Determination 982200

Repair delays caused by repeated and rectified works; additional temporary accommodation costs and non-financial loss

FirmIAG
Decided2024-04-16
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$16,836
Non-financial loss$2,000
Amount claimed—
SourceAFCA PDF

Summary

The complainant's storm damage repairs were delayed 16 weeks because the insurer's builder had to repeat and rectify work. AFCA required the insurer to pay a further $16,836.32 in accommodation costs plus $2,000 non-financial loss.

The delay was caused by the insurer's builder/agent, so the accommodation costs were direct financial loss outside the policy limit and the indirect loss cap.

Issues

Subjects and remedies

home or building damagenatural disasterpay compensationpay non financial loss

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination Case number 982200 Financial firm Insurance Australia Limited Determination | Case number: 982200 Page 2 of 7 Case number: 982200 12 April 2024 1 Determination overview 1.1 Complaint The complainant lodged two claims with the financial firm (insurer) for storm damage to his property. The first claim was lodged on 7 January 2022 and the second on 5 March 2022. The insurer accepted the claims and repaired the damage. However, the complainant says the repair was poorly managed by the insurer and the completion of the repairs was delayed by 16 weeks. The complainant says the insurer should pay for his accommodation costs during the delays. The insurer accepts there have been delays. However, it says it has already paid $14,844 above the policy limit for temporary accommodation and this fairly compensates the complainant. It says it is not obliged to pay any further amounts for temporary accommodation. The insurer also says the temporary accommodation costs sought are an indirect financial loss and therefore the maximum AFCA can award for these is $5,400. 1.2 Issues and key findings Is the complainant entitled to more accommodation costs? Yes. The complainant is entitled to a further $16,836.32 for accommodation costs, because:  the repairs took 16 weeks longer than needed due to needing to be repeated or rectified  this was an unreasonable delay and the insurer is responsible for it  temporary accommodation during the 16-week delay is direct financial loss. Is the complainant entitled to any compensation? Yes. The repair delays caused the complainant physical inconvenience and for the claim to take an unusual amount of time to resolve. The insurer‟s actions also interfered with the complainant‟s expectation of enjoyment or peace of mind. The complainant is entitled to $2,000 compensation for non-financial loss. Why is the outcome fair? The outcome is fair because the parties have had the opportunity to make submissions and respond to the other pa rty‟s submissions . It is fair in the circumstances for the insurer to pay for the complainant‟s accommodation costs during the delays caused by its builder/agent. 1.3 Determination This determination is in favour of the complainant. Within 14 days of being advised of the complainant‟s acceptance of this determination , the insurer is required to pay the complainant:  $16,836.32 for additional accommodation costs  $2,000 for non-financial loss compensation. Determination | Case number: 982200 Page 3 of 7 2 Reasons for determination 2.1 Is the complainant entitled to more accommodation costs? Yes. The complainant is entitled to a further $16,836.32 for accommodation costs, because:  the repairs took 16 weeks longer than needed due to needing to be repeated or rectified  this was an unreasonable delay and the insurer is responsible for it  temporary accommodation during the 16-week delay is direct financial loss. Insurer is responsible for 16-week delay to repair completion The complainant requested for the repairs to be stopped on 4 May 2022 due to concerns he had with the standard of the repairs (workmanship). The complainant says during the period from 4 May 2022 until 12 July 2022 (10 weeks) the insurer‟s builder was repeating and rectifying its strip out and repairs. He says after this there was a further six weeks o f timber floor repairs being repeated due to error by the insurer‟s builder. The insurer acknowledges there was delays and it has not:  disputed that its repairs needed repeating and rectification  provided a persuasive reason for the delays  disputed the com plainant‟s timeframes for the delays. Therefore, I accept there was a total of 16 weeks (112 days) delay in the repair timeframe caused by need to rectify the repairs. In the absence of a persuasive reason for the delay, I am satisfied this was an unreasonable delay. The insurer is responsible for this delay as it was caused by its builder/agent. Temporary accommodation during 16-week delay is direct financial loss Under the AFCA Rules, AFCA can award compensation (for complaints lodged before 1 January 2024) of up to $542,500, including up to:  $5,400 for indirect financial loss  $5,400 for non-financial loss. The AFCA Rules do not define direct or indirect financial loss. When reviewing AFCA‟s jurisdiction, Australian courts have said direct loss is loss that „flows naturally from the breach without other intervening cause‟ ( Australian Capital Financial Management Pty Ltd v Australian Financial Complaints Authority Limited [2021] NSWSC 1577). The repeating and rectifying of parts of the repair meant the completion of the repairs was unreasonably delayed. The complainant could not move back into the property until repairs were complete. The need for t emporary accommodation flowed naturally from the insurer‟s failure to complete repairs without unreasonable delay. There was no other intervening cause preventing the complainant from moving back into the property. Therefore, the additional accommodation costs are direct financial loss. It is not subject to AFCA‟s compensation limit of $5,400 for indirect financial loss. Determination | Case number: 982200 Page 4 of 7 Insurer is required pay an additional $16,836.32 for accommodation costs The insurer says the policy limit for temporary accommodation has been exceeded. There is no dispute:  there is a total temporary accommodation limit of $60,000 ($30,000 per claim)  the insurer has paid a total of $74,844 for temporary accommodation  the insurer paid $14,844 above the policy limit for temporary accommodation  the temporary accommodation cost $1,980 incl GST per week ($282.86 per day). I am satisfied the complainant had to be out of his home from 24 January 2022 until 17 January 2023 (inclusive). This is a total of 359 days. Therefore, the complainant‟s total accommodation cost for the 359 days is $101,546.74. Of the 359 days I am satisfied 247 days (about 35 weeks) is for the claim repairs (359 days less 112 days). This falls within the policy cover and is subject to the $60,000 policy limit for temporary accommodation. The insurer is responsible for the complainant‟s accommodation costs for the 16-week (112 days) delay. At a rate of $282.86 per day this is $31,680.32. I am not satisfied it is fair for the insurer to be entitled to apply the policy limit to this amount. This is because, the additional temporary accommodation costs flowed from the insurer‟s failure to complete repairs without unreasonable delay and not from the claim. The $60,000 policy limit plus the $31,680.32 for the 16-week delay means total amount of temporary accommodation costs the insurer is responsible to pay is $91,680.32. It has already paid $74,844 therefore, it is required to pay an additional $16,836.32 for temporary accommodation costs. 2.2 Is the complainant entitled to any compensation? Yes. The repair delays caused the complainant physical inconvenience and for the claim to take an unusual amount of time to resolve. The insurer‟s actions also interfered with the complainant‟s expectation of enjoyment or peace of mind. The complainant is entitled to $2,000 compensation for non-financial loss. Complainant is entitled to $2,000 non-financial loss compensation The complainant has raised several issues with the insurer‟s handling of the claim and the impact this has had on him including the insurer not completing the repair within a reasonable timeframe. I have not specifically referred to all of these in this determination however, they have been considered. As set out in section 3.3 below, AFCA may award compensation in certain circumstances. The delays due to the need to rectify the repairs caused the complainant physical inconvenience and for the claim to take an unusual amount of time to resolve. I am also satisfied the insurer‟s actions have interfered with the complainant‟s expectation of enjoyment or peace of mind. I am satisfied the insurer‟s actions have had a medium impact on the complainant over a period of several months. I am satisfied the complainant is entitled to $2,000 non-financial loss compensation. Determination | Case number: 982200 Page 5 of 7 2.3 Why is the outcome fair? The outcome is fair because the parties have had the opportunity to make submissions and respond to the other party‟s submissions . It is fair in the circumstances for the insurer to pay for the complainant‟s accommodation costs during the delays caused by its builder/agent. Determination | Case number: 982200 Page 6 of 7 3 Supporting information 3.1 The AFCA process AFCA’s approa ch is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 Relevant case law Australian Capital Financial Management Pty Ltd v Australian Financial Complaints Authority Limited [2021] NSWSC 1577 69. The expressions “direct financial loss” and “indirect financial loss” are not terms of art, and their meaning depends on the context in which the issue arises. The expressions invite consideration of the question whether there is a sufficiently clear and direct connection between the breach and the loss that it can be said that the loss is a direct consequence of the breach or whether the connection falls short of that requirement. As M J explained in P Securities Ltd v Financial Ombudsman Service Ltd [2015] WASC 321 “the essence of the distinction evoked by that meaning is, in general terms, between direct loss which flows naturally from the breach without other intervening cause and indirect loss which does not so flow. Whether particular loss - including loss of Determination | Case number: 982200 Page 7 of 7 profits - is direct or indirect depends on all the circumstances of the particular case”: at [132] (citations omitted). 3.3 AFCA may award compensation in certain circumstances Under section D.3 of the AFCA Rules, we may award the complainant compensation for non- financial loss where the insurer‟s actions have caused an unusual amount of:  physical inconvenience  time taken to resolve the situation  interference with the complainant‟s expectation of enjoyment or peace of mind. AFCA can also award compensation for indirect financial loss (out of pocket expenses or other liabilities, which are caused because of the insurer‟s conduct). This complaint was lodged with AFCA prior to 1 January 2024 and therefore compensation for both non-financial loss and indirect financial loss is capped at $5,400 per claim. The nature of insurance means when a claim is lodged something has gone wrong or some loss has occurred. This will most likely cause some inconvenience. AFCA cannot award compensation for the normal inconvenience arising from the circumstances causing the claim. Further, in deciding whether to award compensation, AFCA expects complainants to be moderately robust, to bear the normal degree of inconvenience experienced when a problem occurs and take reasonable steps to manage the situation.