Home / Hollard / Determination 976810
Determination 976810
Partial denial of storm damage claim for roof and internal damage, with delays
Summary
Insurer partially denied a storm damage claim for roof damage, saying undersized trusses caused it. AFCA found the storm was the proximate cause, and required the insurer to cover roof and internal repairs, temporary accommodation, $5,400 non-financial loss to each complainant and the expert report cost with interest.
The storm was the proximate cause of the roof damage, the insurer's denial lacked probative evidence, and its avoidable delays caused further internal damage and loss.
Issues
- Claim denial primary · upheld“the insurer has provided no probative evidence to support its decision to partially deny the claim because of undersized roof trusses”
- Poor claim handling secondary · upheld“Avoidable delays and claim mismanagement; internal damage worsened”
- Inadequate claim investigation secondary · upheld“insurer chose not to seek additional expert (and documentary) evidence about the size of the roof trusses”
- Delay secondary · upheld“The timeline shows significant delays... the insurer's management of this claim has been of a very poor standard indeed.”
- Poor communication secondary · upheld“information about undersized trusses was not conveyed to the complainants until they called on 5 October 2022”
Subjects and remedies
health or medicalhome or building damagemental healthnatural disasterpay claimpay compensationpay interestpay non financial lossreassess claimrepair or rectify
Related
Text of the determination
Determination
Case number 976810
Financial firm Hollard Insurance Partners Limited
Determination | Case number: 976810 Page 1 of 12
Case number: 976810 13 November 2023
1 Determination overview
1.1 Complaint
The complainants hold a home and contents insurance policy with the financial firm (insurer)
and lodged a claim for damage following a severe storm on 29 October 2021.
The insurer initially accepted the claim but subsequently reversed its decision and partially
declined that part of the claim related to roof damage. The insurer now says the roof damage
was due to undersized trusses in the roof space.
The complainant disagrees and wants the insurer to accept the claim for all storm-related
damage to the roof and associated internal damage caused by ongoing water ingress.
1.2 Issues and key findings
Is the insurer entitled to decline the repairs to the roof?
No. The available evidence shows the roof damage was caused by the October 2021 storm.
Is the insurer liable for the internal damage?
Yes. The available evidence shows further internal damage caused by rain water ingress has
occurred because of, amongst other things, avoidable delays.
Is the insurer required to cover ongoing temporary accommodation?
Yes. The insurer is required to fund ongoing temporary accommodation.
Are the complainants entitled to non-financial loss?
Yes. The insurer is required to pay $5,400 non-financial compensation to each complainant.
Are the complainants entitled to the cost of an expert report?
Yes. The insurer should reimburse to the complainants the cost of an expert report, together
with interest on this sum. The expert report helped establish the cause of damage.
Why is the outcome fair?
The available evidence does not support the ins urer’s decision to partially deny the claim,
with subsequent delays causing additional internal damage, rendering the home unfit for
habitation. The mismanagement of the claim and avoidable delays have also had a significant
adverse impact on the physical and psychological well-being of both complainants.
1.3 Determination
This determination is in favour of the complainants.
The complaint should be resolved in accordance with section 2.6, below.
Determination | Case number: 976810 Page 2 of 12
2 Reasons for determination
2.1 Is the insurer entitled to decline the repairs to the roof?
Complainant has onus to establish a valid claim
It is established insurance law that the complainant first has the onus to establish the claimed
loss is a result of an event covered under the policy. This must be established on the balance
of probabilities, meaning that it is more likely than not.
If the complainant is able to establish a valid claim, the onus shifts to the insurer to show, on
the balance of probabilities, it is entitled to rely on an exclusion under the policy or is
otherwise entitled to decline the claim.
The policy c overs loss or damage caused by an insured event, being the incidents listed in
the Product Disclosure Statement ( PDS) and the Certificate of Insurance . These incident s
include “ storm ” (see page 34 of the PDS) . Page 3 of the PDS defines a “storm” as: -
Storm:-
violent wind (including cyclone);
rain, hail or snow of unusual volume, force or duration.
The claim
On 29 October 2021 a violent storm lasting approximately six hours struck the region around
Scotsburn, in country Victoria. The storm caused substantial damage to the complainants’
property, including damage to the roof, the rear porch and a bedroom. Trees felled by the
storm also damaged a boundary fence.
The insu rer arranged for CS, builders, to inspect the complainants’ home on 15 November
2021 and perform make- safe works. CS’s report written pursuant to that inspection is
thorough and logical. It also contains a comprehensive scope of works (SOW) concerning the
necessary storm-related repairs.
CS concluded that all damage, apart from the damage to the rear porch, was caused by the
storm. (CS concluded the damage to the rear porch came about because of pre-existing
maintenance issues related to guttering above the porch that was in poor condition).
In regard to the roof, CS found:-
Our inspection of the external roof identified that sections of the ridge capping had
been dislodged due to high winds. Further damage has occurred to the various roof
tiles which were cracked due to impact from debris. Additional damage to the roof
rafters which are now bowed and split has been caused by uplift and movement from
the solar hotwater system on the roof above due to the winds.
VT, leak detector and roof plumber, also inspect ed the complainants’ home on 29 November
2021. In regard to the roof, VT noted that storm-related damage was causing water ingress
into the ceiling cavity during further rain events. VT concluded:-
In my professional opinion water ingress is due to resultant damage to roof caused by
strong winds during storm….
Determination | Case number: 976810 Page 3 of 12
Resulting damages:-
6 metres of ridge capping tiles dislodged
All cement pointing affected by storm
Roof tiles under hot water service broken
Roof trusses under hot wat service damaged
1 roof tile cracked due to fallen ridge capping (replaced with new tile).
Clearly, following inspections by CS and VT, the complainants had established a valid claim
for storm damage to their property, including to the roof of their home.
Insurer caused substantial avoidable delays
The clear evidence of a valid claim as of late November 2021 is set out above. Moreover, on
24 December 2021 CS advised the insurer as follows:-
Hi Claims,
I am just following up on this claim, as there is still water ingress from the damaged
roof that we cannot stop until the repairs are carried out.
However, despite the reports of CS and VT, and despite advice from CS that water ingress
into the complainants’ home was continuing, the insurer did not communicate its acceptance
of the claim for the storm-related damage (apart from the damage to the rear porch) until 24
January 2022.
Subsequently, matters did not progress well, and further delays ensued.
In the absence of any progress regarding the necessary repairs, especially the remedial
works required to the roof, on 29 June 2022 the complainants advised the insurer that their
home was “ no longer liveable ”. They enquired whether temporary accommodation was
available.
The insurer then arranged for SD, design consultants and engineers, to inspect the
complainants’ home on 9 August 2022. SD’s report is comprehensive and logical and is
supported by many helpful photographs. SD’s inspection included entering the roof cavity and
sighting widespread tile movement, allowing sunlight through the gaps. SD noted the location
of such tile damage correlated with the internal ceiling damage.
SD concluded the damage was caused by the storm of October 2021:-
Damage sustained to the roof cladding has allowed moisture and wind gusts into the
roof cavity damaging the interior ceilings.
Despite SD’s report, very little progress was made. Then, on 8 September 2022, CS
commenced work on the roof. However, it immediately advised the insurer that the damage
was more significant than first thought. The insu rer’s claim notes reveal the following: -
….. CS called and advised that the roof needs a full repair and there is no point
repairing a part of it when the whole needs replacement….. the roof is not in good
condition and it is unsafe for the insured to reside in that property until repairs are
done. I have advised (CS) to let the insureds know we can organise temporary
accommodation until the repairs are done.
CS also advised the insurer at that time (or shortly afterwards) it could not warrant any works
it performed on the roof as the trusses were undersized.
Determination | Case number: 976810 Page 4 of 12
Unfortunately, this information was not conveyed to the complainants until they called the
insurer on 5 October 2022. Subsequently, despite the complainants paying the excess
applicable to their policy, and despite their repeated requests for updates and further
information, very little substantive progress was made in relation to the roof repairs. Then, on
20 February 2023, the complainants again telephoned the insurer. The insurer’s claim note
pertaining to that call includes the following:-
(Complainant) called to advise he hasn’t heard from anyone since xmas.
(Complainant) advised there is mould growing in the house, the ceiling will fall down
soon.
A further claim note provided by the insurer indicates that, four days later (that is, 24 February
2022), an internal review of the claim was foreshadowed. However, nothing of substance
appears to have eventuated.
Claim notes dated 31 March 2023 then reveal that:-
At 11.46 am CS again contacted the insurer to advise that the roof of the
complainants’ home was sagging due to the age of the roof and wear and tear. CS
apparently reported that the storm of October 2021 may have exacerbated “ it a little ”
but the main cause is roof-age. CS also reported tha t the property is “ nearly
inhabitable ” (I am not certain what the term, “ nearly inhabitable ” means in this context)
At 11.53 am one of the complainants again contacted the insurer to advise that the
sagging of the roof had, “ become much worse…. due to exte rnal roof being exposed
from DOL, during rainfall, water enters the roof cavity and is making the insulation wet
causing the ceiling to sag…. it is much worse and getting lower by the day ”. During
this conversation the complainant also advised she was very concerned for her own
safety and that of her family, as she thought the roof would collapse. The complainant
again enquired about temporary accommodation. Funding for this was approved by
the insurer.
One of the complainants then called the insurer again on 11 April 2023 and was advised,
amongst other things, a decision about whether the insurer would fully or partially accept the
damage to roof was “ still pending ” .
More than two weeks later, on 28 April 2023, the insurer advised the complainants that:-
regarding the roof trusses, given they are undersized the insurer would, “not consider
upgrades under the policy” and
“an assessor” had “been appointed”.
Little substantive progress followed. Then, on 3 May 2023 one of the complainants advised
the insurer that, “ this has taken a toll on her and her husband’s mental health ” .
Finally, on about 4 May 2023, the insurer advised the complainants that their claim had been
partially denied. The insurer advised:-
….. the “sag to the roof” was also not accepted as th e proximate cause of the
damages are the undersized trusses and not as a result of a one-off storm event.
Additional evidence about the roof obtained by both parties
Both parties then obtained further evidence regarding the roof following the insurer ’s par tial
denial of the claim.
Determination | Case number: 976810 Page 5 of 12
The complainants engaged BC, engineer, who inspected their home on 15 June 2023 and
provided a report dated 21 June 2023. BC’s conclusions are based upon, amongst other
things, the observations he made during the inspection and a full structural design review of
the roof framing (the structural design is set out on page 2 of his report).
BC noted:-
There was evidence of strengthening works on the internal roof structure that
appeared no more than 10 years old, thus proving the roof structure had been
maintained
The nature of the failure of several roof trusses was consistent with wind uplift which
would be partially due to internal pressure in the roof cavity after tiles were dislodged
The main cause of damage to the roof would likely be uplift on the roof structure
Damage to two trusses under the hot water service is due to localised wind pressures
on the hot water service which has exerted additional load on to the trusses.
In sum, BC concluded:-
….. the damage to the roof trusses….. is due to the localized pressures during wind
gusts on 29 October 2021. The damage has resulted in the failure of several trusses
leading to deflection in the roof structure. This movement, in conjunction with some
displaced tiles has resulted in water infiltration and subsequent mould growth. The
residence has areas that are unsafe and is not habitable in its present state.
The insurer then arranged for HR, building restorers, to inspect the complainants’ home on 18
August 2023 and prepare a report dated 30 August 2023. HR concluded the mould damage,
which affected the entire property, was caused by an, “ ongoing roof leak since 2021, which
was caused by storm damage/heavy winds ”.
Finally, FM, engineers, inspected the complainants’ home o n 15 September 2023 for the
insurer. FM’s report made pursuant to that inspection includes the following conclusions: -
There may have been some nail plate failure on one or more of the roof trusses prior
the storm
Absent this pre-existing problem, failure of the roof trusses would not be expected in
the recorded wind conditions
Nevertheless, the storm was a contributing factor in the failure of the roof. In
particular, the localised wind pressure increases would have exacerbated the
pressures acting on the roof
Moreover, the localised damage and dislodgement of roof tiles would have allowed
additional localised pressures to have occurred.
Significantly, FM was of the opinion that, had the size of the roof trusses been a major
contributing factor to the failure of the roof, one would have expected the body of the truss
members to have failed in the storm, and not just the nail plates and connections.
Proximate cause of damage and “sagging” ceiling damage was the storm
Damage can have more than one cause. For instance, in this matter the complainants say the
damage to the roof and ceilings of their home was caused by the storm, whilst the insurer
maintains that the damage to the roof was the result of undersized roof trusses.
Determination | Case number: 976810 Page 6 of 12
In deciding whether the policy responds, it is necessary to identify the proximate cause of
damage. The proximate cause is not necessarily the first or the last or the sole cause of the
loss. It is the effective or dominant or operative cause of the loss.
If there are several causes of a loss operating contemporaneously, each must be examined
for the qualities of reality, predominance and efficiency as the active, efficient cause that sets
a relevant chain of events in action. If one cause would have caused the harm in any case,
and the other would not have done so in the absence of the first, the first is the proximate
cause.
I have considered all available evidence. I am of the opinion the proximate cause of the
structural damage to the roof was the storm. This is because of the following factors:-
The reports of CS and VT are discussed above. As mentioned, both CS and VT
concluded the roof damage was storm related. (I do note a subsequent short report
from CS dated 31 March 2023, but that report makes no mention of roof trusses)
Aside from part of the overall analysis of FM which, I note, is based upon observations
of the roof made almost two years after the storm of October 2021, the evidence of all
experts overwhelmingly supports the complainants’ submission that the storm was the
cause of the roof failure and subsequent internal damage
The storm was severe. Bureau of Meteorology (BOM) data indicate a peak wind gust
speed of 100 km/h during the storm. Moreover, media reports state Victoria’s State
Emergency Service received more than 950 calls for help following the storm, and the
BOM issued a near state-wide severe weather warning for damaging winds (see SD ’s
report dated 9 August 2022, page 6)
No evidence has been supplied by the insurer to prove the trusses were undersize.
CS apparently reported that information to the insurer on about 8 September 2022,
but did not supply any documentary evidence to support the assertion. Moreover, in its
report SD makes no mention of “undersized” roof trusses. In addition, FM concluded
the size of the trusses was not a contributing factor to the failure of the roof. In short,
there is no probative evidence whatsoever that the size of the roof trusses played any
significant causal role in the failure of the roof
The complainants ’ home was constructed in about 1982 and there is evidence the roof
had been maintained. Moreover, the insurer has presented no evidence of roof failure
prior to the storm of October 2021
The complainants say they first noticed damage to the roof tiles immediately following
the storm and then noted internal damage a few weeks later. They also reported to
FM there was, “….. significant crashing and noise as a result of wind during the storm
dated 29 October 2021 ”. The insurer has presented no evidence to impugn the credit
of the complainants. I therefore have no reason to doubt their honesty and credibility
BC appears to have conducted the most comprehensive inspection and analysis of
the internal roof structure. I note that other experts were somewhat limited in their
internal inspection of the roof due to safety concerns. BC concluded that no other
causal factors, apart from the storm of October 2021, played a role in the roof failure.
In sum, the insurer has provided no probative evidence to support its decision to partially
deny the claim because of undersized roof trusses. It follows that the insurer must accept the
claim for the roof damage and should settle the claim as set out under section 2.6, below.
Determination | Case number: 976810 Page 7 of 12
2.2 Is the insurer liable for the internal damage?
Insurer caused significant delays
The storm-damaged roof subsequently allowed substantial and repeated rain water ingress
into the complainants’ home over the following months. I have no doubt the internal damage
caused by this water ingress is, therefore, also storm-related.
However, to appreciate the degree to which the internal structure of the house was subject to
water ingress and, therefore, to understand the extent of toxic mould damage now present in
the complainants’ home, a review of the claim delays caused by the insurer i s warranted.
The evidence in this matter, including the claim notes supplied by the insurer, reveal the
following timeline of events:-
31 October 2021 Claim lodged (date of loss is 29 October 2021)
15 November 2021 CS attends and reports roof damage is storm-related
29 November 2021 VT reports roof damage is storm-related
24 December 2021 CS reports ongoing water ingress until roof repairs are done
24 January 2022 Insurer accepts the claim
29 June 2022 Complainants advise insurer their home is “ no longer liveable ”.
They enquire whether temporary accommodation is available
9 August 2022 SD reports damage is storm related
8 September 2022 CS begins roof repairs. Finds damage is worse than expected.
CS says home is uninhabitable. Repairs cease. CS also tells
insurer roof trusses are undersize, but insurer seeks no
documentary independent evidence to substantiate this claim
20 February 2023 Complainants call insurer and advise they has not heard from
anyone associated with the insurer since Christmas 2022. Also
tell the insurer mould is growing in the house and the ceiling will
fall down soon
31 March 2023 Complainants tell insurer of additional water damage and raise
safety concerns. Insurer funds alternative accommodation
11 April 2023 Insurer tells complainants decision to accept or deny roof
damage is still pending
4 May 2023 Partial denial of claim regarding roof damage communicated to
complainants.
Determination | Case number: 976810 Page 8 of 12
The timeline shows significant delays. Whilst I acknowledge this claim occurred during
several weather catastrophes, this does not excuse the insurer ’ s responsibility to assess
claims in a timely manner. The delays are excessive, particularly given the insurer was first
notified the complainants ’ home was uninhabitable in late June 2022. I n short, the insurer’s
management of this claim has been of a very poor standard indeed.
Erroneous denial of roof damage created delays
The insurer declined the structural roof damage on the basis the damage was caused by
undersized roof trusses, not the storm.
As mentioned, the insurer has not provided any reports to support its position. The contact
notes indicate it relied on a conversation between CS and the insurer ’ s claims area in this
regard.
Significantly, in its report dated 15 November 2021, CS concludes all roof damage can be
attributed to the storm event on 29 October 2021. This included structural damage to the
rafters/trusses.
At the time of making the decision to deny the structural roof damage the insurer had reports
from an engineer, SD, and a roof plumber, VT, stating the damage was caused by the storm.
The insurer has not explained why it placed so much reliance on CS’s verbal report on about
8 September 2022 and rejected the opinions of a roof plumber and engineer, both of whom,
on the face of it, appear relatively more qualified to report on roof damage. Moreover, the
insurer has not revealed why it chose not to seek additional expert (and documentary)
evidence about the size of the roof trusses in a timely manner.
In all the circumstances, the decision by the insurer to decline the claim, insofar as it relates
to the structural roof damage, was patently incorrect. Quite simply, that denial was not (and
still is not) supported by any probative evidence. Moreover, it caused significant, avoidable
delays which have not only resulted in additional substantial internal damage to the
complainants’ home, but also caused a great deal of stress, anxiety and psychologic al upset
for both complainants.
Further internal damage and mould due in part to erroneous denial by insurer
Contact notes show CS notified the insurer on 24 December 2021 that water ingress would
not stop until the roof was repaired. Moreover, both parties now agree the internal damage
worsened after CS stopped working on the roof in September 2022.
The insurer appointed HR to report on mould growth inside the house. A technician attended
on 18 August 2023 and reported microbial growth on surfaces, cabinetry and contents
throughout the house. HR recommended the appointment of a hygienist to report further on
the extent of the mould growth and the remediation required.
The insurer did not appoint a hygienist. It maintains its position that the mould has been
caused by the damage to the roof, the liability for which has been declined.
I note that SD ’s report recorded mould growth in August 2022 . SD’s report and HR ’s report
are 12 months apart. Taken together, they show a significant increase in mould infestation
during that 12-month period. It is therefore reasonable to assume that, had the insurer not
delayed repairs when it erroneously declined the structural damage to the roof, remedial
works would have been undertaken sooner and the internal damage thereby likely minimised.
Determination | Case number: 976810 Page 9 of 12
It follows that the insurer is required to accept the claim insofar as it relates to all internal
damage caused by repeated rain water ingress following the storm of October 2021 (see
section 2.6, below). Moreover, the quantum of such claim and the works necessary to
remediate the internal damage is not limited by the terms and conditions of the policy as it
stems from avoidable delays and claim mismanagement on the part of the insurer.
2.3 Is the insurer required to fund ongoing temporary
accommodation?
Alternative accommodation to continue
The policy covers reasonable temporary accommodation for a period of 12 months if the
home is rendered uninhabitable due to an insured event. A large part of this benefit has been
exhausted because of avoidable delays, claim mismanagement and the erroneous decision
by the insurer to decline the claim regarding storm-damage to the roof.
It follows that the insurer is required to fund ongoing alternative accommodation until remedial
works have been completed and the complainants and their son are able to return to their
property. Moreover, the total quantum of this benefit is not limited by the policy terms and
conditions as the need for it stems from avoidable delays and claim mismanagement on the
part of the insurer.
Alternative accommodation to allow for son and pets
The complainants ’ son is a student and he resided in the family home until it became
uninhabitable. The complainant has also explained they have dogs that remain at the
damaged property and they travel to feed them.
In all the circumstances, it is fair and reasonable that any ongoing temporary accommodation
should include arrangements to accommodate the complainants ’ son and their pets.
Similarly, the insurer should also fund all necessary storage costs required for the contents of
the complainants ’ home until repairs and remediation works are completed.
2.4 Are the complainants entitled to non-financial loss?
Both complainants have suffered physically and psychologically
Under the AFCA rules, non-financial loss compensation (capped at $5,400) may be awarded
in circumstances where a complainant has suffered an unusual degree or extent of physical
inconvenience, time taken to resolve the situation or interference with their expectation of
enjoyment or peace of mind.
AFCA takes a conservative approach to compensation for non-financial loss. It is not awarded
when a person suffers the normal degree of inconvenience when a problem occurs.
Moreover, non-financial loss is not intended to be a punishment for any wrongdoing on the
part of the insurer.
I accept the complainants in this matter has suffered an unusual degree of physical
inconvenience and interference with their expectation of enjoyment and peace of mind.
Indeed, each complainant has suffered both physically and psychologically during the
processing of this claim.
Determination | Case number: 976810 Page 10 of 12
For instance, there were significant delays in processing the claim. I am of the opinion these
delays were mostly avoidable and well beyond what would normally be expected, even during
a period of high claims volume.
As explained, significant delays originated from an unsupported denial of the structural roof
damage. Consequently, the complainants have been compelled to watch as the damage to
their home gradually worsened. They now face the possibility of the home being unrepairable.
In addition, the insurer was first made aware the home was uninhabitable June 2022.
However, alternative accommodation was not arranged until March 2023 when the
complainants expressed serious concern for their safety.
In all the circumstances, I am of the opinion the insurer must pay to each complainant the
maximum non-financial loss compensation available under the AFCA Rules. This means the
insurer must pay the sum of $5,400 to each complainant.
2.5 Are the complainants entitled to the cost of an expert
report?
The complainants paid for BC to inspect their property and report following the insurer’s
partial denial of their claim. BC’s report was instrumental in establishing the proximate cause
of the damage to the roof and its consequent failure.
Accordingly, the insurer is required to reimburse the complainants for the cost of the report. In
addition, the insurer must pay interest to the complainants on the cost of BC’s report in
accordance with section 57 of the Insurance Contract Act (1984) (the Act).
2.6 Claim should be resolved in this way
Avoidable delays and claim mismanagement mean time is of the essence
Within 14 days of receiving notice the complainants accept this determination, the insurer
must:-
engage an engineer, roofing specialist, expert builder, or other suitably qualified
expert, together with a mould restoration expert, to draw up a SOW regarding the
necessary repairs and associated works to the roof of the premises and the internal
structures and fixtures of the complainants’ home that have been storm damaged
and/or rain water-damaged; and
cover the cost of ongoing temporary accommodation for the complainants, their son
and their dogs, together with all necessary storage costs, until all repair, restoration
and remediation works are completed and the complainants can return to their
property; and
pay the sum of $5,400 in non-financial loss compensation to each complainant; and
reimburse to the complainants the cost of the BC report and pay interest on that sum
from the date the report was paid for by the complainants to the date of settlement in
accordance with section 57 of the Act. The insurer must also provide to the
complainants an explanation, and breakdown, of how the interest has been
calculated.
Within a further 14 day period of receipt of the SOW, the insurer is to obtain at least one
actionable quotation based upon the SOW, either by way of a tender process or otherwise.
Determination | Case number: 976810 Page 11 of 12
All repairs and remedial works included in the SOW and quotation(s) must also comply with
all current and applicable Commonwealth and Victorian building-related, safety-related and
health-related laws, regulations and codes.
Within a further seven days of receipt of the associated quotation(s), the insurer must elect to
either:
commence the necessary repairs and associated works as soon as possible, or
offer a cash settlement to the complainants comprising a sum equal to the total of
the preferred actionable quotation, plus a 20% contingency on top of this to factor
in the risk of the works passing to the complainants and the likely possibility that
further works may be required.
Finally, given the poor claims management and avoidable delays which have already
occurred, and the deleterious effect these delays and mismanagement have had upon the
complainants, I emphasize to the insurer that time is of the essence.
2.7 Why is this a fair outcome?
The outcome is fair in all the circumstances because:-
The proximate cause of the damage was the storm of October 2021
The insurer erroneously denied part of the claim
Internal damage to the complainant’s home (in particular, mould damage) was caused
by ongoing rain water ingress following the original storm-related damage
Avoidable delays have resulted in additional internal damage, thereby rendering the
complainants’ home uninhabitable. It follows the insurer should pay the costs of
ongoing temporary accommodation and storage costs
Poor management of the claim by the insurer has had a significant and deleterious
impact, both physically and psychologically, on both complainants. It follows that an
award of non-financial loss compensation is fair, reasonable and appropriate
Throughout this complaint AFCA’s approach has remained objective, consistent with
the facts and based upon the law.
Determination | Case number: 976810 Page 12 of 12
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.