Partial decline of flood claim for internal and external cracking damage as pre-existing or excluded foundation movement

FirmAllianz Australia
Decided2024-03-20
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainant claimed for flood damage to her home; the insurer accepted part and declined cracking damage as pre-existing or due to foundation movement. AFCA required the insurer to cover fresh internal cracks by repair or cash settlement plus 15% contingency, but upheld the decline for external and pre-existing damage.

Expert evidence showed external and slab cracking was pre-existing foundation movement, but the insurer failed to prove fresh internal wall and ceiling cracks were excluded, given 36 hours of inundation.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimrepair or rectify

Related

All Allianz Australia determinations · Find similar determinations

Text of the determination

Determination Case number 989092 Financial firm Allianz Australia Insurance Limited Determination | Case number: 989092 Page 1 of 5 Case number: 989092 14 March 2024 1 Determination overview 1.1 Complaint The complainant holds a home building insurance policy with the financial firm (insurer). The complainant lodged a claim for damage to her property following a flood event in February 2022. The insurer has partially accepted the claim offering the cash settlement of $151,488.84 for damage it has assessed to be due to the flood event. The insurer has declined to cover internal and external cracking damage it says it not related to or caused by the flood event. The insurer says this is pre-existing damage and/or due to circumstances excluded under the policy. The complainant says the cracks have developed in her property because of the flood and requests the insurer to pay for the cost to repair this damage. 1.2 Issues and key findings Is the insurer ’s assessment of its liability under the policy reasonable? No. The available information shows some of the internal cracking damage to the walls and ceilings is fresh and most likely due to the flood event. However, it is fair that the insurer be entitled to decline cover for the external walls, cracks to the concrete slabs, cracks to the patio flooring/tiles and areas which have been shown to have been previously patched by the complainant since purchasing the home. Why is the outcome fair? The outcome is fair because it is based on the information provided by the parties and the policy. It is fair to accept, in addition to the damage already accepted under the claim, the insurer is to cover the cost to repair the non-structural fresh internal cracking damage. It is also fair that the insurer be allowed to decline cover for what has been shown to be pre- existing damage and due to ongoing foundation movement. 1.3 Determination This determination is partially in favour of the complainant. Within 14 days of receiving notice of the compla inant’s acceptance of this determination, the insurer is to:  arrange for a suitably qualified builder to provide an actionable repair quote for the damage in the form of internal cracks to the walls, cornices and ceiling stress  the insurer at its discretion can either arrange for the repairs to be completed or alternatively cash settle the complainant for the cost of these repairs  if cash settled, the settlement is to be increased by a further 15% to allow for contingencies. Determination | Case number: 989092 Page 2 of 5 2 Reasons for Determination 2.1 Is the insurer ’s assessment of its liability fair? No. The available information shows some but not all the cracking damage to the internal walls and ceiling is fresh and most likely due to the flood event. However, it is fair that the insurer be entitled to decline cover for the external cracking, cracks to the concrete slabs, cracks to the patio flooring/tiles and areas which have been shown to have been previously patched by the complainant since purchasing the home. No dispute the complainant has established damage that triggers cover There is no dispute the insured property has suffered significant damage due to a flood event in February 2022. The insurer has accepted the claim and offered (cash settled) the complainant $151,488.84 towards damage it accepts to be consistent with the flooding event. The insurer has declined to cover for certain internal and external areas of cracking damage as well as sagging ceilings on the basis this is not damage caused by the flood event. The insurer says the excluded damage is not due to the flood. Rather, that it is old damage, and which has occurred over a long period of time due to foundation movement, which is excluded under the policy. Complainant says flood caused the cracks The complainant accepts the house did present with some movement damage before the flood event in February 2022, and that her home was not perfect. However, she says there are cracks that have appeared since the flood event, and the insurer should be required to cover all this damage. The complainant relies on her appointed engineering consultants ‘F’ who after completing an assessment has provided a report dated 17 April 2022. Th complainant points out that F says: Protracted floods events would be expected to cause soil saturation and softening at depth and this would be likely to exacerbate footing and slab settlements and house damages. Information from appointed consultants is reasonably consistent I acknowledge the complainant’s position and reference to the report from F. Ho wever, having reviewed this report in its entirety, I am not satisfied it supports a view that all the external and internal cracking damage claimed is due to the flood event. Rather, I am of the view most of the information in this report supports the ins urer’s position. I note F says:  it is highly likely that there has been long term consolidation of loose material under the footings predominantly at the east and south sides and this has caused the settlements and damages. It is also likely that the settlements and damages are ongoing  it is likely that the house settlements had been occurring from when the house was being constructed and have been ongoing ever since  t he house has severe differential settlements and damages, some of which are ongoing, and underpinning is required. The insurer appointed building consultants ‘J’ to inspect the insured building and determine the cause and extent of the damage. J has provided a report dated 4 May 2022 which notes Determination | Case number: 989092 Page 3 of 5 that there is damage consistent with the flood event as well as some water ingress damage due to maintenance related issues. J recommended the appointment of an engineer to determine the cause and extent of damage caused by the flood event. The insurer appointed engineering consultants ‘T’ who vis ited the insured property on 4 May 2022 (external inspection) and 17 October 2022 (internal inspection). T has provided two reports dated 18 May 2022 and 19 January 2023. With respect to its assessment of the external areas of the home, T says:  the site is located on the Brisbane River flood plain and as such the founding soils are alluvial, reactive and of poor quality  the Brisbane City Council Flood Awareness Map indicates the site was flooded in the January 1974 and January 2011 floods  there is a considerable body of evidence from the observations made during the inspection, that the movement damage to the external areas has occurred some time ago with evidence of previous repairs/patching  the head over the sliding glass door (observation 8) has been constructed in this position which indicates the movement had occurred prior to the enclosure of the original patio area  i n T’s opinion that the visible damage resulting from building movement is not due to the flood event in February 2022. Rather, that the evidence suggests the movement has occurred in the past as many of the cracks have been previously filled and patched. With respect to the internal damage in dispute, T says:  the level survey results for the internal areas show that the house has pre-existing fall from the front of the house to the rear, in particular the southeast corner of the house  there are cracks in the floor slab which have paint in the crack areas, indicating the cracks were pre-existent to the last renovation  cracks in gyprock ceilings were evident and were generally located in the areas where gyprock commonly cracks  most of the defects in the ceilings and cornice are due to the material movement created by the shrinkage and expansion of the gyprock ceilings, and the detailing of the expansion joints installed  the cause of the dropping sheets at the expansion joint is not known  the visible internal damage is not structural, has resulted from movement in the gyprock ceilings and has not been caused by the flood event in February 2022. Complainant accepts the insured building did have pre-existing damage I note the complainant says she purchased the property in 2014, at which time she was informed the property was in a flood plain, so she made sure to have flood cover. The complainant in her communications with the insurer and AFCA concedes that the insured building was not in perfect condition before the February 2022 flood event. Also, that prior to the flood event the insured building did present with movement damage, some of which has been patched in the past. However, the complainant says some of the cracks noted to the insured building have appeared after and due to the flood event, and therefore, should be covered by the insurer. Insurer has shown external cracking damage is not covered under the policy The insurer says all the excluded cracks have occurred because of soil movement over time, material expansion and gradual deterioration which the policy excludes. Determination | Case number: 989092 Page 4 of 5 I accept the insurer has provided reasonably compelling information in support of the view that all the external cracking to the brickwork, concrete slabs, patio tiles etc is not the result of the flood event. It is most likely this damage pre-existed the flood event with clear evidence of previous repair attempts. It is possible that the flooding event has exacerbated and/or re-opened the cracks, but I am satisfied the damage was already present and not covered under the policy. Insurer to increase cover under the claim to include fresh internal cracks I accept there exists damage within the home that has also been shown to most likely have been present prior to the flood event in 2022, this being cracking damage to the floor slab and the pre-existing fall (floor level issues) from the front to rear of the house. This damage is consistent with long term foundational movement and not the flood event. In saying that, I am not satisfied there is persuasive information to decline cover for the more recent and fresh internal cracking and distress to the ceilings, cornices and walls within the home. I note T says these cracks are in locations were gyprock commonly cracks, however, T has not provided any information to support and/or explain this. This comment alone, in my opinion, it not enough to show this damage to fall within the policy exclusions. I note T acknowledges the cause of the dropping sheets at the expansion joints is unknown and does not provide any evidence to show the cause to be excluded under the policy. Merely saying this damage is not due to the flood event, in the absence of any persuasive supporting information, is not adequate to establish this damage is excluded under the policy. There is no dispute the floodwaters remained within the insured building for around 36 hours. I accept it is reasonable to accept this is a significant period of inundation and that this will have caused and/or contributed to the fresh cracks noted to the walls and ceilings above the water inundation level. Having considered the available information, I am satisfied the internal cracks to the walls, cornices and ceiling distress (including the garage ceiling) appears to be fresh and recent damage. I am satisfied, in the absence of compelling information to the contrary, it is fair to accept this damage is due to the flood event, and the insurer has not been successful in showing an entitlement to decline cover for this damage. Insurer to increase level of indemnity offered under the claim In line with the above, within 14 days of receiving notice of the complainant’s acceptance of this determination, the insurer is to:  arrange for a suitably qualified builder to provide an actionable repair quote for the damage in the form of internal cracks to the walls, cornices and ceiling stress  the insurer at its discretion can either arrange for the repairs to be completed or alternatively cash settle the complainant for the cost of these repairs  if cash settled, the settlement is to be increased by a further 15% to allow for contingencies. 2.2 Why is the outcome fair? The outcome is fair because it is based on the information provided by the parties and the policy. It is fair to accept, in addition to the damage already accepted under the claim, the insurer is to cover the cost to repair the non-structural fresh internal cracking damage. It is Determination | Case number: 989092 Page 5 of 5 also fair that the insurer be allowed to decline cover for what has been shown to be pre- existing damage as well as that assessed to be due to ongoing foundation movement. 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.