The insurer denied a home building claim for water ingress, mould, corrosion and movement damage. AFCA required it to cover the mould and corrosion, but not the movement damage, and to pay $1,200 for non-financial loss.

Storm caused the mould and corrosion, and the insurer did not prove the gradual deterioration exclusion; movement damage occurred outside the 72-hour window; claim delays warranted compensation.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interestpay non financial loss

Related

All Allianz Australia determinations · Find similar determinations

Text of the determination

Determination Case number 954219 Financial firm Allianz Australia Insurance Limited Determination | Case number: 954219 Page 1 of 7 Case number: 954219 28 November 2023 1 Determination overview 1.1 Complaint The complainant holds home building insurance issued by the financial firm (insurer). On 16 May 2022, she lodged a claim for movement damage, water damage and mould after discovering water pooling in the subfloor area of her home. The insurer has denied the claim. It says that the damage was not caused by an insured event. Rather, the damage is due to gradual deterioration and long-term ground movement. The policy excludes cover for damage from those causes. The complainant maintains that the damage occurred within 72 hours of a storm. She wants the insurer to accept the claim. She is also dissatisfied with the insurer’s claim handling. 1.2 Issues and key findings Is the insurer entitled to deny the entire claim? No. The complainant has, on balance, established a claimable loss under the Storm insured event for the mould and subfloor corrosion. The insurer has not shown an exclusion applies to that damage, so it must cover it. However, the movement damage is not covered as it occurred more than 72 hours after the claim event. Is non-financial loss compensation payable? Yes. The insurer’s unreasonable delays caused the complainant stress, frustration and inconvenience. It is required to pay her $1,200 in non-financial loss compensation. Why is the outcome fair? The complainant has established a claimable loss under the Storm insured event for the mould and subfloor corrosion. The insurer has not shown this damage is excluded. It is therefore fair to require the insurer to cover that damage. It is also fair that the insurer pays non- financial loss compensation for the stress it’s claim handling delays have caused. 1.3 Determination This determination is substantially in favour of the complainant. Within 14 days of the complainant providing written notice she accepts this determination the insurer is to pay her:  $3,000 in reimbursement for corrosion repair costs  interest pursuant to section 57 of the Insurance Contracts Act, 1984 (Cth) on $3,000 from 28 June 2023 (date of payment) to the date the reimbursement is provided  $3,414.24 for mould removal costs, and  $1,200 in non-financial loss compensation. Determination | Case number: 954219 Page 2 of 7 2 Reasons for determination 2.1 Is the insurer entitled to deny the entire claim? No. The complainant has, on balance, established a claimable loss under the Storm insured event for the mould and subfloor corrosion. The insurer has not shown an exclusion applies to that damage, so it must cover it. However, the movement damage is not covered as it occurred more than 72 hours after the claim event. Complainant must show a claimable loss under the policy terms The complainant is required to show, on the balance of probabilities (that it is more likely than not), that she suffered a claimable loss under the policy she holds. This means she must show the loss was caused by a risk for which she is insured. Subject to the terms and conditions set out in the product disclosure statement (PDS), the policy covers d amage to the complainant’s home caused by a listed insured event. Those events include ‘Storm, cyclone, rainwater or run - off’ (Storm) and ‘Water or other liquid damage’ (that is, escape of liquid – EOL). The claim was lodged on 16 May 2022. While investigating mould and a musty smell affecting the lower level of the home, the complainant had discovered a large pool of water in the subfloor area. The complainant was initially uncertain of the cause of the water ingress, but subsequently attributed it to heavy rainfall in early to mid-2022. Once the complainant proves the existence of a claimable loss, the insurer is liable for the loss unless it shows an exclusion or limiting condition applies. The insurer has the onus of proving on the balance of probabilities the application of the exclusion or condition. Insurer says it is entitled to deny the claim The insurer’s appointed builder, RN, inspected the home on 20 May 2022. RN could not locate any obvious cause for the water ingress. It noted that three doors downstairs could not be closed, suggesting movement, and there was a musky smell, suggesting there was mould under the house. RN recommended further investigations be undertaken. On 28 June 2022, engineer KM inspected the property. KM reported to the insurer that:  the home was built on the side of a steep hill and had been cut in, with the front (southern) wall retaining approximately 1800mm of fill  large amounts of subterranean water had entered under the home in that area  the fill material had been built up well above weep holes and approximately 1500mm above the internal floor level  an ag line was located at the retaining wall’s base, and was next to the side of the home  the internal doors had moved back closer to their original positions and were not jamming  the complainant said in June 2021 a pest inspector advised that it was dry under the home  ‘ All the dam ages observed to the house itself have occurred due to a combination of the swelling of the [highly reactive] soils during the event and the most likely differential drying whi ch has occurred since’  unless a waterproof membrane had been applied to the front brickwork, the backfill against it would allow water ingress into the under-floor area  if the ag line was blocked, this would cause water to build up in the fill  while further investigations were recommended, including after a 12-month drying period, any issues associated with the backfilled area were ‘owners maintenance’. Determination | Case number: 954219 Page 3 of 7 The insurer’s claim notes record that on 30 December 2022, KM verbally advised that while cracking may have occurred within 72 hours of the claimed event, that was highly unlikely. On 31 August 2022, plumber AL inspected the home. Thermal imaging did not show any moisture under the building. Based on the complainant’s description of what occurred in May, AL thought the musty smell and mould was the re sult of ‘ground water due to excess rain’ . AL reattended on 23 February 2023. Following a CCTV inspection, AL said there were no major issues with the ag line. However, AL was unable to confirm if there was any drainage in the backfill. The insurer engaged a second engineer, SB, after the complainant lodged her complaint with AFCA. SB inspected the property on 17 April 2023. By then the complainant had installed a new retaining wall and drainage and had removed all the fill that had been resting against the southern wall of the house. SB said:  Bureau of Meteorology data showed that 901.6mm of rain fell in the local area in February 2022, with 612.6mm falling from 26 to 28 February. 356.2mm fell in May 2022  the rainfall experienced in May 2022 rainfall would not be expected to result in damage to the building. The intense late February rainfall, likely caused the groundwater level to rise. That and surface water run-off during the rain events likely contributed to the water ingress  the cracking and movement-related damage has been contributed to by footing movement because of long term and ongoing differential moisture content variations within the underlying reactive clay soils (swelling when wetter and shrinking when dry)  water ingress into the subfloor has occurred during multiple heavy rain events and most likely was more pronounced during the early to mid-2022 rainfall. This water ingress during multiple previous rain events contributed to the corrosion to steel columns, mould to timber floor members and efflorescence staining to the internal face of the brickwork  images supplied by the complainant show the corrosion and mould were present prior to the May 2022 rainfall  the use of thick timber packers to concrete piers to re-level the house in the past is indicative of long-term downwards settlement-related movements  the separation of external paving away from the rear northern wall was due to long term processes, involving subsidence and rotation  ‘the proximate [operative] and underlying cause of the cracking and movement-related damage to the house is due to long term and on-going seasonal moisture content changes of underlying reactive clay soils ’ . SB provided a supplementary report dated 26 September 2023, in which it said:  due to the backfill against the southern wall, the subfloor was inherently susceptible to surface water run-off and groundwater entry during storms  the backfill level had been well above the subfloor ground level, in breach of the Building Code of Australia (BCA)  once water enters the subfloor space there is little to no avenue for the water to egress. The site slopes from the front to the rear and there are no openings at the rear through which the water may escape  plans for the 1996 lower level extension of the house, and the BCA, required the steel subfloor columns to be encased in concrete, finishing 100mm above ground level. That was not complied with, leaving the columns susceptible to corrosion by subfloor water  BCA requirements for subfloor ventilation have not been met as only the eastern wall has brick air vents. This allowed mould to develop on timber in the subfloor Determination | Case number: 954219 Page 4 of 7  w hile the rainfall in late February and in May 2022 ‘ most likely precipitated to water entering the subfloor space’, the proximate causes of the corrosio n and mould in the subfloor are the issues set out above. The insurer says the claim is not covered because:  the complainant has not shown a claimable loss under the EOL insured event  the complainant has not shown a claimable loss for the movement damage under the Storm insured event as that insured event only covers damage caused by arising from ground movement if it is caused directly by and occurs within 72 hours of a storm  the PDS excludes damage as a result of, caused by or arising from: > ground movement unless it is caused directly by and occurs within 72 hours of (relevantly) a storm > ‘ gradual deterioration, wear and tear or lack of maintenance’ > anything not directly related to one of the insured events. Complainant says insurer should accept the claim The complainant says: We made an insurance claim in May upon discovery of water during an unprecedented series of floods and extreme rainfall down the east coast of Australia early in 2022. All previous inspections under our home have been dry and there has been no rust or mould. Pest inspection mid 2021 noted the subfloor was dry. She says that there had never before been any evidence of water entering the home, and that the cracking damage only appeared after the water ingress occurred. The complainant says the claim event was the extreme rainfall experienced in early to mid- 2022, and notes KM’s report clearly refers to ‘the event’ as being causative. The complainant says the insurer should have obtained a second report from KM rather than engaging SB, and that the insurer refused to allow her to get a report from KM. She points out that her home was built about 30 years ago. She says that there is no way of knowing whether the dirt now seen around the steel subfloor columns was placed around them at the time of construction. She suggests the dirt may have shifted over time, including because of the water ingress and subsequent digging undertaken to drain the water away. The complainant says there are air vents in the eastern wall, southern wall and northern wall. She has provided photos of a vent in each of the southern and northern walls. The photos of the vent in the southern wall shows the vent is above where the fill and retaining wall were. The complainant also says that hygienist EC provided a quote for removal of mould in the subfloor area. EC told her most of the mould was directly above where the water had entered. In addition, the complainant notes the subfloor photos she provided to SB were taken in May 2022, not February 2022. She says the corrosion seen on the steel columns is at the same level the water was before being pumped out. She says the Queensland heat, humidity and wet conditions would have sped up the corrosion process. Further, that if the water ingress had been occurring for a long period, the corrosion would have been much worse. Determination | Case number: 954219 Page 5 of 7 Insurer is not entitled to deny the entire claim Based on the exchanged information, I am satisfied that the complainant has established a claimable loss under the Storm insured event for the mould and subfloor corrosion. The insurer’s experts AL, KM and SB all acknowledge that excessive rainfall in February (especially) and May 2022 resulted in the subfloor water ingress. This means the insurer must show an exclusion applies if it is to avoid liability for the mould and the corrosion. The exclusion relating to anything not directly related to one of the insured events cannot apply given my finding that the complainant has established a claimable loss. As the ‘more than 72 hours of a storm’ exclusion only applies to ground movement, it is also irrelevant. The only other exclusion the insurer has said is applicable is that precluding cover for gradual deterioration, wear and tear and lack of maintenance. The insurer does not assert that the mould and corrosion are the result of lack of maintenance. In any event, I am not satisfied that aspect of the exclusion applies. ‘Wear and tear’ is not defined in the PDS, so its ordinary meaning is to apply. The Macquarie Dictionary defines the te rm as ‘ diminution, decay, damage, or injury sustained by ordinary use ’. Again, I am not satisfied the mould and corrosion are due to ordinary use. I acknowledge that mould and/or corrosion can occur through a gradual process. However, in this case, I consider it more likely than not that both occurred quickly and directly as a result of the (rain)water ingress. The complainant has unequivocally stated that there were no issues until the February 2022 storm, and the images of the water levels and subsequent corrosion levels are persuasive. The complainant has, on balance, established a claimable loss under the Storm insured event for the mould and subfloor corrosion. The insurer has not shown an exclusion applies to that damage, so it must cover it. However, the movement damage is not covered as I am satisfied, on balance, it occurred more than 72 hours after the claim event. There is no persuasive evidence showing that is not the case. This means the complainant has not shown a claimable loss for the movement damage. The complainant has provided EM’s mould removal quote dated 14 July 2023, totalling $2,968.90. The insurer is to pay the complainant the quoted amount plus a 15% contingencies uplift, $3,414.24, as a cash settlement. The complainant has provided an invoice for ‘subfloor construction and restumping’. The invoice indicates that the works were completed on 27 June 2023 for a total cost of $6,000. The invoice is not on letterhead, does not specify an ABN and does not refer to GST. Of the eight listed work items, only four relate to rectifying the corroded steel posts: • Removed all surface and flaking rust from 30 posts. • All coated with rust converter, steel primer, anti -corrosive topcoat and bitumen. • Fabricated 90x90x5mm sleeve welded aro und one affected existing post. Coated with bitumen and sealed. Determination | Case number: 954219 Page 6 of 7 • Removed all mess made. The complainant says the relevant trade undertook the work in exchange for a cash payment. The trade is not willing to provide a compliant invoice. The complainant has provided a redacted bank statement showing she paid the $6,000 on 28 June 2023. As the corrosion items represent 50% of the listed work items, I am satisfied that it is reasonable in the circumstances to require the insurer to reimburse the complainant $3,000. It is also to pay interest on that amount pursuant to section 57 of the Insurance Contracts Act, 1984 (Cth) from 28 June 2023 to the date the reimbursement is provided. 2.2 Is non-financial loss compensation payable? Yes. The insurer’s unreasonable delays caused the complainant stress, frustration and inconvenience. It is required to pay her $1,200 in non-financial loss compensation. AFCA can award compensation for poor claim handling Under paragraph D.3 of the AFCA Rules, we may award compensation for non-financial loss (capped at $5,400) where the insurer’s actions have caused an unusual amount of:  physical inconvenience  time taken to resolve the situation  interference with the complainant’s expectation o f enjoyment or peace of mind. Insurer has caused stress and inconvenience The complainant says that she has experienced significant stress and inconvenience because of the insurer’s claim handling. She refers to extensive delays and poor communication. I agree with the complainant that the insurer unreasonably delayed the claim’s progression. The claim was lodged on 16 May 2022, but the insurer did not make a claim decision until six months later, on 17 November 2022. That is outside the standard four-month period referred to in the General Insurance Code of Practice. I also anticipate that the insurer’s decision to engage a second engineer rather than obtaining a further report from KM has contributed to the delays experienced. I am satisfied that the insu rer’s unreasonable delays have caused the complainant stress, frustration and inconvenience. It is therefore required to pay her $1,200 in non-financial loss compensation. 2.3 Why is the outcome fair? The complainant has established a claimable loss under the Storm insured event for the mould and subfloor corrosion. The insurer has not shown this damage is excluded. It is therefore fair to require the insurer to cover that damage. It is also fair that the insurer pays non-financial loss compensation for the str ess it’s claim handling delays have caused. Determination | Case number: 954219 Page 7 of 7 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.