Cash settlement offer for storm water ingress and mould damage was insufficient; scope of works incomplete
Text of the determination
Determination
Case number 966206
Financial firm Insurance Australia Limited
Determination | Case number: 966206 Page 1 of 17
Case number: 966206 20 September 2023
1 Determination overview
1.1 Complaint
The complainant holds a home building and contents policy of insurance with the financial
firm (insurer). The complainant originally lodged a claim for water ingress arising from a storm
event in February 2022. The internal damage to the insured home was not discovered until
January 2023 and the insurer was notified.
The insurer has accepted the claim for storm damage and offered a settlement of
approximately $47,200 to cover the internal damage and temporary accommodation.
The complainant says this offer is insufficient to cover the cost of repairs as the scope of
works (SOW) needs to include repairs to the bathrooms, kitchen, mould remediation,
appropriate temporary accommodation and external tiling to the patio and pool. The
complainant also seeks non-financial compensation. The complainant has obtained a
quotation in the sum of $284,014.43 for the cost of repairs.
The complainant has brought two prior AFCA complaints which do not relate to the matters
for consideration in this complaint. Accordingly, AFCA may still consider this complaint.
1.2 Issues and key findings
Is the insurer’s offer of settlement appropriate?
No. The settlement of the internal works is based on a scope of works that does not include
all relevant repair works and this also impacts the offer made for temporary accommodation.
Additional evidence is required to determine if the patio and swimming pool tiles should be
included in the repair works arising from storm/flood damage.
Is the complainant entitled to non-financial compensation?
Yes. The original expert reports in January 2023 confirmed there was damage resulting from
an insured event and the offer of settlement in May 2023 was insufficient. This has delayed
resolution of the claim during which time the complainant and his family, including an
immunocompromised child, have been living in a home with mould.
Why is the outcome fair?
The outcome is fair as it is in accordance with the law, evidence and policy terms and
conditions.
1.3 Determination
This determination is in favour of the complainant. The insurer, within 21 days of receiving
notice of the complainant’s acceptance of this determination, is to:
appoint an independent hygienist to report on the mould damage and appropriate
remediation methods including containment and storage of contents. The
recommendations of the hygienist will need to be included in any scope of works
Determination | Case number: 966206 Page 2 of 17
appoint the building consultant NB to provide recommendations on any specific destructive
testing relating to the bathrooms and implement those recommendations. If this presents a
safety risk to the complainant and his family, then the destructive testing should take place
once the residents of the home building are in temporary accommodation
allow NB to confirm whether the tiles in the family room can be restored or if all the tiles in
the area need to be removed and replaced. Further, NB should provide an opinion as to
the tiles in the kitchen area are damaged as a result of the storm event and/or whether
these tiles can be restored or need to be replaced
allow NB to confirm whether the patio tiles and swimming pool tiles (external tiles) are
damaged as a result of the storm/flood event and, if so, the appropriate repair method
the building consultant from NB is to provide an updated scope of works (SOW) based on
the recommendations of the hygienist, results of any destructive testing, the findings of this
determination and further inspections of the kitchen and external tiles
two independent builders are to provide quotes based on the NB SOW (including mould
remediation)
within 21 days of receiving the quotes, provide them to the complainant and pay the
complainant the higher of the two quotes plus 20% for contingencies, less any outstanding
policy excess
within 21 days of receiving the quotes, pay the complainant $2,500 in non-financial loss
compensation.
Determination | Case number: 966206 Page 3 of 17
2 Reasons for determination
2.1 Is the insurer’s offer of settlement appropriate ?
No. The settlement of the internal works is based on a scope of works that does not include
all relevant repair works and this also impacts the offer made for temporary accommodation.
Additional evidence is required to determine if the patio and swimming pool tiles should be
included in the repair works arising from storm/flood damage.
The policy terms permit a cash settlement
A review of the policy terms and conditions confirms the insurer is entitled to arrange for
repairs (if the insured agrees) or provide a cash settlement instead of undertaking repairs. In
the current circumstances, the insurer has elected to cash settle the claim which the policy
terms permit.
In considering whether the insurer’s offer of cash settlement is appropriate, it is necessary to
have regard to the items in dispute which are:
internal damage claimed as well as associated costs
temporary accommodation
external patio and pool tiles
This determination will consider each of these items separately having regard to relevant
expert evidence relating to the scope of works and repair quotations.
Internal Damage
Stormwater ingress created mould damage
The expert reports agree that the internal water damage experienced was due to the insured
event of storm or flood. The water has pooled against the North and West exterior walls of the
home and the water has entered the home. Further, the expert reports generally appear to
accept that the elevated moisture levels under the flooring have been responsible for the
mould discovered in bedroom 2. Any concern of a contribution from other water sources, such
as a leak from the showe r recess or base, has been deemed negligible by the insurer’s
building expert NB.
The scope of works provided by all experts agree that the following rooms were impacted by
the storm event and/or mould:
Office (or Study)
Master bedroom (also described as bedroom 1)
Bedroom 2
Bedroom 3
Bedroom 4
Family room.
Based on the expert reports provided, storm water ingress caused elevated moisture levels
within the home, which coupled with humidity, caused mould damage to occur. The mould is
damage as it creates a potential health hazard to the occupants of the home. The mould is a
damage caused by the storm water ingress and therefore its removal forms part of the cost of
repairs.
Determination | Case number: 966206 Page 4 of 17
The experts disagree on which items can be restored
I have reviewed all the SOWs provided and note the following:
some of the SOWs do not clearly state the provision of building materials or labour costs.
the SOWs are not unanimous in whether items can be restored or are required to be
replaced with new materials.
some of the SOWs state ‘remove and replace’ rather than remove, supply and install which
would cover removal of the item, plus the supply and labour costs for the item.
The SOW provided by the insurer’s experts varies between experts on whether items can be
restored or need complete replacement. This introduces a concern regarding whether the
items identified in some SOWs are in fact restorable. The offer of settlement is based on a
quotation for a SOW which may not properly allow for supply of new materials, and if this is
the case, then it would not reflect the true repair costs.
The bathrooms have not been properly assessed for damage
There was also some variance in the expert reports relating to the bathrooms which are also
located along the same wall as the rooms accepted as having storm damage. The reason
only some experts include the bathrooms in their reports or SOWs appears to be because no
destructive testing was conducted to determine if these rooms have in fact sustained water
ingress and mould damage.
The NB Report proposed a SOW recommending a hygienist be engaged to take samples
from affected wall cavities. This includes the back of the plaster wall cavities and the back of
the plaster wall cavity directly behind the shower cubicle and under the timber floor. This
expert further recommended that the SOW may need to be amended and invasive testing
would be required.
Based on the material provided, the destructive testing has not been carried out. The
complainant’s building expert, DC, has explained its quotation included the bathrooms
however they could not definitively confirm the presence of black mould without removing the
external bricks or tiles and waterproofing. DC did confirm its view that, considering the other
walls on that side of the house, there was a high probability that the bathroom would also be
affected.
The evidence provided by the experts is not definitive as to whether the bathrooms have
sustained damage. However, the evidence of the experts is that there is a probability such
damage exists, and that testing is required to confirm same. I have not located an item for
such testing in the quotations provided by the insurer. Further, the testing is necessary to
determine the full extent of the storm water ingress and mould damage and whether the cash
settlement offered is appropriate.
Later SOWs do not make an allowance for a hygienist
The NB and RC (restoration specialist) water reports and the OB report (building expert)
dated 31 January 2023 provide SOWs which include an allowance for a hygienist and mould
remediation. The later quotations from OB removed this allowance for a hygienist and mould
remediation from the SOW quoted but no reason was provided. The quotations on which the
insurer has based its settlement offers accordingly do not contain the cost for a hygienist and
mould remediation.
The SOWs provided also differ on whether the contents of the home can be stored onsite or
ought to be stored offsite. In my view, the engagement of a hygienist would allow for an
Determination | Case number: 966206 Page 5 of 17
expert opinion on containment of other living areas and whether contents ought to be stored
onsite or offsite. The hygienist could also provide testing services to determine the extent of
the mould damage throughout the agreed rooms and assist in confirming whether mould
remediation is required to the bathrooms.
The SOWs vary on whether the kitchen requires repairs
The kitchen has also become another point of difference between the scope of works. DC has
stated that the kitchen renovation is:
The blackened grout and the drummy sound of the floor ties (sic) are both strong
indicators of moisture infiltration. Additionally, the squish sensation experienced
when walking on the tiles further supports the presence of water-related
problems.
Given the tiles were laid more than a decade ago, and the current tiles available
differ from the ones on the floor. Moreover, there are two layers of tiles, and the
process of removing gyprock, skirting, and tiles requires specialized expertise, as
improper handling could lead to further complications and potentially exacerbate
the issue.
…the need for kitchen renovation is primarily linked to the flooring issue.
Whilst most of the experts consulted have confirmed an issue with the vinyl flooring, not all
the experts or SOWs have indicated a concern with the tile flooring. I note the RC report
dated 17 January 2023 recorded that the family room tiles were affected and that the tiles
were restorable.
The kitchen itself does not appear to be aligned to the West or North external walls. However,
the family room is along the affected external wall and in an open plan kitchen/family room
area. The kitchen is some distance from the external wall and it is unclear whether the storm
water ingress would be responsible for any of the issues noted with the tiles in this area. It is
also not clear what investigations have been undertaken for any issue of matching or
restoring the existing tiles.
Additional expert information is required to confirm the state of the tiling in the open plan
kitchen/family room area and whether the storm water ingress has caused the issue. If the
storm water ingress has impacted the tiles beyond those restorable tiles indicated by RC,
then the quotation will need to be amended to include relevant repair works.
Based on the material provided, I do not consider that the cash settlement adequately
represents the cost of internal repairs. I am of the view that a hygienist should be engaged to
provide relevant opinions regarding storage of contents, containment and testing to the
bathrooms. If the hygienist recommends the storage of contents offsite, then this cost should
be added to the costs of repairs. Further, if the hygienist confirms, after testing, that the
bathrooms contain mould in the walls then the cost of repairs should be added to the cash
settlement for internal repairs.
Temporary Accommodation
The policy provides some cover for temporary accommodation
Determination | Case number: 966206 Page 6 of 17
The policy provides cover for temporary accommodation, however there is no cover for
boarding cats and dogs unless the complainant has selected this optional cover. A review of
the certificate of insurance provided shows the complainant has not selected the optional pet
lover ’ s pack which provides cover for temporary boarding of cats and dogs. Given this, the
cost of boarding pets is not covered.
The temporary accommodation cover is for when the home cannot be lived in whilst it is being
repaired. The costs covered include:
Costs for temporary accommodation that we agree are reasonable and
appropriate for you, your family and your pets that you normally keep at your site.
Accordingly, I am satisfied the temporary accommodation must extend to include the
complainant’s pets normally kept at the insured site.
The scopes of work provided suggest that temporary accommodation is appropriate given the
extent of work to the bedrooms and potentially bathrooms which is required. I note the insurer
has already agreed to pay $10,000 for temporary accommodation in its offer of settlement.
Currently, due to the outstanding queries relating to repairs, it cannot be known what period
of time the home will be unliveable due to the repairs. Given this, I cannot make a finding as
to the exact cost of the temporary accommodation. The temporary accommodation costs will
need to be calculated once the time frames to repair the home are known and a temporary
accommodation located which also accepts pets. The temporary accommodation can then be
calculated in accordance with the terms of the policy.
External Patio and Swimming Pool Tiles
The complainant has produced a quotation and correspondence from DC dated 29 July 2023
which provides for the removal and replacement of tiles on the patio and around the
swimming pool. None of the other scopes of work provide for these items.
Patio Tiles
The DC quotation and report does not respond to the issues raised by NBS report.
The report by NB does agree that the floor tiles on the covered patio area are still firmly
adhered to the concrete slab save for 1m2 to the western edge of the covered patio. Further
the finished floor level (FFL) is 150mm below the internal floor level and the floor tiles are
internal floor tiles. These tiles were exposed to water over the surface and the performance of
the adhered tile will be the same if the slip rating was compliant or not. There was
delamination and perishing of the grout observed which is an indication of performance
relating to poor installation or failure of the substrates due to the event of this nature.
To be covered under the policy, the failure or damage of the tiles must be due to the storm
water event and not due to an excluded cause, such as deterioration or faulty design or
workmanship.
The only substantive evidence on causation is contained in the NB report which provides two
potential causes. Even if the tile damage is caused by the storm or flooding event then there
needs to be more information regarding repair methods and whether all tiles are required to
be replaced.
Determination | Case number: 966206 Page 7 of 17
Swimming Pool Tiles
The DC report included a quotation to address the swimming pool tiles. Further
correspondence from DC does not specifically address the cause of any damage to the
swimming pool tiles.
Similarly, the NB reports do not state the level of damage to the swimming pool tiles or any
specific cause of damage to the tiles. The NB report dated 5 May 2023 provides a statement
that the installation of the pool and spa may not have been built in a manner compliant with
the National Construction Code which applied at the relevant time. In particular, the external
pathways were constructed without consideration of the FFL. It is unclear whether this is
considered a potential cause of the damage to any swimming pool tiles.
There is insufficient information provided for me to determine that the patio and swimming
pool tiles should form part of the repair costs. However, there is sufficient evidence to warrant
further investigation as to whether the damage to these tiled areas arises from the insured
event or due to any deterioration or construction defects. Further, more information is
required as to appropriate repair methods.
2.2 Is the complainant entitled to non-financial loss?
Yes. The original expert reports in January 2023 confirmed there was damage resulting from
an insured event and the offer of settlement in May 2023 was insufficient. This has delayed
resolution of the claim during which time the complainant and his family, including an
immunocompromised child, have been living in a home with mould.
AFCA’s approach to non -financial loss compensation
When deciding whether to award compensation for non-financial loss, AFCA looks at the
severity and duration of the impact of t he financial firm’s conduct on the complainant.
AFCA takes a conservative approach to assessing compensation for non-financial loss. The
maximum award for non-financial loss is $5,400.
In deciding whether to award compensation, AFCA expects complainants to be moderately
robust, to bear the normal degree of inconvenience experienced when a problem occurs and
take reasonable steps to manage the situation.
AFCA will only award compensation for non-financial loss where there has been an unusual
amount of:
physical inconvenience
time taken to resolve a situation
interference with the complainant’s expectation of enjoyment or peace of mind
AFCA will look at the time frames and the type of inconvenience or hardship caused to the
complainants to determine any appropriate award.
AFCA may also consider whether the complainant has contributed to their loss arising from
the financial firm’s conduct. If so, it may be appropriate for the financial firm and the
complainant to share responsibility for the loss.
Additional non-financial loss is appropriate in these circumstances
A review of this matter confirms the following general chronology:
the complainant lodged their claim on 27 February 2022
Determination | Case number: 966206 Page 8 of 17
the damage to the internal portion of the home was not identified until January 2023
initial expert reports from RC are dated January 2023 and confirm storm damage
a complaint was lodged with AFCA on 28 March 2023
additional expert reports were received in May 2023 together with scopes of work
an offer of settlement was provided on 30 May 2023
the complainant provided a SOW in July 2023 in response to the offer of settlement which
included additional works for other items claimed.
I note the General Insurance Code of Practice (Code) stipulates there should be a four-month
time frame for handling claims. This time frame extends to 12 months in the event of an
extraordinary catastrophe declaration by the Insurance Council of Australia. The Insurance
Council of Australia declared an ‘Insurance Catastrophe’ but not an Extraordinary
Catastrophe under the Code.
The time frames in the Code are a general guide, there will be times when it is appropriate for
the claim to take longer – particularly if there are complex matters for investigation and
resolution.
The original RC reports recorded internal damage due to an insured event. Supplemental
expert reports only served to support the original assessing expert’s opinion. Given the
evidence received from the insurer’s own expert, I consider there were grounds to proceed to
settle the claim after confirming an appropriate SOW. Based on the exchanged material
however, I am satisfied the SOW on which settlement is based is insufficient.
The personal circumstances of the complainant and his family is that they have a child who is
immunocompromised and the mould in the home carries a risk to that child. Further, the
complainant and his wife say that they have been subjected to lung infections which they
believe was caused by exposure to the mould. Whilst there is no medical evidence to support
the lung infection being the result of the mould, it is generally known that mould in a home
carries several health risks including to the respiratory tracts of inhabitants.
Due to the time frames involved and the stress and interference with the peace of mind of the
complainant and his family, I consider $2,500 to be an appropriate award for non-financial
loss.
2.3 Why is the outcome fair?
The outcome is fair as it is in accordance with the law, evidence and policy terms and
conditions.
Determination | Case number: 966206 Page 9 of 17
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
Determination | Case number: 966206 Page 10 of 17
3.2 Relevant Policy Terms
Flood and rainwater run-off
If loss or damage is caused by flood and/or rainwater run-off.
Covered
- Flood
- Rainwater run-off, and
- Landslide or subsidence that happens immediately as a direct result of flood
or rainwater run-off.
For example, excessive, rainfall in your local area causes a build up of water in
the street gutters and the water enters your home and causes damage.
…
Water and oil leaks
..
Covered
- Water or oil leaking or escaping from
- gutters, drainpipes or pipes located at or on the site
- water mains or water supply pipes
..
Not covered
Loss or damage caused by:
..
- Water leaking or escaping from a shower recess or shower base
..
Temporary accommodation for home owners
If a listed event cause loss or damage to your home and we agree you can’t live
in it and you need to move out so it can be repaired or rebuilt.
Covered under Buildings Insurance
- Costs for temporary accommodation that we agree are reasonable and
appropriate for you, your family and your pets that you normally keep at your
site.
- Any additional living expenses that we agree are appropriate
- Costs to remove and store your contents and then return them to your home.
…
Conditions
- You must have lived in your home permanently before the listed event took
place
- We must agree to pay the costs before you make any arrangements
Determination | Case number: 966206 Page 11 of 17
- We don’t cover costs caused by unreasonable delays in repairing or rebuilding
your home.
..
How we settle your buildings claim
We will choose to settle your claim for loss or damage to your home and any
‘other benefits’ in one of the following ways:
1. Arrange for repairers, builders or suppliers to repair or rebuild your home
If you agree, we can arrange for our preferred repairers, suppliers or builders to
repair or rebuild your home. We may enter into a contract with our selected
repairer, builder and/or supplier on your behalf.
2. Pay you the reasonable cost to repair or rebuild your home
We can choose to:
• pay you
• pay your nominated repairer, supplier or builder, or
• provide you with store credits from one of our nominated suppliers.
For example, we may pay you directly when:
• you decide not to repair or rebuild your home, or
• you don’t start repairing or rebuilding your home within 6 months from when the
loss or damage takes place, or within any longer period we agreed to in writing.
3.3 Assessment and Expert Reports
Record Key points
Complainant’s Expert
RC Mould Report
19 January 2023
Due to the February floods in 2022, water has pooled up on the
outside of the north and west facing exterior walls.
When doing renovations to bedroom 2, evident mould growth was
present on the floating floor and behind the skirting boards.
Elevated moisture levels were presen t in the wall with the window.
Evident mould growth was present on the wall with the window
and wall backing onto the toilet at skirting height.
Moisture readings were taken in the north facing walls of the
Master bedroom, study, bedroom 3.
Bedroom 3, 4 an d family room has elevat ed moisture levels in the
west facing walls backing onto the pool yard.
Elevated moisture levels were present in all affected room floating
floor.
All moisture readings were between 18 - 20%
No evident mould growt h was visible in any other area.
The evident mould growth in bedroom 2 was contained and
treated
An AFD was installed to scrub the air for 3 days
Determination | Case number: 966206 Page 12 of 17
Record Key points
Insurer’s expe rt
AL Leak Detection Report
17 February 2023
An investigation was carried out to the main bathroom.
The leak detection tests showed there were no visible signs of
moisture present but the wall and tile grouting and wall spray tests
failed.
The report recorded significant amounts of grout joints in the
shower. This allowed water to fill the cavity between the tiles and
water proofing. This dispersed into the effected room suggesting
the waterproofing has failed. The bathroom is otherwise working
as designed.
Insurer’s expert
OS Building Assessment
Report
18 January 2023
The report provides two attendance dat es of 18 January 2023 and
22 March 2022.
The reinspection date of 18 January 2023 occurred due to the
discovery of black mould when removing the vinyl floor boards.
Internal inspection confirmed bedroom 4 partially st ripped out and
sealed. Evidence of moisture testing through affected areas.
Restorer attendance on 19 January 2023 confirmed high moisture
readings to all internal wall linings along the right hand external
brick wall of the property. Initial remediation of affected internal
rooms has been completed, however completion of strip out and
restoration is pending.
The report references a Restoration Report and a Leak Detection
Test.
The Restoration report is recorded as stating that there were
elevated moistur e levels present in the wall with the window
(bedroom 2) and wall backing onto the toilet at skirting height.
Moisture readings were also taken in the nort h facing walls of the
master bedroom, study and bedroom 3.
Bedroom 3, 4 and the family room has elev ated moisture levels in
the west facing walls backing onto the pool yard. Elevated
moisture levels were present in all affected room floating floor.
The moisture readings were between 18 - 20% but there was no
evidence of mould growth in any other area.
The report recorded water damage to the flooring, skirting, wall
lining and architraves of bedroom, 1, office, bedroom 2, bedroom
3, bedroom 4 and family room.
The inspection confirmed that damage was caused by excessive
rainwater runoff during the February s torm event, causing water to
enter the building through external walls. This has only occurred
as a result of the one - off severe weather event and would likely
not occur under regular circumstances.
The waterproofing failure to the bathroom may have cont r ibut ed to
the damages to the walls adjoining the bat hroom in the office.
The damage present in the office and bathroom would be
considered as affected by a separate escape of liquid event. I tis
unclear how long the issue with the wat erproofing has been
o ccurring. The maintenance listed would be required to be
completed prior to any repairs of the office and bathroom being
Determination | Case number: 966206 Page 13 of 17
Record Key points
undertaken.
Insurer’s expert
OS Building Assessment
Report
24 January 2023
Inspection of the property by another trade confirmed high
moisture readings to all internal wall linings along the right hand
external brick wall of the property.
Due to the February floods in 2022 water has pooled up on the
outside of the north and west facing exterior walls.
No maintenance/unrelated damage wa s identified on site
The cause of the damage is confirmed to have been a storm
containing severe rainfall which affected the area during the
claimed event.
Recommendation was made to accept the variation as an
additional claim related damage observed durin g reattendance.
Insurer’s Expert
NB Building Inspection Report
12 May 2023
At the time of inspection, some minor maintenanc e has been
carried out to the main house bathroom as advised in an initial
builder’s report.
Extensions and upgrades to the existing stormwater drainage
installed around the property had also occurred.
The brickwork has vertical expansion joints installed at 6 m
intervals which have been recently resealed. These are potentially
a point of ingress if the waterproof seal delaminates over an
extended period of time.
Moisture readings in bedroom 2 were now in the range of normal.
There is a PVC stormwater pipe acting as an electrical cable
ducting which is located on the external wall of the bedroom butted
against the wall frame - there is a 2 - 3 mm movement crack in the
concrete slab directly above where the PVC pipe has been laid.
Based on the measurements taken on - site the depth of cover to
the top of the PVC pipe is 150 mm below FFL of the conc re te - this
has the appearance of a full crack through the dept h of the
concrete slab to the aggregate sub - base below which has the
potential to allow water ingress.
There are spider hairline cracks observed on the surface concret e
slab – these do not have t he appearance of a full penetrative crack
to the concrete slab.
The section of the plasterboards that the shower cubicle backs
onto appears unstained and does not have the appearance of
long - term ex posure to water escape – the external face of the
plasterb oard is not showing water staining or delaminating paint
nor is it starting to lose its integrity. It is noted in the Leak
Detection Report that the shower did fail a spray test – on review
of the thermal imagery it appears to be a vertical flow of liquid
suggesting the egress from the shower cubicle is from a pipe
penetration either from the mixer tap or the feed to the shower
head as a foc used water spray test on these areas will exaggerat e
what would be experienced in normal usage.
Moisture readings take n from the plasterboard that backs onto the
Determination | Case number: 966206 Page 14 of 17
Record Key points
shower cubicle are consistent with readings taken from areas
outside this area of concern.
There is no efflorescent deposit, or any recent or historical staining
to the concrete slab where the shower cubicle is l ocated.
There is no wat er staining or swelling of the door frame observed.
The missing grout to the tiled walls documented in the Leak
Detection Report have been filled.
There is still missing grout observed to the shower base floor tiles
and around the fl oor waste.
The silicone beads placed to the floor and wall ceramic tile
transitions and the shower screen to tile are showing missing
sections and are delaminating.
There is no silicone beading placed on the top of the shower wall
tiles to the wall lining, with a clear gap where moisture can access
behind the wall tiles.
There is a free - standing linen cupboard to the left hand side (LHS)
of the shower cubicle – this was removed to allow a visual
inspection of the external section of the shower hob and the
s hower screen and it was observed that there is evidence of water
escape from the shower screen and tile hob at the bottom LH
corner of the shower screen which is aligned with the delaminated
silicone beading observed within the shower cubicle.
Based on the deteriorated condition of the silicone sealant applied
to the perimeter and within the shower cubicle it is deemed
reflective that the beading placed (if any) to the pipe penetration
through the waterproof membrane is allowing moisture into the
wall cavit y. NB did try and remove the cover plate to inspect the
water feed penetration but it was sealed to the wall – clear gaps
were obs erved around the cover plate that will allow water to
access behind the mixer cover plate.
The plasterboard in bedroom 2 direc tly behind the shower cubicle
is not showing any long - term damages related to prolonged
exposure to wat er – no staining or delamination to the plaster paint
were obs erved, nor were the plasterboards losing their structural
integrity, nor efflorescence stai ning historic al or new to the
exposed concrete slab.
The water escape observed from the bathroom shower cubicle to
bedroom 2 is negligible where the heightened moisture levels
taken to all bedrooms are reasonably aligned between 18 - 20%, as
documented in pr ior reports .
No elevated moisture level was observed directly behind the
shower cubicle at the time of inspection with the reading aligned
with those taken in other areas of the property.
The mould growth is contributed to the underside of the timber
floor being ex posed to elevated moisture levels from the slab after
the event.
Determination | Case number: 966206 Page 15 of 17
3.4 Quotations and Scopes of Work
Quote Provider Brief summary of the work
OB
31 January 2023
The quotation is for $16,664.48 (incl GST)
The Scope of Work (SOW) includes relocating contents to
unaffected areas of the property and creating cont ainment zones
between affected and unaffected areas.
disposing of non - restorable floating floor and underlay from all
bedrooms and study.
Removing an d disposing of skirting boards and plasterboards of
either the affected north or west facing walls to all bedrooms and
family room
Decontamination and drying required.
The engagement of a hygienist to clear the works and make ready
for reinstatement.
The re is no separate itemisation for reinstatement costs for
building materials or labour costs.
The quote confirms that temporary accommodation will be
required during the process of remediation.
NB SOW
5 May 2023
Engagement of hygienist and allowance for containment of
contaminated areas prior to demolition.
Removal and storing of personal belongings outside of
construction areas
Strip out to 1200mm in affected areas (is allowed for generally in
the SOW).
Assess door jambs and cabinetry for viability of r estoration
Review ensuite linings for event related damage where
surrounding room linings have been removed.
Remediat e wall frames, wall cavities and general areas. Allow for
mould remediation sanitisation and structural drying.
Supply and install timber t o match as close as possible with
previously existing, including underlay and smooth - edge.
The rooms nominated for repairs include bedroom 2 and house
bathroom 2400mm high. However, there is a notation that this
room is coming to the end of its serviceabl e life span and a full
renovation is recommended to be conducted prior to any works to
bedroom 2. Further works are stated as maintenance and other
works to prevent pot ential worsening of water escape from the
shower cubicle.
OB
24 May 2023
The quotation refers to removing and replacing skirtings and the
vinyl plank flooring in the study, bedrooms and family room .
The quotation refers to supply and installing plasterboard wall for
the external facing wall up to nearest board join (but not removal
c osts) in the study, bedrooms and family room
The quote also refers to painting walls and skirtings in each room.
The quote refers to removing and covering contents items and
Determination | Case number: 966206 Page 16 of 17
Quote Provider Brief summary of the work
storing onsite away from work fronts.
There is no allowance for hygienist or decontam ination. The quote
particularly states that no allowance has been made for restoration
or mould removal works.
There is no reference or allowance for any works to the bathroom
walls facing the external walls.
The quotation is $21,307.53 (GST incl).
OB
23 May 2023
The scope of works includes replacing plasterboard to external
facing wall (up to nearest board join), removing and replacing
skirtings and arc hitraves, removing and replacing vinyl plank
flooring. Painting the architraves, skirtings and walls .
The above works were to be carried out to the office, bedroom 1,
bedroom 2, bedroom 3, bedroom 4 and family room.
Cont ents were to be removed and stored onsite away from work
sites.
No allowance has been made for any restoration works or mould
removal.
The cost of the works was $30,939.37
RC Report
17 January 2023
A suggested scope of works was included with the report.
The quotation allows for works to the master bedroom (bedroom
1), study, bedroom 2, bedroom 3, bedroom 4 and family room.
The reloca tion of contents from affected areas to unaffected areas.
Remove and dispose of non - restorable floating floor and underlay
from all bedrooms and study.
Remove and dispose of skirting and plasterboard from the walls
facing the external walls in the Master bedroom, study, bedroom 2,
bedroom 3, bedroom 4 and family room.
Decontamination, drying and chemical treatment together with
testing prior to PRV clearance (requiring engagement of a
hygienist)
Temporary accommodation will be required
DC
29 July 2023
Strip external wall lower gyprock sheet from all bedrooms, study,
family room, bathrooms and toilets.
Due to breaking of waterproof membrane which will be caused by
the work, both bathrooms and toilet will require new tiles and
waterproofing.
Replace all flooring through bedrooms and study.
Replace all tiles in family room, dining, kitchen, laundry, living and
hallway due to water damage in wall of family room which will
damage existing tiles that cannot be matched.
Remove and replace tiles in patio and t iles around pool due to
water ingress making all tiles drummy.
Repaint entire house except storage and garage
Purity Air – black mould and AC treatments
Skip bins
Determination | Case number: 966206 Page 17 of 17
Quote Provider Brief summary of the work
Re - s heet disturbed areas and make good
Remove and replace kitchen island bench and replace w it h new.
The quotation is for $284,014.43 (GST incl)
There is no allowance for storage on or offsite or a hy gienist