Home / Auto & General / Determination 955099

Determination 955099

Storm damage claim declined and policy cancelled back to inception

FirmAuto & General
Decided2023-09-28
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The insurer declined a storm claim for water ingress and cancelled the home building policy back to inception. AFCA found the claim decline was correct but the cancellation was ineffective, and determined partially in favour of the insurer.

Exclusions for openings not created by storm and gradual deterioration applied, but the insurer did not establish a ground or follow the notice requirements for cancellation under sections 59 and 60 of the Insurance Contracts Act.

Issues

Subjects and remedies

home or building damagereinstate policy or contract

Related

All Auto & General determinations · Find similar determinations

Text of the determination

Determination Case number 955099 Financial firm Auto & General Services Pty Ltd Determination | Case number: 955099 Page 1 of 12 Case number: 955099 28 September 2023 1 Determination overview 1.1 Complaint The complainant holds a home building insurance policy underwritten by the financial firm (insurer). The complainant lodged a complaint on or about 12 December 2022 for damage caused by a storm. The insurer declined the claim on the basis that the damage was not caused by storm. The insurer‟s position is that the damage arose due to gradual deterioration and poor condition of the roof which are excluded causes of loss under the policy. The insurer also notified the complainant that the policy was cancelled as it would not have covered the building if it had been aware of pre-existing issues. The complainant disputes the claim decision and the policy cancellation. 1.2 Issues and key findings Is the loss covered by the policy? No. The evidence provided is that the stormwater ingress occurred due to deterioration of roof elements and not from a storm created opening. Was the insurer entitled to cancel the policy based on the notice provided? No. The insurer has not established it met the notification requirements for cancellation which renders the cancellation ineffective. Why is the outcome fair? The outcome is fair as it is in accordance with the law, evidence and policy terms and conditions. The insurer has shown that exclusions apply to preclude cover for the claim. However, it has not met the legal requirements to enable it to the cancel the policy. 1.3 Determination This determination is partially in favour of the insurer. Determination | Case number: 955099 Page 2 of 12 2 Reasons for determination 2.1 Is the loss covered by the policy? No. The evidence provided is that the stormwater ingress occurred due to deterioration of roof elements and not from a storm created opening. The policy provides cover for storm subject to exclusions The policy contains cover for loss or damage to the home building caused by storms and rainwater. The cover is subject to event specific exclusions including loss or damage caused by:  an opening that was not created by the storm or any other insured event  the home not being in good condition, including guttering and drain pipes. The policy also contains general exclusions which apply to all insured events. The general exclusions apply to all insured events and preclude cover for loss or damage:  caused by rust, corrosion, rot, mould, rising damp, mildew, wear, tear, fading, or other gradual deterioration  incurred because the home was not in good condition and existing def ects or faults contributed to or caused the loss or damage. The cause of loss must be due to storm and not excluded from cover In a claim under a general insurance policy, the term „proximate cause‟ is used to describe whether an event is the cause of the loss or damage. The proximate cause of a loss is the dominant, effective or operative cause. It does not have to be the first, the last or the only cause. If there are several causes, each should be examined to determine whether it is a dominant, effective or operative cause of the loss. For example, if one cause would have caused the loss on its own, and the other cause would not have caused the loss without the first, then the first is the proximate cause. It is possible to have more than one proximate cause of a loss. However, in most cases, there will be one proximate cause. Under insurance law principles, the complainant is required to show, on the balance of probabilities (that it is more likely than not), that she suffered a claimable loss under the policy. This means she must show the loss was caused by a risk for which she is insured. Once the complainant proves the existence of a claimable loss, the insurer is liable for the loss unless it shows an exclusion or limiting condition applies. The insurer has the onus of proving on the balance of probabilities the application of the exclusion or condition. Accordingly, it is important to review the evidence as to the cause of the damage to determine if there is cover or an exclusion applies to the damage. The evidence does not show that storm was the proximate cause of the damage I have reviewed the prior insurance assessment reports from 2020 and the expert reports from 2023 relevant to the current claim. Determination | Case number: 955099 Page 3 of 12 The prior assessment reports provided by the insurer discuss escape of water from the shower recess through defective sealants and waterproof membrane. The current reports depict water ingress through the roof which entered the ceiling and wall cavities. The expert reports from 2023 support a finding that the water ingress is from stormwater through the roof rather than an escape of liquid from the shower recess. I accept those findings as there is water damage to the plaster ceilings in rooms outside of the bathroom which is unlikely to be caused by an escape of liquid from the shower recess. I have considered the expert reports provided by both parties. There are two main reports which consider the cause of the damage to the insured home building. The roof report by LD, adopted by the insurer‟s buil ding consultant PB, and the engineering report from BE on which the complainant relies. The report from LD states there was no storm created opening to the roof. LD believed water ingress had occurred through the roof because the hopper flashing is non-compliant as roof sheets are on the upstream and back fall allowing the water to run under the hopper flashings. LD also concluded there were other issues with the roof including:  the roof pitch was non-compliant (less than 1 degree)  the left gutter was completely blocked full of debris  the right hand box gutter was filled with debris that was blocking the right corner downpipe  two vent penetrations through the roof were in poor condition due to the deteriorated silicone and required maintenance. The report from BE states the roof was observed to be well maintained, considering the substantial hedges on the neighbouring property which would contribute significant leaf and vegetation placement in the guttering system. The gutters were found to be free from vegetation. No pre-existing maintenance issues were identified. BE has stated that the observed damages to the bathroom, ensuite and master bedroom were caused by surface run-off rainwater. However, BE then goes on to explain that the storm water run-off (which he describes as a liquid escape event) (time unknown) has overcome the flashing and sealant, which has deteriorated subsequently with each additional downpour of rainfall. BE stated this was a major contributing factor causing the observed damages. I note that BE has also referred to an Average Recurrence Interval (ARI)100 year cumulative rainfall event. The ARI is an estimated probability that a particular rainfall depth will be equalled or exceeded at a particular place, within a particular time interval (duration) and over any given period of time. This would ordinarily be calculated using the amount of rainfall and duration of the rainfall compared to historical rainfall data for that location. BE has not referenced the data to explain the claim that the damage is linked to a ARI100 year cumulative rainfall event. The Bureau of Meteorology data provided states the rainfall in December 2022 was close to average at all reporting sites in Greater Melbourne except at Melbourne airport which received nearly double the December average on 22 December 2022. There were also heavy rainfall and strong winds and hail resulting in damage to homes in Melbourne‟s Northern suburbs on 22 December 2022. However, 22 December 2022 postdates the date of loss listed in the lodgement details provided. The report by LD provides an explanation as to how the stormwater has entered the roof cavity through deteriorated hopper flashings which allow water to run under them. Additionally, LD records there were issues of blockages to the gutters and a downpipe and vents with deteriorated silicone. Determination | Case number: 955099 Page 4 of 12 BE‟s report states there were no maintenance issues but then provides an explanation for the stormwater ingress, being that the flashing and sealant have been overcome and deteriorated with each additional downpour of rainfall. There is no suggestion in BE‟s report that the storm has created an opening through which water ingress occurs. The only explanation is that of deteriorated flashing and sealant. Both experts have essentially provided evidence that the rainwater ingress has occurred due to deterioration of roof elements rather than due to the storm, winds or other damage to the roof caused by the one-off storm event. The damage to the roof which led to the water ingress was not from a one-off storm event on but due to deterioration of the roof. If the roof had not had deteriorated sealants, deteriorated flashings or blocked guttering/pipes then the rainwater ingress would not have occurred. The policy exclusions apply to the claimed damage The storm cover in the policy has event specific exclusions which exclude loss or damage that occurred through an opening that was not created by the storm. The expert evidence does not support a finding that the rainwater occurred through a storm created opening but rather an opening caused by deterioration of the roof elements. This mechanism or cause of loss falls within the event specific exclusions. I am also of the view that the expert evidence of deterioration would establish the general exclusion for loss or damage caused by gradual deterioration applies to preclude cover. Given this, the policy does not cover the loss that has arisen from stormwater ingress through the roof. 2.2 Was the insurer entitled to cancel the policy based on the notice provided? No. The insurer has not established it met the notification requirements for cancellation which renders the cancellation ineffective. Policy cancellation requirements are set out in the Insurance Contracts Act An insurer‟s right to cancel a policy is limited by the Insurance Contracts Act 1984 (Cth) (the Act). Section 63 of the Act says that, except in accordance with the Act, an insurer may not cancel a policy, and any purported cancellation is of no effect. To cancel a policy, an insurer must:  establish a right to cancel under the Act  exercise the right to cancel in accordance with the Act. The right to cancel an insurance policy Section 60 of the Act sets out the basis for cancellation of a contract of insurance. The insurer may cancel the contract of general insurance if: Determination | Case number: 955099 Page 5 of 12  a person who is or was at any time the insured failed to comply with the duty of the utmost good faith  there was a relevant failure (being a breach by the insured to comply with their pre-policy disclosure obligations)  a person who is or was at any time the insured failed to comply with a provision of the contract, including a provision with respect to payment of the premium  the insured has made a fraudulent claim under the contract or under some other contract of insurance (whether with the insurer concerned or with some other insurer) that provides insurance cover during any part of the period during which the first-mentioned contract provides insurance cover  if the contract of insurance either - requires notification by the insured of a specified act or omission of the insured or - the contract authorises a refusal to pay a claim (in whole or part) by reason of an act or omission of the insured then if that act or omission occurs after the contract was entered into, the insurer may cancel the contract. Requirements to cancel a general insurance policy Section 59 of the Act sets out the obligations of the insurer for cancellation of a contract of insurance. This requires the insurer to provide notice in writing of the proposed cancellation to the insured and that the notice has the proposed (compliant) time of the cancellation. An insurer must give notice in writing of any proposed cancellation. This notice should clearly set out the insurer‟s intention to cancel the policy. The notice should include the date of the proposed cancellation and the reasons for it as a matter of good industry practice. Once the notice is given, the policy is then cancelled at the latest of the following times:  Three business days after the notice is given  If a time is specified in the contract – that time  If a time is specified in the notice – that time The insurer purported to cancel the policy on 18 January 2023 The insurer provided an email dated 18 January 2023 stating the claim was not accepted and the policy had been cancelled back to inception. An automatic refund had been generated. There is nothing in the correspondence to suggest that the cancellation would be effective on a future date given the use of the past tense „has been cancelled‟ suggests it has already occurred. I have not received copies of any earlier notification of the purported cancellation. The notification requirements for a cancellation notification are not met which renders the cancellation ineffective. However, if the policy is ongoing then the complainant would still need to meet the premium requirements. The insurer has not stated one of the bases for cancellation of the policy under section 60 of the Act and nor does the insurer provide the prospective warning of cancellation under section 59 of the ICA. There is a later notice on 4 February 2023 provided but this notice simply states the cancellation is in accordance with the policy and that the: “…recent changes to your policy mean that it no longer meets our acceptance criteria, and we are unable to offer you insurance” Determination | Case number: 955099 Page 6 of 12 The notice again does not provide forward notice of the cancellation for the later of the three business days, time specified in the contract or time specified in the notice. It is unclear if this was because the notice dated 4 February 2023 was based on the older notice of 18 January 2023. However, the contents of the second notice do not provide a separate effective notice of cancellation. The reference in the notice dated 4 February 2023 is unclear as to what recent changes to the policy are being referred to as there was no material suggesting the complainant attempted to change the terms of the insurance contract. It is possible the statement referred to a change which did not meet the conditions of cover. The policy states cancellation may occur if the insured does not meet a condition of cover. The policy provides a statement regarding conditions of the insured cover which includes a right for the insurer to cancel if the insured does not tell the insurer anything the insured is required to tell the insurer or if there is a fraudulent failure. However, the insurer did not provide any specific statements about a failure to disclose in the notices of cancellation or its notice of response. Further, no underwriting material was provided to demonstrate what would have occurred had the insurer been informed of the state of the property when cover was taken out. It is unclear from the correspondence whether the insurer believed the complainant had not disclosed something relevant to the decision to insure the complainant. There was a prior claim related to escape of liquid from the bathroom, but all the current expert evidence indicated that the current water ingress was through the roof. Further, the complainant states they undertook roof works five years ago which may have led to a reasonable belief the roof was watertight. There is a lack of clarity in the correspondence as to the grounds for cancellation and whether the insurer had a proper basis for cancellation under the Act or its policy terms. The Notice of Response provided suggests the policy was cancelled as the home was in poor condition and no longer met the underwriting guidelines. The insurer has not provided those underwriting guidelines to confirm that the property would not have met those guidelines. There is no ground stated by the insurer which would give rise to a right to cancel the policy provided under section 59 or 60 of the Act. The insurer has not followed the appropriate cancellation process under the Act in terms of notice or established a proper ground under the Act or policy to cancel. Based on the material provided, I can only find the notice of cancellation was not effective. 2.3 Why is the outcome fair? The outcome is fair as it is in accordance with the law, evidence and policy terms and conditions. The insurer has shown that exclusions apply to preclude cover for the claim. However, it has not met the legal requirements to enable it to the cancel the policy. Determination | Case number: 955099 Page 7 of 12 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. Determination | Case number: 955099 Page 8 of 12 3.2 Relevant Policy Terms and Conditions Storm and rainwater You are covered for Loss or damage caused by storms and rainwater, including from: • earth movement that occurs within 72 h ours of a storm or heavy rain, and as a result of that storm or heavy rain • surface run -off rainwater from surrounding areas that occurs within 24 hours of a storm or heavy rain • the escape of rainwater from any water pipe, drain, or gutter • wind damage caused by storms or heavy rain. You are not covered for Loss or damage: • caused by flood unless you have selected and we have agreed to provide the optional Flood cover on page 50 • caused by rain, hail, wind, snow, or dust due to: – an opening that was not created by the storm or any other insured event – defects in design, structure, materials, workmanship, or construction that you knew about or should reasonably have known about – rain entering the building due to construction, alteration, or renovation work being carried out – the home not being in good condition, including guttering and drain pipes. See conditions of your cover on page 12. … General Exclusions: What this policy will never cover Some events and causes are never covered by this policy. These are known as „General Exclusions‟ and apply to the whole policy. You are not covered for any loss, damage, or legal liability you incur resulting directly or indirectly from events and causes listed below. .. Gradual deterioration You are not covered for loss or damage caused by rust, corrosion, rot, mould, rising damp, mildew, wear, fading, or other gradual deterioration. .. Poor condition You are not covered for loss or damage you incur because: - You have not done building work to the home requested by a relevant authority before the loss or damage occurred; or Determination | Case number: 955099 Page 9 of 12 - You have not kept the home or contents in good condition and existing defects or faults contributed to or caused the loss or damage. 3.3 Expert Reports Record Key points PB Builder‟s Report 28 December 2022  The property was inspected for storm damage on 16 December 2022  PB records the complainant stated that over 18 months ago they had a claim declined due to failed waterproofing in the bat hroom. There is now more damage to the bathroom, ensuite and master bedroom. The complainant believes the damage is due to wat er ingre ss through the roof.  The inspection found damage to the bat hroom, ensuite and master bedroom from water ingress through the tiled floor in the bathroom cracking to the tiled walls in the bathroom and ensuite as well as water ingress to the ceiling and wall plasterboard of the master bedroom.  A roof report was obtained which PB appears to rely on. LD Roofing Report Inspected 22 December 2022  LD inspected the roof noting it was in poor general condition and the roof condition was non - compliant.  LD did not consider there was a storm created damage to the roof.  Roof pitch throughout is non - compliant at less than 1°. Roof pitch was measured at between 0.4° – 0.9°.  Left - hand side of house gutter is completely blocked full of debris.  Right - hand side of house box gutter has some nat ural debris build - up. This is causing a blockage to the front right hand corner downpipe.  During an overflow event water will be able to ingress the wall/ceiling cavity due to the eave sheet running into the dwelling.  This may be the cause of damages however due to the condition of the roof and potential for leaks through the hopper flashing LD cannot confirm until we complete a spray test to the hopper flashing.  2X vent penetrations through roof are in poor condition. These require a deck tight (sic) rubber flashings installed due to deteriorated silicone.  Hopper flashing installation across the front right - hand corner of the house is n on - compliant as the roof sheets on the upstream and back fall. This will allow water to run underneath the hopper flashings rendering them useless.  The hopper flashing is typically used to cover the termination of an old roof penet ration.  To confirm thi s as being the cause of damages LD would recommend a spray test to the hopper flashings to identify ingress into ceiling cavity. Determination | Case number: 955099 Page 10 of 12 Record Key points  Roof sheets back fall towards the top of hopper flashing. This will allow water to track down roof sheets underneath hopper to wards right - hand side of house. The hopper flashing installation is typically used to cover old roof penetrations which in this case would be allowing water into those old penetrations.  The following maintenance issues were identified with the roof: - The r oof requires renewal/refalling - Extend hopper flashings to the section of the roof where water cannot run int o top end - Clean gutters - Repair vent penetration seals and adequately flush using deck tight rubbers BE Engineering Report 5 June 2023  The common bat hroom showed delaminat ed wall tiles and deflection of the wall with cracks also sighted in the cement grout. BE was of the opinion that stormwater was entering from the roof structure through the guttering system. This created the damage to t he cement based adhesive and caused the wall tiles to deflect.  The ensuite had cracked tiles which was also caused by storm water entering from the roof structure through the guttering system.  The master bedroom had black mould on the plaster ceiling and wall. The cause is recorded as stormwater from the roof structure, through the guttering system.  The observed distresses are consistent with a stormwater event due to excessive rainfall. The inundation of the wall cavity from surface runoff through the r oofing flashing, causing excessive moisture build up, has resulted in black mould, tile delamination and excessive condensation.  The roof was observed to be well maintained, considering the substantial hedges on the neighbouring property which would contr ibut e significant leaf and veget ation to the guttering system. The gutters were found to be free from vegetation. No pre - existing maintenance issues were identified.  It is evidence from the inspection of the bathrooms and presence of mould directly below the roofline in the master bedroom that the observed damages have been caused by surface run - off rainwater that has occurred. A liquid escape event (time unknown) has overcome the flashing and sealant, which has det eriorated subsequently with each addition al downpour of rainfall. This is the major contributory factor, causing the observed damages.  No defects in design or construction were observed and the exceedance of ARI100 year cumulative rainfall events are deemed to have caused the damage.  BE recomme nded the following works: - Engage a mould hygienist to deal with the mould damage and ensure an appropriate mould remediation specialist completes the works. Determination | Case number: 955099 Page 11 of 12 Record Key points - Reseal roof guttering and flashing on western elevation. BE recommended the engagement of a qualified plumber to reseal all the roof fixings and flas hings to ensure compliance with the current Australian Standard AS3500. Particularly on the western elevati on from the northwest corner to the southside of the adversely impacted moisture ingress above the common bathroom. This will ensure the roofline is adequately waterproofed to aid in preventing the moisture ingress of the wall cavity. - Remove and replace delaminated bathroom tiles. Bureau of Meteorology November 2022  The complainant provided a link to the Bureau of Meteorology (BOM) for November 2022 which records higher than average rainfalls.  High rainfalls were recorded down the c oastal regions of Victoria o n the 14 November 2022.  The nearest rain gauge to the insured property throughout November 2022 does not exceed 29.6mm . The next highest rainfall is 21.2mm  Parts of Greater Melbourne experienced thunderstorms, heavy rainfall and flash flooding on the 8 th and 13 th of November 2022.  The wettest day recorded was 80. 6mm at Ros ebud on 14 November 2022.  The stated date of loss recorded is 8 December 2022 and not in November 2022. However, a check of the December 2022 rainfall suggests low rainfall wit h the highest rainfall being 17. 2mm on 12 December 2022. SA Insuranc e Report Inspection on 14 October 2020  The insuranc e report was prepared for another insurer and not the insurer relating to this claim.  The bathroom had been renovated 7 years ago.  The assessor attended to inspect cause of wat er related damages to the hallway flooring along with the bathroom subfloor. There was further lifting of the bat hroom floor tiles due to causes unknown.  The assessor concluded that there was water escaping the shower recess through defective sealants and waterproof membrane within the shower recess. The assessor was of the opinion that poor and faulty workmanship during the renovation was the cause. SA Specialist leak detection report 14 October 2 020  After completing leak detection tests, the proximat e cause of the water escaping the shower recess was deemed to be defective sealants and the waterproof membrane wit hin the shower rec ess.  All pressure testing to pipes and tap fitting indicates no leaks from these items.  SA provided the following conclusions: - The recess grout is in good condition where as the caulking is Determination | Case number: 955099 Page 12 of 12 Record Key points becoming det ached. - A shower base flood test failed with a detected leak tracking towards the bathroom door. - As there is no signs of a water stop at the door, this would allow staining to the hallway floor boards from the escaped water from the shower recess. - On arrival the bathroom floor was saturated and wat er was c oming out of the grout when stepped on, however no water escape was identified during todays testing. The water escape is a usage issue. - Detached caulking in the shower recess is the direct cause of water egress from the bathroom tiles. This is causin g the tiles to become loose. - A subfloor inspection under the bathroom identified water seeping through the substrat e and join under the glass shower screen. - This has confirmed that the membrane of the recess and bathroom has failed.  Maintenance reco mmendations included strip out and reconstruction of the shower recess to ensure waterproof and watertight enclos ure.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.