Determination 961033

Delay in repairing earthquake-damaged property causing exhaustion of 52-week rental loss benefit

FirmSuncorp Group
Decided2024-02-28
ProductGeneral Insurance · Landlord
OutcomeFor the complainant
Amount awarded—
Non-financial loss$3,000
Amount claimed—
SourceAFCA PDF

Summary

A landlord's earthquake-damaged property remained unrepaired, and the 52 weeks of rental loss cover was exhausted due to delays. AFCA found the insurer contributed to the delay and ordered it to keep paying rent at $680 weekly until repairs finish, plus interest and $3,000 non-financial loss.

The insurer and its experts unreasonably delayed matters within their control, and had it acted promptly the rental loss limit would likely not have been exhausted, so it is fair to continue benefits.

Issues

Subjects and remedies

broker or intermediaryhome or building damagenatural disasterpay claimpay interestpay non financial loss

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 961033 Financial firm AAI Limited Determination | Case number: 961033 Page 1 of 7 Case number: 961033 27 February 2024 1 Determination overview 1.1 Complaint The complainant ’s tenanted property was damaged by an earthquake on 22 September 2021. Her tenant also vacated the property in early March 2022, following an emergency order issued by a relevant council. The complainant claimed for property damage and for rental loss under her landlord policy with the financial firm (insurer). The insurer accepted both claims and authorised repairs. There were significant delays in getting the property’s repair underway. This caused the complainant to exhaust the policy ’s 52 weeks rental loss entitlement before repairs began. The complainant says the insurer delayed and is still delaying her property’s repair , so it must continue covering her rental losses until repairs are complete. The insurer says it does not need to do so because:  it already paid the complainant ’s maximum policy entitlement for rental losses  the delays that occurred were beyond its control. 1.2 Issues and key findings Must the insurer continue paying rental loss benefits? Yes. While some delays were outside the insurer’s control, it still took, and is still taking, an unfair and unreasonably long time to complete matters within its control. This significantly contributed to the overall delay that occurred and is still causing ongoing delays. Given this, it is fair that the insurer pays rental loss benefits until the property ’s repair is complete and some compensation for non-financial loss. Why is the outcome fair? The insurer significantly contributed, and is still significantly contributing, to the delays in resolving the complainant’s property damage claim. This caused, and is still causing, the complainant rental losses and unusual inconvenience and interference. Given this, it is fair to compel the insurer to provide the remedies outlined above. 1.3 Determination This determination is in favour of the complainant. Within 14 days of being notified of the complainant’s acceptance of this determination, the insurer is to pay her:  rental loss benefits at the rate of $680 per week on and from 10 March 2023 onwards until her property’s repair is completed  interest on unpaid rental losses incurred before the date of this determination from the date each weekly rental loss was incurred until these losses are reimbursed  $3,000 as compensation for non-financial loss. Determination | Case number: 961033 Page 2 of 7 2 Reasons for determination 2.1 Must the insurer continue paying rental loss benefits? Yes. While some delays were outside the insurer’s control, it still took, and is still taking, an unfair and unreasonably long time to complete matters within its control. This significantly contributed to the overall delay that occurred and is still causing ongoing delays. Given this, it is fair that the insurer pays rental loss benefits until the property’s repair is complete and some compensation for non-financial loss. No dispute insurer paid policy’s maximum entitlement for rental loss There is no dispute:  the complainant’s property sustained earthquake damage on 22 September 2021  the damage it sustained caused the relevant council to issue an emergency order in February 2022, requiring the property to be evacuated and made safe  the complainant’s tenant vacated the property following the emergency order. This resulted in the complainant suffering and claiming for rental loss, which the insurer accepted and paid the policy’s maximum entitlement of 52 weeks rent at $680 per week. The relevant policy extracts regarding rental loss are set out in section 3.2 of this determination. Insurer says it is not liable to cover further rental losses The insurer says it is not liable for the complainant’s further rental losses because:  it already paid her maximum entitlement for rental loss under the policy  the delays that occurred were due to the need to obtain the relevant council’s approval and permits to enable repairs to proceed, which were outside its control. At the time of its 30 March 2023 notice of response, the insurer says a ‘permit application’ was made on 9 February 2023 and it was presently waiting for permits to begin re pairs. In August 2023, it supplied a 22 August 2023 update from assessor ‘ S ’ that said:  the relevant council granted a building permit on 11 August 2023  the property ’s repair is ‘in progress’  builder ‘AB’ anticipates ‘all repairs’ to be completed by 31 October 2023. Complainant says insurer delayed repair, so it must continue paying rental loss The complainant says the insurer must continue covering her rental losses as it delayed and is still delaying the property’s repair. She says AB prepared the relevant paperwork on a piecemeal basis and took too long to complete and submit them for council approval. The complainant is assisted by a representative, who says the insurer gave misleading information about the application for the relevant council approvals. The representative says he contacted the relevant council directly and was told AB:  only made an enquiry about getting a planning permit exemption on 9 February 2023  was told an exemption would not be given and it would need to apply for a planning permit  only applied for planning permit on 26 March 2023. The representative provided a 5 June 2023 email and his 21 March 2023 email to the complainant’s insurance broker, which outline his discussion with the relevant council. Determination | Case number: 961033 Page 3 of 7 Property’s repair wa s significantly delayed and remains incomplete to date There is no dispute there were significant delays in getting the complainant’s property repair underway and its repair has not been completed to date. Although the relevant council approvals have since been obtained and ‘all repairs’ were anticipated to be completed by 31 October 2023, AB’s 15 January 2024 ‘client update’ now says the ‘scheduled completion date’ is 28 March 2024 because of ‘specialist trades having extended holidays’. AB could not do any work on the property for the first five months of the claim The exchanged information shows o ne of the property’s damage d walls was shared with a neighbouring property. There were complications with this wall that delayed the settling of a scope of works (SOW) and repair quote to reinstate the property. The wall first needed to be made safe as it was old, in a poor condition, and continuing to deteriorate and rotate towards a neighbour’s property. As the property was heritage listed, and the neighbour was apparently unwilling to give AB access to stabilise the wall, a council order was needed before any make safe works could be done. The information suggests AB sought a ‘work order’ from the relevan t council by around 13 October 2021. However, the council only inspected the property and issued an emergency order directing it to be evacuated and made safe on 23 February 2022. This meant AB could not do any work on the property for the first five months of the claim. Insurer took nearly 13 months to finalise repair works and council applications The information shows initial make safe works were completed within a week or so of the council’s February 2022 emergency order. However, what occurred after th is is not clear. The information shows the rotated shared wall appeared to require engineering, geotechnical, plumbing and architectural input before a SOW and repair quote to repair the property was ultimately finalised. Since it was a shared wall it also appears t he neighbour’s involvement was required to facilitate its repair. AB appeared to complete some of these works while waiting for council’s initial approval to make safe the property. The insurer says AB sent it a repair quote on 22 February 2022, which appeared to be based on a 29 November 2021 SOW designed by engineer ‘ S S’ . The insurer and AB also appeared to believe only a building permit was needed at the time. However, the information is vague about when an application for this was made. AB says it made the application on 22 May 2022, presumably because it says it received architectural and engineering documents on 1 and 15 May 2022 respectively. However, S said ‘all paperwork’ for a building permit were already received and the application was already submitted in its 28 April 2022 report. No reliable information was provided about when the application was made, so it is unclear when it occurred. In any case , S wrote to the complainant’s broker on 18 May 2022 saying:  there was only ‘one final document’ that was needed for a building permit to be issued  AB ‘appears confident’ it was ‘only a few days away’ from the permit being issued. This did not appear to happen, and no clear explanation was given why. What the exchanged information seems to show was that the property was reinspected on or around 22 June 2022 and more extensive damage was discovered. Determination | Case number: 961033 Page 4 of 7 The claim’s progress appeared to be delayed for at least another four months because of this, as further expert input and a SOW variation and quote were now required. The insurer’s 4 November 2022 claim note says the following works were still outstanding as at that date: UPCOMING WEEK Finalize engineering to submit to complete building permit Arrange meeting with neighbour to insured regarding signing of documentation form seven and eight Schedule works for removal of brick wall Arrange connection of power and removing over head power (sic) It is u nclear when the ‘engineering’ referred to above was ultimately finalised. Nor is there any explanation why this remained incomplete nearly four months after it became apparent the property required more extensive repairs. However, the exchanged information shows part of the delays that occurred from then until early February 2023 were also contributed to by year-end holidays and plans to meet the neighbour to get some documents signed. I do not accept AB applied for a planning permit on 9 February 2023. The document provided was merely council’s acknowledgement that AB asked for a permit exemption on 6 February 2023. The insurer has not shown when the permit application was made. Therefore, I accept the complainant’s representative’s evidence this probably happened on 26 March 2023. In summary, from the time initial make safe works were completed, the insurer and its appointed experts effectively took nearly 13 months to finalise the documents and works needed to repair the property and apply for the relevant council permits. Insurer was aware wall must be replaced and planning permit may be needed It also appears that during this period the insurer and its experts were aware:  the relevant shared wall had to be demolished and rebuilt by early July 2022  a planning permit may be needed for such work from as early as late September 2022. In its 7 July 2022 report, SS said the shared wall needed to be demolished and rebuilt as a repair ‘will not prevent future rotation of the middle and west end’ of the wall, and underpinning ‘is not recommended for safety reasons’. In a 21 September 2022 claim note, the insurer also recorded: [D] advised - "I met with [AB] yesterday on site with the Engineer and Draftsman who indicated previous similar jobs in the area had to go [through] the planning process decided by the Council due to the Heritage factor. This isn't confirmed, just a possibility and won't be known till the plans have been submitted to Council for the permit for them to make the decision. If it does have to have Planning, that could [take] several months, so it's a time issue more than anything. This is just fyi." (sic) Determination | Case number: 961033 Page 5 of 7 Insurer has not satisfactorily explained delays on matters within its control I accept the insurer and its experts cannot control when a local council would issue planning or building permits to carry out works on a property. I also accept they cannot control when the neighbour would sign documents they needed to sign to facilitate the property’s repair. I further accept the property’s damage and repair were likely complicated, so a repair plan would take some time taken to develop, refine and finalise. However, the insurer and its experts had control over the works required to prepare the relevant engineering plans, architectural drawings, SOWs, quotes and other documentation needed to apply for the relevant council permits and to repair the property. This includes:  finding out if repairs would require a planning permit in addition to a building permit  applying for a planning permit if one was required  applying for a planning permit exemption if they wanted an exemption. Notwithstanding complexities with the property’s repair , the insurer has not satisfactorily explained why its experts needed nearly 13 months (from when initial make safe works were completed) to attend to or finalise such matters. This is particularly when they were aware:  the relevant shared wall had to be demolished and rebuilt anew in early July 2022  a planning permit may be needed for such work in late September 2022. It is also unclear when AB initially made an application for a building permit to repair the property. As noted earlier, AB and S have given materially inconsistent information about this and no reliable evidence has been provided to show when the application was made. Property’s repair is still incomplete without any reasonable basis Further, the property’s repair remains incomplete to date despite the relevant council having granted a building permit on 11 August 2023. The exchanged information appears to be consist ent throughout that the property’s repair should take 12 weeks to complete. Given this, it should have been completed by 31 October 2023 as S’s 22 August 2023 email said . No reasonable explanation was given why the property’s repair remains incomplete to date. I do not accept ‘specialist trades having extended holidays’ is a reasonable or satisfactory explanation. This is especially so when the insurer is aware the repair is significantly delayed and remains incomplete almost two and half years after claim lodgement. Considering these matters, I cannot be satisfied the insurer did not contribute to the significant delays that have occurred and are still occurring. Fair for insurer to pay rental loss benefits until repairs are complete Without reasonable explanation why nearly 13 months was needed to finalise matters to apply for the relevant council approvals and repair the property, I consider these matters should have been completed within three months from completion of initial make safe works. On balance, this means:  applications for the relevant council approvals should have occurred by 4 June 2022, based on the insurer’s account that make safe works were completed on 4 March 2022  the relevant council approvals should have been provided by around 22 October 2022, since the council took about 20 weeks from 26 March 2023 to grant such approvals  the property’s repair should have begun by around 29 October 2022 if the insurer took seven days to start work  the repair should have been completed by around 21 January 2023 based on a 12-week repair timeframe, or by 21 February 2023 if a month is allowed for year-end holidays Determination | Case number: 961033 Page 6 of 7  the complainant would unlikely have exhausted the policy’s maximum entitlement for rental loss had the insurer acted reasonably promptly in settling the matters required to apply for the relevant council approvals to repair the property. Since the property’s repair remains incomplete, and the insurer has paid rental loss benefits until 9 March 2023, I am satisfied the insurer must continue paying such benefits at the rate of $680 per week on and from 10 March 2023 until the property’s repair is finally completed. Insurer must also pay interest and compensation for non-financial loss I am also satisfied the insurer must pay interest under the section 57 of the Insurance Contracts Act 1984 on unpaid rental losses that already occurred before the date of this determination. Interest is to run from the date each weekly rental loss was incurred until the complainant receives her compensation. It is also fair that the insurer pays the complainant $3,000 as compensation for non-financial loss. This is to account for the unusual delay, inconvenience and interference caused by its contribution to the significant delays in he r property’s repair . 2.2 Why is the outcome fair? The insurer significantly contributed, and is still significantly contributing, to the delays in resolving the complainant’s property damage claim. This caused, and is still causing, the complainant rental losses and unusual inconvenience and interference. Given this, it is fair to compel the insurer to provide the remedies outlined above. Determination | Case number: 961033 Page 7 of 7 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. I have reviewed and considered all information the parties have provided. While the parties have raised several issues in their submissions, I have restricted this determination to the issues that are relevant to the outcome. 3.2 Relevant policy wordings Loss of rent – Insured event  What we cover When you have property cover If we accept your claim for loss or damage to your property due to an insured event occurring during the period of insurance and we agree it cannot be lived in, we will pay the weekly rental amount for the reasonable amount of time we decide it should take to repair or rebuild the property so it can be lived in again. … The longest period we will pay for any one event is 52 weeks.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.