Claim denial for movement damage to investment property, relying on earth movement and defects exclusions
Text of the determination
Determination
Case number 969751
Financial firm Hollard Insurance Partners Limited
Determination | Case number: 969751 Page 2 of 11
Case number: 969751 6 October 2023
1 Determination overview
1.1 Complaint
The complainant holds landlord insurance with the financial firm (insurer). On 9 January 2022,
he lodged a claim for significant movement and cracking damage to his investment property.
The insurer has denied the claim. It says the damage was not the result of an insured event
covered by the policy. Rather, the damage was caused by the building’s footings being
undermined by a stormwater pit built by the local council, and ground movement due to a
long-term stormwater pipe leak. Damage from such causes is excluded by the policy terms.
The complainant maintains that the damage has been caused by escape of liquid (EOL),
which is an insured event. He wants the insurer to accept the claim and reimburse his
professional costs. The complainant is also dissatisfied with the insurer’s claim handling.
1.2 Issues and key findings
Is the insurer entitled to deny the claim?
No. The EOL insured event specifically covers EOL from a stormwater pipe. Damage caused
by a leaking stormwater pipe usually involves ground and associated building movement,
which is what occurred in this case. A claimable EOL loss has been established and the
panel is not satisfied the insurer has shown a reasonable entitlement to exclude the claim.
Is the insurer required to reimburse costs?
Yes. The insurer’s delays meant that the complainant acted reasonably in ob taining an expert
report from FM, engineer, which assisted him in establishing his claim. The insurer is to
reimburse the professional costs the complainant paid to FM. It is also reasonable that the
insurer reimburses proven make safe repair costs the complainant incurred (if any).
Is non-financial loss compensation payable?
Yes. The insurer caused extensive delays, communicated poorly and failed to treat the
complainant as a vulnerable customer. The delays and poor claim handling each caused the
complainant major stress and inconvenience and significantly affected his mental health.
Why is the outcome fair?
It is fair that the insurer accepts the claim because the complainant has established a
claimable loss and the insurer has not shown a reasonable entitlement to exclude the claim.
The insurer’s delays and poor claim handling mean it is fai r that the insurer reimburses the
complainant’s costs and pays him non -financial loss compensation.
1.3 Determination
This determination is in favour of the complainant.
Determination | Case number: 969751 Page 3 of 11
If the complainant provides written notice he accepts this determination (notice), the insurer is
required to:
accept the claim in full and assess it in accordance with the policy’s terms and conditions .
In doing so, the insurer is to consider whether any policy additional benefits (such as for
loss of rent) apply
if it elects to pay the complainant a cash settlement rather than attending to covered
repairs, it must pay an amount based on a current quotation actionable by a retail
customer, and the quoted amount must be increased by a 20% contingencies uplift
within 14 days of receiving the notice, reimburse the complainant the $2,803 he paid to
FM, and pay interest on that amount pursuant to section 57 of the Insurance Contracts Act,
1984 (Cth) (ICA), from 24 May 2023 to the date reimbursement is paid
within 14 days of receiving proof of payment from the complainant, reimburse the
complainant for make safe repair costs he incurred, and pay interest on those amounts
pursuant to section 57 of the ICA, from the date of each payment until to the date
reimbursement is paid
within 14 days of receiving the notice, pay the complainant $2,700 compensation for the
stress and inconvenience caused by its delay
within 14 days of receiving the notice, pay the complainant $5,400 compensation for the
stress and inconvenience caused by its poor claim handling (including failure to treat the
complainant as a vulnerable customer).
Determination | Case number: 969751 Page 4 of 11
2 Reasons for determination
2.1 Is the insurer entitled to deny the claim?
No. The EOL insured event specifically covers EOL from a stormwater pipe. Damage caused
by a leaking stormwater pipe usually involves ground and associated building movement,
which is what occurred in this case. A claimable EOL loss has been established and the
panel is not satisfied the insurer has shown a reasonable entitlement to exclude the claim.
Complainant must show a claimable loss under the policy
The complainant is required to show on the balance of probabilities (that it is more likely than
not), that he suffered a claimable loss under the policy. This means he must show the loss
was caused by a risk for which he is insured.
Subject to the terms and conditions set out in the product disclosure statement (PDS), the
complainant’s policy covers damage to his investment property caused by a listed insured
event. Those events include ‘Sudden escape of liquid’:
Your building and/or contents are covered for loss or damage caused by the
sudden and unexpected escape of liquid from any:
• water, stormwater or sewerage pipe (but not a garden hose)
…
On 9 January 2022, the complainant lodged a claim with the insurer. He said that his tenant
had notified him of cracks and other movement damage affecting his investment property.
Once the complainant proves the existence of a claimable loss, the insurer is liable for the
loss unless it shows an exclusion or limiting condition applies. The insurer has the onus of
proving on the balance of probabilities the application of the exclusion or condition.
Where there are multiple potential causes of loss, it is necessary to determine the proximate
cause. The proximate cause of a loss is the dominant, effective or operative cause. It does
not have to be the first, the last or the only cause.
Insurer has denied the claim
Following claim lodgement, the insurer appointed builder UB. On 12 January 2022, UB
inspected the property and reported:
the presence of damage consistent with foundation movement. The south west corner of
the dwelling was sinking, opening up large cracks.
the adjacent council footpath had sunk up to 75mm at the back of a stormwater pit (photos
of the area suggest it had only recently been resurfaced before sinking)
the complainant said that works to the stormwater pit had been completed more than two
years earlier
however, the damage to the dwelling appeared to be recent
a causation report from a specialist was required.
The insurer ’s appointed engineer, PG, inspected the property on 22 February 2022, and
reported that the property was at risk of failure and immediate preventative measures were
Determination | Case number: 969751 Page 5 of 11
required. It noted that around the time the damage appeared, depressions in the adjacent
footpath had been filled with asphalt.
PG concluded:
the sinking and subsequent damage to the residence is caused by ground
movement in the road reserve adjacent to the property boundary. There is
existing infrastructure (all presumably local council assets) that has potentially
failed exposing the insured’s house to severe ground movement resulting in
extensive damage. Given the damage observed during the visit, and photos of
previous repairs taken during January 2022, I believe the underground
stormwater pipe has either been crushed or come loose from its socket. This has
resulted in the pipe failing to distribute the stormwater to the adjacent pit ensuring
the immediate area has become saturated during all rain events.
On 7 April 2022, the insurer wrote to the complainant advising that his claim had been denied.
The insurer relied on a general exclusion set out on page 54 of the PDS, which states:
Under this policy there is no cover provided for any loss, damage or liability
caused directly or indirectly by or in any way connected with:
…
10. the vibration, settling, shrinking or expanding of earth or any building,
foundation, wall, pavement or path (except under a 'Lightning', 'Earthquake',
'Explosion' or 'Sudden Impact' claim);
As the complainant disagreed with the insurer’s claim decisi on, the insurer engaged a second
engineer, SE. While SE inspected the property on 7 July 2022, its report is dated 22 May
2023. The complainant advised SE that damage to the property’s external wall was first
noticed in early January 2022, soon after works on the adjacent footpath were completed.
According to SE, it obtained a leak detection report from MW plumber. MW confirmed there
was EOL from the stormwater pit in the footpath into the surrounding soils. CCTV inspection
of the stormwater line (pipe) located a crack in the drain near the front pit.
SE concluded that the proximate cause of the movement damage to the dwelling was:
the excavation and construction of the local council’s stormwater pit encroaching within the
angle of repose of the dwelling’s f ootings, undermining and destabilising them, and
a long-term leak from the defective stormwater pit and, potentially, water escaping from a
cracked stormwater drainage pipe near the front of the stormwater pit, elevating the soil
moisture of the highly reactive soils at the site.
SE noted that the extent of damage was severe and could not be remediated. Rectification
would require demolition and rebuilding of a section of the western wall and the entire
southern wall and façade. The new walls would require new footings. This was consistent
with multiple failed attempts at make safe repairs by the insurer, from 17 February 2022.
In referring to the site’s highly reactive soils, SE relied on a geotechnical report by SG,
geologist. SG classified the soils as H2 (highly reactive clay). It also noted that the test site
closest to the adjacent stormwater pipe had the highest moisture content.
Determination | Case number: 969751 Page 6 of 11
On 31 May 2023, the insurer provided the complainant with an updated claim decision. It
concluded that the damage claimed ha d not been caused by an insured event. Adopting SE’s
conclusions, the insurer said the damage was instead due to excluded causes:
in relation to the leak, PDS general exclusion 10 (outlined above) applies, and
in relation to the stormwater pit’s excavation /construction, PDS general exclusion 1
applies. That exclusion precludes cover for loss or damage caused directly or indirectly by
or in any way connected with ‘defects, structural or design faults, faulty workmanship or
faulty design’.
Complainant says the claim should be accepted
The complainant maintains that the claim should be accepted as covered under the EOL
insured event.
His appointed engineer FM inspected the property on 6 April 2023. FM said the movement
damage began on and had continued since January 2022. It concluded:
The primary cause of foundation settlement, movement and damage at the south
west corner of my client’s dwelling is as a result of founding soil bearing failure
due to soil saturation which has been exacerbated by the construction of a
roadway side entry drainage pits that undermined my client’s dwelling foundations
located adjacent to the roadway drainage pits.
The source of the water which caused the saturation of the founding soils is more
likely to be from a leaking service …
FM noted two stormwater pits had been installed over ten years ago, and there had been no
visual signs of movement damage before December 2021. The pits had recently been
repaired by grout patching of voids around their walls. FM said the repairs indicated the pits
had ‘most likely been leaking water into the surrounding soils, including the building
foundation soils which are next to the pit walls.’
Like SE, FM considered that the damage was ‘beyond the realm of remediation’. It said that
the south west section of the dwelling would require demolition and reinstatement.
Insurer is not entitled to deny the claim
To establish a claimable loss under the EOL insured event, the complainant must show on
the balance of probabilities that damage has been caused by the sudden and unexpected
EOL from specified sources. The specified sources include stormwater pipes.
The panel is satisfied the complainant has established a claimable EOL loss. This is because:
each of PG, SE and FM refer to EOL from the stormwater pit/pipe as causing damage
given the proximity between the council’s works on the footpath/pit and the rapid
manifestation of significant damage, and the comments of UB, PG and FM, it is reasonable
to conclude that the EOL was on balance ‘sudden and unexpected’
even assuming that there has been a series of leaks from the stormwater pit/pipe, the
policy in effect treats as a single incident ‘ a series of incidents arising from the same
originating cause, that was unexpected and has directly caused the loss or damage ’ .
As the complainant has established a claimable loss, the insurer is liable unless it can show
on the balance of probabilities that a policy exclusion applies.
Determination | Case number: 969751 Page 7 of 11
PG, SE and FM each refer to the stormwater pit’s excavation/construction as contributing to
the damage to the insured property. However, the panel is not satisfied the insurer has
established it is entitled to rely on general exclusion 1.
There is no evid ence the pit’s excavation/construction was the proximate cause of loss. SE
says it was a proximate cause, along with the EOL. Moreover, PG and FM both say the EOL
was the primary cause of damage. The panel therefore accepts that the EOL was the
proximate c ause of damage, not the pit’s excavation/construction.
General exclusion 10 is very broadly worded, purporting to exclude damage caused by or in
any way connected with the vibration, settling, shrinking or expanding of:
earth, or
any building, foundation, wall, pavement or path.
Most building insurance policies cover damage caused by water leaking from pipes but
exclude cover for damage caused by certain types of earth movement.
AFCA has taken a consistent approach to policy exclusions for earth movement:
if damage is caused by normal earth movement (e.g. ordinary settlement, natural erosion,
or movement due to seasonal moisture variation), then earth movement is the proximate
cause of the damage, and the exclusion will apply
if damage is caused by earth movement that was caused by an insured event (e.g. storm,
flood, or EOL from water pipes), then the insured event is the proximate cause of the
damage, and the exclusion will not apply.
This approach is consistent with well-established legal principles of insurance policy
interpretation that:
a policy is a commercial contract and should be given a businesslike interpretation
a construction that would defeat the commercial purpo se of the contract of indemnity is to
be avoided
exclusion clauses are to be interp reted by construing the clause according to its natural
and ordinary meaning, read in the light of the contract as a whole
an exclusion clause should not be interpreted so as to circumscribe excessively the
insuring clause .
Taking into account AFCA’s appro ach and those legal principles, the panel is not satisfied the
insurer has shown a reasonable entitlement to rely on general exclusion 10, because:
the expert evidence shows the proximate cause of damage was the EOL, with earth
movement a consequence of the EOL
general exclusion 10 only applies to the vibration, settling, shrinking or expanding of earth.
None of those forms of earth movement occurred. Rather, the founding soils lost load
bearing capacity due to being saturated
the EOL insured event specifically covers EOL from a stormwater or sewerage pipe
the most likely damage caused by a leaking stormwater or a sewerage pipe involves
ground and associated building movement, which is what occurred in this case
the policy does not define ‘settle’, so it is to be given its natural and ordinary meaning. The
Macquarie Dictionary relevantly defines ‘settle’ as ‘to sink down gradually; subside’. The
movement affecting the complainant’s building was rapid and significant, not gradual
if general exclusion 10 were permitted to apply to rapid and significant building movement
proximately caused by EOL from a stormwater pipe, the coverage under the EOL insured
event would be excessively and unreasonably circumscribed.
As the complainant has established a claimable EOL loss and the insurer has not shown a
policy exclusion applies, the insurer is required to accept the claim in full and assess and
Determination | Case number: 969751 Page 8 of 11
settle it in accordance with the policy’s terms and conditions. In doing so, the insurer is to
consider whether any policy additional benefits (such as for loss of rent) apply and to cover
those, as appropriate.
If the insurer elects to pay the complainant a cash settlement rather than attending to covered
repairs, it must pay an amount based on a current quotation actionable by a retail customer,
and the quoted amount must be increased by a 20% uplift to allow for contingencies and loss
of the lifetime guarantee that otherwise applies to insurer approved repair work.
2.2 Is the insurer required to reimburse costs?
Yes. The insurer’s delays meant that the complainant acted reasonably in obtaining an expert
report from FM, engineer, which assisted him in establishing his claim. The insurer is to
reimburse the professional costs the complainant paid to FM. It is also reasonable that the
insurer reimburses proven make safe repair costs the complainant incurred (if any).
AFCA may require insurer to contribute to a complainant’s professional costs
The AFCA Rules enable AFCA to require an insurer to contribute to the professional costs
incurred by the complainant. These costs are, however, usually capped at a total of $5,000,
unless special circumstances apply.
When considering whether to require an insurer to make a costs contribution, AFCA takes
into account matters such as the complexity of the complaint and whether the particular
complainant needed to incur costs to understand or establish their claim.
Insurer is required to reimburse complainant costs paid to FM
After the complainant disagreed with its claim denial issued on 7 April 2022, the insurer
agreed to obtain a second engineering opinion on causation. Despite inspecting the property
on 7 July 2022, SE did not provide a report until 22 May 2023. The insurer provided the
complainant with a copy of that report on 31 May 2023.
In the circumstances, the panel is satisfied that the complainant acted reasonably in seeking
his own causation opinion from FM before the insurer provided him with SE’s report. Further,
FM has assisted the complainant in establishing his claim is covered under the policy.
The complainant has provided a copy of FM’s invoice dated 9 May 2023 for preparation of its
report. After deducting the $900 deposit the complainant previously paid, the invoice totals
$1,903. The invoice required payment within 14 days (by 23 May 2023).
The total amount the complainant paid FM was $2,803. The insurer is required to reimburse
that amount to him. It is also to pay interest pursuant to section 57 of the ICA from 24 May
2023 to the date the reimbursement is paid.
Insurer is required to reimburse complainant make safe repair costs
In June 2023, the insurer told the complainant he was responsible for any further make safe
repairs. By then, the complainant had received notices from the local council stating that the
insured property presented a public health and safety risk. The notices required emergency
works to be undertaken, with the maximum fine for non-compliance exceeding $82,000.
Accordingly, it may be that the complainant incurred costs attending to make safe repairs. As
the insurer is required to accept the claim, it must reimburse those costs (under the policy and
not as professional costs subject to the $5,000 AFCA limit) upon receiving proof of payment
Determination | Case number: 969751 Page 9 of 11
from the complainant. It is also to pay interest on those amounts pursuant to section 57 of the
ICA, from the date of each payment until to the date reimbursement is paid.
2.3 Is non-financial loss compensation payable?
Yes. The insurer caused extensive delays, communicated poorly and failed to treat the
complainant as a vulnerable customer. The delays and poor claim handling each caused the
complainant major stress and inconvenience and significantly affected his mental health.
AFCA can award compensation for poor claim handling
Under paragraph D.3 of the AFCA Rules, we may award compensation for non-financial loss
(capped at $5,400 per claim ) where the insurer’s actions have caused an unusual amount of:
physical inconvenience
time taken to resolve the situation
interference with the complainant’s expectation of enjoyment or peace of mind.
AFCA takes the view that a ‘claim’ refers to the set of facts that, put together, gives the
complainant the right to ask for a remedy. The $5,400 compensation cap for non-financial
loss claims applies to each claim, so AFCA can award a complainant more than $5,400 in
total in a complaint if they have several claims.
When considering an award for non-financial loss, AFCA considers the severity and impact of
the insurer’s conduct on the particular complainant.
Insurer has caused major stress and inconvenience
The complainant says he relies on rent from the insured property as his source of income. He
says the insurer’s extensive delays, poor communication and lack of timely updates have
caused him major stress and inconvenience. The complainant particularly highlights that the
insurer provided no guidance or support in relation to the notices from the local council.
Having reviewed the information submitted by the parties, including the insurer’s claim notes,
the panel is satisfied the insurer has unreasonably caused the complainant extreme distress,
frustration and inconvenience. These matters have significantly affected his mental health.
T he insurer’s extensive delay s amount to a stand- alone ‘claim’ in assessing non-financial
loss. Those delays include more than ten months between informing the complainant it would
obtain a second causation report (from SE) and informing him of SE’s opinion. As it engaged
SE, the insurer is respons ible for SE’s conduct.
The insurer’s poor claim handling is a second stand-alone claim giving the complainant a right
to request non- financial loss compensation. The insurer’s claim notes contain many instances
of poor communication and of the complainant having to request updates. There is also
nothing to show the insurer provided the complainant any material assistance with the council
notices.
There were clear indications during the claim that the complainant was a vulnerable
customer. That was certainly confirmed in a telephone conversation with the insurer in mid
January 2023. The complainant advised he was having difficulty sleeping and his health was
being affected. However, the insurer did not treat the complainant as being vulnerable or offer
him any additional support.
The insurer has not provided any explanation or apology for its delays or its poor claim
handling.
Determination | Case number: 969751 Page 10 of 11
The panel is satisfied that the insurer is to pay two claims for non-financial loss
compensation:
$2,700 for stress and inconvenience caused by delays
$5,400 for stress and inconvenience caused by poor claim handling.
2.4 Why is the outcome fair?
It is fair that the insurer accepts the claim because the complainant has established a
claimable loss and the insurer has not shown a reasonable entitlement to exclude the claim.
The insurer’s delays and poor claim handling mean it is fair that the insurer reimburses the
complainant’s costs and pays him non -financial loss compensation.
Determination | Case number: 969751 Page 11 of 11
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel
includes:
an ombudsman
a member with significant experience in consumer and small business advocacy
a member with extensive experience in the insurance industry.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.