Home / Auto & General / Determination 985568
Determination 985568
Insurer refused gutter/overflow works after storm damage to garage, cash settled internal repairs and delayed with inadequate quotes
Summary
A garage was storm damaged; the insurer accepted internal water damage but refused gutter/overflow works and offered a cash settlement. AFCA upheld the refusal of gutter works but required a higher cash settlement of $8,434.80 plus 20% and $500 compensation.
The gutter system was not storm damaged so no valid claim existed for it, but the insurer's quotes were inadequate so the cash settlement should be increased and compensation paid.
Issues
- Claim denial primary · not upheld
“The gutter/overflow system was not damaged by the storm. The complainant has therefore not established a valid claim for same.”
- Claim amount dispute secondary · upheld
“it is fair the insurer cash settles the complainant for internal damage for $8,434.80 plus a 20% mark up.”
- Poor claim handling secondary · upheld
“its repair quotes were incomplete, inadequate and not actionable.”
- Delay secondary · not upheld
“The insurer generally processed the claim in a timely manner.”
- Offensive or intimidating behaviour secondary · unclear
“The complainant says the representative was arrogant and impolite.”
Subjects and remedies
home or building damagenatural disasterpay claimpay non financial loss
Text of the determination
Determination
Case number 985568
Financial firm Auto & General Services Pty Ltd
Determination | Case number: 985568 Page 1 of 7
Case number: 985568 25 January 2024
1 Determination overview
1.1 Complaint
The complainant lodged a claim with the financial firm (insurer) after his garage sustained
storm damage.
The insurer accepted the claim for internal water damage and offered to cash settle the claim.
It refused to undertake additional works to the gutter/overflow system as recommended by
the roofer. The roofer considered the gutter/overflow was insufficient to cope with the amount
of water being discharged from the roof.
The complainant seeks the insurer to undertake the additional gutter/overflow works and
internal water damage repairs. He remains unhappy with the insurer’s claim delays.
1.2 Issues and key findings
Is the insurer entitled to deny works required to the gutter?
Yes. The gutters/overflow system was insufficient to cope with the amount of water
discharged from the roof. It did not sustain any storm or accidental damage. The complainant
has not established a valid claim in this regard. The insurer is not obliged to conduct works
required to prevent future water ingress.
Is the insurer entitled to cash settle the claim?
Yes. The insurer’s repairer refused to undertake the internal repairs until the recommended
works to the gutter/overflow system were first completed by the complainant as they were
unable to guarantee their repair works. The insurer should however increase the cash
settlement offer to the current revised repair estimate plus 20% mark up for contingency and
transfer of risk.
Is the insurer required to pay compensation?
Yes. The insurer generally processed the claim in a timely manner. However, its repair quotes
were incomplete, inadequate and not actionable. The insurer should pay $500 non-financial
loss compensation for the claim experience extended to the complainant.
Why is the outcome fair?
It would be unfair to expect the insurer to cover claims outside the agreed policy terms. The
insurer should pay compensation for its claim service.
1.3 Determination
This determination is substantially in favour of the complainant.
If the complainant accepts this determination, the insurer should settle the claim as detailed in
section 2.2 and also pay $500 compensation for non-financial loss. The insurer is entitled to
deny the claim for roof works.
Determination | Case number: 985568 Page 2 of 7
2 Reasons for determination
2.1 Is the insurer entitled to deny works required to the gutter?
Onus on the complainant to establish a valid claim
The complainant is required to show, on the balance of probabilities (that it is more likely than
not), that he suffered a claimable loss under the policy. This means he must show the loss
was caused by a risk for which he is insured. This is referred to as a valid claim.
Once the complainant proves the existence of a claimable loss, the insurer is liable for the
loss unless it shows an exclusion or limiting condition applies. The insurer has the onus of
proving on the balance of probabilities the application of the exclusion or condition.
Policy cover is subject to terms, conditions, and exclusions
There is no dispute among the parties the complainant received a copy of the policy
documents. The insurer is therefore entitled to rely on the terms of the policy in assessing the
subject claim.
The policy covers storm and accidental damage to the property. There is no dispute among
the parties the garage sustained storm damage. Even though there was no storm created
opening, and the same area had sustained similar damage about 12 months prior to the
current loss event, the insurer considered the complainant was most likely unaware of the
issues with the gutter. Therefore, the insurer accepted liability for internal water damage.
Gutter/overflow system did not sustain damage
The insurer would be obliged to repair the gutter/overflow system if it sustained
storm/accidental damage. The available information from the roofer confirms the existing
system was insufficient to cope with the water discharged from the entire roof. The
gutter/overflow system was not damaged by the storm.
The complainant notified the insurer that the same area had sustained water damage a year
prior to the current event. This was the subject of a claim with another insurer. The claim was
accepted, and the damage repaired.
The builder’s assessment report notes there was evidence of pre -existing water ingress
indicated by water staining in the plaster. It was brittle from water exposure.
Roof report dated 16 February 2023:
Damages to the ceiling were pointed out. It was explained a similar failure
occurred approximately 12 months ago. The advice provided was to install gutter
guard and spreaders. The damages are consistent of overflow.
Inspections of the roof and ceiling above the affected area revealed the sump is
well under sized at 50mm deep and 300mm long, the minimum requirement is
150mm deep x 400mm long.
The high level overflow is not configured in accordance with the standards with no
spill way and terminates back into the storm water via a rain head instead of
atmosphere.
Determination | Case number: 985568 Page 3 of 7
Creating even more flow restrictions is the new gutter guard installed, the gutter
guard conceals the already inadequate overflow shifting the blockage / overflow
point to the box gutter and into the ceiling.
Further exacerbating the issue is the upper roof catchment which is in excess of
75sqm discharges via 2 spreaders, the maximum permitted per spreader is
15sqm. This high volume flows into the high end of the box gutter with a depth of
only 40mm, the minimum requirement is 75mm.
The damages are the result of the above installation defects.
Please note, the original design appears to have been altered reducing the box
gutter depth.
…
NOTE:
Buildings constructed prior to 1990 do not have to comply with AS/NZS 3500.3
Buildings constructed prior to 1992 do not have to comply with AS HB 39
Any alterations or replacements after the above years must comply with the
current standards.
The additional works recommended by the roofer would likely prevent future water ingress
into the garage. The responsibility remains with the complainant to ensure the gutter/overflow
system is adequate.
The parties have argued whether the gutter/overflow system met the required building codes
and standards. This is not relevant to this complaint. The insurer is only required to respond
to this area if it sustained storm/accidental damage. I do not accept it did. Instead, the issues
identified are to do with its pre-existing state prior to the claimed event and to mitigate the
issues happening again. The policy does not respond in such circumstances.
Insurer not obliged to undertake additional works to gutter/overflow system
The gutter/overflow system of the property did not sustain storm or accidental damage. The
complainant has therefore not established a valid claim for same. The insurer is not obliged to
take additional works, even if the complainant is willing to pay for such works.
2.2 Is the insurer entitled to cash settle the claim?
Insurer entitled to cash settle repairs
The policy allows the insurer to choose the claim settlement options:
How we settle your claim
Determination | Case number: 985568 Page 4 of 7
If we agree to pay a claim for loss, theft, or damage to your home, contents, or
personal effects, we will pay up to the limits stated in your policy documents.
Following discussion with you, we will choose to do one of three things:
repair the damaged property to the same standard, specification, or quality
as it was when it was new
replace the damaged property where available, or with the nearest
equivalent property available in Australia
pay you the reasonable amount it would cost to repair or replace the
property.
In the complainant’s case, the insurer’s repairer refused to undertake repairs to the internal
damage until the complainant completed the additional works recommended to the
gutter/overflow system.
The insurer provided several opportunities for the complainant to conduct these works.
However, the parties challenged the issues discussed above regarding the construction
satisfying the relevant building codes and this issue remained unresolved.
Considering the circumstances surrounding this claim and dispute, it is fair the insurer chose
to cash settle the complainant for the repairs. This would have also avoided any delays with
the claim process.
Insurer should increase its cash settlement offer
The insurer, i n response to AFCA’s initial request, indicated the claim for internal damage
would be cash settled for $6,800.64. This offer contained a 15% mark-up for contingency and
transfer of risk.
In rejecting the preliminary assessment provided by this service, the complainant argued that
the builder had indicated the repairs for internal works would be $8,338.44. He provided text
messages from the builder dated 1 August 2023 confirming this amount.
As the builder had initially refused to conduct works to the gutter/overflow system, it was
unclear why the amount quoted to the complainant was higher than the amount proposed by
the insurer. Further, the builder’s qu ote relied upon by the insurer initially amounted to
$4,606.80 and did not match the initial cash settlement offer of $6,800.64.
The insurer obtained a revised quote from the builder recently which amounted to $8,434.80.
The insurer is willing to add another 15% mark up as the final settlement. The builder’s email
states the quote has been updated to reflect the current cost of repairs and items missed from
the original quote.
The complainant remains disappointed with the insurer and says it had attempted to settle the
claim for a lower value and would have done so if he had not raised the issue about the
settlement amount.
The insurer’s initial quote was incomplete and not actionable. However, I am satisfied the
insurer’s current quote is actionable and complete. A mark up for contingencies and transfer
of risk is offered. This accounts for the loss of repair warranty under the policy and the risk of
the works transferring to the complainant.
Determination | Case number: 985568 Page 5 of 7
Considering all of the above, it is fair the insurer cash settles the complainant for internal
damage for $8,434.80 plus a 20% mark up. I am satisfied this would cover the risks
discussed above.
2.3 Is the insurer required to pay compensation?
AFCA may award compensation in certain circumstances
Under paragraph D.3 of the AFCA Rules, we may award compensation for non-financial loss
(capped at $5,400) where the insurer’s actions have caused an unusual amount of:
physical inconvenience
time taken to resolve the situation
interference with the complainant’s expectation of enjoyment or peace of mind.
We take a conservative approach to compensation and expect a complainant to bear a
normal degree of inconvenience during a claim. When considering non-financial loss
compensation AFCA looks at what is reasonable and fair in all the circumstances. In
considering what is fair in all the circumstances, it is appropriate to factor the overall claims
experience, rather than focusing on specific individual events.
Complainant is entitled to compensation
T he complainant remains unhappy with the insurer’s service and claim delays.
The insurer says its handling of the claim was reasonable. This is because the claim was
lodged in February 2023 and the complainant was notified of the claim approval and
additional works required to be completed following attendance within three weeks.
The insurer made two offers ($1,000 and $1,300) to resolve the complaint which the
complainant refused to accept. The insurer subsequently withdrew all offers made in this
regard.
The complainant says the insurer misled him about the gutter/overflow not meeting building
standards. He had to chase up a response from his builder who was under liquidation. He
believes the standards quoted by the insurer do not apply to his property.
The complainant says the insurer did not allow him to speak while on the phone until he
warned the representative he would disconnect the call. The representative was arrogant and
impolite.
He seeks compensation for the harassment and mental trauma faced through the high
handedness and inconsiderate behaviour/actions of the insurer.
As discussed above, the insurer was not obliged to undertake the additional works required to
the gutter/overflow system. However, the insurer was obliged to share the repair quotes it
relied on in making cash settlement with the complainant. This would have enabled him to
review the scope of works at the time.
The repair quote messaged by the builder to the complainant on 1 August 2023 was higher
than the cash settlement offered by the insurer. The insurer’s builder recently states the initial
quote had missed certain items which means it was not actionable.
The claim could have been settled earlier had the complainant undertaken the proposed
works or provided an independent report from another roofer explaining why the suggested
Determination | Case number: 985568 Page 6 of 7
works were not required. The insurer was willing to perform internal repairs at the time and it
would have accepted the additional costs arising out of the repairs if this option was taken.
The delays experienced were also caused by the complainant’s decision to challenge the
insurer’s position regarding the additional works to the gutter/overflow system which were not
the insurer’s responsibility .
Having considered all of the above, I am satisfied the insurer should pay $500 non-financial
loss compensation for the complainant’s claims experience.
2.4 Why is the outcome fair?
Outcome is fair
It would be unfair to expect the insurer to cover claims outside the agreed policy terms. The
insurer should pay compensation for its claim service.
Determination | Case number: 985568 Page 7 of 7
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.