Home / Suncorp Group / Determination 960939

Determination 960939

Dispute over cash settlement amount for accepted flood claim, loss of rent and claim assessment delay

FirmSuncorp Group
Decided2023-07-31
ProductGeneral Insurance · Landlord
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$450,131
SourceAFCA PDF

Summary

The complainant disputed the insurer's cash settlement of his accepted flood claim, sought more loss of rent and alleged delay. AFCA found the insurer's scope of works and offer fair, the rent limit exhausted and no unreasonable delay.

The insurer's panel builder's scope of works was reasonable and actionable, the loss of rent policy limit of 10% of the sum insured was exhausted, and the General Insurance Code allowed 12 months for catastrophe claims.

Issues

Subjects and remedies

home or building damagenatural disasterno remedy

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 960939 Financial firm AAI Limited Determination | Case number: 960939 Page 1 of 9 Case number: 960939 11 July 2023 1 Determination overview 1.1 Complaint The complainant holds a landlord insurance policy with the financial firm (the insurer). He lodged a claim for damage caused by flood to property 226. The claim has been accepted. The insurer assessed the damage and obtained an actionable scope of works (SOW) for the repairs, which its repairer was willing to complete. The insurer has offered to cash settle the accepted repairs at the property. The complainant has provided his own SOW and has contested the amount offered by the insurer, stating the scope of the accepted repairs is insufficient, and the offer inadequate. The complainant wants the insurer to accept his SOW and increase the cash settlement amount. In addition, the complainant has raised concerns about loss of rent and unreasonable delay in assessment of the claim. 1.2 Issues and key findings Is the insurer’s offer of settlement fair ? Yes. The complainant’s SOW does not reflect the reasonable cost of repairs. The insurer’s amended quote of $225,318.01, is appropriate to cash settle because the SOW is reasonable and actionable. Is the complainant entitled to any loss of rent under the policy? The complainant is not entitled to additional loss of rent as the insurer has paid 10% of building sum insured and exhausted the policy limit. Did the insurer unreasonably delay the assessment of the claim? The insurer did not unreasonably delay the claim because it received numerous claims due to a significant weather event and this resulted in delays in its assessments. Therefore, the insurer’s offer of $1,000 is fair in recognition of the impact of its assessment timeframes. Why is the outcome fair? The outcome is fair because:  the insurer’s SOW is fair, reasonable and actionable  the complainant has exhausted the policy limit for loss of rent and  the insurer did not unreasonably delay the claim assessment, but in recognition of its assessment timeframes, it has offered $1,000 as non-financial loss compensation. 1.3 Determination This determination is in favour of the insurer. Within seven days of acceptance of this determination by the complainant, the insurer is required to cash settle the complainant for an amount of $225,318.01. Determination | Case number: 960939 Page 2 of 9 2 Reasons for determination 2.1 Is the insurer’s offer of settlement fair ? Yes. Based on the available information, the insurer’s offer of settlement is fair. The complainant has established a valid claim As the policy holder, the complainant is required to show, on the balance of probabilities, he suffered a loss caused by an event insured against under the policy. This is known as establishing a valid claim. If established, the onus shifts to the financial firm to show, on the balance of probabilities:  the policy does not cover the loss or damage,  the financial firm is otherwise entitled to deny the claim. There is no dispute the complainant’s investment property suffered flood damage. The claim has been accepted. However, a dispute continues as to the appropriate cash settlement. The policy covers the property against loss or damage caused by specified events, including flood. Cover under these benefits is subject to the conditions, limitations and exclusions specified in the product disclosure statement (PDS). Complainant disputes cash settlement offer The complainant disputes the cash settlement offer because he says the insurer’s quote is not actionable. The complainant details his key concerns, that include;  no allowance for several items,  items missing,  under allowance for several items,  unrealistic allowance for some items,  builder’s mark-up is different for the two properties, one 16%, the other 15%, and  items missing from the SOW The complainant requested that the insurer review its builder’s quotes and revise the consumer price index component. The complainant also requested that a quantity surveyor review the SOWs, so the pricing is based upon tod ay’s market. Complainant provided a repair quote The complainant provided a repair quote from his own builder on 8 December 2022, totalling $450,130.78. The insurer identified that the complainant’s builder is charging significantly more for every item. Further, the quote was not provided on the builder ’s letterhead and it did not provide the builder ’s details. It was provided over the insurer’s builder’s SOW. As a result, the insurer approved its builder’s amended quote for an amount of $224,686.87. Determination | Case number: 960939 Page 3 of 9 It appears the complainant accepted the cash settlement proposal but disputed the amount. Insurer says its SOW is actionable The insurer says:  The policy clearly informs the complainant that repairs can be completed by the insurer.  Therefore, the insurer obtained a SOW and approved cash settlement of $224,686.87.  The policy provides for the assessment of the complainant’s quotes when a member of the insurer’s supplier network is unable to complete the repair.  The insurer’s repairer is willing to complete the repairs, therefore the SOW provided by its representatives is actionable and represents the cost of repairs and its liability. Once the complainant lodged a complaint with AFCA, the insurer reviewed the complaint and says, the skip allowance is not present in the SOW, so it requested an amended SOW from its builder. In the meantime, the complainant provided a quote from his builder for an amount of $354,200. The insurer’s assessor reviewed the complainant’s quote and rejected it because the SOW included less repairs than the insurer’s panel builder quotation. The assessor says the rates quoted by the complainant’s repairer are higher and not fair and reasonable. The insurer’s assessor approved the amended quote for an amount of $225,318.01, which included an allowance for the skip bin. It is reasonable for the claim to be cash settled for $225,318.01 Due to dissatisfaction with the conduct of the insurer and its trades, the complainant wants the claim to be cash settled and he obtained a quote from his builder. A review of the insurer’s and complainant’s SOW s, show that the complainant’s builder has quoted higher amount. The high er amount quoted by the complainant’s builder does not mean it’s repair quote is more accurate or comprehensive. It appears the insurer was able to obtain lower rates due to the amount of work it supplies to its panel builders. However, the insurer’s buil der has advised it is prepared to do the work for the amount quoted. The insurer’s quote shows builder’s mark-up of 15% and flood levy 20%, to allow for contingencies. I am persuaded by the thorough assessment of the insurer’s SOW, by the assessor. I am also satisfied that the insurer’s SOW is actionable, fair, reasonable and allows for the repair of the complainant’s property 226. Therefore, it is reasonable to cash settle the claim for $225,318.01. Given the date of SOW and quote is 4 May 2023, I am not persuaded that interest is payable on this amount. Determination | Case number: 960939 Page 4 of 9 2.2 Is the complainant entitled to any loss of rent under the policy? No. The complainant has reached the policy limit and therefore, he is not entitled to any further loss of rent. Complainant says he has suffered loss of rent The complainant says:  because the repairs have not yet started he is suffering loss of rent  the bank has given him two months grace to pay the mortgage, after that he will have to pay the outstanding mortgage on the property  until the property repair is completed he cannot have renters  the property is jointly owned by his family and he has moved in with his mother  this is causing him stress and inconvenience and he had to take medical leave recently. Insurer says loss of rent benefit paid out under the policy The policy states the longest period of loss of rent it will pay for one incident is 52 weeks and the most it will pay in total is 10% of the building sum insured. The insurer says that the complainant has been paid $49,500, which is 10% of the building sum insured. The policy schedule confirms the building sum insured at the time of loss was $495,000. Therefore, 10% of $495,000 is $49,500. In my view, the complainant is not entitled to any further loss of rent because he has already reached the policy limit. 2.3 Did the insurer unreasonably delay the assessment of the claim? No, the insurer did not unreasonably delay the assessment of the claim. The claim was decided within 12 months after lodgement with the insurer The complainant lodged the claim for flood damage to property 226 on 2 March 2022. The insurer accepted the claim under the insured event flood by 27 April 2022. The insurer made an offer to cash settle the property on 25 October 2022. The length of time for the insurer to assess a claim in accordance with industry standards is four months as set out in clause 77 of the General Insurance Code of Practice (the code), unless clause 78 applies. Clause 78 of the code provides; In circumstances where: a. your claim arises from an Extraordinary Catastrophe; b. …. then within 12 months of receiving your claim we will tell you our decision in writing. If we cannot make a decision in 12 months, we will tell you in writing about our Complaints process. Determination | Case number: 960939 Page 5 of 9 Given the exchanged material, I am satisfied that the complainant’s claim arises fr om an Extraordinary Catastrophe. Therefore, Clause 78 of the code applies and the insurer has 12 months to make a decision regarding the claim. Complainant considers the insurer unreasonably delayed claim assessment The complainant says:  he lodged the claim on 2 March 2022  the cash settlement offer was made by the insurer on 1 August 2022  this delay has caused him financial hardship and mental stress. Requirements under the General Insurance Code of Practice The requirements under the code are:  within 10 business days from claim lodgement, the insurer will inform the complainant if further information or assessment is needed  the insurer will give an update to the complainant every 20 days  once the insurer receives all the relevant information and enquiries are done, it will provide a decision on the claim within 10 business days  a decision will be made within four months of receiving the claim form unless paragraph 78 applies  if paragraph 78 applies, within 12 months of receiving the claim, a decision will be given in writing. Timeline of event A timeline of events is detailed below: Date Action 27 - 2 - 2022  flood damage to the property 2 - 3 - 2022  c laim lodged 26 - 4 - 2022  engineer’s report and SOW received 1 - 6 - 2022  assessor’s report received 4 - 7 - 2022  builder assessment report and SOW for an amount of $217,721.72 received 1 - 8 - 2022  the assessor approved the SOW for an amount of $217,721.72  the complainant was offered a cash settlement 10 - 8 - 2022  roofer repor t received which indicated water ingress from the roof was not caused by an insured event and it was due to maintenance and wear and tear and gradual deterioration 27 - 10 - 2022  the insurer informed the complainant of maintenance issues with the roof 8 - 12 - 2022  the complainant provided quote for the repairs which was an Determination | Case number: 960939 Page 6 of 9 altered copy of the insurer’s builder’s SOW. The amount was $450,130.78 12 - 12 - 2022  the insurer received an updated SOW from its builder for an amount of $224,686.87 16 - 12 - 2022  the asse ssor accepted its builder’s quote for $224,676.87 28 - 2 - 20 23  the complainant confirmed he would acc ept a cash settlement but disputed the amount. Insurer ’s offer of $1,000 in recognition of the assessment timeframes is fair The insurer says:  it has acted in good faith by ensuring it has captured all flood related damage at the property and maintenance issues with the roof.  it could have completed its respective assessments sooner  it extends its genuine apologies for his claim ’ s experience  it has offered $1,000 of non-financial loss compensation in recognition of the assessment timeframes. In my view, the insurer’s offer of $1,000 is fair because the in surer received a significant number of claims due to significant weather event and this resulted in delays in assessments. Why is the outcome fair? The outcome is fair because:  the insurer’s SOW is fair, reasonable and actionable  the complainant has exhausted the policy limit for loss of rent  the insurer did not unreasonably delay the claim assessment, but in recognition of the impact of its assessment timeframes, it has offered $1,000 as non-financial loss compensation. Determination | Case number: 960939 Page 7 of 9 3 Supporting information 3.1 The AFCA processes AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. Determination | Case number: 960939 Page 8 of 9 3.2 Product Disclosure statement prepared on 25 March 2021 Flood (page 45) We cover loss or damage caused by flood We don’t cover ‒ loss or damage caused by actions or movements of the sea or storm surge; ‒ loss or damage to retaining walls, sea walls, revetments, garden borders and free- standing outdoor walls; ‒ resultant cracking to sealed paths, sealed roads and sealed driveways, but we will cover them if they are washed away by the flood; ‒ loss or damage to a sporting surface or court including a tennis court, squash court or multi-court surface; ‒ loss of damage to boat jetties, pontoons, mooring poles and their attachments and accessories, including if they are washed away by the flood; ‒ damage to external paintwork of the property, if that is the only property damage caused by the flood; ‒ loss or damage to gates, fences or wall fences that would be considered by a reasonable person to be in obvious state of disrepair before the loss or damage occurred; ‒ loss of damage caused by erosion, vibration, subsidence, landslip, landslide, mudslide, collapse, shrinkage or any other earth movement, but we will cover damage caused by a landslide or subsidence proved to have occurred within 72 hours of, and directly because of, flood and not because of erosion, structural fault or design fault; ‒ the cost of cleaning your undamaged contents. Loss of rent following an Insured event (pages 58-59) We cover When you have property cover If following an insured event, the property cannot be lived in or cannot be re-leased, we will pay the weekly rental amount for the time it should take to repair or rebuild the property so that it can be lived in again or re-leased. We will engage a builder to determine how long the repairs or rebuild should take. For example, if you have a claim for fire damage to the kitchen and our builder determines that the repairs would take 4 weeks complete, you will be entitled to 4 weeks loss of rent under this additional cover. We don’t cover – loss of rent ‒ if you do not intent to repair or replace the property, unit or contents; ‒ if the tenant still has an obligation to pay the rent; ‒ once the insured address is able to be lived in again or be re-leased because the repair or rebuilding process for the damage covered under this policy is complete; ‒ if you have made a claim for same incident under ‘loss of rent - tenant default’ (see page 66) and have already been compensated for your loss under that additional cover; ‒ if you do not have a rental agreement. But we will provide cover if the property would have been rented, during the time taken to repair, replace or rebuild the property. Determination | Case number: 960939 Page 9 of 9 You may be able to show this by a signed rental agreement from a tenant that was due to move in; ‒ … Limit When you have property cover The longest period we will pay for one incident is 52 weeks and the most we will pay in total is 10% of the property sum insured. How we settle property claims (page 86) We will aim to use a member of our supplier network to repair or rebuild the damage to the property. Sometimes, this is not always possible for example if there is pre-existing damage. This will determine how the property claim will be settled. When a member from our supplier network can complete the repair or rebuild (page 87) When your claim for loss or damage to the property is covered, we will engage a builder form our supplier network to prepare a scope of works and provide a quote on the cost of repair or rebuild the property on a ‘new for old’ basis. Once the scope of works and quote is provided to us, we will arrange for it to be assessed. This will involve reviewing the quote to make sure that the quote is appropriate and reasonable for the scope of works. This includes a consideration of the appropriateness of materials, repair method, labour and material costs and overall cost effectiveness. If the amount of the assessed quote to repair or rebuild the property is less than or equal to the property sum insured, we will offer you the choice to have the property repaired or rebuilt (based on the recommendation of our builder). … If you choose to not accept the offer You will be paid the amount of the assessed quote to repair or rebuild on a ‘new for old’ basis. Note: this amount may be less that what it would cost you to arrange the repairs or rebuild with your own builder. We are also able to secure supplier discounts from within our supplier network.