Cash settlement amount for roof rectification, internal repairs and mould remediation after faulty insurer repairs
Text of the determination
Determination
Case number 956541
Financial firm AAI Limited
Determination | Case number: 956541 Page 1 of 29
Case number: 956541 6 February 2024
1 Determination overview
1.1 Complaint
On 31 October 2018 the complainants lodged a claim for hail damage to the property with the
financial firm (insurer). The insurer accepted the claim and repaired the roof. In October 2021
the complainants notified the insurer of issues with its roof repairs.
In October 2022, the insurer authorised its builder to complete the roof remediation works and
cash settled the complainants for additional internal damage. On 11 November 2022 the
insurer’s builder notified the insurer it could not complete the repairs because it could not
warrant the work due to the undamaged roof tiles being painted previously. The insurer
advised the complainants and made a cash settlement offer for the roof rectification works.
The complainants agree to be cash settled for the repairs, however they are dissatisfied with
the insurer ’s proposed amount. They want the insurer to cover the costs of retiling the entire
roof, pay a 40% increase on cash settlements received, and cash settle the mould
remediation. Further, they say the insurer misled them and mishandled the claim.
1.2 Issues and key findings
Has the insurer correctly assessed the roof rectification works?
No. The insurer must cover half the complainant’s quote for roof retiling and include a 20%
uplift, but not including sarking for the reasons provided in this determination. The insurer is to
cash settle the claim as set out in section 2.1.
Is the insurer required to increase its offer for internal damages?
Yes. The insurer must increase the cash settlement offer for the outstanding internal repairs
by 20%. The insurer must obtain a quote for the mould remediation and cash settle the
complainants with a 20% contingency applied for the transfer of risks to the complainants.
The insurer is to pay the complainants as set out in section 2.2.
Did the insurer misled the complainants?
The insurer’s decision to cash settle the roof repairs after having authorised the repairs can
be seen has misleading. However, the loss suffered by the complainants as a result is
adequately covered by the additional settlement awarded by this determination. Accordingly,
it is not fair to award compensation for this.
Are the complainants entitled to compensation for non-financial loss?
The complainants experienced delays with their claim, causing them and their family undue
stress and inconvenience. Accordingly, it is fair to award the complainant’s $2,000 non -
financial loss compensation.
Determination | Case number: 956541 Page 2 of 29
1.3 Determination
The determination is partially in favour of the complainants. The insurer must settle the
complainants $22,980 for the roof, a further $10,774.79 as contingency towards outstanding
internal repairs.
The insurer must obtain an actionable quote for mould remediation and cash settle that
amount plus a twenty percent uplift.
The insurer is to pay $2,000 non-financial loss compensation.
Determination | Case number: 956541 Page 3 of 29
2 Reasons for determination
2.1 Has the insurer correctly assessed the roof rectification
works?
Complainants maintain roof damage is extensive
Before lodging the complaint with AFCA, the complainants wanted the insurer to complete the
rectification works to the roof. However, the complainants have now accepted the insurer’s
decision to cash settle the repairs as they have lost trust in the insurer.
I am satisfied a cash settlement in circumstances where works cannot be warranted, and the
relationship has broken down, is fair.
The complainants say the insurer should be liable to cover the costs of retiling the entire roof.
The complainants say there are well over 100 broken tiles. They say broken tiles cannot be
identified unless each roof tile is lifted individually and inspected because they are
overlapping. The complainants rely on their expert CGB ’s’ observations that ‘many cracked
water courses are not obvious until the overlapping til e is removed’. The complainant s also
rely on photographs depicting cracked tiles underneath the overlapping tiles which were
removed.
The complainants have provided their own photographs of the different sections of the roof
and marked and counted approximately 112 tiles visibly damaged tiles on those photographs.
The complainants say the number of broken tiles is far greater than this.
This is in line with the complainant ’ s roof report from A6, which says it observed too many
broken tiles to count during its inspection of the roof. It attributes the cause of damage to foot
traffic. The complainants also rely on their own photographs of the tiles taken from the roof
cavity during wet weather which shows water seeping into the roof cavity along the tiles.
Complainants want roof retiled
The complainants provided a further opinion from CGB which recommends the removal and
disposal of the existing tiled roof and instalment of a new roof and a quote from MG for the
same for $36,300 (excluding sarking). The complainants want the insurer to cover these costs
and say they will bear the costs of installing sarking.
The complainants also submit that if the insurer does not cover the costs of retiling the entire
roof, it should be liable to cover the costs of painting all the roof tiles to create a uniform look
and put the roof in the condition it was in before the damage.
Insurer says it assessed works correctly
The insurer accepted liability for poor roof repairs, and acknowledges it is likely there is
further unforeseen damage. Its cash settlement offer for the roof is $11,066.84, being
$7,066.84 for the replacement of 100 tiles, with a further $4,000 as contingency to be applied
towards painting the replacement tiles. This offer is based on its builder, R’s q uote submitted
on 15 August 2022.
The insurer says the offer is fair because the roof report from its expert SCR dated 11
November 2022 found approximately 50 damaged tiles and the offer allows for those plus an
additional 50 tiles for unforeseen damage.
Determination | Case number: 956541 Page 4 of 29
The insurer says it is not liable to cover the costs associated with painting the tiles.
Information shows insurer’s assessment is not accurate
In view of the available information and given the insurer acknowledges it is likely there is
further, unforeseen damage, I accept the complainants ’ submission that some cracked tiles
cannot be seen unless the overlapping tile above is removed. However, I am not persuaded
the insurer should be liable to re-tile the entire roof.
While the three roof reports obtained by the insurer all found in the vicinity of 50 tiles requiring
replacement I am not persuaded these reports are accurate. This is because the photographs
provided by the complainants show there are a lot more than 50 tiles requiring replacement.
The insurer says A6 findings that there were to many broken tiles to count is not supported by
any photographic evidence. The insurer’s assessor suggests the discrepancy between the
insurer’s latest roof report dated November 2022 and the complainants could be due to
people/ trades the complainants have engaged to access the roof since November 2022. On
balance, I consider this speculative and am not persuaded the insurer can establish this with
any degree of certainty.
Rather on balance I am satisfied the number of broken tiles on the roof is greater than 100
and due to faulty repairs completed by the insurer and missed damaged tiles caused by foot
traffic on the roof as a result of SES staff attendance. This is because the information
available does not show all the tiles on the roof are damaged and require replacement. There
is no expert evidence or other information demonstrating, on the balance of probabilities, the
damage is so extensive the entire roof needs to be replaced.
Accordingly, I am satisfied it is fair and reasonable the insurer cover half of the costs of
retiling the entire roof. This is because, on balance, I am satisfied the number of damage tiles
is far greater than 100 tiles but not enough to warrant a full roof replacement.
Further, given the transfer or risks and life warranty to the complainants I am satisfied it is fair
and reasonable a further 20% contingency should apply. I am satisfied this is the fairest
approach given the exact extent of damage is uncertain.
Insurer not required to cover painting costs
I accept painting all the roof tiles would create a uniform look. However, under the policy the
insurer is only liable to cover the costs of replacing the damaged tiles. Therefore, it would not
be fair to require the insurer to cover the costs of repainting all the roof tiles. Accordingly, on
balance, I am satisfied the insurer is not liable to cover these costs.
Insurer liable to cover half of the roof retiling costs
The complainant provided a quote from A6 for full roof repairs for $36,300 (not including
sarking) and a quote for $1,200 for the removal and refit of the complainants’ solar panels .
In line with this determination’s findings, the insurer must cash settle the complainant $18,150
towards the roof repairs with a further 20% contingency of $3,630.
Accordingly, the insurer must pay the complainants $21,780 and a further $1,200 for the
removal and re-installation of the solar panels.
Determination | Case number: 956541 Page 5 of 29
2.2 Is the insurer required to increase its payments for
outstanding internal damages?
Outcome complainants seek is excessive
Five payments totalling $84,158.32 were made for:
$18,013.84 for internal repairs
$31,134 for outstanding bathroom repairs
$1,100 for complainants ’ costs for his expert report
$11,170.75 for temporary accommodation
$22,739.93 for outstanding internal repairs.
The complainants seek a 40% increase on the total amount of cash settlement payments
received. The complainants submitted costs of labour and materials increase every month but
have not provided information to support this. I accept there is an ongoing increase in costs of
materials and trades in the current economic climate. However, I am not persuaded the
increase warrants a 40% uplift. This is well in excess of what AFCA usually considers a
reasonable uplift to account for transfer of risk and loss of warranty.
Further I am not satisfied it is fair to apply and uplift to all payments to date. This is because:
the payment for $18,013.84 relates to repairs already completed
the $1,100 was a reimbursement of the complainants ’ report fees
the $11,170.75 payment was for temporary accommodation costs sourced from Airbnb.
Nevertheless, I am persuaded the insurer must increase its settlement liability.
Insurer must include adequate contingency for internal repairs
The insurer submits no contingency should be applied to the bathroom payment because the
figure is based on the complainants ’ quote which was approximately 20% higher than the
insurer ’s quote. I am not persuaded by the insurer’s submission. This is becau se the
complainants still bear the transfer or risks and lifetime warranty.
The bathroom and the outstanding internal repairs have not been completed because the roof
remediation works have not been attended to, due to the ongoing dispute, neither the roof
repairs or outstanding internal repairs have been completed.
Further, the insurer has not provided any information to show the complainant’s quote is
excessive. Conversely, the insurer’s quote is based on its preferred repairers quote. There is
no information to show this is the established market rate for the repairs.
Therefore, in view of the above, I am satisfied it is fair a contingency should be applied to
allow for the transfer of warranty and risk to the complainants.
The insurer acknowledged no contingency was allowed for the other outstanding internal
repairs and that 15% was appropriate. I am not persuaded 15% is fair. Rather I am satisfied
20% is more appropriate to allow for the likely increase in costs of materials and trades,
transfer of other risks and loss of warranty.
Accordingly, the insurer must pay the complainants the previously offered cash settlement
plus:
$6,226.80 as 20% contingency for the bathroom repairs
$4,547.99 as 20% contingency for outstanding internal repairs.
Determination | Case number: 956541 Page 6 of 29
Insurer liable for mould remediation
The insurer obtained a mould assessment report from MCCP. The report found the roof cavity
was affected by mould and included recommendations for remediation.
Relevantly the insurer says this is not a causation report. The insurer has declined to cover
the remediation costs. It relies on its assessor’s reports of 15 September 2023 which found
that the cause of the mould is not attributable to the original hail event. The assessor found
that the moisture ingress observed on th e complainant’s photographs of the tiles is due to
paint/ debris blocking the water channel on the tile and therefore should not be covered.
The proximate cause of damage is the effective or dominant cause of the claimed damage. It
is neither the first, last or sole cause of such damage. It is what had the most significant
impact in bringing about the claimed loss. It must be determined on the balance of
probabilities and requires a common-sense evaluation of the applicable facts and
circumstances.
Even if I accept the assessor’s analysis , I am not persuaded that moisture ingress is likely to
be the proximate cause of mould in the roof cavity. There is limited information about the
extent and duration of this issue.
Conversely, there is no dispute the in surer’s faulty roof repairs clearly allowed further water
ingress and caused internal damage. This is supported by the complainant’s information,
including photographs showing water seeping into the roof cavity from the damaged tiles
during wet weather. On balance, I am persuaded this is more likely to be the dominant cause
of mould in the given circumstances.
Therefore, I am satisfied the insurer should cover the mould remediation in the roof cavity.
The insurer must obtain an actionable quote for the mould remediation and cash settle the
complainants with a 20% contingency applied for the transfer of risks to the complainants.
2.3 Did the insurer misled the complainants?
Insurer did not mislead complainants
The complainants say the insurer engaged in misconduct. However, the complainants have
not provided any evidence to support this allegation.
The complainants say the insurer misled them because the insurer authorised the roof repairs
and reversed its decision based on SCR’s findings abo ut the paint on the tiles. The
complainants say SCR’s report is at odd s with the other roof reports. SCR’s report is the only
one which raises the issue of the tiles being painted.
I accept this was the first time the issue was raised and none of the othe r insurer’s appointed
builders raised any concerns about their ability to do the roof repairs and warrant their work.
Relevantly, the insurer did the initial roof repairs which turned out to be faulty.
However, from the images provided it is clear the roof tiles have been painted.
I accept the insurer changing its position from repair to cash settle during the course of a
complaint is misleading. However, even if I accept the insurer misled the complainants by
changing its decision to complete the repairs, I am not persuaded the complainants suffered
any additional loss requiring compensation.
Determination | Case number: 956541 Page 7 of 29
This is because the complainants are no longer seeking that the insurer completes the repairs
and the insurer is liable to cash settle them for the roof repairs and to pay a further 20%
contingency on outstanding internal repairs and roof repairs. For the reasons provided in this
determination, I am satisfied this will address the complainant’s concerns and restore their
claimable loss.
Ultimately, it is regrettable the insurer did not go ahead with the roof rectification works. This
demonstrates poor claim handling on its part. Accordingly, it will be addressed under
compensation for non-financial loss below.
2.4 The complainants are entitled to compensation for non-
financial loss
The complainants are entitled to compensation for non-financial loss. The complainants
experienced delays with their claim causing them undue stress and inconvenience.
AFCA can award compensation in certain circumstances
AFCA’s rules enab le it to award compensation to a complainant for non-financial loss outside
of the policy terms (capped at $5,400). Compensation for non-financial loss is limited. AFCA
may decide an insurer should compensate a complainant for such a loss only where there
has been:
an unusual amount of physical inconvenience,
time taken to resolve a situation, or
interference with the complainant’s expectation or enjoyment or peace of mind.
AFCA takes a conservative approach to compensation for non-financial loss and expects a
complainant to be moderately robust and bear the usual degree of inconvenience when
managing a claim.
Complainants entitled to compensation for claim handling experience
The insurer’s decision not to go ahead with the roof repairs had a significant impact on the
complainant. The complainants had lined up trades to commence the internal repairs in
January 2023 and was compelled to cancel them.
To date no repairs have been done because the roof must be remediated before the internal
repairs can occur. The complainants continue to live in a damaged home which is subject to
ongoing water ingress. The complainants have suffered a significant amount of stress and
inconvenience as a result.
Further, in view of this determination’s findings, I a m satisfied the insurer’s handling of the
claim was less than ideal, and its final position and offer for roof repairs is inadequate and not
reasonably formed. Given this, I find the complainants are entitled to non-financial loss
compensation.
The insurer has offered a $1,000 ex-gratia payment in recognition of the complainant s’ overall
claim experience. In view of the above I am not persuaded this is sufficient
Rather, I am satisfied it is fair in the circumstances that the insurer compensates the
complainants $2,000 for non-financial loss. This is because the complainants have been
living in a home subject to water ingress and with internal damages for a significant amount of
time.
Determination | Case number: 956541 Page 8 of 29
2.5 Why the outcome is fair
The outcome is fair in all the circumstances because the insurer failed to reasonably assess
its liability and did not handle the claim properly.
Determination | Case number: 956541 Page 9 of 29
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
3.2 Relevant supporting information
Relevant expert reports extracts
CGB report dated 29 December 2023
CGB
Accredited with Master Builders
Association of NSW
Inspection and report by:
CS (Licensed Builder)
‘Roof (page 3)
a. The roof has Monier cement tiles
laid at an approximate pitch of 21 degrees.
Tiles have been spray painted with replaced
tile patches have been added with failed
paint. See photos 1, 2 and 3.
Determination | Case number: 956541 Page 10 of 29
CGB report dated 29 December 2023
CSH (Licensed Builder / Supervisor )
Building Consultant accredited with
Master Builders Assoc (NSW)
b. The roof is hip and ridge
construction with Dutch gables at 3 ends.
See plan marked in red.
c. Roof trusses and battens are of
Pine timber.
d. No sarking is evident.
e. A number of cracked and defective
tiles have been left in water courses that are
cracked through allowing ingress onto the
new bathroom ceiling, living, and
garage/rumpus rooms. See photos 4,5,6,7,8
and 9, showing typical throughout the roof.
Note, many cracked water courses are not
obvious until the overlapping tile is removed.
It is likely many of these tiles were cracked
with SES temporary “make safe” works and
were not identified or repaired.
f. Attempts were made to seal tile
joints as water courses were cracked
beneath. See photo 10 where sealant has
been applied. These tiles sho uld have been
replaced.
Roof space
a. The roof has Monier cement tiles
laid at an approximate pitch of 21 degrees.
Tiles have been spray painted with replaced
tile patches have been added with failed
paint. See photos 1, 2 and 3.
b. The roof is hip and r idge
construction with Dutch gables at 3 ends.
See plan marked in red.
c. Roof trusses and battens are of
Pine timber.
d. No sarking is evident.
e. A number of cracked and defective
tiles have been left in water courses that are
cracked through allowing ingress onto the
new bathroom ceiling, living, and
garage/rumpus rooms. See photos 4,5,6,7,8
and 9, showing typical throughout the roof.
Note, many cracked water courses are not
Determination | Case number: 956541 Page 11 of 29
CGB report dated 29 December 2023
obvious until the overlapping tile is removed.
It is likely many of these til es were cracked
with SES temporary “make safe” works and
were not identified or repaired.
f. Attempts were made to seal tile
joints as water courses were cracked
beneath. See photo 10 where sealant has
been applied. These tiles should have been
replaced.‟
CONCLUSION
(page.4)
a. All damage identified in this report is
most likely from water ingress from
the storm event and subsequent
ongoing ingress due to defective
repairs.
RECOMMENDATIONS (page 5)
a. The roof and tiles require a thorough
inspection. Defective tiles with
damaged water courses to be
replaced with new, and undertake
repairs as required including
flashings. Inspection and repairs to be
undertaken by a licensed roof tiling
contractor to meet AS2050.
CGB additional comments - email of 28 June 2023
CGB Consultants
Accredited with Master Builders Association
of NSW
CSH
„I note with interest that your insurance
claim is broken down into separate issues
with only the roof tiles left as a matter with
AFCA.
It was proven that ongoing ingress into your
bathroom, after roof tiles and ceiling had
been replaced by the insurance company,
caused the bathroom to further dilapidate
Determination | Case number: 956541 Page 12 of 29
CGB additional comments - email of 28 June 2023
with ongoing ingress from cracked tiles
directly above and not visible until re moved.
The false and misleading reports
commissioned by the insurance company
as to cause, were refuted and you have
had your bathroom issue settled.
I not e the assessment made by B H made
mention of the same storm event that
passed through Berowra with numerous
claim s made under this event. S Group
received a lot of call backs 1 - 2 years after
the event with customers finding cracks. I
do not agree with his explanation of the
cause of tiles cracking. I inspected many
houses in Berowra immediately after th at
storm event and after insurance companies
had carried out repairs, when I was
approached by many home owners who
had cracked roof tiles not identified and
replaced. I undertook inspections and found
in most cases that complete roof
replacement was neces sary. Most of these
cases were settled and roofs were
replaced. Some owners however could not
continue with the ongoing defective works
being done, and excuses of wear and tear,
lack of maintenance etc. There are a
number of ongoing disputes I am still
inv olved with where insurance companies
have gone all out to not replace roofs.
I will not provide a quote to replace say 100
tiles or quote to re - paint same. I stand by
my Report in regard to the extent of hail
damage. I recommend that the existing tiled
roof be removed and disposed of, and a
new tiled roof installed with heavy duty
sarking to meet all relevant Australian
Standards. It is my opinion that the
insurance company should bear the cost of
the hail/storm event damaged roof, and you
cover the cost of sarking and any additional
repairs not related to hail damage. I can
provide quotes for same, and provide the
mandatory HBCF insurance required,
something most insurance company
contractors do not do.‟
Determination | Case number: 956541 Page 13 of 29
SCF - Roof report dated 11 November 2022
SCF „ Comments:
I‟ve been to the above address and
inspected the roof. I have found 19 broken
tiles only on inspection whilst on the roof.
No inspection of tiles was done inside roof
cavity as this is not something we carry out
usually. One of the 19 tiles is under the top
ridge. All top ridges are missing weep
holes. We have found tiny chips in
approximately 30 tiles that we don‟t believe
is storm related. The roof has been painted
and it appears this has caused the tiles to
become porous as the paint is peel ing from
the tiles. Water issues are also apparent on
bottom of tiles where paint is piling up and
not allowing water to run away freely. Two
skylights on the back part of the roof need
to be re flashed and tiles cut in properly as
they are kicking up on b oth sides and will
cause water to enter. Front bellcast is
dropping down due to not being installed
correctly. Any repairs to the job will not be
warranted by us due to the poor quality of
the tiles.‟
RNF Specialist Report dated 28 March 2022
R NF
Assessment completed b y RNF Specialist
‘Please provide a conclusion with
related damages and recommendations
(page 2)
As requested by RNF, Plumbing Services
have attended the above - mentioned
property on the 28/03 at 3.30pm at a pre -
arranged meeting to i nspect and report on
damages due to storm.
At the time of the roof assessment, Mr.
Insured advised that as a result of a
previous hail event that passed through the
area in 2019, subsequent hail related
damage had occurred to the tiled roof line.
During this period, multiple persons varying
Determination | Case number: 956541 Page 14 of 29
RNF Specialist Report dated 28 March 2022
from th e SES to trade personnel have gain
access to the main roof line to either install
protection coverings or replace hail
damaged material.
Nb; Mr. Insured believes that this foot traffic
has resulted in a large number of roof tiles
sustaining fractures to th e under - tile water
course, some of which have resulted in
additional internal damage.
Roof Inspection noted the following:
The main roof was found to be cladded in a
Monier „Centurion‟ profiled concrete roof tile
with a recorded pitch reading of 20.3°.
(co mpliant).
For the purpose of the roof inspection each
roof line was thoroughly inspected 3x times.
Each tile viewed to have either a missing or
fractured tile water course was marked out
with white chalk. In total, approx. 46x
concrete roof tiles were note d to have
either missing or partially fractured water
courses.
Nb; When on site, the insured requested
that I inspect each tile individually from
within the roof cavity. In my opinion, the
external assessment was thorough enough.
In my professional opinion , damaged
watercourses viewed and marked out on
the main roof line would be attributed to a
number of issues some of which are listed
below.
1. Water courses sustaining hair line
fractures during the manufacturing,
packaging, and
transportation process and being installed
by trades when the main roof was cladded.
The water courses then fail over time due to
the general expansion & contraction
process.
2. Water courses sustaining fractures due
to foot traffic. Nb; The attached photo
marked out with white dot s, does clearly
Determination | Case number: 956541 Page 15 of 29
RNF Specialist Report dated 28 March 2022
show a line of traffic where others have
used to inspect or to install tarps at the time
of the storm event.‟
EMR – Roof Inspection Report dated 8 July 2022
E MR ‘Strom Works Identified
During the inspection the following findings
were identified as storm issues. It is
recommended that these works be
attended to in the near future to ensure the
property remains watertight:
I recommend all the cracked tiles be
replaced with the exact same sized tiles –
minimum 50 tiles
Re point any cracks on ridge cappings
Re fit any loose tiles and make them sit
correctly‟ .
ARR – Roof report dated 23 September 2023
ARR
WH (R oof Tiler)
I inspected the above roof on Wednesday
20th of September 2023 at the request of
the residential owner.
I was provided with and read the report of
BH dated 15 September 2023. I disag ree
with the report of Mr H in particular his
opinion that when the roof was painted, the
paint sealed the gaps between adjoining
tiles causing leakage. I utilized a torch to
see the underside of the tiles and could see
no blockages from paint debris.
On my inspection, I could find no evidence
of any such issue. In my opinion as a
licensed roof tiler, when a roof is painted,
the paint seals the individual tile, which acts
Determination | Case number: 956541 Page 16 of 29
ARR – Roof report dated 23 September 2023
as a coloured membrane for each individual
tile, not as a tile to tile adhesive or seal the
gaps. The paint thickness is estimated at
120 microns.
Furthermor e, on my inspection of the roof
many of the water courses, being the tile lip
under each linking tile, were broken a
number to which I felt were too many to
count. In my opinion, the cause of the leaks
is most likely related to damage caused by
foot traffi c. Upon my investigation with the
owner of the property, I was advised that on
or around 2018 the property sustained
substantial hail damage and to rectify such
damage, emergency services followed by
repatriation workman walked on the roof for
the purposes of repair. I have concluded
that it is such extensive foot traffic that has
led to the broken, slipped, and loose tiles
and consequential leaks.
The tradesmen who repaired the roof
previously, due to hail damage, used
incorrect tiles and silicone to temp orary fix
out of place tiles. The roof showed minimal
roof paint peeling, with less than 2% of the
whole roof being subject to paint peel.
I reviewed the images supplied by the
owner and believe that the damage to the
tiles and subsequent water damage to the
inside of the residence was from the hail
event and subsequent repair work
performed on or around 2018 and not the
paint restoration of the roof.
Insurer internal assessor report dated 14 June 2023
AAMI BH Page 3 – 5
CRACKING OF ROOF TILES. The insured
has stated that his repairer recommends
each roof tile is lifted individually and
inspected for cracking. I do not believe this
is required for the following reasons.
Determination | Case number: 956541 Page 17 of 29
Insurer internal assessor report dated 14 June 2023
The second claim, Hxxxxx 9028, is for hail
damage that is the same storm that passed
through Berowra. Berowra is approx 40km
North, North East of Chipping Norton. I
assessed numerous claims in Berow ra
under this event. The S Group received a
lot of calls back approx 1 - 2 years afte r the
event with customers advising they were
finding cracked tiles on their roof. When
reinspection's were carried out it was found
that many of the tiles had hairline cracks
that weren‟t visible immediately after the
event (during initial assessments or repairs)
but had become visible. The roof tiles are
made from cement. With the changes in
seasons, the tiles will expand in summer
when they are hot and contract in winter
when its colder. When the cement tile is
heated during the summer months it will
exp and. During the winter/colder months,
the tile will contract in size. Any cracks that
are present will remain open when the tile
contracts, thus the cracking becomes
visible. Given the panel repairer repaired
the roof in 2019 I believe that if any tiles di d
sustain hairline cracking it would have been
visible by now as we have been through 3 -
4 years of seasonal changes. Also, as
above, there is no sarking under the tiles so
any cracks would likely have visible water
stains to the underside of the tiles wher e
the rainwater has passed through the
crack. This expansion and contraction that
occurs is less than millimetres and over the
course of a few years, a crack that is
present may only be 1mm wide, but visible.
As there has been various assessment
carried ou t on the roof, foot traffic is more
likely to be the cause of any additional
cracked tiles. Assessor agrees that an
allowance should be included in the
settlement for the replacement of additional
tiles. An allowance of 50 tiles has been
requested. Assesso r recommends 100 tiles
are allowed to ensure there is sufficient
coverage. While it is unlikely there will be
this amount present, this amount will also
Determination | Case number: 956541 Page 18 of 29
Insurer internal assessor report dated 14 June 2023
allow for any additional damages to the tiles
during future repairs. PAINTING OF TILES.
Based on the in formation present, it
appears the tiles that were replaced have
been painted. This not common practice
under a repair as painting of roof tiles
cannot be warranted by a repairer. As roof
tiles are exposed to the elements, paint
failure is almost guaranteed , with roof
painting specialists generally only
warranting roof restorations for 10 - 12 years.
As the S Group include a lifetime warranty
to repairs, this is not a risk that is usually
undertaken. As above, a high volume of
claims was lodged under this even t and
many repairs were completed under a
make safe, i.e., instead of tarping a roof to
stop water ingress damages occurring, tiles
were replaced to ensure the dwellings were
watertight. Many tiles were replaced that
were different colours but the same pro file.
If a tile is of a differing profile to the existing
is installed, the watercourses on the tiles do
not match and the tile will not be seated
correctly, this will allow water ingress. I
cannot state why the tiles were painted.
What should have occurre d, and usually
does, is the allowance for painting of the
damaged tiles only is cash settled to the
insured. The insured can then
use these funds as a contribution to have
the entire roo f painted, as above, the S
Group cannot warrant this as part of a
repa ir. It is also common practice to remove
undamaged tiles from the least visible
elevation of the dwelling and use these to
replace the damaged tiles with the new
(potentially) different coloured tiles used to
replace the undamaged tiles from the least
visi ble elevation. This is usually to the
bottom course of tiles on the side of the
dwelling or over a pergola. This will aide in
providing a more uniform appearance to the
roof. One of the submitted reports states
the paint is failing across the entire roof. By
the insure ds own admission on claim
Hxxxxx 3892, he had roof maintenance
Determination | Case number: 956541 Page 19 of 29
Insurer internal assessor report dated 14 June 2023
completed approx 2 years earlier. Images
contained in the initial Home Repair roof
report show close - up photos of the roof tiles
and it is visible in these photos that the
paint tha t has been applied to the tiles is
thin and has worn due to exposure to the
elements. These images were taken
8/11/2018, over 4 years ago. It would be
expected that the condition of the paint has
worsened in the time that has passed since
the initial Home Repair report. As stated
above in this report, painting of roof tiles
cannot be guaranteed for an extended
period. Given the insured had the roof
painted approx 8 years ago, possibly longer
as the insured has only stated he had
maintenance completed 2 year s prior nd
does not specify the roof was painted, the
paint that has been applied would be
approaching the end of its serviceable life
and would require a new application. As the
entire roof does not form part of the claim,
this would not be covered under either of
the claims. Based on the above I believe
the allowance provided for painting of the
tiles that have been replaced is sufficient.
The allowance for painting should be
increased to cover the 100 additional tiles
only as a gesture of good will to th e
insured. Assessor recommends the above
information is used to settle the claim.
Insurer internal assessor report dated 15 September 2023
AAMI BH Assessor has reviewed the hygienist report
regarding the possibility of mould
contamination in the ro of space at the
insured site and spoken with M from BB
regarding his attendance.
Assessor has also reviewed the emails
submitted by the insured showing the
condition of the underside of the roof tiles.
The hygien ist report submitted by BB was
carried out by hygienist Mr AN .
Determination | Case number: 956541 Page 20 of 29
Insurer internal assessor report dated 15 September 2023
The report outlines that inspection that was
undertaken at the site and the results of the
inspection.
The report states - "Based on the
information presented in this report, it i s the
opinion of MP that:
• Visible mould was observed w ithin the
roof space on timber joists
• No damp or musty odours were perceived
throughout the subject area during the
inspection
• Mould surface sample MSS1 collected
from the timber joist in the roof space
returned mould spore
concentrations which were c onsidered
„Very High‟ and showed high levels of intact
fungal hyphae.
• The dominant genus within sample MSS1
was Cladosporium which is associated with
water damage in
buildings. The presence of high levels of
intact hyphal structures indicates recently
active mould
growth;
• No elevated moisture readings were
observed throughout the roof space
• Due to the levels of mould identified wit hin
this report, MP recommends remediation
works are undertaken to reduce these
levels".
MP have provided the followi ng remediation
plan based on the report.
"• Any moisture ingress issues should be
addressed prior to remediation works
commencing;
Roofing should be assessed prior to
undertaking any internal remediation works;
• The following building materials should be
removed as a part of remediation works:
Roof space, yellow insulation batts,
throughout;
• The following building materials should be
cleaned and remediated:
Roof space, timber joists and framework,
throughout;
Determination | Case number: 956541 Page 21 of 29
Insurer internal assessor report dated 15 September 2023
Roof space, top side of gyprock ceilin g
linings, throughout".
This was discussed with BB.
He has advised the remediation based on
the findings would be to remove the
insulation batts and carry out a Hepa
vacuum of the ceiling space.
This report was based on the findings that
were evident at the time of the inspection,
the report does not provide a causation.
The MP inspection was carried out on
25/8/2023.
Mr insured has submitted two emails on
14/9/2023.
These emails contain images Mr insured
has advised he took on 30/8/2023, 5 days
after the MP assessment.
Mr insured has advised he took these
images as it was raining at the time, and he
was showing various points of water
ingress through the roof.
The images supplied by the insured show
the underside of the roof tiles with what
appears to be moisture coming through. It
was noted that all the images showing this
show moisture along the joints of the tiles,
not coming through the tiles. This would
suggest the tiles are not broken/ cracked
from impacts, rather that the watercourse or
water ch annel in the roof tile is blocked not
allowing rainwater that has entered the joint
between the roof tiles to escape as per the
design of the roof tile.
It is noted on the claim that the insured had
completed a roof restoration shortly before
the event o ccurred.
It is this assessor‟s opinion that the
moisture ingress noted by the insured can
be related to paint/debris blocking the water
channel on the tile.
This is not related to the claimed event,
Determination | Case number: 956541 Page 22 of 29
Insurer internal assessor report dated 15 September 2023
rather the restoration of the roof. When a
roof is paint ed, the paint will seal the gap
between the adjoining tiles and the water
channel on the nose of the tile prohibiting
water that enters into the joint from
escaping. Given the time since the
restoration was completed by the insured,
exposure to the element s, and the foot
traffic that has passed over the roof, it is
likely movement of the tiles would have
occurred causing the paint covering the
joints to crack.
Based on the insureds submitted images,
the ingress shown is not claim related,
therefore assesso r does not recommend
the remediation outlined by the hygienist is
covered under the claim.
As above, the hygienist report is not a
causation report and only outlines the
findings at the time of the inspection. The
images supplied by the insured do not
sho w any evidence of cracking to the tiles,
only moisture uptake along the edges of the
tiles suggesting the ingress is occurring
through the joints, not through cracking.
The remaining reserve of $5,000.00 does
not require amending at this stage of the
cla im.
Insurer internal assessor’s report dated 6 October 2023
B AAMI Page 6
The insured has submitted a quot e from MR for
the sum of $38,610.00 to remove and replace
all roof tiles and battens and install sark ing. It
should be not ed there is no sark ing under the
roof tiles at present and has not been since the
time of construction.
This quote provides a total cost for t he work but
does not provide a break down of costs with
quantities. Based on this, I am unable to
Determination | Case number: 956541 Page 23 of 29
Insurer internal assessor’s report dated 6 October 2023
determine if the quote is fair and reasonable.
I do not believe the damages sustained during
the hail event were substantial enough to
warrant a full roof rep lac ement.
The images submitted by the insured show
moisture ingress around the perimeter of the
tiles and no crack ing is visible from the
underside of the tiles. This is what led me to
believe the watercourse or water channel in the
roof tiles are block ed , not allowing rainwater
that has entered the joint bet ween the roof tiles
to escape as per the design of the roof tile.
This is discussed in greater detail in my report
submitted on 15/9/2023.
The SCF report also discusses the issues and
contains images to show what the author notes
as issues with the tiles.
The report by hygienist of MP was reviewed
and discussed fully in the report submitted on
15/9/2023.
The repo rt by MP does include a remediation
plan for mould that was found in the roof.
The testing found Cladosporium which is
associated with water damage. The presence of
high levels of intact hyphal structures indicates
recently active mould growth.
As noted in the hygienist report, there was no
evidence of elevated moisture levels in th e roof
space at the time of the inspection.
Mr insured submitted images from inside the
roof space tak en 5 days after the MP inspection
was complet ed and advised it was raining at the
time he took the images.
As I have previously discussed, the moisture
noted in the roof space, shown in the insureds
submitted images, was noted to be entering
around the perimeter of the tiles. The cause of
this was discussed in the S CF report.
Based on these t wo reports I have
recommended the hygienists remediation
recomm endations were not carried out under
Determination | Case number: 956541 Page 24 of 29
Insurer internal assessor’s report dated 6 October 2023
the claim as the cause of the mould has not
been related to the hail event.
When noting the condition of the roof in their
report, SCF state - “Any repairs to the job will
not be warranted by us due to the poor quality
of the tiles.”
Mould assessment report dated 4 September 2023
AN Page 5
Recommendations
Based on the information presented within
the body of this report, Mc C P
recommends the following
remediation works. All remediation and
removal works should comply with IICRC
S520 standards:
• During works personnel accessing the
subject area must wear appropriate PPE
and a facial fit test is
recommend for any personnel undertaking
remediation works;
• Any moisture ingress issues should be
addressed prior to r emediation works
commencing;
o Roofing should be assessed prior to
undertaking any internal remediation works;
• The following building materials should be
removed as a part of remediation works:
o Roof space, yellow insulation batts,
throughout;
• The fol lowing building materials should be
cleaned and remediated:
o Roof space, timber joists and framework,
throughout;
o Roof space, top side of gyprock ceiling
linings, throughout;
Determination | Case number: 956541 Page 25 of 29
Mould assessment report dated 4 September 2023
• Air filtration devices fitted with High
Efficiency Particulate Air (HEPA) fi lters
should be installed
throughout the subject area for the duration
of remediation works;
• Any additional visible mould observed or
uncovered during works should be
remediated or removed
at the remediators discretion;
• Ensure all air filtration device s are
switched off 24 hours prior to undertaking
the clearance or PRV
inspection; and
• Remove containment measures after
receiving a mould clearance / PRV report
for the subject area
from an experienced Occupational
Hygienist.
Product disclosure statement
What we do not cover – general exclusions
Page 40 ..
You are not covered under any section of your
policy for damage, loss, cost or legal liability that
is caused by, arises from or involves:
Wear, tear and gradual deterioration
wear, tear, rust, fading, rising damp, mould,
mildew, corrosion, rot, action of light,
atmospheric or climatic conditions or gradual
deterioration such as, but not limited to :
• tiles and their adhesive or grouting br eak ing
down;
Determination | Case number: 956541 Page 26 of 29
What we do not cover – general exclusions
• weathering of roof tiles or roof ridge capping;
• gradual weathering and break down of brick s,
mortar or concrete.
..
How we settle building claim s
Page 45 ..
If we agree to pay a claim for loss, theft or
damage to the building, we will decide if we will:
• repair damage to the building;
• rebuild the building;
• pay you what it would cost us to repair or
rebuild the building;
• pay you the building sum insur ed shown on
your certificate of insurance;
Note: This does not apply if you have selected
the Complete Replacement Cover® option.
• give you a voucher, store credit or stored
value card for the amount it would cost us to
repair or rebuild an item.
If we rebuild (or pay you what it would cost us to
rebuild), we will do so on a `new for old‟ basis.
If we repair (or pay you what it would cost us to
repair), we will at our option do so on a `new f or
old‟ basis or repair to a similar condition to what
the bui lding was in before the loss or damage
occurred.
Unless we tell you otherwise, we will deduct any
amounts you owe us from any amount we owe
you.
We will not:
Determination | Case number: 956541 Page 27 of 29
How we settle building claim s
• pay more than the relevant sum insured
(unless you have the Complete Replac ement
Cover® option ) or policy limit;
• pay extra to repair or rebuild the building to a
better standard, specification or quality than it
was before the loss or damage occurred except
as stated in the meaning of „new for old‟;
• fix a fault that existed before the loss or
damage occurred.
„New for old‟ means:
• New materials, new it ems
we rebuild or repair wit h new it ems or new
materials that are available at the time of
replacement or repair from Australian suppliers.
• New for old, regardless of age
we rebuild or repair regardless of age, with no
allowance for depreciation.
• Same type, standard and specification as
when new
we replac e or repair to the same type, standard
and specification (but not brand) as when new.
If the same is not available, i t means of a similar
type, standard and specification (but not brand)
when new. We can replace wit h a different
brand.
„New for old‟ does not:
• include paying the extra cost of replacing or
purchasing an extended warranty on any item;
• mean of a bette r standard, specification or
qualit y than when new.
..
Dealing with defects
Determination | Case number: 956541 Page 28 of 29
Dealing with defects
Page 49 ..
If a k nown defect is the cause of the damage
We do not pay for loss or damage caus ed by a
defect, structural fault or design fault at the
building that you k new about (or should
reasonably have k nown about) and did not fix
before the loss or damage occurred.
If an unk nown defect is the cause of the
damage
If an incident covered by your policy damages
the building and an unk nown def ect was the
cause or part of the cause, we will pay for the
resulting damage. If the unk nown defective part
of the building is also damaged by the same
incident, we will f ix this as well.
We do not rectify structural or design faults
When we accept a claim, we will not pay extra
to rectify a structural or design fault at the
building that you k new about (or should
reasonably have k nown about). We will only pay
you what it would have cost us to fix the
damage from the incident covered by your
policy or if we agree, you can pay us the extra
amount it costs to rectify the structural or design
fault at the building.
If undamaged defective parts of the building will
not suppor t repairs
If undamaged defective parts of the building you
k new about (or should reasonably have k nown
about) will not support repairing the damage
caused by an incident covered by your policy,
we will only pay what it would have cost us to
repair the dam age had the building not been
defective.
For k nown defects or faults
Once you become aware of a defect, structural
or design fault at the building, you must rectify it
as soon as possible because there is no cover
for loss or damage due to that defect. I f you do
not rectify the defect or fault, you may not be
Determination | Case number: 956541 Page 29 of 29
Dealing with defects
covered or we might not offer a renewal of your
policy.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.