Home / QBE / Determination 951592

Determination 951592

Insurer deducted $56,692.79 removal of debris costs from building total loss cash settlement

FirmQBE
Decided2023-09-28
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$56,693
SourceAFCA PDF

Summary

After a fire, the insurer accepted the claim and cash settled the building as a total loss but deducted $56,692.79 of debris removal costs from the sum insured. AFCA found the deduction was consistent with the policy and decided in favour of the insurer.

The PDS states additional benefits such as removal of debris are paid as part of the sum insured, the works were urgently authorised due to a council order before total loss was determined, and the insurer managed the claim reasonably.

Issues

Subjects and remedies

broker or intermediaryhome or building damageno remedy

Related

All QBE determinations · Find similar determinations

Text of the determination

Determination Case number 951592 Financial firm QBE Insurance (Australia) Limited Determination | Case number: 951592 Page 2 of 7 Case number: 951592 28 September 2023 1 Determination overview 1.1 Complaint The complainant holds a home insurance policy (policy) with the financial firm (insurer). On 2 March 2021, a claim was lodged for damage to the insured property caused by a fire event earlier the same day. The insurer has accepted the claim. The insured building and contents have been assessed as a total loss. The insurer has offered the complainant cash settlements based on the policy’s sum insured amounts nominated by the complainant. The complainant is dissatisfied with the insurer’s decision to deduct $56,692.79 from the settlement for the insured building, said to be costs spent on removal of debris works (ROD). The policy was arranged through the complainant’s broker ‘K’ and who is assisting the complainant with this complaint. In the interest of brevity, reference to the complainant includes both K and the complainant, unless specified otherwise. 1.2 Issues and key findings Is the insurer entitled to reduce the claim settlement by the ROD costs? Yes. The insurer’s assessment of its liability, including reducing the final claim settlement offer to the complainant by the ROD cost, is consistent with the policy. Why is the outcome fair? The outcome is fair as the available information shows the ROD costs in question were incurred prior to the decision confirming the insured building was a total loss and in line with an order issued by ‘B’ Council. The policy clearly informs such costs fall un der the nominated sum insured, and therefore, it is fair that the insurer deducts these costs from the complainant’s settlement. 1.3 Determination This determination is in favour of the insurer. The insurer is entitled to reduce the final claim settlement for the damaged insured building by the ROD costs in line with the policy. Determination | Case number: 951592 Page 3 of 7 2 Reasons for determination 2.1 Is the insurer entitled to reduce the claim settlement offer? Yes. The insurer’s assessment of its liability, including reducing the final claim settlement offer to the complainant by the ROD cost, is consistent with the policy. The policy covers the insured property against accidental loss or damage The insurer provided the complainant with the relevant policy documentation including the product disclosure statement (PDS) and certificate of insurance (COI). I accept the insurer is entitled to rely on the policy provisions to assess its liability under the claim. The policy covers the insured property against accidental loss or damage. Cover under the policy is subject to the conditions, limitations and exclusions specified in the PDS. The complainant has shown damage that triggers cover under the policy There is no dispute between the parties that:  the complainant has established loss or damage that triggers cover under the policy  the insurer’s assessment and associated claim settlement offer for the damaged contents is consistent with its obligations under the policy  the cost to repair the insured building has correctly been assessed to exceed the policy sum insured including the adjustment for inflation and therefore is a total loss  the insurer appointed the complainant’s preferred engineering consultants’ ‘I M ’ t o investigate the extent of damage to the insured building and provide a scope of works. Further, that IM determined the building structure was repairable and did not require total demolition, other than the fire damaged roof. The complainant says the ins urer’s cash settlement offer for the insured building is not fair because:  the policy does not clearly inform that ROD costs fall under the insured building sum insured and should be accepted to be a benefit on top of the sum insured  given the extent of damage to the insured building, the insurer should have declared it a total loss prior to authorising the ROD works to consultants ‘E’  the ROD works did not include demolishing the entire building, which means the complainant will need to spend a further $60,000 (approximately) to demolish the building. Scope and cost of ROD works fall under the policy’s building sum insured I have considered the relevant policy wording specified in the PDS relating to cover for ROD costs. I am satisfied the policy clearly informs that cover for ROD costs falls under Section 4 – Additional benefits provided on page 37 and that payment for these additional benefits is covered as part of the sum insured for the home or contents. The relevant policy wording in the PDS states: Section 4: Additional benefits We give you the following additional benefits. For any additional benefits to be payable, you must suffer or incur the relevant loss, liability or damage during the period of insurance. Determination | Case number: 951592 Page 4 of 7 We pay additional benefits 1 to 20 as part of the sums insured for home or contents,... I do not accept the complainant’s position that the policy is uncl ear or ambiguous in this regard. I accept the policy does inform that the ROD benefit falls under the building sum insured. I note K’s concerns regarding the difficulty in nominating the sum insured amount for the policy period, and especially relating to expenses relating to demolition and ROD expenses. However, I am not of the opinion this assists the complainant’s position. The responsibility to ensure the cover meets the complainant’s needs, which includes nominating an adequate sum insured amount, rests with the complainant and/or his nominated broker. It would be unfair to hold the insurer liable for a failure to nominate an adequate sum insured or to absorb the costs of the ROD works in these circumstances. Insurer ’s management of the claim was reasonable I have reviewed all the information from the parties and am satisfied this shows the insurer pro-actively managed the claim. The insurer has provided all the reports from the various consultants appointed to the claim including loss adjusters’ ‘S’, engineering consultants I M and the two b uilding consultants’ ‘J’ and E . The complainant has not provided any reports in support of his position. I note from the various reports that S were appointed within days of the claim being lodged to investigate the cause and extent of the damage to the insured property. S arranged for the complainant’s preferred engineer I M to be appointed to the claim, as well as, arranging the two builders to provide repair quotes based on the scope of works (SOW) provided by IM. I am satisfied the insurer and its consultants were pro-active in the management and assessment of the claim. S provided the parties with regular updates and the insurer efficiently provided and authorised instructions to the consultants at each stage of the assessment process. The complainant was kept involved in each stage of the process with S regularly seeking information, opinions and approval from him regarding matters such as the floor plan, SOW’s, temporary accommodation, contents claim etc. I am not of the view it can fairly be said that the insurer or its consultants were responsible for any unreasonable delays or periods of inactivity over the life of the claim. The consultants assessed the insured building to be repairable I acknowledge the complainant’s opinion that the insurer should declared the insured building was a total loss earlier. Further, that this would possibly have avoided the need for the ROD works in question being authorised under the claim. I am not satisfied it has been shown that the insurer caused any unreasonable delays. Rather, I accept the expert reports show the insurer was originally advised the insured building was repairable. I note the insurer did ask S in April 2021 whether the insured building would possibly be a total loss, with S advising based on information to hand it is repairable. I am not satisfied it would be fair to determine the insurer failed to declare the insured building a total loss earlier than it did. This is because I accept the insurer’s assessment and Determination | Case number: 951592 Page 5 of 7 investigations were reasonable given the complexities of the claim and the available expert advice. I am satisfied the insurer is entitled to undertaken reasonable investigations to assess its liability under a claim. Further, that it was not until the quotes from the builders were received towards the end of June 2021 and July 2021, that it became apparent the cost of repairs would exceed the complainant’s entitlements under the policy. I note attempts were made by the insurer and S to possibly bring the cost of repairs under the building sum insured through negotiations with E and seeking a fixed price repair quote. I am satisfied the information shows the insured building is not a total loss based on structural or safety related concerns. Rather, that in line with IM ’s assessment the building is repairable but that the complainant’s n ominated building sum insured is not adequate to cover the cost of completing the required repair and therefore it is an economic total loss. ROD works authorised on urgent basis at complainant’s request I am satisfied it was reasonable for the insurer to arrange the ROD works which included demolition of the damaged roof and removal of debris from the insured property. Further, that these works were completed by E at a cost of $56,692.79, this being the lower of the two quotes sourced by S for the works. The complainant has not provided any information to show that these costs were excessive for the works completed. The ROD works were authorised by the insurer due to concerns raised by the complainant about being contacted by the relevant local council demanding specific works be carried out to the fire damaged property. The complainant was ultimately issued with a letter by B Council dated 29 June 2021 ordering him to arrange the required works within 7 days. Failure to do so would result in an offence under the relevant Act and carries severe penalties, possible legal action or the council arranging the works and charging the complainant for the related expenses. The complainant requested urgent action through S, which the insurer accepted and instructed S to arrange for the necessary roof demolition and other ROD works to be completed urgently. S authorised E to carry out the works urgently based on the scope of works and quote ($56,692.79), which had already been submitted by E as part of its quoting process based on IM ’s SOW. I am satisfied the available information shows the decision to declare the insured building a total loss had not yet been made by the insurer. At this time, the insurer was still awaiting further information from the consultants regarding the expected repair costs and was reasonably under the impression the insured building was repairable. I am not satisfied it has been shown the insurer or the consultants caused any unreasonable delays in this regard. For these reasons, I am not satisfied it has been shown that it would be fair to conclude the insurer is liable for the demolition and ROD costs due to unreasonable delays or mismanagement of the claim. Further, I am not satisfied the complainant has shown any resulting financial prejudice from the insurer authorising these works. I accept these works would have had to be arranged by the complainant at his cost as part of the repairs/rebuild of the insured building, even if the works were not arranged by the insurer before settlement of the claim. Complainant is not covered for the total demolition of the insured building Determination | Case number: 951592 Page 6 of 7 I acknowledge the complainant’s position that ROD works completed did not include total demolition of the insured building to ground level. However, in line with the assessment and SOW provided by the engineer, the insured building (other than the roof) was assessed as being repairable and did not require total demolition. If the insurer were to have authorised the total demolition of the insured building, this would in fact mean it was causing the complainant further economic loss. If the complainant’s intention is to com pletely demolish and rebuild the home, this is a personal decision and any associated additional costs fall to him. As noted above, the expert evidence shows the structure of the building is repairable and can be used in returning/repairing the home to its pre-event condition. FF is entitled to reduce final claim settlement offer under the policy For the above reasons, I am of the view it would be unfair to require the insurer to absorb the demolition and ROD costs subject of this complaint. The insurer arranged these works on an urgent basis to assist the complainant given the council orders, and the costs do fall under the insured building’s sum insured as specified in the PDS. Accordingly, the insurer is not required to reimburse and is entitled to reduce the final claim settlement payment for the insured building by the $56,692.79 spent on the required demolition and ROD works. 2.2 Why is the outcome fair? The outcome is fair as the available information shows the ROD costs in question were incurred prior to the decision confirming the insured building was a total loss and in line with order issues by ‘B’ Council. The policy clearly informs such costs fall under the nominated sum insured, and therefore, it is fair that the insurer deducts these costs from the sum insured before cash settling the complainant under the claim. Determination | Case number: 951592 Page 7 of 7 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.