Home / Suncorp Group / Determination 982796

Determination 982796

Delay in assessing a fire claim and dispute over the temporary accommodation benefit limit

FirmSuncorp Group
Decided2023-09-29
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$2,000
Amount claimed$79,660
SourceAFCA PDF

Summary

The complainant sought a further $79,660 for temporary accommodation after a fire total loss, arguing the policy was ambiguous or the insurer delayed. AFCA rejected the ambiguity argument but found unreasonable delay, ordering three months of temporary accommodation and contents storage costs, $2,000 non-financial loss, $1,320 for the timber report and interest.

The TA wording was clear so the 10% cap applied, but the insurer's cumulative unreasonable delays used up benefit time, making it fair to pay three extra months plus non-financial loss under Rule D.3.3.

Issues

Subjects and remedies

home or building damagepay claimpay compensationpay interestpay non financial loss

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 982796 Financial firm AAI Limited Determination | Case number: 982796 Page 1 of 10 Case number: 982796 22 September 2023 1 Determination overview 1.1 Complaint The complainant holds a home and contents insurance policy with the financial firm (the insurer). On 14 July 2019, he lodged a claim for damage to his property caused by a fire. The insurer accepted the claim and appointed its trades to assess the extent of damage. The insured property was assessed to be a total loss and the complainant has been paid his maximum entitlements under the policy including the temporary accommodation entitlements. The complainant is seeking an additional $79,660 on the basis the policy wording regarding the temporary accommodation benefit is unclear and should be interpreted to his benefit i.e. increasing the extent of cover available under the policy. Alternatively, the complainant says the insurer caused unreasonable delays in assessing its liability under the claim. This has negatively impacted on his temporary accommodation and contents storage cover. The complainant says the insurer should make further payments towards these expenses under the claim. 1.2 Issues and key findings Are the policy provisions regarding temporary accommodation clear? Yes. The policy provisions regarding the temporary accommodation benefit (TA) are reasonably clear and unambiguous. The insurer’s interpretation of the policy is fair in the circumstances. Is the insurer required to make further payment to the complainant? Yes. It is fair that the insurer be required to pay the complainant for an additional three months of TA and contents storage expenses. This is due to the unreasonable delays caused by the insurer in assessing its liability and settling the claim. Is the complainant entitled to compensation? Yes. Given the insurer’s management of the claim, it is fair that the insurer pays the complainant $2,000 in non-financial loss compensation (NFL). Further, the insurer is to reimburse the complainant $1,320 for the cost in obtaining the timber report. Why is the outcome fair? The outcome is fair because the delays caused by the insurer in assessing the claim have negatively impacted on the c omplainant’s TA and contents storage benefits. It is also fair that the insurer pays the complainant $2,000 in NFL and reimburses him for the timber report. Determination | Case number: 982796 Page 2 of 10 1.3 Determination The determination is in favour of the complainant. Within 14 days of receiving notice of the complainant’s acceptance of this determination, the insurer is to settle the claim as set out under sections 2.2 and 2.3 of this determination. Determination | Case number: 982796 Page 3 of 10 2 Reasons for determination There is no dispute the complainant has established an entitlement to cover under the policy and that the insurer has paid the complainant his maximum entitlements as set out in the policy. Consideration of this complainant is limited to the concerns raised by the complainant regarding the policy wording relating to the TA benefit and the insurer’s overall management of the claim. 2.1 Are the policy provisions regarding the TA benefit clear? Yes. The policy provisions regarding the TA benefit are reasonably clear and unambiguous. The insurer’s interpretation of the policy is fair in the circumstances. Policy provides cover for temporary accommodation The policy provides cover for loss or damage to the insured property caused by an insured event, that occurs within the period of insurance, including fire. There is no dispute t he complainant’s property suffered significant fire damage due to the claimed event. The complainant has selected classic advantages cover. Page 28 of the Product Disclosure Statement (PDS) sets out the policy limits for TA under classic advantages cover. The PDS says: The most we will pay under this feature is 10% of your home sum insured and the longest period you can claim for is 24 months. The complainants Certificate of Insurance (COI) shows that the building sum insured at the time of the loss was $742,600. Therefore, the insurer says the complainant is entitled to a maximum of $74,260 for TA. Complainant says policy terms are ambiguous The complainant says that a reasonable person in the circumstances would interpret the policy wording to mean an insured is entitled to 10% of the home sum insured per year for up to 24 months under classic advantages cover. The complainant says, ‘ every statement/phrase gives a meaning and perception of the implied benefit of up to 24 months for the highest level of cover ’ . The complainant believes this could be construed as 10% per year for up to 24 months. The complainant notes that the PDS has since been reworded and reference to the 24 months period and 100 weeks has been removed. Given this, the complainant says he should be entitled to a further $74,260 in TA payments. The insurer disagrees that the wording is ambiguous. It says the policy clearly states the most it will pay is 10% of the building sum insured and the longest period that can be claimed is 24 months. It says that this means that if the complainant had been in cheaper accommodation and was required to stay there for over 24 months, the insurer would cease to cover the costs once the 24-month period had been reached. Determination | Case number: 982796 Page 4 of 10 The policy wording is reasonably clear and unambiguous The panel is not persuaded that the complainant is entitled to an additional $74,260. This is because the panel does not consider the policy wording is ambiguous or that the c omplainant’s position is reasonable in the circumstances . The panel is satisfied that cover under the policy is subject to the conditions, limitations and exclusions specified in the policy documentation. Having reviewed the policy, the panel is satisfied the insurer’s maximum financial liability under the TA benefit is 10% of the building sum insured at the time of the loss. The panel accepts that cover under the TA benefit can be claimed for up to 24 months whilst 10% of the relevant sum insured has not been exhausted. In the instance 10% of the sum insured is exhausted prior to the 24-month limit or at the end of 24 months of the TA (where the 10% of the sum insured has not been exhausted), the insured’s entitlement to TA comes to an end. The panel acknowledges the complainant has a different opinion on the TA benefit provisions and says the legal principle of contra proferentum should be applied to his benefit. However, given the panel is satisfied the policy wording is reasonably clear and unambiguous, it is not satisfied there is scope for the application of the said legal principle in these circumstances. The panel empathises with the complainant’s predicament. However, the panel notes the insurer had put the complainant on notice from very early in the claim that his chosen temporary accommodation and associated weekly rent of $1,500 would exhaust the TA benefit in under 12 months. The panel is satisfied the insurer is entitled to rely on the policy wording and limitations in assessing its liability. Further, that the insurer’s assessment of its liability under the TA benefit is fair and consistent with the policy. 2.2 Is the insurer required to make further payments? Yes. Given the unreasonable delays caused in assessing its liability under the claim, it is fair that the insurer pays the complainant an amount equal to three months of TA and contents storage expenses. Information relevant to the consideration of this aspect of the complaint Having considered the available information, the panel notes the following information:  the insured property suffered significant damage due to a fire on 14 July 2019 for which the claim was lodged the following day  at the time of the loss the insured building was insured for the sum insured of $742,600  the claim was referred to and subsequently release d from the insurer’s investigations department on 27 August 2019, this being over a month after the claim was lodged  on 16 September 2019, the insurer paid out the contents component of the claim as a total loss  the insurer’s appointed building consultants’ ‘J’ first provided a high-level quote to repair the insurer building in the amount $811,232.63, which exceeds the policy sum insured amount  the insurer has not provided the full document and therefore a date has not been provided for this quote, nor has this information been provided in the insurer’s notice of response. On the available information, the panel is satisfied this high-level quote was provided in the beginning of September 2019 Determination | Case number: 982796 Page 5 of 10  an assessment report from J dated 3 September 2019 shows the consultants believed the cost of repairs would be very close, if not exceed, the po licy’s building sum insured However, that this could not be confirmed until demolitions works were completed  demolition works were completed prior to a dual assessment by an assessor from the insurer and J on 27 September 2019  the insurer ’s appointed consultants ‘M’ ($999,922.33) and J ($721,550.90) did not provide their scope of works and associated quotes until 9 December 2019 and 13 December 2019, this being five months after claim lodgement  arising from various concerns with J’s quote, it was instructed to provide an amended quote which was received on 10 January 2020 in the amount of $838,863.07  on 22 January 2020, six months after claim lodgement, the insurer’s building coordinator recommends the claim be settled on the basis the insured building is a total loss  on 5 May 2020, some 10 months after claim lodgement and four months after determining the building is a total loss, the insurer arranges payment to the complainant for building component of the claim. Complainant says insurer delayed assessment Given the concerns regarding the potential of the insured building being a total loss at the initial assessments at the start of September 2019, the complainant says the insurer failed to act diligently. In line with its duty to act with the utmost good faith, the insurer should have turned its mind to matters like the critical changes to the Building Code and Regulation, which will have impacted the cost of construction and realise it was impossible to rebuild within the sum insured. The complainant refers to the BMT Quantity Surveyors website which shows the average cost per square meter to rebuild an ‘architecturally designed residence’. The complainant expects J and M could have used a similar resource to prevent delay and confirm the sum insured was inadequate to repair the property immediately, as opposed to the six months it took for the insurer to come to this conclusion. The complainant notes the insurer does not dispute there were delays in its assessment of the claim, which supports his position. The complainant believes the decision to declare the insured building a total loss could have been made in September 2019 instead of late January 2020. Accordingly, he says it is fair the insurer be held responsible for the delays and associated impact on his benefits under the policy. Insurer says it acted reasonably in the circumstances Insurer says it acted reasonably in the circumstances. While the insurer acknowledges there were some delays, it does not consider the timeframe was excessive. It submits the following timeline:  J attended on 3 September 2019 and demolition was required to be completed before it could provide a scope of works  J reattended on 27 September 2019 with an engineer  the insurer’s second builder M attended on 1 October 2019  J ’s engineer provided a report on 8 October 2019  M provided its quote on 9 December 2019  J provided initial quote on 13 December 2019  the J and M quotes were assessed on 19 December 2019. The insurer says that due to the difference in quotes and repair methods proposed by J and M, a building coordinator ’s expert advice , and a further assessment was arranged with J on Determination | Case number: 982796 Page 6 of 10 23 December 2019. J then provided an amended quote on 10 January 2020 and on 22 January 2020, the decision was made to settle the building sum insured. Insurer did cause unreasonable delays over the course of assessing the claim The panel accepts the complainant’s position that the insurer is responsible for delays experienced over the course of the claim. However, the panel is not of the view that it would be fair in these circumstances to require the insurer to increase settlement under the claim or pay compensation to the extent claimed by the complainant. The panel accepts the insurer’s view that it is entitled to arrange necessary assessments and consultants so to allow it to assess its liability under the policy. The panel is not satisfied it is a case of the insurer failing to act with the utmost good faith and that it did make genuine and reasonable efforts to address the complainant’s concerns. However, having considered the available information, the panel is satisfied there have been periods of unreasonable delays over the life of the claim. It may well be that there may not have been one single extended delay, however, the panel accepts the cumulative effect of multiple delays over the life of the claim have collectively negatively impacted on the complainant’s TA and contents storage benefits. It is important to note that these benefits are not only limited by quantum but also time related restrictions. Further, that it is reasonable to accept the intention behind these benefits is to provide the complainant TA and storage cover whilst the insured property is being repaired/rebuilt following a valid claim. The panel is of the opinion, it is fundamentally unfair for the insurer to use up a significant portion of the period these benefits are available to the complainant, to complete its investigations, assessments and decision on liability. The panel notes the insurer and its appointed consultants/agents caused unreasonable delays over the life of the claim such as:  it took close to two months from claim lodgement to even begin the assessment process in September 2019. There was nothing preventing the insurer from commencing the assessment process whilst it chose to investigate the claim  the insurer failed to give greater consideration to the early advice and high level quote from J, which informed of the very real potential that the insured was a total loss, including looking into the financial impact of the relevant building codes and standards  it took the insurer 12 days to refer the engineer’s report to its building consultants for review, this could have been sent on the day it was received rather than wait almost two weeks  it took over two months for the insurer to obtain the scope of works and quotes from its building consultants. Further, the quotes were not assessed to be fair and therefore required further time to be amended, only adding to the delays  it was close to six months after claim lodgement that the decision to declare the building a total loss was made on 22 January 2020. This is despite being put on notice in September 2019 that it most likely a total loss  it took the insurer over one month to then generate the first Terms of Settlement (TOS) letter to the complainant on 26 February 2020  the TOS letters which required several rounds of redrafting took close to two months before the final draft was completed on or about 28 April 2020  the complainant did not receive his settlement for the building component of the claim until 10 months after the claim was lodged. Determination | Case number: 982796 Page 7 of 10 The panel acknowledges that the complainant has also contributed to some of the delays experienced and that it would be unfair to hold the insurer solely responsible. The complainant did incorrectly dispute the interpretation of the policy terms and at times took longer than required to respond and/or return communications to the insurer. The panel also accepts that it is fair that the insurer be permitted to undertake reasonable investigations so to assess its liability, this includes appointment of various experts. However, as noted above, the panel is of the opinion when considering the various minor and other more significant delays caused by the insurer collectively, it is fair to accept the delay experience is unreasonable and i mpacted negatively on the complainant’s policy entitlements. Given this, the panel is satisfied that the insurer be required to make further payment to the complainant. The insurer is to arrange payment amounts equal to three months TA and contents storage expenses. The payments are to be arranged within 14 days of receiving notice of the complainant’s acceptance of this determination and subject to reasonable supporting information for the expenses from the complainant. The insurer is to pay interest on these amounts in line with section 57 of the Insurance Contracts Act 1984 from 14 January 2020 (six months from claim lodgement) to the 5 May 2020. In the interest of completeness, the insurer is not required to make any further payments relating to any other expense raised by the complainant, other than those relating to the TA and contents storage expenses considered above. 2.3 Is the complainant entitled to compensation? Yes. The insurer is pay the complainant $2,000 in NFL as well as reimburse him $1,320 for the cost incurred in obtaining the timber report. AFCA can award NFL in certain circumstances The Rules (Rule D 3.3) allow for an award of up to $5,400 for non-financial loss compensation, if the insurer caused the complainant to suffer an unusual degree or extent of inconvenience, delay or interference. AFCA takes a conservative approach when considering any award of compensation. Insurer to pay $2,000 in NFL in line with the AFCA Rules The complainant is seeking $5,400 compensation for non- financial loss due to the insurer’s delays in claim handling and reimbursement for the timber report he sourced in the amount of $1,320. The insurer acknowledges it is responsible for some delay under the claim and offered the complainant $1,000 in NFL. However, it has declined to reimburse the complainant for the timber report. In line with the matters discussed above, the panel is satisfied the insurer’s overall management of the claim did cause the complainant to suffer undue levels of stress, anxiety, inconvenience and delays over the life of the claim. The panel is satisfied it is fair that the insurer be required to pay the complainant $2,000 in NFL in line with the AFCA Rules. This is to be paid within 14 days of receiving notice of the complainant’s acceptance of this determination. Determination | Case number: 982796 Page 8 of 10 Insurer must pay for complainant’s timb er report fees The complainant engaged an expert to support his concerns with the insurer’s decision to re - use existing timbers, beams, joists and cladding, based on its engineer’s report. The c ost of the report was $1,320. The panel is satisfied this repo rt did impact on the insurer’s assessment of its liability and supported the concerns raised by the complainant. Given this, the panel accepts it is reasonable that the complainant be reimbursed for this report under the claim. Accordingly, the panel is satisfied that the insurer should reimburse the complainant $1,320 to wards this report within 14 days of receiving notice of the complainant’s acceptance of this determination. The insurer is to pay interest on this payment in line with section 57 of the Insurance Contracts Act 1984 from the date of the invoice to the date payment is issued to the complainant in line with this determination. 2.4 Why is the outcome fair? The outcome is fair because the delays caused by the insurer in assessing the claim have ne gatively impacted on the complainant’s TA and contents storage benefits. It is also fair that the insurer pays the complainant $2,000 in NFL as well as reimburses him for the timber report. Determination | Case number: 982796 Page 9 of 10 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. A panel determined this matter Due to the nature of this complaint, we referred it to a panel for determination. The panel includes:  an ombudsman  a member with significant experience in consumer and small business advocacy  a member with extensive experience as an industry representative. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. Determination | Case number: 982796 Page 10 of 10 3.2 AFCA Rules D.3.3 An AFCA Decision Maker may decide that the Financial Firm is to compensate the Complainant for non-financial loss: a) for a complaint relating to an individual’s privacy rights - injury has occurred to the Complainant’s feelings or humiliation has been suffered by the Complainant; or b) for other complaints – an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the Complainant’s expectation of enjoyment or peace of mind has occurred.