes are not fully itemised; they list the work to be done, but do not list the cost of each work item. This makes it difficult to assess why they are higher than the insurer ’s quote s, which are fully itemised. The complainant’s quotes include major work items that have not been shown to be necessary to repair claim-related damage, including:  demolition of the pool surface and all landscaping around the pool  removal of all ceiling linings  repairs to cracks in the slab and external walls. JPF’s quote does not include external painting, or the replacement of the garden shed. The panel has found the insurer should pay for these items. However, these items are relatively minor. Overall , the panel believes JPF’s quote is more reliable than the complainant’s quote s. Determination | Case number: 990033 Page 9 of 12 Insurer must pay contingency for potential variations The complainant says that if JPF started repairs, they would submit variations increasing the cost of repairs. If JPF started repairs, and found this required work not included in its quote, it could submit a variation for the extra work to the insurer. If the variation was justified, the insurer would have to pay for the extra work. The damage to the complainant’s home is widespread. Repairs will require extensive work by several different trades. For these reasons, the panel considers it likely there would be a variation during repairs. The panel believes it is fair for the insurer to pay a contingency for potential variations. The panel considers a fair contingency would be 10% of the estimated cost of repairs. Best estimate of cost of repairs is $188,830.86 For the above reasons, the panel considers the settlement to be paid for the cost of repairs should be calculated as follows: Item Amount JPF’s quote $164,489.16 External painting $ 5,580.26 Garden shed $1,595 Subtotal $171,664.42 Contingency for potential variations ( 1 0%) $ 17,166.44 TOTAL $ 188,830.86 Insurer must pay interest JPF’s quote is dated 24 October 2023. Building costs are likely to have increased since then. To account for this, the insurer should pay interest from 24 October 2023. The insurer should settle the claim for building damage by paying $188,830.86, plus interest at the rate determined under section 57 of the Insurance Contracts Act 1984 (Cth) from 24 October 2023. 2.3 Should the insurer pay other compensation? The insurer was responsible for a delay of about seven months. The insurer should pay:  the cost of the complainant’s accommodation for seven months after the policy limit for accommodation is exhausted (i.e. to 14 June 2024)  $2,000 compensation for non-financial loss. Insurer responsible for delay of seven months On 14 November 2022, the complainant lodged the claim. Determination | Case number: 990033 Page 10 of 12 On 2 December 2022, the insurer said it was trying to arrange remediation, but this was difficult ‘ due to the current influx of storm and flooding events ’. The insurer’s notes indicate remediation started on 12 January 2023, and was expected to be completed by 17 February 2023. However, because the first round of remediation was not completely successful, remediation was not completed until 12 September 2023. The initial failure of the remediation delayed repairs by approximately seven months. As the remediation was performed by the insurer’s contractors, the insurer is responsible for this delay. Complainant did not allow repairs after remediation The insurer offered to appoint a builder to repair the property. This could have started after the post-remediation verification certificate was issued on 27 September 2023. However, from June 2023, the complainant said he wanted his home completely demolished and rebuilt. On 31 October 2023, the complainant said he was no longer seeking to have his home demolished. However, he said he wanted further remediation work done before any repairs. He also said he wanted the insurer to cash-settle the claim (instead of appointing a builder to repair the property) because he did not trust the insurer or its contractors. Demand for demolition was not justified The first round of remediation was mostly successful. Three hygienists inspected the property after the first round of remediation. EHS said the mould had ‘ returned to a pre-event condition ’. VAS found e vidence of abnormal microbial growth in only two rooms. MS found fungal growth on only one sample. After the second round of remediation, the only outstanding issue was that the bathroom base plates needed to be cleaned. The insurer arranged this cleaning the next week. After this, tests by both parties’ experts confirmed the home had a normal microbial environment. The complainant had reasonable concerns about contamination after his home was inundated with sewage. These concerns grew when the insurer enco untered delays in arranging remediation. However, the first round of remediation removed most of the abnormal microbial activity from the home. While some tests showed further remediation was required, they never suggested the home was so severely contamin ated that it should be demolished. Insurer not responsible for delay after September 2023 After September 2023, repairs were delayed because the complainant:  demanded the insurer pay the cost of having his home demolished and rebuilt  said he wanted further remediation work done before any repairs  asked the insurer to cash-settle the claim instead of arranging repairs. These factors were not the insurer’s fault. The available information indicated the home was repairable, and the insurer was willing and able to complete repairs. The insurer is not responsible for the delay in repairs after September 2023. Insurer agreed to extend accommodation cover by seven months The policy says the insurer will not cover accommodation costs for more than 12 months after damage occurs (i.e. after 14 November 2023). Determination | Case number: 990033 Page 11 of 12 On 8 August 2023, the insurer told the complainant : ‘ due to the ongoing delays your claim has had, we have agreed to extend your accommodation past the 12 month mark should it be required ’. The insurer subsequently agreed to cover the complainant’s accommodation to May 2024. For the reasons set out above, the insurer was responsible for a delay of approximately seven months (from February 2023 to September 2023). Therefore, after the policy limit is exhausted (after 14 November 2023) , the insurer should pay the cost of the complainant’s accommodation for an additional seven months (to 14 June 2024). Insurer must pay compensation for non-financial loss Under the AFCA Rules, we can award up to $5,400 compensation for non-financial loss if a complainant suffered an unusual degree of stress, inconvenience, or delay because an insurer mishandled a claim. We do not award compensation for the usual amount of inconvenience involved in making a claim. We do not award compensation for delays caused by the complainant, or other factors outside the insurer’s control. The complainant’s home was inundated with sewage. The home needed stripping out, drying, and mould remediation to prepare it for repairs. The home has been uninhabitable since it was damaged, and still needs extensive repairs before it is habitable again. For these reasons, the complainant has suffered severe stress and inconvenience, and would have done so even if the insurer handled the claim perfectly. As stated above, the insurer was responsible for delaying repairs by approximately seven months. This added to the complainant’s stress and inconvenience. The panel believes this warrants compensation for non-financial loss in the sum of $2,000. 2.4 Why is the outcome fair? The insurer is liable for the cost of repairing the complainant’s home. With the available information, the best estimate of the cost of repairs is $188,830.86. The panel is satisfied that this determination provides the fairest possible outcome, based on the available information. Determination | Case number: 990033 Page 12 of 12 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. A panel determined this matter Due to the nature of this complaint, we referred it to a panel for determination. The panel includes:  an ombudsman  a member with extensive experience in consumer and small business advocacy  a member with extensive experience in insurance. Complainant represented by family member or friend At times during the course of this complaint, the complainant was represented by a family member or friend. In this determination, statements by the complainant’s representative are treated as if they were made by the complainant.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.