Determination 970628
Dispute over the fair cost to repair storm damage and temporary accommodation costs
Summary
The insurer accepted a storm water-ingress claim but disputed the repair cost. AFCA ordered a settlement of $188,514.85 less amounts already paid for building damage, plus $2,500 non-financial loss and reimbursement of expert reports up to $5,000, and rejected further accommodation costs.
With no actionable insurer quote and a breakdown in communication, the only fair basis was the complainant's builder quote less the amount already settled on the earthquake claim.
Issues
- Claim amount dispute primary · upheld“The insurer's offer is not based on an actionable quote to repair the damage. The insurer must pay $188,514.85”
- Poor claim handling secondary · upheld“The insurer did not obtain an actionable repair quote to address the building damage; communication sporadic and strained”
- Delay secondary · upheld“caused an unusual degree of stress, inconvenience and delay for the complainant”
- Product terms interpretation secondary · not upheld“insurer has already paid more than the policy entitlement for temporary accommodation”
Subjects and remedies
home or building damagenatural disasterpay claimpay compensationpay non financial loss
Related
Text of the determination
Determination
Case number 970628
Financial firm The Hollard Insurance Company Pty Ltd
Determination | Case number: 970628 Page 1 of 6
Case number: 970628 9 February 2024
1 Determination overview
1.1 Complaint
The complainant holds a home and contents insurance policy underwritten by the financial
firm (insurer). She lodged a claim for damage following a storm event which occurred on 7
November 2022. This caused water ingress into the home.
The insurer accepted the claim. The parties disagree over the fair cost to repair the damage.
The complainant also raised issues with the settlement for temporary accommodation costs
and seeks compensation for non-financial loss.
1.2 Issues and key findings
Is the insurer’s building settlement fair in the circumstances?
No. The insurer’s offer is not based on an actionable quote to repair the damage. The insurer
must pay $188,514.85 (less any building-related amounts already paid) to resolve the building
claim. This amount includes remediation costs. The contents claim has been settled.
Is the insurer required to pay more accommodation costs?
No. The insurer has already paid more than the policy entitlement for these costs.
Is the complainant entitled to an award of compensation?
Yes. The insurer’s handling of the complaint caused an unusual degree of stress,
inconvenience and delay for the complainant. The insurer must pay compensation of $2,500.
Why is the outcome fair?
The communication breakdown between the parties makes it untenable to require further
assessment or negotiation to better determine an exact building repair figure. The proposed
overall settlement fairly compensates the complainant in these circumstances, considering
the other amounts already paid by the insurer.
1.3 Determination
This determination is partially in favour of the complainant. Within 14 days acceptance of this
determination, the insurer is to pay the complainant:
$188,514.85 for repairs and remediation, less any building settlement payments already
issued (this does not include the contents settlement, which has already been paid)
$2,500 in non-financial loss compensation.
The insurer is further required to reimburse the complainant for any expert reports she
obtained, up to a total limit not exceeding $5,000.
There is no need to pay interest or a contingencies uplift in relation to the settlement amount.
Determination | Case number: 970628 Page 2 of 6
2 Reasons for determination
2.1 Is the insurer’s settlement fair and reasonable?
No. The insurer’s offer is not based on an actionable quote to repair the damage. The insurer
must pay $188,514.85 (less any building-related amounts already paid) to resolve the building
claim. This amount includes remediation costs. The contents claim has been settled.
Complainant lodged three separate claims for damage
The complainant lodged three separate claims for damage to her home:
storm damage which reportedly occurred on or about 5 September 2021 (first claim)
earthquake damage from 22 September 2021 (second claim), and
further storm damage which occurred on 7 November 2022 (third claim).
This complaint is solely focussed on the resolution of the third claim, however the handling of
the first two claims are relevant to how and why the third claim was handled.
The insurer denied the first claim. It accepted water entered the home and caused damage
but found this damage pre-dated the claimed storm event. The insurer identified various
maintenance-related issues with the property, which permitted water to enter over time.
The second claim, related to earthquake damage, was lodged shortly after the first claim. The
insurer accepted there was some claimable damage. Builder AJ estimated this damage was
worth $17,124.09. The insurer cash settled the complainant as it said it could not undertake
the repairs, due to the mixture of prior unrelated damage and claim damage.
For the third claim, the insurer agreed there was water ingress into the property which caused
damage. However, due to a communication breakdown with the complainant and the
unrepaired damage from the first two claims, the insurer said it could not conduct repairs for
the third claim. It initially paid $30,796.92 for the building damage but acknowledges this
settlement does not represent the full extent of damage caused.
Later quotes confirmed the extent of damage exceeded the insurer’s early estimates.
Through builder AJ, the insurer estimated this damage would cost $132,342.20. The
complainant obtained her own quote through builder BC for $205,638.94 and seeks this to
resolve the third (building) claim.
Differing views offered on the cause and extent of damage
AJ found the damage was caused by a ‘prolonged and severe weather event’ and the home
was inundated up to a depth of 90cm. It found there was pre-existing damage to the walls and
the ceilings from the earthquake claim.
Photos provided by the complainant show extensive water intrusion into the property and the
effect this had on the carpet and other areas. I accept the home sustained significant
inundation and damage.
A mould report compiled by remediation expert BE for the complainant notes the home was
‘exceptionally mouldy throughout’. BE said it will require a ‘complete strip - out/remediation’ of
all contents and much of the home.
Carpet specialist AA assessed the damage at the property for the complainant. AA wrote that
the extent of water inundation in the home would require a:
Determination | Case number: 970628 Page 3 of 6
full strip out of the 3 bedroom house back to the raw frame. This will include strip
out of all wet areas including, kitchen, bathroom, laundry, toilet and all cabinetry,
fixtures and fittings within.
AA noted all plaster and wall ceiling linings would have to be removed. A significant number
of contents items were considered unsalvageable.
The insurer arranged for internal assessor OG to review the reports. It is not clear if OG
visited the property. OG considers the BE report problematic as there are no ‘analytical
laboratory results’ to confirm its findings. Further, BE was not aware of the prior claims or
damage caused (either excluded or already settled). This impacts the resolution of the matter.
Not all the damage at the home is covered
Photos and the insurer’s expert reports show there is damage unrelated to the storm the
subject of the third claim and water ingress at the home. I accept this damage did not arise
from the claimed event and the insurer should not be required to repair this damage.
However, the reports and provided quotes are not sufficient for me to determine what is
specifically covered and what is not.
Noting the prior claims at the home, I accept there is unrepaired damage which is not related
to the third claim and should not be covered as it either:
arose from the first claim and was not covered by the policy
arose from the second claim and the insurer has already settled the complainant for this,
and/or
was pre-existing damage that is not covered at all.
I further note it is difficult to get an accurate estimate of this damage due to the deterioration
of the relationship between the complainant and the insurer. The insurer will not arrange for
experts to visit the home due to its concerns with some aspects of the complainant’s
behaviour. Some of the reports are based on desktop work and this makes evaluating the
extent of covered damage difficult.
A final estimate of the damage covered under the third claim was submitted by AJ for
$132,342.20. BC submitted a quote for the complainant to cover all damage for $205,638.94.
AJ is not prepared to undertake the work and therefore I am not satisfied this is an actionable
quote for the basis of a cash settlement. The complainant could not go to that builder and
have the work completed for the quoted amount. BC’s quote was prepared on 19 July 2023
and has since expired. The principal issue with this quote is it makes no delineation between
covered and uncovered damage.
Fair that the insurer pays a settled figure to resolve the claim
Given the parties cannot work cooperatively, I do not consider there is a likelihood an exact
calculation of the damage can be obtained. Therefore, I consider the only fair option is to
work with the BC quote as a basis for settlement. It is the only actionable quote compiled to
address the damage.
In accordance with what is fair in the circumstances, I consider the insurer should pay the full
quoted amount ($205,638.94) less $17,124.09 it already settled the complainant for the
second claim. This means a settlement of $188,514.85.
Determination | Case number: 970628 Page 4 of 6
I accept there is likely a substantive amount of damage included in the BC quote which is not
related to the claim. However, I have not made any further deduction for this damage as I
cannot reasonably calculate it based on the exchanged material.
To offset this, I made no allowance for a contingencies uplift, remediation costs or possible
cost increases. I expect these factors likely cancel each other out. It means the complainant
will not have a settlement based on a firm and payable repair figure, however this is
consistent with a home that had considerable pre-existing and unrepaired damage.
I acknowledge this calculation is not precise, the information provided by the parties does not
enable an empirical assessment. However, I am satisfied it is the fairest way to calculate an
acceptable payout of the claim and meet the needs of both parties.
Insurer agreed to pay the contents claim in full
The insurer initially settled the complainant $35,000 for damaged contents, based on a rough
estimate of damage by the complainant.
It has since paid the full policy entitlement for this aspect of the claim ($133,900) less the
amount already paid ($35,000). The insurer deducted an outstanding premium amount
($233.50) from this settlement. The insurer also agreed to pay the policy limits for:
document replacement, being $500
food spoilage, being $500.
The complainant accepted settlement for $99,666.50 for these losses. The insurer processed
a payment on 28 September 2023. I am satisfied nothing further is required on this issue.
The insurer noted it will also cover the ‘reasonable and necessary’ costs for re moving debris
from the property, subject to receipt of invoices. Any ‘reasonable and necessary’ amount
incurred may be claimed by the complainant to the insurer when the repairs are completed.
She will need to provide invoices for the work.
Similarly, if it has not already done so, the insurer must reimburse the complainant for the
costs she incurred to obtain expert reports. The complainant must provide evidence of
payment and the total costs claimable may not exceed $5,000 as detailed in AFCA Rule D.5.
2.2 Is the insurer required to pay more accommodation costs?
No. The insurer has already paid more than the policy entitlement for these costs.
Insurer not required to pay additional temporary accommodation costs
The amount of water which went through the home and the extent of mould infestation meant
it was not habitable for the complainant.
Soon after the loss, the complainant arranged for an onsite caravan to be delivered for her
use. This permitted her to stay on the property.
The insurer covered this expense over a prolonged period and ultimately paid temporary
accommodation costs of $78,034. This included a final ‘lump sum’ payment of $33,470 to the
complainant in June 2023.
The insurer says the amount paid far exceeds the maximum entitlement under the policy
(which is the lesser of 12 months’ accommodation expenses or 10% of the sum insured). The
policy provided building cover of up to $334,700 meaning the maximum entitlement does not
exceed $33,470.
Determination | Case number: 970628 Page 5 of 6
I accept there has been delays and the insurer has contributed to these. I am satisfied the
amount paid is fair in the circumstances and there should be no further entitlement to
temporary accommodation under the policy.
2.3 Is the complainant entitled to an award of compensation?
Yes. The insurer’s handling of the complaint caused an unusual degree of stress,
inconvenience and delay for the complainant. The insurer must pay compensation of $2,500.
AFCA can award compensation for non-financial loss
Under our Rules, AFCA can award up to $5,400 compensation for non-financial loss. This
must relate to poor claims handling or other actions of the insurer which cause an unusual
degree of stress, delay, or inconvenience.
We expect complainants to be moderately robust, and we will not award compensation for the
ordinary degree of inconvenience involved in making a claim.
Insurer to pay the complainant $2,500 compensation for non-financial loss
I acknowledge both parties have endured frustration in attempting to resolve this matter.
The insurer handled aspects of the claim well. Parts of the claim were settled with an obvious
emphasis on being fair to the complainant. However, the insurer also made some errors. I
accept these caused an unusual degree of stress, inconvenience and delay for the
complainant.
Resolution of the contents claim was protracted and difficult. The insurer did not obtain an
actionable repair quote to address the building damage. Some of the expert reports were
unhelpful. It is apparent communication with the complainant has been sporadic and strained.
I am satisfied an award of compensation is warranted and fair. The insurer must pay the
complainant $2,500 compensation for non-financial loss.
2.4 Why is the outcome fair?
The communication breakdown between the parties makes it untenable to require further
assessment or negotiation to better determine an exact building repair figure. The proposed
overall settlement fairly compensates the complainant in these circumstances, considering
the other amounts already paid by the insurer.
Determination | Case number: 970628 Page 6 of 6
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.