Determination 963019
Cash settlement of flood damage claim; complainant sought full sum insured to demolish and rebuild
Summary
After the 2022 Brisbane floods the insurer offered a $96,243.77 cash settlement; the complainant sought the $448,100 sum insured to rebuild. AFCA rejected the sum-insured claim but required a market-rate settlement with a 20% contingency, $500 for delay, and assessment of resiliency and accommodation costs.
The policy covers only repair of flood-damaged parts (or cash settlement at market rates), not demolition or relocation for future flood risk, and the building was not a total loss; delay warranted modest non-financial loss compensation.
Issues
- Claim amount dispute primary · upheld
“The insurer's calculation needs to account for the current market rate of building repairs and should add 20% contingency on the relevant settlement amount.”
- Claim denial secondary · unclear
“Accommodation costs: complainant gave no itemised detail, so AFCA made no finding and allowed her to lodge invoices for assessment.”
- Delay secondary · upheld
“There was a delay beyond what would be expected in the claims handling during which time the complainant was required to live out of her home.”
- Product terms interpretation secondary · not upheld
“The policy does not contain any provision requiring the insurer to make additional payments in line with the recommended actions of demolition and rebuilding.”
Subjects and remedies
home or building damagenatural disasterpay claimpay non financial lossreassess claim
Text of the determination
Determination
Case number 963019
Financial firm AAI Limited
Determination | Case number: 963019 Page 1 of 11
Case number: 963019 13 September 2023
1 Determination overview
1.1 Complaint
The complainant holds a home building and contents policy of insurance with the financial
firm (insurer). The complainant made a claim on 28 February 2022 following the Brisbane
floods on 27 February 2022. The insurer accepted the claim and in November 2022 offered a
cash settlement for the building repairs in the sum of $96,243.77.
The complainant disputes the settlement and seeks the full sum insured of $448,100 in order
to rebuild the property as it has been deemed as needing to be built above the flood level.
This requires a demolition and rebuild of the property.
The insurer’s position is that the policy of insurance does not cover the cost of relocation due
to future risk of flooding. Further, the damage to the property does not render it a total loss
which would allow payment of the sum insured. The policy does not extend to undamaged
parts of the building.
1.2 Issues and key findings
Has the insurer appropriately settled the claim?
No. The insurer’s calculation needs to account for the current market rate of building repairs
and should add 20% contingency on the relevant settlement amount of either $96,243.77 or
$99,973.78 which has been listed in the insurer’s claim file notes . The insurer is not required
to otherwise pay the sum insured.
Is the complainant entitled to non-financial compensation?
There was a delay beyond what would be expected in the claims handling during which time
the complainant was required to live out of her home. Given this, an amount of $500 should
be provided as compensation for non-financial loss.
Why is the outcome fair?
The outcome is fair as it is based on the law, evidence and policy terms and conditions to
calculate the settlement entitlement of the complainant.
1.3 Determination
This determination is partially in favour of the complainant. Within 14 days of the
complainant’s acceptance of this determination, the insurer will:
confirm whether the figure of $96,243.77 or $99,973.78 is payable based on its claim notes
which suggest an increase on the quotation pr ovided (relevant settlement figure) and
allow for a 20% contingency fee to be applied to the relevant settlement figure to address
any inflation and increase in building costs since the quotation was provided.
pay the relevant settlement figure net of any excess owed or repair costs (forming part of
the relevant settlement) already paid to the complainant.
Determination | Case number: 963019 Page 2 of 11
pay $500 in non-financial compensation to the complainant for claim delays.
The complainant is entitled to provide material to allow the insurer to assess whether she can
claim a further $5,000 for building resiliency costs
If there are any outstanding accommodation costs, the complainant should lodge any
invoice(s) together with any relevant contract with the insurer who will provide a claim
decision within 14 days.
Determination | Case number: 963019 Page 3 of 11
2 Reasons for determination
2.1 Has the insurer appropriately settled the claim?
No. The insurer is required to base a cash settlement on market rates. There appears to be
no assessment of the complainant’s entitlement to an amount for buildin g resilience.
The parties agree the insured building was damaged by an insured event
The parties and the expert assessing reports agree that the building was inundated by flood
as defined by the policy on 27 February 2022.
The parties also agree that the policy of insurance covering the building provides building and
contents cover for flood.
The complainant has raised a concern with two aspects of the claim settlement which are:
settlement of the building claim, and
non-payment of accommodation costs
Each issue will be dealt with separately below.
2.1.1 Settlement of the building claim
The policy provides cover for repairs to the building up to the sum insured
The policy of insurance provides cover to repair loss or damage to the insured building
caused by an insured event. In this case, the policy covers the loss or damage to the building
caused by the flood.
The policy also makes it clear that no cover extends to:
pay more than the relevant sum insured
pay extra to repair or rebuild the home to a better standard, specification of quality than it
was before the loss or damage occurred
pay extra to repair or rebuild undamaged parts.
The policy does provide limited cover for relocating to another site. However, the wording of
the policy makes it clear this occurs only in circumstances the home is to be rebuilt and the
complainant would pay an extra cost involved in doing so.
Broadly speaking, in order to access the full sum insured under the contract, the loss or
damage would need to meet or exceed the sum insured or the building be determined as a
total loss. That is, the damage to the building is so substantive that it cannot be properly
repaired or is uneconomical to repair.
Neither party has provided an assessment that the repairs would exceed the sum insured or
that the building is a total loss.
The complainant seeks payment of a sum insured based on government assessment
The complainant provided correspondence from the relevant state government body (RHF)
dated 7 March 2023. The correspondence suggests the complainant is able to apply for
funding for demolition, rebuilding and relocation through the Queensland Rural and Industry
Development Authority (QRIDA). The correspondence confirms the maximum amount
claimable under the funding allowance is $100,000 and that the complainant would be
required to provide any additional funds.
Determination | Case number: 963019 Page 4 of 11
The complainant has also provided correspondence from the Queensland Reconstruction
Authority dated 13 March 2023. The correspondence su ggests the complainant’s property is
not eligible for buy-back as it did not meet the floodwater depth criteria.
Based on the correspondence, it is clear that the insured building is in an area prone to
flooding and which is a subject of concern for the Queensland Government.
The policy however does not contain any provision requiring the insurer to make additional
payments in line with the recommended actions of demolition and rebuilding provided by the
RHF. A total loss under the insurance policy is a different assessment to demolition and
rebuilding under the RHF. There is only limited additional cover for resiliency building benefits
under the policy to address future flood risk.
Further, there appears to be no relevant law or building code referred to by the complainant
which would require the complete demolition and rebuild of the building rather than repair.
The insurer is therefore only bound by the contract terms which permit it to either repair or
provide a cash settlement for the cost of repairs.
The policy is separate to the Queensland Government funding regime
It is clear that the Queensland Government is taking steps to mitigate the loss and damage to
homes and contents caused by flooding and future floods. This is demonstrated by the use of
funding to reduce the impact of flood or encourage new construction which can resist flood by
using methods such as changing the siting of the home and/or raising the finished floor levels.
The Queensland Government is focused on future floods and reducing the impact of same.
The policy however only extends to cover damage that has arisen from a flood and only has
limited installation of resiliency building enhancements. Under the complainant’s certificate of
i nsurance, she has ‘Classic’ cover which only provides a $5,000 payment for any one incident
for the net cost (less any government subsidy to which she is entitled) of purchasing and
installing the resiliency building enhancement.
The complainant must provide proof of whether she can claim the subsidy before receiving
the benefit. There is insufficient material to confirm whether the complainant has been
assessed for such a benefit by the insurer, but the complainant would be entitled to lodge a
claim for assessment pursuant to the policy terms and conditions.
The cash settlement must reflect the cost of engaging a builder to complete the works
The policy provides terms for the provision of a cas h settlement for repairs when the insurer’s
builder cannot complete the work as follows:
When your claim for loss or damage to the home is covered and a member of our
supplier network is unable to complete the repair or rebuild, we will ask you to
engage a builder to provide a scope of works and provide a quote on the cost to
repair or rebuild your home on a ‘new for old’ basis.
The complainant has not provided quotations for the cost to engage a builder of her choice to
complete the repair works. The cash settlement figure appears to be calculated on the
i nsurer’s own repairer which does not match the settlement terms in the policy. It is not clear
from the material provided whether the complainant has been informed that she should
engage a builder to quote on the costs of repairs for the flood damage to the building.
However, I have no other costings on which to base a decision of settlement. Further, the
Determination | Case number: 963019 Page 5 of 11
complainant has not objected to the costing provided on the basis it is insufficient to effect
repairs but rather because she seeks the sum insured.
It should also be noted that the cash settlement amount of $96,243.77 net of excess offered
by the insurer does not match the claim notes dated 23 May 2023 for the building scope of
works which was $99,973.78. It is unclear why the amount for the building scope of works has
increased from the original cost of $96,243.77 which was based on a quotation provided by
the insurer’s builder . The increase does not appear to be related to any builder’s contingency
fee which usually ranges from 15% to 25%. I further note the age of the quote may not reflect
the current market rate for the repairs taking into account inflation and the rising cost of
building materials and labour. Further, given the nature of the event and repairs to be
undertaken it would be appropriate to arrange for a higher contingency amount.
In the circumstances, I consider that the following calculation for repair costs is fair in all the
circumstances:
the insurer should confirm whether the figure of $96,243.77 or $99,973.78 is payable
based on its claim notes which suggest an increase on the quotation provided (relevant
settlement figure) and
allow for a 20% contingency fee to be applied to the relevant settlement figure to address
any inflation and increase in building costs since the quotation was provided.
the complainant is entitled to provide material to allow the insurer to assess whether she
can claim a further $5,000 for building resiliency costs
The insurer should then pay the repair costs net of any excess owed or repair costs (from the
relevant settlement) already paid to the complainant.
2.1.2 Future accommodation costs
The complainant has noted that there had been non-payment or delay in making payment of
accommodation costs.
The complainant has not itemised how much was outstanding, how long it was outstanding or
whether it continued to remain outstanding.
Without this information I determine any amount or find that the accommodation is still
outstanding and ought to be paid by the insurer. If there is any outstanding entitlement under
the policy the complainant should lodge invoices and/or any other relevant contract for the
accommodation with the insurer and the insurer should provide a claim payment decision
together within any payment within 14 days.
2.2 Is the complainant entitled to non-financial loss?
There was a delay beyond what would ordinarily be expected in the claims handling during
which time the complainant was required to live out of her home. Given this, an amount of
$500 should be provided as compensation for non-financial loss.
The insurer has apologised for delay but not offered compensation
The insurer has offered an apology for the delays caused in claims handling but there
appears to be no offer of compensation for non-financial loss.
Determination | Case number: 963019 Page 6 of 11
AFCA’s approach to non -financial loss compensation
When deciding whether to award compensation for non-financial loss, AFCA looks at the
severity and duration of the impact of the financial firm’s conduct on the complainant.
AFCA takes a conservative approach to assessing compensation for non-financial loss. The
maximum award for non-financial loss is $5,400.
In deciding whether to award compensation, AFCA expects complainants to be moderately
robust, to bear the normal degree of inconvenience experienced when a problem occurs and
take reasonable steps to manage the situation.
AFCA will only award compensation for non-financial loss where there has been an unusual
amount of:
physical inconvenience
time taken to resolve a situation
interference with the complainant’s expectation of enjoyment or peace of mind
AFCA will look at the time frames and the type of inconvenience or hardship caused to the
complainants to determine any appropriate award.
AFCA may also consider whether the complainant has contributed to their loss arising from
the financial firm’s cond uct. If so, it may be appropriate for the financial firm and the
complainant to share responsibility for the loss.
Additional non-financial loss is appropriate in these circumstances
A review of this matter suggests the following general chronology:
the complainant lodged their claim on 27 February 2022
the insurer did not obtain a relevant engineering report until approximately 7 months after
the insured event
the complainant was forced to move and live out of the home in circumstances where
locating an appropriate rental was difficult. This included a rental property where the
landlord refused to fix the lock on an external door leading to an unsecured premise
the insurer did not offer any settlement of the claim until November 2022
I note that a 4-month time frame for handling claims applies under the General Insurance
Code of Practice (Code). This time frame extends to 12 months in the event of an
extraordinary catastrophe declaration by the Insurance Council of Australia. The Insurance
Council of Australia declared an ‘Insurance Catastrophe’ but not an Extraordinary
Catastrophe under the Code.
The time frames in the Code are a general guide, there will be times when it is appropriate for
the claim to take longer – particularly if there are complex matters for investigation and
resolution.
Due to the length of time taken to finalise the claim and the continued stress of obtaining
appropriate long-term rental accommodation, I consider it is appropriate to provide some
compensation for non-financial loss. In the circumstances, I consider an award of $500 is
appropriate.
Determination | Case number: 963019 Page 7 of 11
2.3 Why is the outcome fair?
The outcome is appropriate as it is in accordance with the law, evidence and policy terms and
conditions.
Determination | Case number: 963019 Page 8 of 11
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
Determination | Case number: 963019 Page 9 of 11
3.2 Relevant policy wording
“We Cover
Loss or damage caused by flood
..
Repairing or rebuilding damaged parts
We will only repair or rebuild the parts that are damaged in the incident covered
by your policy. Apart from the limited circumstances where we will repair
undamaged parts (see ‘Matching undamaged parts’ on page 74) this policy does
not cover you to replace undamaged parts, such as when:
..
- An external wall is damaged
We will replace the damaged parts of the wall, not undamaged areas of the
wall or other sides of the home.
..
If you want to change the design of the home
When repairing or rebuilding the home, if we agree, you can choose to change
the design of the home or upgrade parts of it, provided you pay the extra costs of
doing this including all costs related to the construction and all professional fees
(e.g. architect’s fees). If you want to downsize the home for less cost than you are
entitled to claim, we will not pay more than the assessed quote provided by a
member of our supplier network to rebuild the downsized home. For example, if
your three bedroom home is damaged in a storm and has to be rebuilt, and you
choose to downsize to a smaller two bedroom home, the most we will pay is the
assessed quote for our builder to rebuild the smaller two bedroom home.
Choosing to rebuild on another site
If the home is to be rebuilt following an incident covered by your policy, you can
choose to have the home rebuilt on another site provided you pay any extra costs
involved.
..
When we settle the home claim we will not:
Determination | Case number: 963019 Page 10 of 11
— pay more than the relevant sum insured or policy limit;
— pay extra because you paid more for an item when it was originally purchased;
— pay extra to repair or rebuild the home to a better standard, specification or
quality than it was before the loss or damage occurred, except as stated in the
meaning of ‘new for old’ (see page 92) or unless stated otherwise in your policy;
— fix inherent defects, structural defects, structural faults and/or faulty/poor
workmanship that are not covered by your policy (see section 3 ‘Things we don’t
cover’ on page 33), other than a defect or fault that we guarantee under this
policy;
— pay extra to repair or rebuild undamaged parts (some limited cover is available
in ‘Matching undamaged parts’ see page 74);
— fix or pay to fix pre-existing damage (unless your policy provides otherwise).
..
Words with special meanings
..
Loss or damage
means physical loss or physical damage unless specifically stated otherwise in
your policy.
Resiliency building enhancements
means an alteration or addition to the home designed to improve the home’s
resilience to insured events. These may include items such as cyclone rated
shutters, ember protection options and raising external services around the home
(such air-conditioner units, hot water systems, pool pumps etc.) to alleviate future
flooding damage.
Determination | Case number: 963019 Page 11 of 11
3.3 Relevant material regarding retrofit and relocation
Record Key points
Government Body
Report
Complainant’s report
Undated
The home is in a high flood hazard area and has a continued risk.
The ground floor is 7.2mAHD and the assessed flood level is
10.2mAHD. The height of the 2021 - 2022 rainfall and flooding
event was 7.45 - 7.7mAHD.
The programs the complainant was eligible for included the
Resilient Retrofit Program rather than home raising program. A
number of strategies were recommended to retrofit the home to
minimise fut ure flooding.
The report i s not comprehensive and focuses on measures to
increase your property’s flood resilience and reduc e the impact of
future flood events.
Government Body to
complainant
Letter
7 March 2023
The complainant made an application to the Resilient Homes
Fund and confirmed she could apply to the fund for demolition and
rebuild/relocation from another aut hority.
To apply the complainant is required to provide evidence and if
approved a maximum of $100, 000 can be provided towards
demolition and rebuild/relo c ation. The complainant may need to
contribut e funds.
Government Body to
complainant
Letter
13 March 2023
The complainant applied for a voluntary home buy - back of the
home building.
The outcome of the application was that the complainant’s
property was not identified for the voluntary home buy - back as it
did not meet the depth criteria.