Home / Hollard / Determination 963884

Determination 963884

Liability for damage caused by insurer's contractors during make safe works (trees and dam wall)

FirmHollard
Decided2024-04-05
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$61,670
Non-financial loss$2,000
Amount claimed—
SourceAFCA PDF

Summary

Insurer's contractors damaged trees and a dam wall while making safe after storm damage. AFCA ordered cash settlement of $61,670 for the heritage palm, a reasonable dam wall quote with 20% uplift, and $2,000 non-financial loss, rejecting other claimed costs.

The panel accepted the first arborist valuation and the need for a wider wall rebuild, but found the complainants' other costs (T2 replacement, water cartage, driveway) unsubstantiated.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay compensationpay non financial loss

Related

All Hollard determinations · Find similar determinations

Text of the determination

Determination Case number 963884 Financial firm Hollard Insurance Partners Limited Determination | Case number: 963884 Page 2 of 9 Case number: 963884 3 April 2024 1 Determination overview 1.1 Complaint The complainants lodged a claim with the insurer for storm damage. The insurer ultimately settled the complainants $5,000 for this claim. On 30 August 2022, while completing a make safe for the storm damage claim, the insurer’s contractors, T&G, caused damage to the compla inants’ proper ty, including to two trees and a dam wall. The insurer’s liability for this damage is in dispute. The complainants also note service issues and delays. 1.2 Issues and key findings What is the insurer’s liability for the damage? The insurer is required to meet its obligations to the complainants by complying with the provisions of this determination. Is the insurer liable to pay compensation for non-financial loss? Yes. The insurer is to pay $2,000 in compensation for non-financial loss. Why is the outcome fair? The complainants have substantiated some costs sought, and not others. It would not be fair to require the insurer to pay all claimed costs in the circumstances. 1.3 Determination This determination is substantially in favour of the insurer. The insurer is to cash settle the complainants:  $61,670 for the heritage palm tree (T3)  the amount of a reasonable quote for the dam wall repairs, in accordance with the provisions of this determination and  $2,000 in compensation for non-financial loss. Determination | Case number: 963884 Page 3 of 9 2 Reasons for determination 2.1 What is the insurer’s liability for the damage? 1. Heritage palm tree (T3) The complainants originally supplied a quote from an arborist (BTC) for replacement of the heritage palm tree (T3). This quote used the ‘Thyer Valuation Method’ to a ssess the value of T3 as $61,760. The complainants later submitted a higher quote from BTC, for T3, in the sum of $143,056. The insurer accepted the initial BTC quote as fair and reasonable. The subsequent Thyer Tree Valuation worksheet used for BTC’s second va luation provides a different ‘size factor’ for the tree. It is not known how this was calculated (for example, if BTC measured the cut-up pieces of the tree that the complainants said had been ‘hidden’ by T&G around the yard, to determine the actual size of the tree). The complainants have not provided evidence to show why different sizing was used in this second valuation. The insurer supplied a report from a second arborist, TW. The panel is satisfied that TW is qualified to provide an opinion on T3. TW agreed that the original costing provided for the loss of T3, by BTC, is correct, fair and reasonable. The only comment that the complainants made about the TW report was that the wrong tree valuation was used. The complainants did not elaborate on this. The panel notes the original BTC valuation used the ‘2000b’ Thyer worksheet, whereas the subsequent valuation used the ‘2015’ worksheet. The complainants made this comment in their initial response to ACFA, regarding the size of T3; While the other two trees are healthy Livistona australis (Cabbage Tree Palm) 18m tall with trunk diameter of 300mm. This comment matches the size information provided in the second valuation, whereas this further size information is omitted from the first worksheet. It appears that an outdated Thyer worksheet may have been used in the first valuation by BTC, although there is insufficient further information provided from the complainants to support this. Based on the evidence provided, there is insufficient evidence to show that the incorrect valuation was completed in the first instance. Based on the expert evidence of BTC and TW, the panel accepts the first BTC valuation as fair and reasonable. The insurer is therefore to cash settle the complainants $61,670 for T3. 2. Eucalyptus tree (T2) TW agreed that the Thyer Tree Valuation Worksheet used for the eucalyptus tree (T2) is fair and reasonable, based on the data collected by MVM of BTC, also a level 5 arborist. Determination | Case number: 963884 Page 4 of 9 The panel therefore accepts that the tree has been correctly valued at $174,943. However, despite the valuation of this tree, the panel needs to consider whether there is a need to replace this tree, due to T&G’s damage from spiking the tree. Complainants have not established that T2 (the eucalyptus tree) needs to be removed at this stage T&G spiked the eucalyptus tree (T2) to reach the damaged hung tree (T1). The complainants say that the spiking will allow bacteria into the tree. The complainants believe the spiking methodology was incorrect. The insurer acknowledged that its TW report, along with the BTC report, provided several alternative methodologies, that are preferred over climbing spikes. However, the insurer says TW confirmed that in some circumstances climbing spikes are the safest and quickest option. The panel does not agree with the insurer that this was the intention of the TW report. TW said that there are a few situations where a professional may use spikes to climb a tree, such as during a tree removal service, or where a tree is lodged or hanging in another tree. Although both of those situations were present here, the panel is satisfied that the evidence shows overwhelmingly that the incorrect methodology was used here. Based on the information supplied from the complainants in their initial letter of demand, it is evident that a crane should have been used in this situation. Appropriate safety measures were not employed here. The key question then is whether the spikes have caused the eucalyptus tree to become terminal, and that it needs to be replaced. The insurer argues that the spiking method used by T&G has not resulted in an identifiable financial loss at this time. It says it has received no evidence of financial loss to T2. TW said that, while it is critical of the actions taken to conduct the tree works at this site, its report does not include details of a site visit, nor any visual tree assessment of T2. TW says therefore, it has no definitive outcome as to whether this tree can be retained or needs to be removed. BTC noted that T2 was pruned to release T1 from the hung position. BTC also said that: 4.1. Climbing a healthy tree that has been assessed for retention using tree climbing spikes will wound the bark and conductive tissues, the damage caused to a trees outer protective layer will provide an entry point for pest and disease. The use of climbing spikes is not compliant with acceptable pruning equipment as outlined in Section 5.1(a) AS 4373-2007 Pruning of amenity trees. The panel also notes the complainants originally advised: We also would like to point out that we are not claiming the value of the healthy tree that T&G Tree Services spiked but only its removal cost that our arborist set the price at. Determination | Case number: 963884 Page 5 of 9 Insurer not liable for replacement of T2 The Panel notes the general comments provided by BTC, in that climbing a healthy tree using tree climbing spikes will wound the bark and conductive tissues, and that the damage caused to a tree’s outer protective layer will provide an entry point for pest and disease. However, the Panel does not consider that adequate evidence has been provided to show that this is what occurred here. There are no photos of the tree showing damage caused to T2 due to the climbing spikes. The report provided by TW was inconclusive as to whether this tree can be retained or needs to be removed. In the circumstances, the Panel considers that the complainants have not established that the eucalyptus tree (T2) needs to be removed and replaced due to the use of climbing spikes by T&G. In the event the complainants were, in the future, able to establish a loss to T2, caused by the climbing spikes the subject of this complaint, the panel is satisfied it would be fair to allow the complainants to make a further claim at that time. The insurer is required to assess that claim, if made, based upon the available evidence. 3. Dam wall The expert evidence has shown that the dam wall was damaged by the falling hung tree. The insurer has accepted liability for the damage to the dam wall. There exists a dispute about the correct scope of works (SOW) and therefore quote, in respect of the dam wall works. A key difference between the scopes of work is the length of replacement wall required. S (the insurer’s engineer) considered that 3m was sufficient, whereas REM (the co mplainant’s engineer) advised at least 5m is required. The insurer offered to pay the complainants $40,861.92. This amount was based on the DW quote, plus a 20% uplift. The complainants seek the cost of the dam wall works, based on their quote from TGO ($133,500.18) together with the costs of water cartage, construction drawings and the geotechnical report. Total amount claimed $147,340.18. REM advised that:  The integrity of the structure had been compromised by the impact.  There are cracks at the impact site that extend to the foundation level, and concrete benching is loose.  It is unknown what other damage occurred to the wall due to the impact as the inspection was not intrusive, however, the evidence is visible from the surface that significant damage could and most likely has occurred to the retaining wall footing and lower elements of the retaining wall, which will jeopardise the retaining wall’s ongoing stability. To ensure that the wall returns to its pre-incident impact integrity, REM recommended that the section of the wall is rebuilt in the impacted area. The extent to which the wall must be rebuilt will be determined by intrusive investigation but would be a minimum of 5 metres either side. REM also recommended geotechnical investigation. Determination | Case number: 963884 Page 6 of 9 REM advised the new construction should maintain the current aesthetic appearance of the remaining unimpacted wall for visual consistency. In its supplementary report, S disagreed with the REM comment of ‘a minimum of 5 metres either side’. However, S did not provide any commentary as to why it disagrees. It appears S disagrees with this due to an invasive inspection not being conducted, based on the next line in the report: ‘Until determined otherwise by an invasive inspection, or further evidence comes to lig ht at the time of replacement…’ The complainants noted the cracking to the dam wall when they drained the dam for expert inspection. The photos supplied by REM also show cracking to the dam wall. The panel accepts that this supports REM’s position that the cracking has reached the footing, which in turn supports a finding that a wider area of repair is required to reinstate the integrity of the wall. However, the Panel also notes the comments in DW’s reattendance report, where it noted that the existing wall is not constructed within engineering criteria. DW says that there is no evidence of adequate footing ties, or starters bars present. DW says that ‘This is not constructed in a manner that is suitable for this application.’ Any settlement for the dam wall, therefore, should not represent betterment of the wall. Complainants’ quote is inadequate The panel notes TGO’s quote has not been adequately itemised. It does not outline the materials that will be used, or labour required, and it is unclear from the quote whether it accounts for 5 metres of wall either side, as stipulated by REM. The Panel also notes that TG O describes itself as a ‘landscape design & construction’ [company], and therefore is uncertain as to its suitability as the correct expert to conduct repairs to the dam wall. The description with TGO’s Quote relates to gardening. On the other hand, TGO’s quote does account for excavation work on the foundations of the dam wall. REM was unsure whether the footings had been affected but thought this was likely. It is unclear how much of the TGO quote accounts for new foundation work (that likely had not been sufficient prior to the event, taking into account DW’s evidence), as opposed to building a wider wall. As noted above, the TGO quote does not describe whether a minimum of 5 metres of wall either side is to be included in these works. The Panel does acknowledge the complainants’ comments that the DW report provided structural findings, even though the inspector is not a structural engineer. Conclusion – Dam wall SOW and quote Considering the evidence presented, the Panel accepts that the dam wall needs to be rebuilt with 5 metres on either side, as a minimum. The evidence is persuasive that the impact has likely reached the footings of the dam wall, and therefore it would be prudent to rebuild a wider wall, to preserve the integrity of the wall. The Panel also notes, however, that the complainants’ qu ote is insufficient. It has not been adequately itemised and does not show the breakdown between the cost of materials and labour. Determination | Case number: 963884 Page 7 of 9 The insurer is to therefore provide an amended quote from DW, that is actionable and reasonable, and cash settle the complai nants this amount. The Panel notes the complainants’ request to have no further dealings with DW, and therefore considers a cash settlement to be appropriate. The insurer is to add a 20% uplift to the quote to allow for contingencies. Water cartage At the end of the complaint, the complainants sought $10,000 to refill the dam after completion of works. The complainants have not provided evidence to substantiate this amount. The insurer is not liable for this amount as a separate cost. Any water cartage required is to be included in the quote, to be provided by the insurer. Other issues: Potential driveway cracking from SOW works The complainants say that experts advised of an issue with their concrete driveway cracking, from all the big vehicles needed for completion of repairs. The complainants advise this could be a big cost, given expert advice stating replacement is $190/sqm, and their driveway is 3.5 metres wide and 220 metres long. The complainants at this stage, however have not established any damage to their driveway. However, if the complainants are to be cash settled, this may be a further cost that may arise. The panel considers that if any trades cause damage to the complainants’ property, the complainants may choose to pursue those trades directly. The insurer is not liable for the cost of potential drivew ay cracking by the complainants’ trades upon cash settlement of the SOW repairs, as no financial loss has currently occurred. Bridge damage The complainants noted that T&G also damaged their bridge. Some of the expert evidence supports that the proximate cause of damage was T&G’s actions. However, in their response to AFCA, the complainants advised that they ‘are not concerned with this issue’, therefore the damage to the bridge has not been considered in this Determination. 2.2 Is the insurer liable to pay compensation for non-financial loss? AFCA can award compensation for non-financial loss AFCA can award compensation for non-financial loss where considerable stress and inconvenience has been suffered as a result of the actions of the insurer. Complainants suffered some stress and inconvenience The complainants suffered some delay and stress in the processing of this complaint. A large part of the stress was due to the actions of T&G, which are addressed above. Determination | Case number: 963884 Page 8 of 9 The complainants described how they found the owner of T&G walking around their property. This occurred without notification to the complainants, or their consent. The Panel notes the multiple attendances at the property, especially immediately after the incident. The complainant also made contact with the contractors multiple times to follow up. The claim and complaint have taken some time to resolve, although the Panel notes that this has been in part due to the complexity of this complaint. It appears a majority of the dissatisfaction on the complaints’ part has been in relation to the reports provided by the insurer, rather than the actions of the insurer in delaying the claim or with communication. Compensation cannot be awarded for a difference in opinion between the parties. Taking all the information into account, and given the actions of T&G, the Panel considers it fair to award $2,000 in compensation for non-financial loss. 2.3 Why is the outcome fair? The complainants have substantiated some costs sought, and not others. It would not be fair to require the insurer to pay all claimed costs, when these have not been substantiated by the complainants. Determination | Case number: 963884 Page 9 of 9 3 Supporting information 3.1 The AFCA process AFCA’s approach is ba sed on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. A panel determined this matter Due to the nature of this complaint, we referred it to a panel for determination. The panel includes:  an ombudsman  a member with significant experience in consumer and small business advocacy  a member with extensive experience in the insurance industry. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.