Insurer declined roof damage component of storm claim as wear, tear and poor maintenance; resultant damage settlement and claim delay also disputed

FirmIAG
Decided2023-10-02
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$547
Non-financial loss$1,500
Amount claimed—
SourceAFCA PDF

Summary

The complainant's storm claim for roof damage was declined by the insurer as due to rust, wear and poor maintenance, while internal damage was cash settled. AFCA upheld the roof decline but ordered a 25% uplift ($546.51) on the internal damage and $1,500 non-financial loss for poor handling and delay.

The complainant did not establish that the storm was the proximate cause of the roof damage, but the internal settlement lacked a scope of works and the claim handling breached the GICOP timeframe.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay non financial loss

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination Case number 958427 Financial firm Insurance Australia Limited Determination | Case number: 958427 Page 1 of 6 Case number: 958427 31 August 2023 1 Determination overview 1.1 Complaint The complainant holds a home insurance policy with the financial firm (insurer). On 26 February 2022, she lodged a claim for damage to her property following a storm. The insurer has declined the roof damage component of the claim on the basis that the damage is not consistent with a storm event. Further, it says the damage is due to wear, tear and deterioration of the roof sheets, which is excluded from cover. The insurer has, however, agreed to cover the resultant internal damage to the lounge/dining and water closet (WC). The complainant disagrees with the insurer ’s decision and seeks cover for the whole claim. 1.2 Issues and key findings Is the insurer entitled to decline cover for the roof damage? Yes. On balance, the proximate cause of the roof damage is not the storm, but rather rust, wear and tear and poor maintenance. Accordingly, the complainant has not established a claimable loss and the insurer is entitled to decline the roof damage component of the claim. Is the insurer’s settlement of the resultant damage fair? No. The insurer is required to pay the complainant a further $546.51 in respect of the resultant damage. This is in addition to the $2,186.03 it has already paid the complainant. Is the complainant entitled to compensation? Yes. The complainant is entitled to $1,500 in non-financial loss compensation for the delay, stress and inconvenience caused by the insurer’s handling of the claim. Why is the outcome fair? I am not satisfied the complainant has established a claimable loss for the roof damage. It would not be fair to require the insurer to cover this part of the claim in the circumstances. However, the insurer has agreed to pay for the internal resultant damage. Therefore, it is fair that it should also pay an uplift. It is also fair the insurer pays the complainant compensation. 1.3 Determination This determination is substantially in favour of the insurer. If the complainant accepts the determination, within 14 days of being notified of the acceptance, the insurer must pay the complainant:  $546.51 for the resultant damage; and  $1,500 in non-financial loss compensation. Determination | Case number: 958427 Page 2 of 6 2 Reasons for determination 2.1 Is the insurer entitled to decline cover for the roof damage? Yes. On balance, the proximate cause of the roof damage is not the storm, but rather rust, wear and tear and poor maintenance. Accordingly, the complainant has not established a claimable loss and the insurer is entitled to decline the roof damage component of the claim. Onus on complainant to establish a claimable loss The complainant is required to show, on the balance of probabilities (that it is more likely than not), that there is a claimable loss under the policy. This means the complainant must prove, on balance, the loss or damage was caused by a risk that is covered under the policy. Once the complainant proves there is a claimable loss, the insurer is liable for the loss unless it shows an exclusion or limiting condition applies. The insurer has the onus of proving, on the balance of probabilities, that the exclusion or condition applies. Policy covers insured events subject to exclusions The insurer’s policy consists of the policy schedule and product disclosure statement (PDS). It is not in dispute the insurer provided the policy documents to the complainant. The policy is an ‘insured events’ policy. This means not all loss and damage is automatically covered. Rather, only loss or damage caused by an insured event, and not subject to an exclusion, is covered. The insured events are set out in the PDS and include storm. However, the PDS says that cover for storm does not include loss or damage caused by: - water entering through an opening resulting from poor maintenance or defective workmanship, construction or design… - gradual deterioration from rainwater, or… The policy also generally excludes cover for damage which is caused by, amongst other things: Poor maintenance or inadequate maintenance or failure to keep your home in good repair … Wear and tear including gradual deterioration, rust, corrosion, fading or deterioration from exposure to ligh t… Complainant says damage caused by storm The complainant says:  there has been total neglect in the insurer’s handling of the claim. She was not informed of the claim denial until she rang the insurer to request an update on her claim;  a storm event allowed water to enter her home damaging ceilings and walls;  she has had to replace the roof as a consequence of rainwater damage to the roof;  she was not told she could submit her own quote for roof repairs;  the insurer’s assessor said the roof was in disrepair but she had in fact maintained it; Determination | Case number: 958427 Page 3 of 6  by paying for the resultant internal damage the insurer has acknowledged that the roof was damaged by the storm;  a quote was obtained from a roofer, A, for the roof repairs. The quote is dated 6 May 2022 and totals $34,476.20; and  she engaged a roofer, S, to carry out the repairs to the roof in or about March 2023. The cost of the repairs was $26,332.00. This comprised supplying and installing new roof battens, insulation, clips for roof sheets, whirly birds, skylight, flashings for roof join and gables, timber fascia, gable flashing and downpipes. Insurer provided reports commenting on the cause of damage The insurer appointed a builder, E, to assess the property. E engaged a roofer, N, to assess and report on the cause of the roof damage. E says:  there is internal damage to the lounge/dining ceiling and WC which due to the storm event;  there are rusted downpipes near the rear pergola and at the front of the house;  the rusted roof sheeting will also need to be replaced;  the pool liner is torn at the corners and the complainant says the pool pavers have sunk;  bathroom door jambs have been water damaged over a long period. This damage appears to relate to a hole in the bottom of the bath hob;  there is flaking and bubbling paint on the walls in the hallway and laundry which appears to relate to the water escaping from the bathroom or general rising damp;  no storm created opening has led to the damage to the lounge/dining and WC. The other damage is maintenance related; and  the repair estimate for the internal damage to the lounge/dining and WC is $2,186.03. N’s report includes various photographs of sections of rusted roof. It further states:  the metal roof is approximately 45 years old with a pitch of 4 degrees;  there are several rust spots and patches have previously been installed on the roof;  water ingress outside the back door was due to the rusted sheet under the barge flashing;  water ingress in the kitchen area is due to a failed patch over the rust hole; and  the roof needs a lot of maintenance carried out to keep it watertight. If not, the rust will take over and the roof will continue to allow water ingress. Proximate cause of the damage must be established The complainant needs to show the proximate cause of the damage being claimed was, on balance, the storm event which is not otherwise excluded. The proximate cause of a loss is the dominant, effective or operative cause. It does not have to be the first, the last or the sole cause. This is a question of fact depending on the circumstances. If there are several causes, each needs to be examined for qualities of reality, predominance and efficiency to identify the proximate cause. For example, if one cause would have caused the loss in any case, and the other one would not have done so without the first, then the first is the proximate cause. Exchanged information does not show roof damage due to storm Having reviewed all the exchanged information, I am not satisfied that the complainant has established a claimable loss for the roof damage. Determination | Case number: 958427 Page 4 of 6 I accept that water has entered the property and caused damage to the lounge/dining area and WC of the home. However, I cannot be satisfied that the storm is the proximate cause of the roof damage. I am persuaded by the report and photographs provided by N. I consider N is a suitably qualified expert to comment on the cause of the damage. I accept N’s evidence that there is significant rust on the roof and that previous repairs have been carried out with patches installed. The damage appears to have developed over time and not as a result of a single event. Further, the complainant has provided a quote from A and an invoice from S in relation to the roof damage and repairs. However, neither A or S comment on the cause of the roof damage. In the absence of any expert evidence to the contrary, I am satisfied, on balance, that the proximate cause of the roof damage is rust, wear and tear and poor maintenance. To the extent that any previous patch repairs have not been completed properly, this is likely due to faulty workmanship. Therefore, I do not consider the roof damage has been caused by a storm. Accordingly, the complainant has not established a claimable loss and the insurer is entitled to decline this component of the claim. 2.2 Is the insurer’s settlement of the resultant damage fair? No. The insurer is required to pay the complainant a further $546.51 in respect of the resultant damage. This is in addition to the $2,186.03 it has already paid the complainant. Insurer’s assessment for internal resultant damage should be increased The insurer has agreed to cover the internal resultant damage to the lounge/dining and WC in accordance with E’s report. I accept that the insurer is entitled to cash settle the complainant. However, a detailed scope of works has not been provided. The report simply estimates the repair cost is $2,186.03. In the circumstances, and to take into account contingencies and the loss of a lifetime guarantee on repairs, the insurer is required to pay an uplift of 25%. Accordingly, the insurer is required to pay the complainant a further $546.51 for the resultant internal damage it has agreed to cover. 2.3 Is the complainant entitled to compensation? Yes. The complainant is entitled to $1,500 in non-financial loss compensation for the delay, stress and inconvenience caused by the insurer’s handling of the claim. AFCA can award compensation for poor claim handling Under our Rules, AFCA can award up to $5,400 compensation for non-financial loss. This must relate to poor claims handling or other actions of the insurer which causes:  an unusual degree of stress, delay, or inconvenience, and/or  interference with a person’s expectation of enjoyment and/or peace of mind. We expect complainants to be moderately robust, and we will not award compensation for the ordinary degree of inconvenience involved in making a claim. Complainant is entitled to non-financial loss compensation I accept the complainant says the claims process has caused a high level of stress and anxiety, with the insurer showing minimal duty of care in relation to her claim. I acknowledge Determination | Case number: 958427 Page 5 of 6 the complainant’s concerns and dissatisfaction and note that the insurer has issued an apology for her claims handling experience. The complainant lodged her claim on 26 February 2022. In July 2022 she noted that her claim had been deleted form the insurer’s online portal. She says she was regularly checking the portal for updates on her claim. As a result, she called the insurer and was told that her claim had been declined. She later received a letter advising her claim had been declined on 19 August 2022. The claim notes include an entry for 16 July 2022 stating that the claim has been declined and that the insured needs to be notified. The insurer called twice but there was no answer. A voicemail was left that the insurer will try again in 20 minutes. The next entry is dated 17 August 2022 and states the insured has been advised that her claim has been declined. The General Insurance Code of Practice (GICOP) requires that the insurer respond to a claim within four months. In this case, the insurer failed to provide a response on the claim for almost six months. It was only when the complainant telephoned the insurer that it realised that the claim decision had not been communicated. I acknowledge the insurer’s handling of the claim was poor and I accept this caused the complainant an unusual degree of stress and inconvenience. I am satisfied that the insurer is required to pay the complainant non-financial loss compensation in the circumstances. I consider a compensation payment of $1,500 is fair and reasonable in the circumstances. 2.4 Why is the outcome fair? I am not satisfied the complainant has established a claimable loss for the roof damage. It would not be fair to require the insurer to cover this part of the claim in the circumstances. However, the insurer has agreed to pay for the internal resultant damage. Therefore, it is fair that it should also pay an uplift. It is also fair the insurer pays the complainant compensation. Determination | Case number: 958427 Page 6 of 6 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.