Home / Auto & General / Determination 989957

Determination 989957

Cash settlement amount for flood damage repairs, including whether upgrade of non-habitable ground floor to current code was required

FirmAuto & General
Decided2024-03-28
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$210,248
Non-financial loss—
Amount claimed$446,109
SourceAFCA PDF

Summary

The complainant's flood claim was partly settled, and he sought the cost of rebuilding to current standards including upgrading the ground floor to habitable. AFCA found the insurer need not upgrade the area but must increase the cash settlement to include the laundry, toilet and shower, to $210,247.54 plus interest.

The policy only requires repair to pre-loss condition (non-habitable ground floor), not improvements, but the insurer wrongly excluded the laundry, toilet and shower, which were accepted as compliant non-habitable rooms.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interest

Related

All Auto & General determinations · Find similar determinations

Text of the determination

Determination Case number 989957 Financial firm Auto & General Services Pty Ltd Determination | Case number: 989957 Page 2 of 7 Case number: 989957 27 March 2024 1 Determination overview 1.1 Complaint The complainant lodged a claim under his home and contents policy following flood damage to his property on 28th February 2022. While part of the claim has been settled the complainant is wants the insurer to cover the cost to repair the home to current building standards. The insurer says the complainant’s quote of $446,109.31 and scope of works included upgrades to the downstairs area. The insurer has offered a cash settlement of $173,449.47 based on a quote from OSB of $150,825.63 plus a 15% contingency fee. The insurer says that it is only required to repair to the same specification and standard as it was when it was new, which would satisfy the relevant and applicable building and code requirements. It says the policy does not respond to altering the configuration of the home. 1.2 Issues and key findings Has the insurer correctly assessed the claim? Yes. The insurer has correctly assessed the ground floor area as non-habitable. The insurer is only required to restore the building to its pre-loss condition and is not required to upgrade the ground floor area to make the rooms compliant habitable rooms. Is the insurer required to increase its settlement? Yes. The insurer should increase the settlement offer to include the shower, laundry and toilet. The insurer is required to increase its settlement offer to $210,247.54 based on the original quote from GIB of $175,206.29 with a 20% ($35,041.25) uplift for contingencies. Why is the outcome fair? The outcome is fair as it would allow for the repair of the damaged area to a standard compliant with the relevant building requirements and consistent with the terms of the policy. 1.3 Determination This determination is partially in favour of the complainant. Within 14 days of receiving notification that the complainant accepts this determination the insurer is to:  pay the complainant $210,247.54 plus interest pursuant to section 57 of the Insurance Contracts Act 1984 (Cth) from 20 September 2022 to date of payment of the claim. Determination | Case number: 989957 Page 3 of 7 2 Reasons for determination 2.1 Has the insurer correctly assessed the claim? Yes. The insurer has correctly assessed the ground floor area as non-habitable. The insurer is only required to restore the building to its pre-loss condition and is not required to upgrade the ground floor area to make the rooms compliant habitable rooms. The complainant established a valid claim The complainants home and contents policy is an ‘insured events’ policy and includes optional cover for flood and accidental damage. The complainant ’s property is in Wilston, QLD which was impacted by flood in late February 2022. The complainant lodged a claim with the insurer on 28 February 2022 under his home and contents policy, which provides cover for flood. There is no dispute that the loss was caused by an insured event under the policy terms. The issue in dispute is the extent of the insurer ’ s liability. Circumstances of the claim The issues relate to the lower/under floor area. The property is a typical Queenslander which has had the underfloor converted into non-habitable rooms. The main dispute is whether the insurer is required to upgrade this area to make them compliant habitable rooms. The secondary issue is whether the insurer’s SOW and quote, together with an uplift, is sufficient to discharge its liability. There are other areas of damage, e.g. the pool, but it appears that these have been satisfactorily settled, so this determination will deal with the extent of the insurers liability. The complainant obtained a quote from builder GIB on 6 September 2022 to rebuild the home to its original condition which came to $175,206.29. The quote notes that the existing lower level does not comply with the Brisbane City Council City Plan, Queensland Development Code, National Construction Code and Australian Standards. Any work performed as a like- for-like scenario would void any implied statutory warranty and liability. GIB subsequently provided a further quote on 13 October 2022 to rebuild the home to current code including raising the home and upgrade the ground floor, for $446,109.31. The complainant says the construction of the house (pre-1946) and all subsequent renovations have been conducted in accordance with the regulatory requirements of the time, including the habitable floor areas downstairs. The complainant wants the insurer to comply with the requirements of the PDS and “ ensure the repaired or rebuilt parts of your home comply with current building regulations and laws." The insurer says the internal ceiling height of the ground floor is below the required height for a habitable room and below the requirements of the Building Code of Australia 1990. The insurer says measurements of the ceiling heights were taken during the assessment by the its builder and assessor which confirms the room ground floor room heights are non-complaint for habitable rooms, or meet the minimum ceilings heights for the bathroom, toilet or the mud room. The insurer says the policy allows a cash settlement to repair the damaged property to the same standard, specification, or quality as it was when it was new. Therefore, it says it is only required to ensure the home is rebuilt to the same specification and to ensure the lower level Determination | Case number: 989957 Page 4 of 7 is built to code for a storage space. The insurer offered a settlement of in the sum of $150,825.63 with a 15% uplift equalling $173,449.47. The complainant rejected this as he says the ground floor of his home habitable at the time it was built as the National Construction Code (NCC) was not in force at the time of build which was prior to 1946. The complainant says there is no reasonable evidence to support that the downstairs area was not classified as habitable at the time works were carried out. This is because the: - council inspected the building and certified the plans with no pushback - NCC code was adopted in Queensland on 1 st January 1992 and the ground floor was constructed prior to this date as a compliant habitable space with two bedrooms, living, garage, laundry, bathroom and storage area. - plans provided show a partial layout for downstairs showing a laundry and toilet - 1996 plans in red pen applies to the storage area underneath the stairs, not the entire area. - home owners are not required to update their homes every time the NCC updates its code Under the policy, the complainant argues the insurer has an obligation to repair or rebuild parts of the home to comply with current building codes and regulations. Insurer says it has correctly settled the claim The insurer says the dispute is not about whether the home is built to code or not built to code rather whether there is an obligation for the insurer to change the structure to allow for occupancy and rebuilding to a habitable area. Whilst it accepts the requirement to ensure repaired or rebuilt parts of the home comply with current building regulations and laws, it says this does not respond to altering the building configuration to allow for a fundamental change in the dwelling. The insurer says the downstairs area can be rebuilt to original code but not classified as habitable rooms as they were not classified as habitable prior to the event, and the policy does not respond to upgrading the home. As the home can be rebuilt with the same space, there is no obligation under the policy change the structure to allow for occupancy, as this was not the original configuration of the home. Ground floor area not built to code for habitable areas It is accepted by all parties there are no original building plans given the age of the dwelling when it was first built. The historical building records, such as they are, show that the lower level was an approved structure, within regulations, but only so far as the rooms were non- habitable. The key issue is the height of the rooms, which are well short of the minimum required. The records also show the approval was initially for the area to be used as a storage area, at least in part. Although the current partitioned, lined rooms appear to be compliant for building purposes, there is no evidence to show that these rooms were compliant as habitable rooms. The key experts are OSB, who carried out the initial assessment, SOW and quote, and PG who carried out a detailed review and analysis of the property and the applicable building regulations. There is no doubt that the lower area does not currently constitute a habitable space, however it is also clear that these rooms are capable of being brought back to their pre-loss state, without the need to have them meet the ‘habitable’ requirements Determination | Case number: 989957 Page 5 of 7 PG says a habitable room are required to have a room height not less than 2.4 meters and bathrooms and laundry should not be less than 2.1 meters. Given the above, it says a multipurpose room, both utility rooms are classified as non-habitable in accordance with the NCC and are not defined as habitable rooms given the height is less than 2.1meters. Further, the workshop, laundry, bathroom and toilet cannot be defined as habitable as they also do not achieve the required height of 2.1m. The available information from PG suggests the lower level of the dwelling has several compliant non-habitable rooms under the NCC that cannot be classified or used as a habitable space. The complainant has provided a report from building expert NCC. This report states the requirements for a habitable room must have a minimum 2.4m vertical clearance when measured from the floor to the ceiling. Section 3.8.2.2 states a habitable room is defined as the following: In this information the height from ceiling to floor do not reach 2.4m and overall a height of 2.4m over two thirds of the floor area has not been achieved. This report does not assist the complainant to show the area should be defined as a habitable space. Insurer has correctly assessed area as non-habitable The panel has considered the available information and accepts the insurer has correctly determined the ground floor area was a non- habitable space. This is because: ‒ there is no documentation which suggests the ground floor of the property was converted to a habitable area ‒ the council documents in 1996 and 1992 do not suggest this area as being habitable ‒ the available reports confirm the ground floor area did not have a floor to ceiling height of 2.4m 2.2 Is the insurer required to increase its settlement? Yes. The insurer should increase the settlement offer to include the bathroom laundry and toilet. The insurer is required to increase its settlement offer to $210,247.54 based on the original quote from GIB of $175,206.29 with a 20% ($35,041.25) uplift for contingencies. Determination | Case number: 989957 Page 6 of 7 The insurer is not required to pay for improvements The policy provides is settling a claim the insurer will either: -  repair the damaged property to the same standard, specification, or quality as it was when it was new  replace the damaged property where available, or with the nearest equivalent property available in Australia  pay the amount it would cost it to repair or replace the property to ‘as new’ condition. There is nothing in the policy that would suggest the insurer is required to return the area to a habitable zone. The policy states it is required to bring these areas up to code and does not require the insurer to alter the configuration, rather return the home back to its prior condition. The panel accepts that the insurer is not required to cover improvements to the complainant’s building. The requirement is to repair the property to as new condition. Given the area was compliant for the purposes of a non-habitable area, and if restored to that standard would still be an acceptable non- habitable area, the insurer’s liability under the policy is only to restore the building to its pre-loss condition. Offer does not include laundry/toilet/shower As for the scope of the insurer’s offer, the difference between its scope and the GIB scope is the area consisting the laundry/toilet/shower. The insurer says this area was not compliant as functioning areas, so have been excluded. The panel does not agree. PG, in its report noted: The lower-level bathroom/laundry, toilet, and workshop have been previously approved and even though they are under 2.1m as the certifier has included them in the BA in 2006, and in accordance with Building Act 1975 Section 61, I would consider these rooms compliant. The shower area has not been through any approval process and I would not consider this to be a compliant installation for the building. The installation of a shower would also require plumbing approval, the waterproofing of the shower was not in accordance with AS3740-2010. Although approval may not have sought or been granted regulatory approval, they have since been accepted as compliant. This compliance appears to be as non-habitable rooms. Insurer is required to increase its settlement The quote provided by GIB includes the cost to repair the laundry/toilet/shower. The panel accepts that this quote should form the basis of the cash settlement. In the panels view the insurer should increase its offer of $173,449.47 to $210,247.54 based on the original quote from GIB of $175,206.29 with a 20% ($35,041.25) uplift for contingencies. Interest should be paid on the settlement of $210,247.54 from 20 September 2022 to date of payment of the claim pursuant to section 57 of the Insurance Contracts Act 1984(Cth). 2.3 Why is the outcome fair? The outcome is fair as it would allow for the repair of the damaged area to a standard compliant with the relevant building requirements and consistent with the terms of the policy. Determination | Case number: 989957 Page 7 of 7 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. A panel determined this matter Due to the nature of this complaint, we referred it to a panel for determination. The panel includes:  an ombudsman  a member with significant experience in consumer and small business advocacy  a member with extensive insurance industry experience We assess complaints on available information and circumstances AFCA is not a court of law We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.