Determination 981388
Claim declined for cracking damage allegedly caused by vibration from neighbouring earthworks
Summary
The complainant claimed for cracking to her home said to be caused by vibration from neighbouring earthworks; the insurer declined as the damage was long-term movement. AFCA upheld the decline but ordered $500 for non-financial loss due to poor claim and complaint handling.
Evidence showed pre-existing long-term foundation movement and vibration from civil works is not a listed event, but the insurer's poor handling warranted non-financial loss compensation.
Issues
- Claim denial primary · not upheld“damage is due to long term movement, which is excluded under the policy; insurer is entitled to deny the claim”
- Complaint handling failure secondary · upheld“complaint was closed in error and without the complainant's confirmation”
- Delay secondary · upheld“issues with the insurer reviewing the complainant's engineers report ... likely led to delays on the claim”
- Poor communication secondary · upheld“insurer's handling of the matter was poor and it failed to properly inform the complainant of its decision”
- Unconscionable conduct secondary · not upheld“complainant says insurer used bad faith tactics and engaged in unconscionable conduct; no such finding made”
Subjects and remedies
financial hardshiphome or building damagepay non financial loss
Related
Text of the determination
Determination
Case number 981388
Financial firm Insurance Australia Limited
Determination | Case number: 981388 Page 1 of 9
Case number: 981388 28 November 2023
1 Determination overview
1.1 Complaint
The Complainant lodged a claim on 9 November 2022 advising that bulk earthworks at a
development across the road from her property had been using heavy machinery including a
vibrating compacting roller over two working days. Following this, they found visible cracking
to the interior linings in the hallway and bedroom, with new and exacerbated cracks in the
external brickwork.
The insurer declined the claim on the basis that that no listed event had occurred at the
property. Rather, the cracking was pre-existing and consistent with natural building movement
over time, which is excluded under the policy.
1.2 Issues and key findings
Is the insurer entitled to deny the claim?
There available information shows on balance, that the damage to the property is due to long
term movement, which is excluded under the policy. Further, there is no evidence showing
the damage was made worse by the earth works. As such, I am satisfied the insurer is
entitled to deny the claim.
Is the complainant entitled to compensation?
Yes. The insurer did not handle the complaint well and this caused an unusual extent of
stress, delay and inconvenience for the complainant. The insurer must pay non-financial loss
compensation of $500.
Why is the outcome fair?
The events the complainant has described are unfortunate and I understand the complainant
has suffered financial hardship due to reasons beyond her control. However, given the
damage was not caused by an insured event, it would not be fair to require the i nsurer to
accept the claim.
1.3 Determination
This determination is in favour of the insurer.
The insurer is entitled to decline cover for the building damage claimed to be the result of the
civil works undertaken at the neighbour’s home.
Determination | Case number: 981388 Page 2 of 9
2 Reasons for determination
2.1 Is the insurer entitled to deny the claim?
The complainant must establish a valid claim
As the policy holder, the complainant is required to show, on the balance of probabilities, she
suffered a loss caused by an event insured against under the policy. This is known as
establishing a valid claim.
If established, the onus shifts to the financial firm to show, on the balance of probabilities:
the policy does not cover the loss or damage,
the financial firm is otherwise entitled to deny the claim.
The policy is an insured events contract of insurance. The policy provides cover for loss or
damage caused by one or more of the insured events listed in the product disclosure
statement (PDS). Cover under these insured events is subject to the conditions, limitations
and exclusions specified in the PDS.
There is no dispute the complainant was provided with the relevant policy documentation.
Therefore, the insurer is entitled to rely on the policy provisions to assess its liability under the
claim.
It is established law that the onus first rests with the claimant to establish, on the balance of
probabilities (that is, more likely than not) that the loss falls within the terms of the policy.
So, the complainant needs the damage to the insured property, he is seeking cover for, was
caused by an insured event.
T he complainant’s property has sustained cracking and movement damage. However , what is
in dispute is whether this was caused by an event covered by the policy or has occurred over
time.
As such I am satisfied the onus rests with the complainant to establish the damage was
caused by an event covered by the policy
Damage due to vibrations caused by civil works is not covered under the policy
The complainant says the damage to the insured property is the result of civil works
undertaken at her neighbour’s property. The complainant noted the insured property did not
have any damage before these civil works commenced with areas of the home recently
renovated.
The insurer does not dispute the civil works occurred nor that the insured property does
present with damage in various areas. However, it says the damage was not caused by an
insured event.
I have reviewed the evidence from the parties including reports from the insurer’s builder ‘ AG ’
the insurer’s engineer ‘EC’ and the complainant’s engineer ‘BE’ . I accept this information
clearly shows damage to the insured property is consistent with long-term foundation
movement.
The insurer engaged EC to assess the cause and extent of cracking to the dwelling. It
reported long-term foundation movement that has traversed through the house resulting in
cracks in multiple areas. Further, it indicated that the cracks have an old appearance, and
Determination | Case number: 981388 Page 3 of 9
previous photos dated before the commencement of construction works show the front
external cracks to be pre-existing. EC also confirms the dwelling is approximately 25m away
from the construction site and given this distance, no damage would be expected to occur
from the use of a vibratory roller.
I note there is a differenc e in opinion between the complainant’s appointed consultant BE and
EC. BE would seem to accept the damage is related to the civil works. However, EC
dismisses this and says the damage is due to long term foundation movement.
Regardless of the conflicting expert opinions, I do not believe the complainant has
established a claim having regard to the policy provisions. This is because, there is clear
evidence in both engineers reports which show many of the cracks have had previous repairs
conducted on them. This is further confirmed by the google image from 2018 which shows the
cracks at the front of the property.
These two pieces of evidence are persuasive in showing movement and cracking has been
occurring since at the property from at least 2018, some 4 years before the event.
In addition to this, the complainant ’ s expert confirmed there was pre-existing movement
damage at the property.
Further, while I acknowledge the complainant ’ s expert states the compactor used would have
exceeded the recommend vibration limit 4mm/s for residential buildings, it has not supplied
any information which shows the compactor used at the time was capable of doing this.
On the other hand, the insurer ’ s expert provided a table which states the maximum velocity of
the compactor would have been 1.5mm/s at a distance of 25 meters being the distance from
the work site to the complainant property. The insurer ’ s expert confirms this amount of
vibration was not sufficient to cause the damage.
The insurer’s expert also provided a diagram of the expected movement the event would
have caused and compared it to the floor level survey conducted at the property. It is clear
from this comparison that the damage at the property is not consistent with what would have
been expected from the event, further indicating the event did not cause the movement at the
property.
When I consider the above I am satisfied the earth works did not cause the claimed damage
at the property. Accordingly, the insurer is entitled to decline the claim
In any event even i f I were to accept the complainant’s position that the damage was caused
by ground vibration relating to civil works undertaken by the neighbour, which I do not, this is
not an insured event and so a valid claim does not exist.
For these reasons, I am not satisfied the complainant has shown, on balance, that the
damage claimed is because of an insured event.
In the interest of completeness, I note that in the information provided, the complainant has
referred to errors and inconsistencies in EC’s repor t and it not being consistent with the
requirements of the Professional Engineers Act 2002.
I accept the insurer’s position that the circumstances do not reasonably show this . The
complainant has not provided any evidence to support this allegation.
Determination | Case number: 981388 Page 4 of 9
Insurer is entitled to deny the claim
Whilst there is no dispute damage had occurred to the property, including internal and
external cracking, the available information shows the cause of this damage is not related to
any of the listed events under the policy. Even if I were to be satisfied that the damage was
from the earth works, which I am not, it is not a listed event.
As such, I am satisfied the insurer is entitled to deny liability for the claim, as the complainant
has not established a valid claim within the terms of the policy.
In other words, I am satisfied the policy does not extend coverage to the loss claimed.
2.2 Is the complainant entitled to compensation?
AFCA may award compensation for non-financial loss
AFCA can require a financial firm to compensate a complainant for non-financial loss caused
by the firm’s conduct.
AFCA will only award compensation for non-financial loss where there has been an unusual
amount of physical inconvenience, time taken to resolve a situation, or interference with the
complainant’s expectation of enjoyment or peace of mind.
In assessing whether to award compensation, AFCA expects complainants to:
be moderately robust,
bear the normal degree of inconvenience experienced when a problem occurs, and
take reasonable steps to minimise the inconvenience suffered.
AFCA does not award compensation for pursuing a claim or perusing a complaint.
Non-financial loss compensation is warranted
The complainant was frustrated with the insurer’s handling of the c laim and its refusal to
cover all the claimed damage.
The complainant says the insurer used bad faith tactics and engaged in a consistent and
deliberate pattern of unconscionable conduct.
Based on the available information, I note the claim was lodged on 9 November 2022, a site
inspection was conducted by the insurer’s engineer on 2 December 2022 and the decision to
deny the claim was provided to the complainant on 28 December 2022 and 7 May 2023.
Whilst I am satisfied the insurer has correctly assessed its liability in accordance with its
policy terms and conditions. However, I note the insurer’s handling of the matter was poor
and it failed to properly inform the complainant of its decision.
Having reviewed the claim notes, I note the period of concern is December 2022 to May
2023. The claim notes also show there were issues with the insurer reviewing the
complainant’s engineers report and I accept this likely led to delays on the claim.
I note the complainant lodged a complaint that was incorrectly closed and reopened in May
2023, which would have added further frustration to the complainant. Further, I note the
insurer acknowledged the claim was poorly handled and that the complaint was closed on in
error and without the complainant’s confirmation.
Determination | Case number: 981388 Page 5 of 9
On balance, I accept these actions (and inactions) frustrated the complainant. I further accept
this caused an unusual extent of stress, delay and inconvenience in resolving the claim.
Given this, I accept an award of compensation is appropriate. I consider the insurer should
pay the complainant $500 compensation for non-financial loss.
2.2 Why is the outcome fair?
Based on the available information, the damage being claimed was not caused by an insured
event. Rather, the damage is due to long term movement, which is specifically excluded
under the policy. As such, it would not be fair to require the insurer to accept the claim.
Determination | Case number: 981388 Page 6 of 9
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
Determination | Case number: 981388 Page 7 of 9
3.2 Policy wording
Page Policy wording
4 The events we cover
We cover loss or damage to your home and/or contents when
certain things happen. These are known as
‘listed events’. You can make a claim if a listed event takes place
and caus es loss or damage to your home
or contents during the policy period.
…
Listed events
…
Impact damage
..
28 Impact Damage
Covered under building insurance and contents insurance
Loss or damage cause by the impact of:
> external aerials, masts, flagpoles or satellite dishes
> aircrafts, vehicles or watercrafts
> debris from space, aircrafts, rockets or satellites
> trees or branches
66 - 70 General exclusions for all covers and benefits
The exclusions set out in this section apply to all covers and benefits
under your policy.
What we don’t cover
Loss, damage, injury or death arising from:
rust, corrosion, gradual deterioration, depreciation, wear or tear
erosion, deterioration, collaps e, shrinkage or any other earth
movement
…
We do not cover :
…
the settling, shrinkage or expansion in buildings, foundations, walls
or pavements
loss or damage to the site or any reduction in its value
…
compens ation for distress, inconvenience or other non - financial
loss (except if we cover it under liability cover
consequential financial loss, except if specifically covered by this
policy. This means we will not pay for direct or indirect financial or
economic loss. For example, loss of use or enjoyment, loss of
profits
or depreciation.
Determination | Case number: 981388 Page 8 of 9
3.3 Expert Reports
Record Key points
Financial firm’s engineer
expert ( EC )
Report
02 - 12 - 2022
earthworks on a development site across the road opposite the
insured’s property have been taking place during 2022. The
insured has reported a CAT CP12 vibratory soil compactor used
during these works.
the insured has since noticed cracks to the internal and external
walls of the dwelling.
there were multiple cracks observed along the internal and
external walls of the dwelling during our inspection. Evidence
suggests that the cracks observed in the dwelling are a result of a
long - term foundation movemen t.
there is insufficient evidenc e to suggest that the cracks to the
dwelling have been caus ed by or have worsened due to the
construction activity across the road.
during the ins pection of the dwelling, there were multiple cracks
observed in the internal and external walls of the dwelling.
Evidence indicat es that the cracks are a result of a long - t erm
foundation movement that has traversed through the house
resulting in cracks in multiple areas.
further inspection of the cracks indicated that the cracks h ave an
old appearance, and previous photos dated before the
commencement of construction works show the front external
cracks to be pre - existing.
there were multiple instances of previous repairs observed along
the internal and external walls of the dwell ing. This is an indic ation
of long - t erm movement to the dwelling.
there is insufficient evidenc e to suggest that the cracks observed
to the dwelling are caus ed due to the vibration from construction
activity. Furthermore, the below table provides the dist ances and
the level of vibrations due to construction activity.
as the insured’s dwelling is approximately 25m away from the
construction site, no damage would be expected to occur from the
use of a vibratory roller, as reported by the insured
Complainant’s expert (B E )
Report
24 - 02 - 2023
excessive vibration was transmitted from the Compaction Activity
on the Site resulting in vibration damage to the residence on the
Property as follows:
( a) Extensive cracking and vibration damage occurred to the
internal plaster walls and ceiling linings;
(b) New cracking and vibration damage was pres ent to the clay
masonry face brickwork walls to the left side of the residence on
the Property;
Determination | Case number: 981388 Page 9 of 9
Record Key points
(c) The e xtent and width of existing cracking increased significantly
to the clay masonry fac e brickwork walls continuing along the front
and right side of the residence on the Property.
f rom an engineering perspective, the Owner of 20 M Street is
responsibl e
t he re was evidence to support that the Vibration Activity carried
out to the Site did provide vibration into the residence of the
Property significantly great er than 4mm/s peak velocity.