Home / IAG / Determination 963355

Determination 963355

Delay in commencing rectification repairs and request for committed repair start and end dates

FirmIAG
Decided2024-02-13
ProductGeneral Insurance · Strata
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainant wanted the insurer to commit to repair start and completion dates for rectification works after delays. AFCA declined to impose dates, found the $8,400 already paid in compensation fair, and ordered regular written progress updates.

Permit approvals and unquantified variations are outside the insurer's control so fixed dates would be unfair, but given the delays regular GICOP-compliant updates are warranted.

Issues

Subjects and remedies

home or building damageprovide documents

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination Case number 963355 Financial firm Insurance Australia Limited Determination | Case number: 963355 Page 1 of 5 Case number: 963355 5 February 2024 1 Determination overview 1.1 Complaint The complainant is a beneficiary under a strata policy held with the financial firm (insurer). In 2014, the insurer accepted a claim and repaired damage to the complainant’s property. In 2021, the complainant lodged a claim with the insurer for rectification works for faulty repairs completed in the 2014 claim. The insurer assessed and accepted liability for the rectification works on 18 February 2022, however it has not yet commenced repairs. The insurer accepts it has caused delays and that it missed the agreed repair start date outlined in AFCA’s preliminary assessment. The insurer says it has paid the complaint AFCA’s maximum compensation because of this. The complainant wants the insurer to confirm the start date for repairs and for the repairs to be completed no later than April 2024, otherwise she will face tax implications when selling the property. 1.2 Issues and key findings Is the insurer to commit to a repair start and end date? No. While I appreciate the complainant’s concerns, it would be unfair to force the insurer to a commencement and completion date, as there are many factors outside of the insurer’s control that can alter these dates. However, the insurer is to provide regular updates to the complainant in accordance with the General Insurance Code of Practice (GICOP), on the progress of the repairs until they are completed. Is the insurer’s offer of compensation fair? Yes. The insurer has previously paid the complainant $3,000 and a further $5,400 after it did not execute the terms of AFCA’s preliminary assessment. I am satisfied this is a fair and reasonable amount in the circumstances. Why is the outcome fair? It would be unfair to compel the insurer to a start and end date when there are factors outside of its control that can impact the dates, however given the length of time the matter has been on foot it is fair the insurer provides regular updates. 1.3 Determination This determination is in favour of the insurer. Within 14 days of acceptance of this determination by the complainant the insurer is to provide the complainant with its first update and is to continue to do so in line with the GICOP until the claim is finalised. Determination | Case number: 963355 Page 2 of 5 2 Reasons for determination 2.1 Is the insurer to commit to a repair start and end date? No. While I appreciate the complainant’s concerns, it would be unfair to enforce the insurer to a commencement and completion date, as there are many factors outside of the insurer’s control that can alter these dates. However, the insurer is to provide regular updates to the complainant in accordance with the General Insurance Code of Practice (GICOP), on the progress of the repairs Insurer did not adhere to the agreed preliminary assessment On 22 September 2023, AFCA provided the parties with its preliminary assessment that the complaint should be resolved as follows:  the insurer was required to pay the complainant $3,000 in compensation due its claim handling  commence repairs as soon as practical, but not later than December 2023. The parties accepted AFCA’s preliminary assessment and the complaint was resolved with the expectation the parties would adhere to the recommendations in the preliminary assessment. The information shows the insurer settled the complainant $3,000, however, it has yet to start repairs on the property. The insurer accepts it did not adhere to AFCA’s preliminary assessment and in recognition of this has paid the complainant a further $5,400 in compensation. However, the insurer says currently it is unable to give the complainant a guaranteed start date. Complainant is seeking for repairs to be completed before April 2024 The complainant wants the insurer to start repairs as soon as possible and for the repairs to be completed before the start of April 2024. The complainant says repairs need to be completed by this stage otherwise she may face tax implications when selling the property, if it is sold after August 2024. Information shows some delays are unavoidable I have reviewed the further information provided since the preliminary assessment was delivered and it shows:  from 22 September 2023, the insurer has been working on progressing the claim  the insurer’s builder was required to engage an engineer and surveyor to redesign the balcony to ensure it was compliant, with plans expected to be completed by 6 October 2023  on 9 October 2023, a dual assessment was requested due to further issues discovered with the building and the repairs required to ensure they are compliant.  there were delays in arranging the dual assessment and advising the complainant why it was required, it is unclear why there was a delay, however it appears this was within the insurer’s control  a dual assessment took place on 13 December 2023, after the complainant had re- engaged with AFCA  further engineer plans, and reports were completed in early January 2024 to be signed off by the surveyor, so building permits could be obtained. Determination | Case number: 963355 Page 3 of 5  the insurer says the process to obtain the permits will take at least a month, as such it cannot give a start date at this time  once repairs commence there will be a further variation to the works, which can only be quoted once repairs start. Based on the available information I am satisfied the insurer has continued to attempt to progress the matter, however the insurer has delayed the progress by not arranging the dual assessment in a timelier manner. While I accept, there was a two-month delay in arranging the dual assessment I am persuaded the insurer would not have been able to commence repairs before December 2023, due to the issues in ensuring the repairs are compliant and the length of time it takes to obtain a permit. However, I am satisfied the insurer should have been more proactive in relaying this information to the complainant. Unfair to insist the insurer commit to a repair start and end date I accept the rectification claim and complaint has been on foot for a considerable period and that the insurer previously agreed to a start date. However, I am not persuaded this means AFCA should or can compel the insurer to commit to a start date. This is because the information shows the final plans are required to have building permits approved by the relevant authority, which is something the insurer does not have any control or influence over. When final approval for repairs is out of the insurer’s control it would be unfair to hold it to a timeframe for a repair start date. Further, the information shows the insurer has identified a further variation on the works will be required, however this aspect cannot be quoted until repairs are underway. It would be unfair to insist the insurer commit to a completion date, when the impact of the additional works will have on the repair duration is not known. For these reasons I am satisfied it would be unfair to compel the insurer to commit to a start and end date for the repairs. However, I am persuaded in the circumstances the insurer is to commit to providing the complainant with regular updates in writing on the progress of both the approval for repairs and the repairs themselves. I am satisfied in the circumstances the insurer should do so in accordance with GICOP, with the first update to be within 14 days of acceptance of this determination. 2.2 Is the insurer’s offer of compensation fair? AFCA takes a conservative approach to compensation Non-financial loss includes claims for stress or inconvenience caused by an error of the financial firm. We will only award this type of compensation if there has been an unusual degree or extent of inconvenience. We recognise that making a claim can be stressful and time-consuming, even if the insurer handles the claim correctly. We will not award compensation for the ordinary degree of inconvenience that comes with making a claim or for loss a complainant may incur because of pursuing a complaint or rectifying the insurer’s error. When assessing whether the circumstances are of an unusual nature we will review: Determination | Case number: 963355 Page 4 of 5  the degree or extent of physical inconvenience suffered  the general time taken to resolve the dispute  the extent to which the insurer’s actions interfered with the complainant’s expectation of enjoyment or peace of mind. Insurer’s payments for non -financial loss are fair and reasonable Under our rules AFCA can award a maximum of $5,400 in compensation for each claim of non-financial loss. In this complainant I consider there to be two sperate claims for compensation. The first being the initial delays and service issues up to the date the parties accepted AFCA’s preliminary assessment for which AFCA awarded $3,000. As t he amount was agreed and accepted by the parties I consider this claim for compensation resolved. The second claim for compensation and while not specifically raised by the complainant is from the date of the preliminary assessment to the current date. The insurer offered $5,400, which was accepted by the complainant. This is the most AFCA can award. I consider this amount to be more than fair for the service and delays that have occurred since the preliminary assessment was accepted. Accordingly, I am sati sfied the insurer’s offer is fair in the circumstances. 2.3 Why is the outcome fair? It would be unfair to compel the insurer to a start and end date when there are factors outside of its control that can impact the dates, however given the length of time the matter has been on foot it is fair the insurer provides regular updates. Determination | Case number: 963355 Page 5 of 5 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.