Insurer refused to cover waterproofing and full bathroom reinstatement, offered an inadequate cash settlement, and delayed the claim
Text of the determination
Determination
Case number 966959
Financial firm Youi Pty Ltd
Determination | Case number: 966959 Page 1 of 8
Case number: 966959 20 October 2023
1 Determination overview
1.1 Complaint
The complainant held a home insurance policy with the financial firm (insurer). She lodged a
claim for water damage to the insured property arising from a storm in January 2022.
The insurer appointed contractors who undertook demolition and remediation works to the
master bedroom and bathroom. The property remained in a state of disrepair for months.
The insurer agreed to cover repairs to the bedroom. The insurer initially refused to cover the
cost of repairing the bathroom as there was no waterproofing and redoing the bathroom
would be an upgrade. The insurer later offered to cash settle the cost of repairing only the
damaged parts of the bathroom, excluding waterproofing.
The complainant wanted to sell the house and engaged her own builder to complete repairs
to the bedroom and bathroom, including waterproofing. The house has since been sold and
the complainant seeks reimbursement of the cost of repairs from the insurer.
The insurer disputes the cost of repairs claimed by the complainant.
1.2 Issues and key findings
Is the insurer required to pay for the waterproofing?
Yes. The insurer is to pay the cost of reinstating the bathroom to its pre-incident condition
including the cost of waterproofing as this is necessary to meet current building regulations.
How much is the insurer required to pay?
The insurer is to reimburse the complainant for the MC invoice in the amount of $41,140 and
the cost of the air conditioner in the amount of $1,172.60, plus statutory interest.
Is the insurer required to pay non-financial loss compensation?
Yes. The claim was subject to delays and it is fair for the insurer to pay the complainant an
additional $500 compensation for non-financial loss.
Why is the outcome fair?
The outcome is fair because the policy terms and relevant legislation have been applied to
determine the extent of coverage. The complainant made a valid claim and took reasonable
steps to repair her property after delays by the insurer. It is fair for the insurer is to cover the
cost of reinstating the bathroom in accordance with current building regulations.
1.3 Determination
This determination is in favour of the complainant.
The insurer is to pay the complainant $42,312.60 for repairs to the property and $500 for non-
financial loss compensation (in addition to waiving the $700 excess).
Determination | Case number: 966959 Page 2 of 8
2 Reasons for determination
2.1 Is the insurer required to pay for the waterproofing?
Yes. The insurer is to pay the cost of reinstating the bathroom to its pre-incident condition
including the cost of waterproofing as this is necessary to meet current building regulations.
Complainant has established a valid claim
The complainant has established a valid claim under the policy for storm damage and the
insurer accepted the claim.
The insurer engaged contractors to undertake mould remediation works at the property. As
part of the remediation process, the walls and ceiling in the bedroom and bathroom were
stripped and the insurer identified that there was no waterproofing in the bathroom.
The insurer initially refused to cover the cost of any works in the bathroom, but later agreed to
partially cash settle the cost to repair the damaged areas of the bathroom excluding the
waterproofing. The complainant has repaired the entire bathroom, including waterproofing,
and seeks reimbursement for the cost of repairs.
Issues in dispute
The insurer submits that:
it is only liable for the cost to reinstate the bathroom to the condition it was in prior to the
storm event.
because the waterproofing was not damaged in the event, an upgrade to the bathroom
was required and it is not required to pay the cost of installing waterproofing
the complainant would have been liable for these costs regardless of whether the lack of
waterproofing was identified before or after the remediation work.
The complainant submits that
the bathroom needed to be brought up to current standards to meet current regulations
which included waterproofing it
t here would be no need to install waterproofing if the insurer‟s contractors had not
demolished sections of the bathroom wall and floor as part of the claim
the complainant could not sell the house without the waterproofing being done
Insurer is required to comply with current building regulations
There is no dispute that the complainant was provided with the Product Disclosure Statement
and Certificate of Insurance, which set out the insurer‟s obligations and liability.
The policy does not expressly state that the insurer is required to pay the cost to comply with
current building regulations. However, this is implied from provisions within the policy and it is
standard industry practice for an insurer to cover these costs.
Page 12 of the policy states “When deciding how much to insure your buildings for, you
should calculate the replacement cost of your buildings at today‟s prices and allow for the
costs to meet current buildin g codes, regulations and laws.”
Page 28 sets out the general exclusions which apply to all sections of the policy and states:
We will not pay for:
Determination | Case number: 966959 Page 3 of 8
…
2. additional costs resulting from your buildings or any part thereof not being
compliant with building codes, regulations or laws, including any required
approval by the relevant building authority, that were already in place when the
buildings were originally built, subsequently altered or renovated.
3. upgrading undamaged parts of your buildings to comply with current building
codes, regulations and laws;
When the policy wording is read as a whole, it is clear that the policy is intended to cover the
costs to meet current building codes, regulations and laws that were not in place when the
buildings were originally built, altered or renovated. However, the policy excludes the cost of
upgrading undamaged parts of the property.
I am satisfied that the insurer is required to pay the reasonable cost of complying with current
building regulations when repairing damage to the property under a valid claim.
The waterproofing was not damaged in the claim, but the insurer‟s contractors demolished
parts of the bathroom that are required to be waterproofed under current building regulations.
The question for determination is whether the insurer is required to meet current building
regulations and install waterproofing when repairing the bathroom, or whether the insurer is
entitled to exclude the cost of installing waterproofing.
Insurer must reinstate the bathroom to its pre-incident condition
Having considered the available information, I am satisfied that the insurer‟s contractors
removed wall and floor tiles and the toilet as part of the remediation process. The bathroom
was therefore damaged in the claim and the insurer is liable to repair this damage.
It was not possible for the insurer to repair the bathroom by simply patching up the areas that
were demolished for two reasons:
repairing the bathroom in this manner would not comply with current building regulations
due to the lack of waterproofing
the insurer was unable to match the existing tiles in the bathroom and needed to retile the
walls and floor rather than simply patching up the areas that had been stripped
The only way the bathroom could be properly reinstated to its pre-incident condition was to
retile the walls and floor with matching materials and install waterproofing in the bathroom so
that it complied with current building regulations.
I accept that this necessitated additional works, including the replacement of the shower
base, shower screen and associated plumbing works. However, this was the only way the
bathroom could be fixed in accordance with the policy and current building regulations.
Although installing waterproofing in the bathroom may be considered an upgrade, the policy
contemplates that the insurer will pay to upgrade damaged areas to meet current building
regulations that were not in place at the time of construction.
It is not in dispute that there was no waterproofing in the bathroom when the claim was made
and that installing compliant waterproofing would require almost a full renovation of the
bathroom. The insurer also accepts that it is unlikely waterproofing was required when the
bathroom was constructed.
Determination | Case number: 966959 Page 4 of 8
I am therefore satisfied that the insurer is required to pay the cost of installing waterproofing
in the bathroom, subject to the application of any policy exclusions.
Insurer has not established that a policy exclusion applies
The insurer relies on general exclusion 3 and says that it is not required to cover the cost of
upgrading the bathroom to install waterproofing because the waterproofing was not damaged.
I accept that the insurer is not liable for „ upgrading undamaged parts ‟ of the property to
comply with current building regulations. However, the waterproofing cannot be described as
„undamaged‟ - it was not present at all.
I accept that the shower was not damaged in the claim event. Although it is arguable that the
insurer is not required to pay the cost of upgrading the shower, I am not persuaded that is the
correct approach in the context of this claim. The intention of the policy is to reinstate the
bathroom so it is useable and the bathroom must therefore be treated as a whole.
It would be unfair to say that the insurer is only required to cover the cost of patching up the
damaged parts of the bathroom and to require the complainant to cover the significant
additional costs associated with installing waterproofing throughout the entire bathroom.
I also do not accept the insurer‟s contention that the complainant would have had to renovate
the bathroom anyway. The need to install waterproofing arose because damage was
sustained to the bathroom and this would not have been required if it was not for the claim.
For the above reasons, I am not satisfied that the insurer has established the application of
general exclusion 3 or any other policy exclusion. On the contrary, it can be implied from
general exclusion 2 that the insurer is liable for the additional costs associated with installing
waterproofing because there was no requirement for the bathroom to have waterproofing
when it was constructed.
I am therefore satisfied that the insurer cannot exclude the additional costs associated with
installing waterproofing. The insurer is required to pay the full cost of repairing the bathroom
including waterproofing.
2.2 How much is the insurer required to pay?
The insurer is to reimburse the complainant for the MC invoice in the amount of $41,140 and
the cost of the air conditioner in the amount of $1,172.60, plus statutory interest.
Insurer ’s cash settlement offer is inadequate
The insurer previously offered to cash settle the cost of repairs to the bedroom and bathroom
in the amount of $15,819.72.
The insurer relies on a quote by JL in the amount of $13,756.28 for repairs to the property,
including plastering, painting, carpentry, tiling and electrical works. The insurer applied a 15%
uplift to the JL quote to account for loss of warranty and transfer of risk, bringing the total
settlement offer to $15,819.72.
The insurer says the JL quote was based on a reinstatement of the bathroom on a like for like
basis, including reusing existing undamaged fixtures and fittings and did not include the cost
of installing waterproofing. However, it appears that JL have only allowed the cost of patching
up the bathroom wall and floor tiles that were removed during the remediation process.
Determination | Case number: 966959 Page 5 of 8
The complainant‟s bathroom had unique art deco tiles with decorative black feature tiles
around the perimeter of the floor and walls. I am satisfied that JL advised the complainant on
31 January 2023 that they would not be able to match the bathroom tiles and the complainant
would need to find new floor and wall tiles. This is confirmed by a contemporaneous email,
but the JL quote does not appear to allow for this.
Pages 33 and 34 of the policy set out the insurers obligations regarding matching materials.
The insurer is clearly liable for the cost of replacing all floor tiles. Given the unique nature of
the original tiles, it would be unfair for the insurer to replace only the affected wall and this
would result in a sub-standard finish. In any event, these tiles had to be replaced to install
waterproofing. I am therefore satisfied that the insurer is liable to cover the cost of replacing
all tiles in the bathroom.
Given the JL quote does not include the cost of waterproofing or replacing all tiles, it is
insufficient to fully reinstate the bathroom to its pre-incident condition. It follows that the
insurer‟s cash se ttlement offer is inadequate.
Complainant has paid for repairs to the property
The complainant arranged her own repairs to the master bedroom and bathroom, which were
performed by MC in early 2023. She relies invoice from MC in the amount of $41,140.
The insurer submitted they were unable to determine whether the costs claimed are fair and
reasonable because the MC invoice does not outline the rates for labour and materials. The
complainant subsequently provided an updated invoice from MC with further details.
The MC invoice includes plumbing, shower screen and installation of fixtures and fittings
which do not appear to have been allowed for in the JL quote.
The complainant says everything in the MC invoice was necessary to reinstate the bathroom
including waterproofing as required by current building regulations. She says MC only
replaced the tiles, shower screen, shower flooring/drain and toilet. She chose the cheapest
materials and re-used existing fittings including the shower head and taps, towel rail, basin,
taps and faucet. She also acted in accordance with the instructions of JL and sourced tiles
that were $45-$55 per square metre, despite the unique nature of the previous tiles.
This complainant has provided photos of the bathroom before and after the works which
confirm that she has reused items and has not completely renovated the bathroom.
The complainant also says that the insurer‟s contractors incorrectly removed a split system air
conditioning unit in the bedroom and did not let the gas out first. As a result, this unit was
rendered unusable and the complainants had to replace it at a cost of $1,172.60. She has
provided an invoice from TA for the supply of a replacement unit in the amount of $1,172.60.
The insurer has not provided any information to refute this and the JL quote includes the cost
of installing an air conditioner. I therefore accept on the balance of probabilities that the unit
was damaged and the insurer is liable to replace it.
The total cost of repairs incurred by the complainant is $42,312.60 including GST.
No evidence the complainant’s repair costs are unreasonable
The policy sets out how the insurer is required to settle a claim under the heading “How we
settle your claim” on page 32. Page 32 of the policy states:
Determination | Case number: 966959 Page 6 of 8
If we cannot repair or rebuild the damaged part of your buildings, we will pay you
an amount equal to the reasonable cost that you would incur to repair or rebuild
the buildings up to the limits noted in your policy. We will undertake a search of
the market to determine what this cost would be in your area, based on factors
including scope of works and comparison quotes from repairers or builders.
The insurer therefore bears the onus of establishing that the amount claimed by the
complainant is not fair and reasonable.
There is no evidence to suggest that the insurer undertook a search of the market to
determine what the reasonable cost of repairs would be. The insurer only obtained one quote
from JL and, given the lack of waterproofing, this cannot be an actionable quote. The insurer
has not provided any comparison quotes for the cost of repairs including waterproofing.
The complainant, by contrast, has repaired the property using a licenced builder and it is
reasonable to assume she would not have paid above market rates. I am satisfied that this is
the best evidence of the reasonable cost to repair the property. The insurer has not
established that the complainant‟s invoices were unreasonable or excessive.
I am also required to consider what is fair in all the circumstances. The claim was subject to
lengthy delays and, even after the insurer agreed to repair the bathroom, a disagreement
arose regarding how much the insurer would cover. The complainant needed to sell the
property and the delays and inaction by the insurer led her to engage her own builder. In the
circumstances, it would be unfair for the insurer to refuse to cover the cost of repairs.
Having considered all available information, I am satisfied on the balance of probabilities that
the complainant acted as a prudent insured and the amount paid by her to repair the property
was reasonable.
The insurer is required to pay the complainant $42,312.60 plus interest pursuant to section 57
of the Insurance Contracts Act 1984 from the date of the MC invoice.
2.3 Is the insurer required to pay compensation?
Yes. The claim was subject to delays and it is fair for the insurer to pay the complainant an
additional $500 compensation for non-financial loss.
The insurer is required to pay compensation for non-financial loss
Under AFCA‟s Rules, AFCA may award compensation for non -financial loss where there has
been an unusual amount of physical inconvenience, time taken to resolve a situation, or
interference with the complainant‟s expectation of enjoyment or peace of mind.
In assessing whether to award compensation, AFCA expects complainants to be moderately
robust, bear the normal degree of inconvenience experienced when a problem occurs, and
take reasonable steps to minimise the inconvenience suffered. AFCA considers the severity
and impact of the financial firm‟s conduct on the particular complainant.
The maximum amount AFCA can award for non-financial loss is $5,400 per claim.
The claim was subject to lengthy delays and the complainant‟s property remained in a state of
disrepair for months, during which the complainant was unable to use the master bedroom.
Further, the complainant says that she and her family experienced multiple illnesses during
the claim and she was concerned about their health living in the house. The complainant has
Determination | Case number: 966959 Page 7 of 8
also provided a log of her dealings with the insurer, which establishes that she had to follow
up the insurer on multiple occasions.
The insurer acknowledges that there were delays processing the claim and has agreed to
waive the complainant‟s $700 excess as compensation for those delays.
Having considered the available information, I accept that the applicant is entitled to
compensation for non- financial loss as a result of the insurer‟s handling of the claim.
The insured is to make a further payment of $500 for non-financial loss. This amount is to be
paid in addition to the $700 excess waiver, bringing the total compensation to $1,200.
2.4 Why is the outcome fair?
The outcome is fair because the policy terms and relevant legislation have been applied to
determine the extent of coverage. The complainant made a valid claim and took reasonable
steps to repair her property after numerous delays by the insurer.
It is fair for the insurer is to cover the cost of reinstating the bathroom in accordance with
current building regulations, including waterproofing the bathroom as this was not required at
the time of construction. It was not possible to repair the bathroom any other way and it would
be unfair for the complainant to be out of pocket.
Determination | Case number: 966959 Page 8 of 8
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.