Claim for a pit (decommissioned well) under pavers declined as not caused by an insured event

FirmQBE
Decided2024-05-30
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$1,122
Non-financial loss$1,500
Amount claimed—
SourceAFCA PDF

Summary

The complainant's claim for a deep pit found beside his house was declined by the insurer as not caused by an insured event. AFCA upheld the decline but required payment of $1,122 for deck damage from exploratory work and $1,500 for non-financial loss from delay.

Expert evidence showed the pit was a decommissioned well not caused by an insured event, so the claim was outside policy cover, but the insurer's delay in deciding and its damage to the deck warranted payment.

Issues

Subjects and remedies

home or building damagepay compensationpay non financial loss

Related

All QBE determinations · Find similar determinations

Text of the determination

Determination Case number 971441 Financial firm QBE Insurance (Australia) Limited Determination | Case number: 971441 Page 1 of 6 Case number: 971441 26 March 2024 1 Determination overview 1.1 Complaint The complainant holds a home building and contents insurance policy with the financial firm(insurer). On 29 August 2022, the complainant lodged a claim after he discovered a deep pit under pavers at his house. The insurer arranged a number of experts to assess the pit but declined his claim. The insurer says it found no damage caused by an event that is covered by the policy. The complainant wants the insurer to cover the claim. He also says, in the course of assessing the claim, the insurer did insufficient testing and inadequate make safe work. 1.2 Is the insurer entitled to deny the complainant’s claim? Yes. The complainant has not established he more likely than not suffered damage due to an event covered by the policy. That is because, on balance, the expert evidence shows that neither the existence of the pit, nor further erosion at its head, was due to ‘ water or liquid damage ’ , ‘ landslide or subsidence ’ , or any other insured event. Accordingly, the insurer is entitled to deny the claim. Is non-financial loss compensation payable? Yes. The insurer did not handle the claim in a timely manner and this caused unnecessary stress and inconvenience for the complainant. The insurer must pay $1,500 compensation for non-financial loss. Why is the outcome fair? It would be unfair to expect the insurer to cover claims outside the agreed policy terms. The insurer’s offer to pay $1,122 repair costs for damage caused during its exploratory work is fair given it is based on an undisputed builder’s quote. Given the insurer’s delay in deciding t he claim, it is also fair the insurer pays compensation. 1.3 Determination This determination is substantially in favour of the insurer. If the complainant accepts this determination, within 14 days of being notified of the complainant’s acceptance, the insurer is to pay the complainant $1,122 for damage to the complainant’s timber deck and $1,500 compensation for non-financial loss. Determination | Case number: 971441 Page 2 of 6 2 Reasons for determination 2.1 Is the insurer entitled to deny the complainant’s claim ? Yes. The complainant has not established he more likely than not suffered damage due to an event covered by the policy. That is because, on balance, the expert evidence shows that neither the existence of the pit, nor further erosion at its head, was due to ‘ water or liquid damage ’ , ‘ landslide or subsidence ’ , or any other insured event. Accordingly, the insurer is entitled to deny the claim. Background to the claim On 28 August 2022, a large hole (pit) approximately 4.5m deep was discovered at the complainant’s house. The pit is to the north east of the house and under pavers which were found to be at risk of collapsing. When found, the edge of the pit was 1.5m from the house, at its closest point. The complainant claimed on his policy the following day. The insurer’s trades attended that day and fenced off the area of the pit as a make safe. Onus on the complainant to establish a claimable loss The complainant is required to show, on the balance of probabilities (that it is more likely than not) that the loss or damage claimed falls within the terms of the policy. This is known as a claimable loss. Once the complainant has established a claimable loss, the onus shifts to the insurer to establish, on balance, the application of a policy exclusion or that it is otherwise entitled to decline the claim under the policy. Policy cover is subject to terms, conditions, and exclusions The home building policy is made up of the product disclosure statement and the certificate of insurance. There is no dispute the insurer sent these documents to the complainant. The insurer is therefore entitled to rely on the terms of the policy in assessing the claim. The policy is an ‘insured events’ policy. This means not all loss and damage is covered. Rather, only loss or damage caused by one or more of the insured events and not subject to exclusions, is covered. Therefore, to establish a claimable loss, the information must show this. Relevantly, the events covered by the policy include: Water or liquid damage We will cover Loss or damage caused by water or liquid escaping from:  A fixed pipe or an object attached to a pipe, fixed gutter, fixed tank or a drain  … Landslide or subsidence We will cover Loss or damage as a result of a landslide or subsidence if the loss or damage occurs within 72 hours or an insured event being:  …  Liquid escaping from:  A fixed pipe Determination | Case number: 971441 Page 3 of 6 Complainant says damage caused by insured events The complainant says the pit is a sink hole which was caused by a leaking pipe. He says flows of water have been observed at the base of the pit including in October 2022. Further, he says the soil erosion at the head of the pit was caused by leak of water or liquid. Further, the complainant says the insurer failed to undertake sufficient and evidence-based testing. In particular, it did not test further material from the base of the pit. The complainant says the first test of that material was inconclusive because the soil tested was likely to be soil that had fallen from the head of the pit. Accordingly, he says core samples from the base of the pit should be taken and tested. The complainant has not provided an expert report. Experts’ evidence does not support damage caused by insured event The insurer appointed a forensic structural engineer, GP, to assess the pit at the property. GP attended the site three occasions and provided three reports including photos. GP also advised plumbing tests should be conducted. The insurer’s plumbers, PP, conducted and reported on those tests which were then reviewed by GP. In summary, GP says:  the pit is a decommissioned well. Its square cut sides in clay soil is evidence of that  neighbours advised they were aware of a well in the area of the pit that had been decommissioned more than 50 years ago. Therefore, the pit was present at the time of the home’s cons truction  it is assumed that the well was capped but the capping has deteriorated over time  wells are constructed to capture water and bored to depths beneath the water table. Accordingly, water would be expected to be found from time to time at the base of a well  sustained pressure testing of the sewer and stormwater pipes found no change to the amount of water entering the pit. Additional water flowing into the base of the pit would be expected during such testing if a leak from pipe led to the existence of the pit  based on PP’s testing results, water entering the base of the pit was not from the sewer leak  there is no connection between the failure of the capping to the well and a sewer leak at the property. That is shown by the fact that water is entering at the base of the pit and not the head of the pit. Also, the sewer leak is downhill and 14m away from the head of the pit, and  water samples were to be taken from the well to test for waste detergent contaminants that would be present if water entering the pit was from a sewer. As there was soil at the base of the pit, soil was collected for testing. The results were inconclusive. GP said a larger amount of soil was required to complete testing. That further testing was not undertaken. GP said the compl ainant’s request that core samples be taken from the base of the pit was unsafe and unnecessary. Following the recommendation of GP, PP tested for water leaks at the property. PP attended on 15 September 2022 and 25 October 2022 and performed non-invasive leak detection testing. PP’s reports contain photos of the site, tests being conducted and CCTV, and say:  the domestic hot and cold pipework passed pressure testing  hose flowing into the downpipe and rainwater overflow caused no change to the water level in pit  CCTV to the stormwater and the laundry (closest pipe to pit) found no issues Determination | Case number: 971441 Page 4 of 6  the sewer pipes run along the western side of the home and discharge to an easement at the south of the property  deluge testing showed a leak in the sewer pipe at the rear of the property  there is no pipe network and no sewer pipes in the vicinity of the pit  the leak in the sewer line did not influence any water ingress within the pit, and  there are no leaks from the stormwater system. The insurer also engaged engineers, SW, to inspect the site and prepare a report. SW’s report, dated 13 July 2023, contains site photos, aerial photos, water and drainage diagrams, and groundwater data. SW reviewed the relevant reports and testing and says:  the pit is a decommissioned well and not a sink hole. It has the distinct features of a vertical mechanical cut in the ground in a square profile and no record of a growing cavity caused by a leak event. Some loose soil debris had fallen from the head of the void  the leaking pipe was approximately 19m away from the pit. No damage or depressions could be observed in the area surrounding the leak  the leak within the sewer gravity lines has not contributed to the pit, nor was there any damage reported to the other plumbing lines to have caused such an extensive pit in the ground, and  the pit would have become evident after the total failure of the capping from age deterioration over time. The failure of the capping caused the built-up land above the capping to cave in resulting in the opening in the ground. Complainant has not established a claimable loss Having considered all the exchanged information, I am satisfied that the complainant has not established a claimable loss for the damage. That damage is: the existence of the pit itself, and the erosion of soil at the head of the pit. I am persuaded by the expert evidence of GP, SW and PP. That is because their reports and fact-based, show analysis, and are accompanied by photos and, where appropriate, diagrams. The expert evidence shows that, more likely than not, the damage was not caused by ‘ water or liquid damage ’ , ‘ landslide or subsidence ’ , or any other event covered by the policy. That is because:  the expert evidence shows that the pit is a disused well that was decommissioned before the complainant’s house was constructed  despite numerous tests, the expert evidence shows no connection between the broken sewer pipe, or any other leak, and existence of the pit, water at the base of the pit or erosion at the head of the pit  while the complainant says he has seen, and the insurer does not dispute, water at the base of the well including in October 2022 , I am persuaded by the SW’s evidence that minor intermittent natural water flow is expected. That is because SW says a decommissioned well would be connected to an underground aquifer that had subsequently mostly dried up  had the sewer leak been the cause of the claimed damage, erosion of soil would have been expected in the vicinity of the leak. No evidence of soil erosion was found, and  there is no dispute that the head of the pit has widened since discovered by the complainant. However, ‘landslide or subsidence’ covered under the policy is limited to damage that occurs within 72 hours of specific insured events (including water or liquid damage). The exchanged information does not show any link between the widening at the head of the pit and an escape of liquid 72 hours before the erosion, or any other insured event. Determination | Case number: 971441 Page 5 of 6 I have also considered the complainant’s concern that the insurer did not properly assess his claim. In particular, it did not take core soil samples from the base of the pit. However, I am persuaded by SW’s report. SW reviewed the inspections and testing reports, inspected the site and undertook their own analysis. It concluded that, given the evidence available, it is not necessary to take core soil samples from the base of the pit in order to determine the cause of the claimed damage. The complainant has said that the insurer failed to shore up the head of the pit resulting in additional loss of pavers and the hole widening into neighbour ’ s land. The exchanged information shows that, on the day the claim was made, the insurer performed a make safe by fencing off the area around the pit. The insurer’s builders later put a temporary cover over the pit. The complainant has not said what further make safe he believes would have been reasonable that did not require undertaking the repair. As the claim is not covered by the policy it would not be fair to require the insurer to undertake the repair. The insurer accepts that, in the course of its exploratory work, damage was done to the complainant’s timber deck. The insurer has obtained a quote from its builder, AT, for $1,122 for repair of that damage. The complainant has not disputed the amount of that quote. Accordingly, I consider to be a fair settlement for that damage. 2.2 Is non-financial loss compensation payable? Yes. The insurer did not handle the claim in a timely manner and this caused unnecessary stress and inconvenience for the complainant. The insurer must pay $1,500 compensation for non-financial loss. AFCA may award compensation in certain circumstances Under our Rules, AFCA can award up to $5,400 compensation for non-financial loss. This must relate to poor claims handling or other actions of the insurer which cause an unusual degree of stress, delay or inconvenience. We expect complainants to be moderately robust, and we will not award compensation for the ordinary degree of inconvenience involved in making a claim. Complainant entitled to compensation for non-financial loss The insurer has not met its claim handling obligations is assessing this claim. I accept that the insurer arranged a number of experts to assess the claim and perform testing and this took time. However, the insurer took over six months to decide the claim in circumstances that caused unnecessary stress and inconvenience for the complainant. In accordance with what is fair in all the circumstances, I consider an award of $1,500 compensation for non-financial loss should be paid. 2.3 Why is the outcome fair? It would be unfair to expect the insurer to cover claims outside the agreed policy terms. The insurer ’s offer to pay $1,122 repair costs for damage caused during its exploratory work is fa ir given it is based on an undisputed builder’s quote . Given the insurer’s delay in deciding the claim, it is also fair the insurer pays compensation. Determination | Case number: 971441 Page 6 of 6 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.