Home / IAG / Determination 963355
Determination 963355
Delay in commencing rectification repairs and request for committed repair start and end dates
Summary
The complainant wanted the insurer to commit to repair start and completion dates for rectification works after delays. AFCA declined to impose dates, found the $8,400 already paid in compensation fair, and ordered regular written progress updates.
Permit approvals and unquantified variations are outside the insurer's control so fixed dates would be unfair, but given the delays regular GICOP-compliant updates are warranted.
Issues
- Delay primary · upheld“the insurer has delayed the progress by not arranging the dual assessment in a timelier manner”
- Poor communication secondary · upheld“the insurer should have been more proactive in relaying this information to the complainant”
- Repairs or contractors secondary · not upheld“it would be unfair to compel the insurer to commit to a start and end date for the repairs”
Subjects and remedies
home or building damageprovide documents
Related
Text of the determination
Determination
Case number 963355
Financial firm Insurance Australia Limited
Determination | Case number: 963355 Page 1 of 5
Case number: 963355 5 February 2024
1 Determination overview
1.1 Complaint
The complainant is a beneficiary under a strata policy held with the financial firm (insurer). In
2014, the insurer accepted a claim and repaired damage to the complainant’s property. In
2021, the complainant lodged a claim with the insurer for rectification works for faulty repairs
completed in the 2014 claim.
The insurer assessed and accepted liability for the rectification works on 18 February 2022,
however it has not yet commenced repairs. The insurer accepts it has caused delays and that
it missed the agreed repair start date outlined in AFCA’s preliminary assessment. The insurer
says it has paid the complaint AFCA’s maximum compensation because of this.
The complainant wants the insurer to confirm the start date for repairs and for the repairs to
be completed no later than April 2024, otherwise she will face tax implications when selling
the property.
1.2 Issues and key findings
Is the insurer to commit to a repair start and end date?
No. While I appreciate the complainant’s concerns, it would be unfair to force the insurer to a
commencement and completion date, as there are many factors outside of the insurer’s
control that can alter these dates.
However, the insurer is to provide regular updates to the complainant in accordance with the
General Insurance Code of Practice (GICOP), on the progress of the repairs until they are
completed.
Is the insurer’s offer of compensation fair?
Yes. The insurer has previously paid the complainant $3,000 and a further $5,400 after it did
not execute the terms of AFCA’s preliminary assessment. I am satisfied this is a fair and
reasonable amount in the circumstances.
Why is the outcome fair?
It would be unfair to compel the insurer to a start and end date when there are factors outside
of its control that can impact the dates, however given the length of time the matter has been
on foot it is fair the insurer provides regular updates.
1.3 Determination
This determination is in favour of the insurer.
Within 14 days of acceptance of this determination by the complainant the insurer is to
provide the complainant with its first update and is to continue to do so in line with the GICOP
until the claim is finalised.
Determination | Case number: 963355 Page 2 of 5
2 Reasons for determination
2.1 Is the insurer to commit to a repair start and end date?
No. While I appreciate the complainant’s concerns, it would be unfair to enforce the insurer to
a commencement and completion date, as there are many factors outside of the insurer’s
control that can alter these dates.
However, the insurer is to provide regular updates to the complainant in accordance with the
General Insurance Code of Practice (GICOP), on the progress of the repairs
Insurer did not adhere to the agreed preliminary assessment
On 22 September 2023, AFCA provided the parties with its preliminary assessment that the
complaint should be resolved as follows:
the insurer was required to pay the complainant $3,000 in compensation due its claim
handling
commence repairs as soon as practical, but not later than December 2023.
The parties accepted AFCA’s preliminary assessment and the complaint was resolved with
the expectation the parties would adhere to the recommendations in the preliminary
assessment.
The information shows the insurer settled the complainant $3,000, however, it has yet to start
repairs on the property. The insurer accepts it did not adhere to AFCA’s preliminary
assessment and in recognition of this has paid the complainant a further $5,400 in
compensation. However, the insurer says currently it is unable to give the complainant a
guaranteed start date.
Complainant is seeking for repairs to be completed before April 2024
The complainant wants the insurer to start repairs as soon as possible and for the repairs to
be completed before the start of April 2024. The complainant says repairs need to be
completed by this stage otherwise she may face tax implications when selling the property, if
it is sold after August 2024.
Information shows some delays are unavoidable
I have reviewed the further information provided since the preliminary assessment was
delivered and it shows:
from 22 September 2023, the insurer has been working on progressing the claim
the insurer’s builder was required to engage an engineer and surveyor to redesign the
balcony to ensure it was compliant, with plans expected to be completed by 6 October
2023
on 9 October 2023, a dual assessment was requested due to further issues discovered
with the building and the repairs required to ensure they are compliant.
there were delays in arranging the dual assessment and advising the complainant why it
was required, it is unclear why there was a delay, however it appears this was within the
insurer’s control
a dual assessment took place on 13 December 2023, after the complainant had re-
engaged with AFCA
further engineer plans, and reports were completed in early January 2024 to be signed off
by the surveyor, so building permits could be obtained.
Determination | Case number: 963355 Page 3 of 5
the insurer says the process to obtain the permits will take at least a month, as such it
cannot give a start date at this time
once repairs commence there will be a further variation to the works, which can only be
quoted once repairs start.
Based on the available information I am satisfied the insurer has continued to attempt to
progress the matter, however the insurer has delayed the progress by not arranging the dual
assessment in a timelier manner.
While I accept, there was a two-month delay in arranging the dual assessment I am
persuaded the insurer would not have been able to commence repairs before December
2023, due to the issues in ensuring the repairs are compliant and the length of time it takes to
obtain a permit.
However, I am satisfied the insurer should have been more proactive in relaying this
information to the complainant.
Unfair to insist the insurer commit to a repair start and end date
I accept the rectification claim and complaint has been on foot for a considerable period and
that the insurer previously agreed to a start date. However, I am not persuaded this means
AFCA should or can compel the insurer to commit to a start date.
This is because the information shows the final plans are required to have building permits
approved by the relevant authority, which is something the insurer does not have any control
or influence over. When final approval for repairs is out of the insurer’s control it would be
unfair to hold it to a timeframe for a repair start date.
Further, the information shows the insurer has identified a further variation on the works will
be required, however this aspect cannot be quoted until repairs are underway. It would be
unfair to insist the insurer commit to a completion date, when the impact of the additional
works will have on the repair duration is not known.
For these reasons I am satisfied it would be unfair to compel the insurer to commit to a start
and end date for the repairs. However, I am persuaded in the circumstances the insurer is to
commit to providing the complainant with regular updates in writing on the progress of both
the approval for repairs and the repairs themselves.
I am satisfied in the circumstances the insurer should do so in accordance with GICOP, with
the first update to be within 14 days of acceptance of this determination.
2.2 Is the insurer’s offer of compensation fair?
AFCA takes a conservative approach to compensation
Non-financial loss includes claims for stress or inconvenience caused by an error of the
financial firm.
We will only award this type of compensation if there has been an unusual degree or extent of
inconvenience. We recognise that making a claim can be stressful and time-consuming, even
if the insurer handles the claim correctly. We will not award compensation for the ordinary
degree of inconvenience that comes with making a claim or for loss a complainant may incur
because of pursuing a complaint or rectifying the insurer’s error.
When assessing whether the circumstances are of an unusual nature we will review:
Determination | Case number: 963355 Page 4 of 5
the degree or extent of physical inconvenience suffered
the general time taken to resolve the dispute
the extent to which the insurer’s actions interfered with the complainant’s expectation of
enjoyment or peace of mind.
Insurer’s payments for non -financial loss are fair and reasonable
Under our rules AFCA can award a maximum of $5,400 in compensation for each claim of
non-financial loss. In this complainant I consider there to be two sperate claims for
compensation.
The first being the initial delays and service issues up to the date the parties accepted
AFCA’s preliminary assessment for which AFCA awarded $3,000. As t he amount was agreed
and accepted by the parties I consider this claim for compensation resolved.
The second claim for compensation and while not specifically raised by the complainant is
from the date of the preliminary assessment to the current date. The insurer offered $5,400,
which was accepted by the complainant. This is the most AFCA can award. I consider this
amount to be more than fair for the service and delays that have occurred since the
preliminary assessment was accepted.
Accordingly, I am sati sfied the insurer’s offer is fair in the circumstances.
2.3 Why is the outcome fair?
It would be unfair to compel the insurer to a start and end date when there are factors outside
of its control that can impact the dates, however given the length of time the matter has been
on foot it is fair the insurer provides regular updates.
Determination | Case number: 963355 Page 5 of 5
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.