Determination 950046

Storm damage claim: cash settlement of internal damage instead of insurer's builder, roof claim settlement and delay

FirmIAG
Decided2023-10-03
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$134,348
Non-financial loss$5,400
Amount claimed—
SourceAFCA PDF

Summary

Insurer accepted the storm claim late and wanted its builder to repair internal damage. AFCA found in favour of the complainants, ordering a cash settlement based on their builder's quote plus 10% uplift, roof repair cost with s57 interest, and $5,400 non-financial loss.

The insurer's delay and poor handling destroyed trust in its builder, so under the policy's cash settlement option and the complainants' preferences it was fair to settle on the complainants' quotes.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interestpay non financial loss

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination Case number 950046 Financial firm Insurance Australia Limited Determination | Case number: 950046 Page 1 of 6 Case number: 950046 26 September 2023 1 Determination overview 1.1 Complaint The complainants hold a home buildings and contents policy with the financial firm (insurer) and lodged a claim for storm related damage on 9 March 2022 following three days of heavy rain. The complainants say the roof was damaged in the storm resulting in water entering their home causing internal damage to the building and contents. The insurer accepted the contents claim but denied damage to the roof. In June 2023 after the complaint was lodged with AFCA, the insurer agreed to cover the cost to replace the roof and pay the complainants $5400 compensation for non-financial loss. The insurer also accepts liability for the internal damage but wants its appointed builder MBG to complete the repairs. The complainants have lost trust in the insurer and MBG given the delays and seeks a cash settlement of the claim based on the quotations provided. 1.2 Issues and key findings Are the complainants entitled to a cash settlement for the internal damage? Yes. The insurer ’ s claims handling has caused the complainant considerable inconvenience resulting in a lack of trust in the insurers trades. It is fair that the insurer cash settles the complainants claim for the internal damage. Is the offer to settle the claim for the roofing repairs fair? Yes. The insurer has agreed to pay the complainant $39,022.50 being the cost of the roof repairs. Interest pursuant to section 57 of the Insurance Contracts Act 1984 (Cth) (the Act) should be paid from the date the complainant paid for the repairs until payment of the claim. Is the settlement of the non-financial loss claim fair? Yes. The insurer is to pay the complainant $5,400 compensation for non-financial loss. Why is the outcome fair? The outcome is fair as the insurers handling of the claim has caused the complainant to lose faith in the insurer ’ s builder. It is fair in the circumstances to cash settle the internal damage claim based on the quotes obtained. 1.3 Determination This determination is in favour of the complainants. Within 14 days of the complainants accepting of this determination the insurer is to pay the complainants:  $95,325 plus GST as per the quote provided by BL plus a 10% uplift on the quoted sum to cover possible contingencies.  $39,022.50 plus interest pursuant to section 57 of the Act from the date the complainant paid for the repairs to date of settlement of the claim.  $5,400 compensation for non-financial loss Determination | Case number: 950046 Page 2 of 6 2 Reasons for determination 2.1 Are the complainants entitled to a cash settlement for the internal damage? Yes. The insurer ’ s claims handling has caused the complainant considerable inconvenience resulting in a lack of trust in the insurer's trades. It is fair that the insurer cash settles the complainants claim for internal damage. Policy provides option to cash settle the claim. The complainants home and contents policy provide an option to cash settle a building damage claim. In determining how to settle the claim the policy provides the insurer will have regard to the circumstances of the claim and consider any preference the insured may have. The policy provides: “ if you agree, we can arrange for our preferred repairs, suppliers or builders to repair or rebuild your home. We may enter into a contract with our selected repair are, builder and or supplier on your behalf. ” The policy also provides the when calculating a cash settlement, the insurer will: “ if your building is repairable in some circumstances we will choose to settle your claim by deciding to pay you. We will pay you the reasonable costs of what it would cost us provided that cost is available to or actionable by you When calculating the amount of any cash settlement the insurer can ask a complainant to obtain a quote for the repairs or obtain a quote from the insured’s builder for the repairs or for the insurer to obtain a quote from its repairer. Insurer unreasonably delayed assessment of claim. The complainant lodged the claim for storm related damage on 9 March 2022, related to a February 2022 storm event. The insurer accepted the claim for contents damage but did not make any decision on the claim for roof damage until 23 January 2023. The insurer ’s builder MBG assessed the damage on 23 March 2022. MBG confirmed that rain water had entered the home following the recent storms and observed that mould was growing in the master bedroom ceiling on wardrobe. According to MBG, its roofing contractor had recorded multiple maintenance issues. No report was provided by the roofing contractor. The insurer had a second builder B attend the property on the 6 April 2022. B confirmed it was water damage to the ceilings in multiple rooms and recommended roof repairs be carried out prior to internal repairs being actioned. The insurers claim notes show that on the 9 May 2022 the complainants contacted the insurer seeking an update on the claim. During that conversation the insurer confirmed details of the MBG report. The insurer advised it was not happy with the amount of information supplied by MBG and would obtain further information. It appears from the claim notes that no further information was obtained with respect to the roof damage nor any decision communicated to the complainant about liability for the roof repairs. It is not until 3 November 2022 after the complainant had the roof repaired and provided a scope of works from PA to repair the roof that the insurer completes a desktop Determination | Case number: 950046 Page 3 of 6 building assessment of the roof damage. The insurer then obtained a report from an engineer SCE. This should have happened after receiving the report from BL. SCE’s report is dated 4 January 2023. SCE 's inspection of the property occurred after the roof had been replaced by PA. SCE considered inadequate roof and gutter maintenance to be a contributing factor to the cause of the gutter leak. SCE found the valley leak was due to a combination of defective design and insufficient roof maintenance relating to the collection of debris. SCE’s report does not refer to PA’s email dated 17 October 2022 or that PA had been maintaining the roof for ten years. I t does not refer to the complainant’s comments with respect to the regular maintenance performed. Based on the available information SCE wrongly assumed there was a lack of maintenance. The complainants had informed the insurer that the roof was professionally cleaned four times per year, that PA regularly completed necessary maintenance two to three times per year and their own actions in clearing debris. The complainant offered to provide proof. The insurer appears to have ignored this. The insurer subsequently declined the roof claim on 23 January 2023, again on 22 February 2023 and again on 7 March 2023. The denial letters do not r eference the complainant’s comments regarding roof maintenance or PA’s email. The insurer appears to have ignored the information provided by the complainant, delayed in following up its trades and failed to act with any urgency in the claim. It is not until 16 June 2023, after further review, that the insurer agreed to cover the cost of the roof repair. The delay in properly assessing the roof damage has also unreasonably delayed the proper assessment of the internal damage and caused the complainants to lose trust in the insurers trades. Complainants want claim for internal damage cash settled The insurer obtained a quote of $46,176.28 from MBG dated 29 March 2023 to complete the internal repairs based on the scope of works prepared by SCE. The first quote from MBG in April 2020 was for approximately $16,000. I note that the insurer had SE attend the property on 30 March 2023 to provide a scope of works for the electrical works required. The report identifies water related damage to electrical fittings. SE could not rule out water ingress as the cause of damage to the intercom system or the possibility of further wiring faults. This is not included in the quote from MBG or offer from the insurer. The complainants provided a quote from PA dated 30 August 2022 for $64,882.35. On 7 March 2023, the insurer asked the complainant to provide a quote from PA based on the SOW provided by SCE. PA provided a further quote for $108,150. The quote is also dated 30 August 2022, but I accept has been provided after 7 March 2023 based on the accepted repairs. The complainants provided a second quote from BL dated 11 May 2023 of $95,325. That quote is also based on the scope of works from SCE. The complainant quotes are reasonably consistent and reflect the likely cost to the complainants of completing the repairs. The insurer, in its latest submission says MBG can complete and warranty the repairs but suggests MBG reattend and provide an updated quote. The insurer is also prepared to have another panel builder submit a quote for the damage following MBG’s re attendance. The Determination | Case number: 950046 Page 4 of 6 insurer could have done this much earlier given it was aware the complainant did not want MBG completing repairs. I can understand the complainant's reluctance to involve the insurer ’ s builders in the repair of the property. It is now over 18 months since the property was damaged and over 12 months since the insurer had sufficient information to determine its attitude to liability for the roof damage. The insurer was aware the roof had been repaired. It could have reassessed the internal damage at that time. I am satisfied the insurers claims handling has led to the loss of trust in the insurer to fairly assess the claim. The policy provides any settlement will have regard to the claims circumstances and complainant’s preferences. The policy provides a cash settlement is to be based on the reasonable cost to repair the damage after obtaining quotes from the complainants and insurers building repairers. I am not persuaded that the quote from MBG covers all necessary works or would be reasonable for the complainant to complete the repairs. While the insurer says the quote is actionable I do not believe this is a reasonable option given the loss of trust in MBG. The complainant provided two builders reports and quotes. Both reports cover the damage that is now accepted including any necessary mould remediation and electrical works. In my view given the delays associated with the insurers assessment of the claim, it is fair to rely upon the complainant’s quotes in determining the cash settlement. I consider it fair to rely on the lower quote from BL of $95,325.00 plus GST. This includes cover for the intercom, electrical repairs and mould remediation that may be required. I consider it also fair that the insurer provides an uplift of 10% to cover possible contingencies in the repair process in view of the rapidly increasing building costs. Accordingly, within 14 days of the complainants accepting this determination the insurer is to pay the complainants:  $95,325 plus GST as per the quote provided by BL plus a 10% uplift on the quoted sum to cover possible contingencies. 2.2 Is the insurer's offer to settle the claim for the roofing repairs fair? Yes. The insurer is to pay the compliant $39,022.50 plus interest to show it to section 57 of the Act Parties agreed to settlement for the roofing repairs The insurer offered to settle the complainants claim for the cost of the roofing repairs on 16 June 2023. The offer is based on the quote from PA $35,475 excluding GST. The complainants accepted the offer on 19 June 2023. The complainants advise that they have not been paid the settlement monies by the insurer. The compliance had the roof repairs completed by PA in around September/October 2022. They paid for the repairs at that time. As the insurer has not yet paid the settlement monies, in my view it is fair that the insurer pays interest on the repair cost from the date the complainant paid for the repair. Accordingly, I determine that the insurer should pay the complainant $39,022.50 for the roof repairs plus Determination | Case number: 950046 Page 5 of 6 interest. Interest pursuant to section 57 of the Act is payable on the $39,022.50 from the date the complainant paid for the roofing repairs to date of payment of the claim. The complainant will need to provide the insurer with the relevant invoice and receipt from PA to establish date of payment for the repairs. 2.3 Is the insurance settlement of the claim for non- financial loss fair? Yes. The settlement of the claim for non-financial loss of $5,400 is fair in the circumstances Parties agreed to settlement of non-financial loss claim. The insurer offered to settle the complainants claim for non-financial loss for $5,400.00 on the 26th June 2023. The complainant accepted the offer on the same day. The complainant says the non-financial loss settlement monies have not been paid. It is fair in the circumstances that the insurer makes payment of the sum of $5,400 within 14 days of the complainant’s acceptance of this determination 2.4 Why is the outcome fair? The outcome is fair as the policy requires the insurer to have regard to the circumstances of the claim and the complainant’s preferences. The insurer ’ s handling of the claim has caused the complainant to lose faith in the insurer ’ s builder. While I acknowledge the insurer has offered to complete and warrant the repairs or obtain further quotes, I am of the view given the delays it is fair to cash settle the claim. The policy provides the option to cash settle the claim based on the reasonable costs to complete the repairs. I consider it unreasonable to rely on the insurers quote given the way the claim has been handled. In my view it is fair in these circumstances and consistent with the terms of the policy to cash settle the claim based on the quotes obtained. Determination | Case number: 950046 Page 6 of 6 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.