Dispute over the fair cost to repair storm damage and temporary accommodation costs

FirmHollard
Decided2024-02-13
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$188,515
Non-financial loss$2,500
Amount claimed$205,639
SourceAFCA PDF

Summary

The insurer accepted a storm water-ingress claim but disputed the repair cost. AFCA ordered a settlement of $188,514.85 less amounts already paid for building damage, plus $2,500 non-financial loss and reimbursement of expert reports up to $5,000, and rejected further accommodation costs.

With no actionable insurer quote and a breakdown in communication, the only fair basis was the complainant's builder quote less the amount already settled on the earthquake claim.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay compensationpay non financial loss

Related

All Hollard determinations · Find similar determinations

Text of the determination

Determination Case number 970628 Financial firm The Hollard Insurance Company Pty Ltd Determination | Case number: 970628 Page 1 of 6 Case number: 970628 9 February 2024 1 Determination overview 1.1 Complaint The complainant holds a home and contents insurance policy underwritten by the financial firm (insurer). She lodged a claim for damage following a storm event which occurred on 7 November 2022. This caused water ingress into the home. The insurer accepted the claim. The parties disagree over the fair cost to repair the damage. The complainant also raised issues with the settlement for temporary accommodation costs and seeks compensation for non-financial loss. 1.2 Issues and key findings Is the insurer’s building settlement fair in the circumstances? No. The insurer’s offer is not based on an actionable quote to repair the damage. The insurer must pay $188,514.85 (less any building-related amounts already paid) to resolve the building claim. This amount includes remediation costs. The contents claim has been settled. Is the insurer required to pay more accommodation costs? No. The insurer has already paid more than the policy entitlement for these costs. Is the complainant entitled to an award of compensation? Yes. The insurer’s handling of the complaint caused an unusual degree of stress, inconvenience and delay for the complainant. The insurer must pay compensation of $2,500. Why is the outcome fair? The communication breakdown between the parties makes it untenable to require further assessment or negotiation to better determine an exact building repair figure. The proposed overall settlement fairly compensates the complainant in these circumstances, considering the other amounts already paid by the insurer. 1.3 Determination This determination is partially in favour of the complainant. Within 14 days acceptance of this determination, the insurer is to pay the complainant:  $188,514.85 for repairs and remediation, less any building settlement payments already issued (this does not include the contents settlement, which has already been paid)  $2,500 in non-financial loss compensation. The insurer is further required to reimburse the complainant for any expert reports she obtained, up to a total limit not exceeding $5,000. There is no need to pay interest or a contingencies uplift in relation to the settlement amount. Determination | Case number: 970628 Page 2 of 6 2 Reasons for determination 2.1 Is the insurer’s settlement fair and reasonable? No. The insurer’s offer is not based on an actionable quote to repair the damage. The insurer must pay $188,514.85 (less any building-related amounts already paid) to resolve the building claim. This amount includes remediation costs. The contents claim has been settled. Complainant lodged three separate claims for damage The complainant lodged three separate claims for damage to her home:  storm damage which reportedly occurred on or about 5 September 2021 (first claim)  earthquake damage from 22 September 2021 (second claim), and  further storm damage which occurred on 7 November 2022 (third claim). This complaint is solely focussed on the resolution of the third claim, however the handling of the first two claims are relevant to how and why the third claim was handled. The insurer denied the first claim. It accepted water entered the home and caused damage but found this damage pre-dated the claimed storm event. The insurer identified various maintenance-related issues with the property, which permitted water to enter over time. The second claim, related to earthquake damage, was lodged shortly after the first claim. The insurer accepted there was some claimable damage. Builder AJ estimated this damage was worth $17,124.09. The insurer cash settled the complainant as it said it could not undertake the repairs, due to the mixture of prior unrelated damage and claim damage. For the third claim, the insurer agreed there was water ingress into the property which caused damage. However, due to a communication breakdown with the complainant and the unrepaired damage from the first two claims, the insurer said it could not conduct repairs for the third claim. It initially paid $30,796.92 for the building damage but acknowledges this settlement does not represent the full extent of damage caused. Later quotes confirmed the extent of damage exceeded the insurer’s early estimates. Through builder AJ, the insurer estimated this damage would cost $132,342.20. The complainant obtained her own quote through builder BC for $205,638.94 and seeks this to resolve the third (building) claim. Differing views offered on the cause and extent of damage AJ found the damage was caused by a ‘prolonged and severe weather event’ and the home was inundated up to a depth of 90cm. It found there was pre-existing damage to the walls and the ceilings from the earthquake claim. Photos provided by the complainant show extensive water intrusion into the property and the effect this had on the carpet and other areas. I accept the home sustained significant inundation and damage. A mould report compiled by remediation expert BE for the complainant notes the home was ‘exceptionally mouldy throughout’. BE said it will require a ‘complete strip - out/remediation’ of all contents and much of the home. Carpet specialist AA assessed the damage at the property for the complainant. AA wrote that the extent of water inundation in the home would require a: Determination | Case number: 970628 Page 3 of 6 full strip out of the 3 bedroom house back to the raw frame. This will include strip out of all wet areas including, kitchen, bathroom, laundry, toilet and all cabinetry, fixtures and fittings within. AA noted all plaster and wall ceiling linings would have to be removed. A significant number of contents items were considered unsalvageable. The insurer arranged for internal assessor OG to review the reports. It is not clear if OG visited the property. OG considers the BE report problematic as there are no ‘analytical laboratory results’ to confirm its findings. Further, BE was not aware of the prior claims or damage caused (either excluded or already settled). This impacts the resolution of the matter. Not all the damage at the home is covered Photos and the insurer’s expert reports show there is damage unrelated to the storm the subject of the third claim and water ingress at the home. I accept this damage did not arise from the claimed event and the insurer should not be required to repair this damage. However, the reports and provided quotes are not sufficient for me to determine what is specifically covered and what is not. Noting the prior claims at the home, I accept there is unrepaired damage which is not related to the third claim and should not be covered as it either:  arose from the first claim and was not covered by the policy  arose from the second claim and the insurer has already settled the complainant for this, and/or  was pre-existing damage that is not covered at all. I further note it is difficult to get an accurate estimate of this damage due to the deterioration of the relationship between the complainant and the insurer. The insurer will not arrange for experts to visit the home due to its concerns with some aspects of the complainant’s behaviour. Some of the reports are based on desktop work and this makes evaluating the extent of covered damage difficult. A final estimate of the damage covered under the third claim was submitted by AJ for $132,342.20. BC submitted a quote for the complainant to cover all damage for $205,638.94. AJ is not prepared to undertake the work and therefore I am not satisfied this is an actionable quote for the basis of a cash settlement. The complainant could not go to that builder and have the work completed for the quoted amount. BC’s quote was prepared on 19 July 2023 and has since expired. The principal issue with this quote is it makes no delineation between covered and uncovered damage. Fair that the insurer pays a settled figure to resolve the claim Given the parties cannot work cooperatively, I do not consider there is a likelihood an exact calculation of the damage can be obtained. Therefore, I consider the only fair option is to work with the BC quote as a basis for settlement. It is the only actionable quote compiled to address the damage. In accordance with what is fair in the circumstances, I consider the insurer should pay the full quoted amount ($205,638.94) less $17,124.09 it already settled the complainant for the second claim. This means a settlement of $188,514.85. Determination | Case number: 970628 Page 4 of 6 I accept there is likely a substantive amount of damage included in the BC quote which is not related to the claim. However, I have not made any further deduction for this damage as I cannot reasonably calculate it based on the exchanged material. To offset this, I made no allowance for a contingencies uplift, remediation costs or possible cost increases. I expect these factors likely cancel each other out. It means the complainant will not have a settlement based on a firm and payable repair figure, however this is consistent with a home that had considerable pre-existing and unrepaired damage. I acknowledge this calculation is not precise, the information provided by the parties does not enable an empirical assessment. However, I am satisfied it is the fairest way to calculate an acceptable payout of the claim and meet the needs of both parties. Insurer agreed to pay the contents claim in full The insurer initially settled the complainant $35,000 for damaged contents, based on a rough estimate of damage by the complainant. It has since paid the full policy entitlement for this aspect of the claim ($133,900) less the amount already paid ($35,000). The insurer deducted an outstanding premium amount ($233.50) from this settlement. The insurer also agreed to pay the policy limits for:  document replacement, being $500  food spoilage, being $500. The complainant accepted settlement for $99,666.50 for these losses. The insurer processed a payment on 28 September 2023. I am satisfied nothing further is required on this issue. The insurer noted it will also cover the ‘reasonable and necessary’ costs for re moving debris from the property, subject to receipt of invoices. Any ‘reasonable and necessary’ amount incurred may be claimed by the complainant to the insurer when the repairs are completed. She will need to provide invoices for the work. Similarly, if it has not already done so, the insurer must reimburse the complainant for the costs she incurred to obtain expert reports. The complainant must provide evidence of payment and the total costs claimable may not exceed $5,000 as detailed in AFCA Rule D.5. 2.2 Is the insurer required to pay more accommodation costs? No. The insurer has already paid more than the policy entitlement for these costs. Insurer not required to pay additional temporary accommodation costs The amount of water which went through the home and the extent of mould infestation meant it was not habitable for the complainant. Soon after the loss, the complainant arranged for an onsite caravan to be delivered for her use. This permitted her to stay on the property. The insurer covered this expense over a prolonged period and ultimately paid temporary accommodation costs of $78,034. This included a final ‘lump sum’ payment of $33,470 to the complainant in June 2023. The insurer says the amount paid far exceeds the maximum entitlement under the policy (which is the lesser of 12 months’ accommodation expenses or 10% of the sum insured). The policy provided building cover of up to $334,700 meaning the maximum entitlement does not exceed $33,470. Determination | Case number: 970628 Page 5 of 6 I accept there has been delays and the insurer has contributed to these. I am satisfied the amount paid is fair in the circumstances and there should be no further entitlement to temporary accommodation under the policy. 2.3 Is the complainant entitled to an award of compensation? Yes. The insurer’s handling of the complaint caused an unusual degree of stress, inconvenience and delay for the complainant. The insurer must pay compensation of $2,500. AFCA can award compensation for non-financial loss Under our Rules, AFCA can award up to $5,400 compensation for non-financial loss. This must relate to poor claims handling or other actions of the insurer which cause an unusual degree of stress, delay, or inconvenience. We expect complainants to be moderately robust, and we will not award compensation for the ordinary degree of inconvenience involved in making a claim. Insurer to pay the complainant $2,500 compensation for non-financial loss I acknowledge both parties have endured frustration in attempting to resolve this matter. The insurer handled aspects of the claim well. Parts of the claim were settled with an obvious emphasis on being fair to the complainant. However, the insurer also made some errors. I accept these caused an unusual degree of stress, inconvenience and delay for the complainant. Resolution of the contents claim was protracted and difficult. The insurer did not obtain an actionable repair quote to address the building damage. Some of the expert reports were unhelpful. It is apparent communication with the complainant has been sporadic and strained. I am satisfied an award of compensation is warranted and fair. The insurer must pay the complainant $2,500 compensation for non-financial loss. 2.4 Why is the outcome fair? The communication breakdown between the parties makes it untenable to require further assessment or negotiation to better determine an exact building repair figure. The proposed overall settlement fairly compensates the complainant in these circumstances, considering the other amounts already paid by the insurer. Determination | Case number: 970628 Page 6 of 6 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.