Determination 982315

Dispute over scope of works and cash settlement amount for building damage from neighbouring construction, plus claim handling

FirmYoui
Decided2024-02-01
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$298,550
Non-financial loss$2,500
Amount claimed—
SourceAFCA PDF

Summary

The insurer accepted a home claim for damage from neighbouring construction but disputed the scope and cost of repairs. AFCA required a cash settlement based on the complainant's quantity surveyor's quote plus contingency, additional costs, non-financial loss and interest.

The insurer's scope and quote were incomplete, so the complainant's itemised quote better reflects the reasonable cost of repair, and the insurer must pay interest under section 57 of the Insurance Contracts Act.

Issues

Subjects and remedies

home or building damagepay claimpay compensationpay interestpay non financial lossrefund fees or charges

Related

All Youi determinations · Find similar determinations

Text of the determination

Determination Case number 982315 Financial firm Youi Pty Ltd Determination | Case number: 982315 Page 1 of 10 Case number: 982315 30 January 2024 1 Determination overview 1.1 Complaint The complainant holds a home building and contents insurance policy with the financial firm (insurer). She lodged a claim for damage to her property due to neighbouring construction works. After the complainant lodged a complaint with AFCA, the insurer accepted the claim. However, a dispute has arisen about the scope of works (SOW) necessary to repair the damage to the complainant’s property , the reasonable cost of repairs and the way in which the insurer handled the claim overall. 1.2 Issues and key findings Is the insurer required to increase the cash settlement? Yes. The insurer’s quote for repairs is incomplete. The complainant has provided a comprehensive, actionable quote and the claim should be settled on this basis. The complainant should also be compensated for agreed additional items (including removalist costs, out of pocket expenses, temporary accommodation and expert report fees) along with compensation for non- financial loss due to the insurer’s poor handling of the claim overall. Why is the outcome fair? The outcome is fair because the exchanged information shows:  the insurer did not assess the damage adequately  the insurer’s SOW and cash settlement were inadequate  the insurer generally mismanaged the claim, causing the complainant a degree of stress and inconvenience. It is therefore fair that the insurer meets its policy obligations and pays the claim, plus interest. 1.3 Determination This determination is in favour of the complainant. Within 14 days of receiving notice the complainant accepts this determination, the insurer must pay the complainant:  $275,710.40 for building repairs  $12,614.87 for removalist costs  $2,835 for out-of-pocket costs  $2,500 in non-financial loss compensation  $12,629.00 for temporary accommodation  $4,761.76 for the complainant’s expert report fees . The insurer is also required to pay interest on the settlement sum of $275,710.40 pursuant to section 57 of the Insurance Contracts Act 1984 (Cth) (the Act) from 27 May 2023 (one month after the date the MQ repair quote was provided) until the date of payment. Determination | Case number: 982315 Page 2 of 10 Determination | Case number: 982315 Page 3 of 10 2 Reasons for determination 2.1 Is the insurer required to increase the cash settlement? Yes. The insurer’s quote for repairs is incomplete. The complainant has provided a comprehensive, actionable quote and the claim should be settled on this basis. The complainant should also be compensated for agreed additional items (including removalist costs, out of pocket expenses, temporary accommodation and expert report fees) along with compensation for non- financial loss due to the insurer’s poor handling of the claim overall. Policy allows insurer ability to repair damage or cash settle complainant The insurer has accepted the claim. The issue in dispute is whether the insurer should repair the property, and if not, what the amount of any cash settlement should be. Under the terms of the policy, the insurer may settle a claim for damage to the complainant’s property by:  repairing the damage or rebuilding the property, or  paying the complainant, the reasonable cost of doing so. See section 3.2 below for relevant policy terms. The insurer says that it cannot repair the property because the box gutter and roof at the property does not comply with current standards and it cannot warrant the repairs. On that basis, the insurer has decided to cash settle the complainant. No dispute property was damaged The complainant has owned the property since about 2000. In 2019, a new multi-storey development was built at the adjoining property with construction being completed in 2021. During the construction process of t he neighbouring property, the complainant’s property suffered damage because the neighbour’s builder did not install adequate protection. The builder walked on the roof of the complainant’s property and constructed scaffolding over it. After the construction was complete, the builder attempted to repair the damage at the complainant’s property, which caused further damage. This included internal damage. Cash settlement should reflect reasonable cost of repairs Where a claim is to be settled by a cash settlement, the insurer is required to pay the complainant the reasonable cost of repairing the damage to the property. This means the cash settlement amount should be sufficient to ensure that the complainant is able to engage their own contractors to complete the necessary repairs. Parties disagree on extent of liability After the insurer accepted the claim, it appointed several experts to assess the extent of the damage. The insurer engaged a roof expert, PP, who prepared a report dated 6 October 2022 that said:  The roof is in reasonable condition for a house 20+ years old, with some wear and tear, and appears well maintained. Determination | Case number: 982315 Page 4 of 10  All box gutters are non-compliant.  The box gutters are not wide enough.  The box gutter changes direction.  There are non-compliant discharge points.  The box gutters do not have enough fall, and some areas of the gutter have a slight bit of backfall.  The gutters are holding water and have started rusting as a result.  There are no overflow points in the gutters.  The lower roof at the rear of the property has a couple of dints in the roof sheets which are consistent with foot traffic.  The lower roof at the rear of the property has some holes in the apron flashings from impact from an unknown source. PP said that the issues with the gutters are installation related and recommended that all box gutters, flashings and dented roof sheets be removed and replaced with box gutters complying with Australian standards. The insurer appointed a building consultant MM, who attended property and provided a report dated 24 October 2022. MM also prepared a SOW. MM said: During the inspection we observed moisture damage and cracking to the internal ceilings of the dwelling, swelling of the Lightwell window frame, dinting and scuff marks caused by cleaning on the steel roof surface, various expert roofing and building condition reports were also viewed which for the most part stated the insureds home had sustained damage due to the neighbouring construction works being carried out. An electrical safety report was also viewed which showed light circuits damage and the need to replace several light fittings to both the ground and first floors. Damage to these fittings was caused by water ingress due to the use of high-pressure washers used by the builder in an attempt to clean the insureds home. Other damage was also observed but not limited to the front timber tilt gate and north side boundary brick wall. It is [MM’s] opinion that the cause of the damage to the insureds home is due to the neighbouring builder allowing building materials and other debris to spill over on to the insureds home, the use of the insureds home as a platform to construct their high rise building which included the erection of scaffolding and the cutting and storing of floor/wall tiles, the use of incorrect cleaning agents and methods in an attempt to clean up their mess. Determination | Case number: 982315 Page 5 of 10 It is [MM’s] opinion that the steel roof sheets, their associated capping’s flashings and gutters will continue to deteriorate and allow further damage to the insureds home if not replaced. A scope of works has been prepared to remove and replace the steel roof sheets and their associated capping’s, flashings, and gutters along with other items in the home that either are in need of repair or replacement. MM also said:  the roof report prepared by PP (see above) says that the guttering does not currently comply with Australian standards. However, it would have complied with the standards at the time of construction, approximately 20 years ago. The damage to the roof has been caused by the neighbour’s builder.  It is important that once the roof sheets and insulation are removed that a full check of the structural roof framing timbers be carried out to ensure they are still in place. Following receipts of the above reports, the insurer obtained a repair quote from JP for $84,890.34, dated 25 October 2022. The complainant disagrees with the insurer’s SOW The complainant says the insurer’s SOW does not include all damage to the property and is also vague about what replacement materials will be used. The complainant provided a report from IP dated 13 September 2022. IP says: The roofing appears to have been scrubbed in an attempt to remove the debris off the roof. The zinculume roofing products appear acid damaged in areas over the upper and lower roofs. Using acid to clean concrete and render off a zinculume roof will affect the coating and void the warranty of the product. … It is unknown what cleaning products the builder used to remove the concrete and render off the roof. The cleaning process has damaged the coating on the zinculume roofing which will shorten the life expectancy of the roof. There is a section of the box gutter towards the southern side of the upper roof that is rusting. There is a condensation drain entering the box gutter where the rusting has started. It is unknown what condition this section of box gutter was in prior to the works commencing at the adjoining property.  He was provided with pictures and videos from the complainant of scaffolding above the roof and of the tradespeople standing and grinding on the roof. He does not know what protection orders were in place. There is visible damage to the roof and the cleaning process to remove debris has damaged the roof, shortening its life expectancy. The complainant also engaged a quantity surveyor, MQ, to prepare a report dated 27 April 2023. MQ said:  Upon inspection of the property he observed damaged roof sheeting, gutters, render, window, skylights, internal plasterboard and paint, electrical fittings and water damage.  He referred to the AFCA preliminary assessment which had been accepted by both parties as to what items were considered damaged from the neighbour’s builder. Determination | Case number: 982315 Page 6 of 10  On that basis, he prepared a SOW to repair the damage. This SOW encompassed items included in the AFCA prelimin ary assessment, items from the insurer’s SOW and a small number of additional items, including rubbish removal, traffic management, cleaning and certificates of compliance for electrical and plumbing works.  Based on his understanding of labour costs and materials, the cost to repair the damage is $231,842, including GST. He provided a line by line breakdown of costs along with details of hourly labour costs.  Says additional costs of removalists, temporary storage and temporary accommodation (for 6 weeks) equals $18,130. Insurer’s cash settle ment offer The insurer has made a number of offers to cash settle the building claim based on JP ’s repair quote, plus a contingency amount to reflect the transfer of risk. Following the compl ainant’s SOW from MQ , the insurer obtained a second repair quote from another builder, AC for $149,719.52 based on that SOW. The most recent offer was made on 7 September 2023, calculated as follows:  $149,719.52 - building repairs based on AC quote  $44,915.86 – 30% uplift  $194,635.38 – total  Less $2,500 policy excess  Settlement amount offered - $192,135.38. The complainant did not accept the offer. Complainant says insurer’s cash settlement offer for repairs is inadequate The complainant says that the insurer’s cash settlem ent offer based on the quote of AC or JP is inadequate as these quotes do not represent a reasonable assessment of the cost of repairing the claimed damage. The complainant wants the claim to be cash settled based on MQ ’s SOW and costing for $231,842. The insurer says that MQ ’s quote includes repairs for upgrading the roof and box gutters. It says the policy do not provide cover for upgrades and it considers AC ’s quote reasonable as it is based on MQ ’s SOW. MQ confirmed that its SOW and costing did not include any upgrade to the box gutter. MQ says in an email to the complainant dated 7 August 2023: Afternoon [complainant], In response to your email in short, no, I have not allowed for “upgrading” the existing box gutters and or sumps and downpipes. I have allowed for the following within my estimates: 1. Replace existing box gutters (supply and install) – This includes replacing the existing box gutters “like -for- like”. These allowances do not include for upgrading to current regulations. Determination | Case number: 982315 Page 7 of 10 2. Modifications and alterations to existing sumps and downpipes - This includes modifying and altering the existing sumps and downpipes to suit the new box gutter installation. These allowances do not include for replacement or upgrading to current regulations. To “upgrade” the existing box gutters, sumps and downpipes to current regulations, in my opinion there is likely to be structural alterations required. You will note in my report that “Structural alterations” are “excluded” from my costings. Thus meaning, the “upgrade” of any existing box gutters, sumps and downpipes to current regulations is also excluded. Further, the complainant says no allowance has been made by the insurer or MQ for costs associated with the structural damage to roof trusses, both in the first and second floor roofing. This would be an additional cost to her if found to require repairs. She says AC: … omitted significant costs such as: Victorian labour costs, crane hire, reinstating heat/air conditioning unit, project management, like for like light fixtures through out home (not mismatch lights) etc. [sic] MQ ’s quote is preferable I have considered the information provided by both parties in its entirety. I acknowledge that the parties appear to agree that the SOW to repair the damage prepared by MQ is reflective of the works required, save for some items like crane hire, project management and reinstating heating and cooling units. The complainant should be compensated on the basis of a quote that is actionable for her to complete the repairs. I do not consider any of the costings in the quote prepared by MQ to be excessive. MQ has provided details of hourly rates charged for labour and itemised the cost of repairing all of the damage in each room. I consider the disputed items above should be incl uded as part of repairing the damage caused. I accept MQ’s submission that repairing the box gutters is not an improvement which would otherwise be excluded under the policy. In contrast, the AC quote is not as comprehensive, excludes items and it is not clear whether AC actually conducted a site inspection for relevant measurements. For these reasons, I find MQ’s quote is preferable to AC’s quote. I am satisfied MQ’s quote fairly represents the cost to repair the property to a condition which is equivalent to or substantially the same as its condition at the time of loss. In summary, the insurer is to cash settle the claim based on M Q’s quote for $231,842 for building repairs plus a 20% contingency to reflect the transfer of risk, less the applicable excess. This amounts to a settlement amount of $275,710.40. In addition, the insurer is also required to pay interest on the settlement sum pursuant to section 57 of the Insurance Contracts Act 1984 (Cth) (the Act) from 27 May 2023 (one month after the date MQ ’ s repair quote was provided) until the date of payment. Determination | Case number: 982315 Page 8 of 10 The complainant is entitled to additional agreed amounts In addition to the above, the parties have agreed the insurer will pay the complainant the following amounts:  $12,614.87 for removalist costs  $2,835 for out-of-pocket costs  $2,500 non-financial loss compensation  $12,629.00 for temporary accommodation  $3,661.76 for the MQ report fee The complainant also seeks the insurer to reimburse her for IP ’s roof report for $1,100. The insurer says that this report holds little or no evidentiary value and did not assist in advancing the settlement or complaint. I acknowledge the insurer’s position but do not agree with it. At the time that the complainant obtained this report, the dispute between the parties had escalated to the point where the complainant felt she had no option but to obtain her own expert opinions given the history of the claim. Whilst the report is brief, it supported the complainant’s position that the rust damage to the box gutters was c aused by the cleaning chemicals used by the neighbour’s builder when at tempting to rectify the damage. I consider this information was useful and the insurer is liable for this report. 2.2 Why is the outcome fair? The outcome is fair because the exchanged information shows:  the insurer did not assess the damage adequately  the insurer’s SOW and cash settlement were inadequate  the insurer generally mismanaged the claim, causing the complainant a degree of stress and inconvenience. It is therefore fair that the insurer meets its policy obligations and pays the claim, plus interest. Determination | Case number: 982315 Page 9 of 10 3 Supporting information 3.1 The AFCA processes AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 Relevant terms of the policy Page 25: Home cover exclusions Home cover exclusions apply to all sections of your policy and describe circumstances where your policy will not provide cover for any loss, damage or liability arising directly or indirectly from any cause noted below. We will not pay for: 2. additional costs resulting from your buildings or any part thereof not being compliant with the most recent building codes, laws and regulations Determination | Case number: 982315 Page 10 of 10 Page 27: If you claim under your policy, we have the choice to settle your claim in many ways. We will never pay more than the sum insured shown on your policy schedule, or any applicable policy limits as noted in the PDS, plus the extra amounts shown under the Extra Cover section. 1. We can settle your buildings claim by: • paying for the reasonable cost of repair or rebuilding the damaged part of your buildings; • paying you the reasonable cost of repair or rebuilding the damaged part of your buildings; • rebuilding the building to its size and quality before the claim; or • any combination of the above.