Text of the determination
Determination
Case number 948431
Financial firm AAI Limited
Determination | Case number: 948431 Page 2 of 12
Case number: 948431 15 December 2023
1 Determination overview
1.1 Complaint
The complainants hold an events-based home building and contents insurance policy with the
financial firm (insurer). On 21 February 2020 they lodged a claim for damage as a result of
Cyclone Damien.
The insurer accepted the claim. However, a dispute arose about the quality of some work
carried out by the insurer and its subsequent offer of a cash settlement regarding items it
says it is unable to warrant.
The insurer acknowledges some rectification works were required but says, overall, the
repairs have been completed correctly and to Australian Standards.
The complainants do not agree and refused the offer of a cash settlement. They want the
insurer to carry out all repairs and provide warranties for such repairs.
1.2 Issues and key findings
Should the insurer carry out the repairs?
As the insurer cannot warrant the repairs it seeks to cash settle, and the terms and conditions
of the policy empower the insurer to choose how to settle claims, it is not obliged to carry out
some of the repairs. In this instance, there have been numerous issues between the
complainants and the insurer and its service providers, and a cash settlement is appropriate.
However, the insurer must complete repairs to the roof and eaves if the complainants
establish the incorrect product was used.
Should the insurer pay non-financial loss compensation?
It is fair the insurer pays the complainants, jointly, the sum of $3,000 in non-financial loss
compensation.
Why is the outcome fair?
The outcome is fair in all the circumstances because:-
The complainants have established a valid claim for damage to their home
The insurer may choose how it settles the claim
A cash settlement for some of the works is fair and appropriate, save for repairs to the
roof and eaves of the complainants’ home
An award of non-financial loss compensation is fair and appropriate
Throughout this complaint AFCA’s approach has remained objective, consistent with
the facts and based upon the law.
Determination | Case number: 948431 Page 3 of 12
1.3 Determination
This determination is substantially in favour of the complainants.
The complaint should be resolved in accordance with Section 2.3, below.
Determination | Case number: 948431 Page 4 of 12
2 Reasons for determination
2.1 Should the insurer carry out the repairs?
Insurer has discretion over how claims are settled
The terms and conditions of the policy are set out in the Product Disclosure Statement (PDS)
and the Certificate of Insurance. Page 87 of the PDS states:-
How we settle your claim
We choose how we settle home claims
If we agree to pay a claim for loss, theft or damage to your home, we will
decide if we will:-
repair damage to your home
rebuild your home
pay you what it would cost us to repair or rebuild your home
pay you the sum insured for your home
give you a voucher, store credit or stored value card for the amount it
would cost us to repair; or
rebuild an item (emphasis added).
In short, the policy provides the insurer with discretion as to how it will settle claims, including
repairing damaged items or cash settling for the amount those items cost to repair.
The claim
On 8 February 2020 Tropical Cyclone Damian struck the Pilbara coast of Western Australia
near the townships of Dampier and Karratha. Th e complainants’ single storey home was
damaged.
The insurer appointed WB, building consultant, to assess the complainants’ property and
report on the cause and extent of damage. WB’s first report written pursuant to that inspection
is dated 17 March 2020. WB notes the complaina nts’ home was built in about 1970. It is a
brick-veneer construction sitting atop a concrete slab foundation.
WB observed the following damage that was considered to be consistent with the insured
event:-
Carport barge flashing damage – made safe but requires replacement
Water staining to carport ceiling
Wind driven rain ingress with water staining to hallway ceiling panel
Wind driven rain ingress to bedroom 3 window
Wind driven rain ingress to living area ceiling
Aggregate blasting to 1x external patio post
Storm damage to external gates
Claimed patio dislodgement/minor rafter twist (steel) to rear – Unable to confirm if fair
wear and tear related or age – Costing to be based on liability quote due to inability to
warrant structure.
The insurer then accepted the claim and a scope of works (SOW) was provided.
Determination | Case number: 948431 Page 5 of 12
In June 2020 concerns were raised about the SOW in relation to the roof. The insurer
appointed MC, builder and engineer , to inspect the complainants’ property . MC ’s first report is
dated 24 August 2020. It is comprehensive and logical and is supported by illustrative
photographs.
Upon inspection MC noted, amongst other things:-
The cracking in the house is all very minor (however one cannot determine what
winds have occurred since the painting was carried out in the house)
It is possible that due to the fail ed or corroded Cyclone tie down….. that the cracking
will continue to open-up (especially if there are further high winds experienced at this
house)
The roof structure is able to rack laterally by the application of forces to horizontal
members (which are in the area of the missing Cyclone tie down rod)
In my opinion the tie down should be repaired so that it resists Cyclonic wind loads (as
it was designed to do)
The cracking to the ceiling, cornice and walls (adjacent to the failed Cyclone tie down
rod) is minor and under 0.5mm wide at this stage. This could, however increase
should high winds be experienced before the tie down is repaired to its designed
condition and the roof structure has some additional bracing inserted to prevent any
roof structure racking occurring.
MC concluded there were issues that could cause further water ingress. Indeed, MC
recommended the following:-
In my opinion there are three issues that require attention to ensure that there are no
further moisture ingresses (or that the minor cracking issues do not continue to
become later more serious problems). These are as follows:-
The replacement of a fully operational tie down (to replace the existing
damaged Cyclone tie down)
The bracing of the flexible roof structure (to ensure that no further racking can
occur), and
The sealing along the underside of the whole of the roof capping.
Consequently, the SOW was amended.
Further investigations were undertaken which also led to amendments to the SOW. For
instance, damage to the patio and hot water system were included.
The sheeting on the roof of the complainants’ home was then removed and replaced by WB.
Roofing hold-down upgrades were also installed and inspected for compliance by MC.
Overall, the insurer appointed a number of service providers during the course of the
complaint, including building consultants and engineers. The complainants have since raised
numerous concerns about the quality of the works, including repairs to the roof.
On 23 September 2021 WB provided a final report recommending cash settlement in the sum
of $10,202.28, being a sum intended to cover the works that could not be warranted. This is
generally because of pre-existing structural and maintenance issues. The insurer agreed with
this recommendation.
However, the dispute between the parties continued. Consequently, the insurer arranged for
SC, engineers, to inspect the complainants’ home on 27 June 2022 and comment on any
Determination | Case number: 948431 Page 6 of 12
outstanding de fects. SC’s report dated 3 August 2022 is also comprehensive and logical and
is supported by many helpful photographs. The persistent defects SC noted include, but are
not limited to, internal defects (including cracking in plasterwork), problems with the external
fascia, potential problems with the sarking in the roof and flashing in the roof and the gables,
and issues concerning the brick storeroom.
In sum, it is not disputed the complainants ’ property suffered damage as a result of an
insured event. This complaint concerns the quality of some repairs carried out by the insurer
and its subsequent offer of cash settlement for any outstanding works it says it cannot
warrant.
Complainants’ concerns are extensive
The main concerns of the complainants, together with the insurer’s responses to these
concerns, are listed below. These are also set ou t in the insurer’s Building Coo rdinator Report
dated 15 August 2022.
Internal
i. Cracking to cornice junctions & mitre joins
ii. Cracking to ceiling sheets at junction beading
iii. Residual staining showing through ceiling paint after repairs by builder
iv. Staining/water droplets to underside of lower window sill trim (bedroom only)
v. Staining/water ponded on laundry ceiling from leak in new roof (noted as from the
valley and reported as now repaired from the builder)
vi. Cracking to ceiling sheet in Hallway due to contractor mis-step/dropping item).
The insurer’s conclusion (after reviewing all reports) is: -
As items (i) and (ii) are the result of normal thermal expansion and contraction of
the dwelling that may have been influenced by roof movement during the cyclone
event, the repairs should be included in the claim. However, as the builder is
unable to provide a warranty that further differential movement throughout the
substrates will not occur, we recommend the complainants be suitably
compensated to undertake the repairs
The water staining presenting on the ceilings will require sealing and painting,
however as the above sections (i) and (ii) will require painting once completed, it
would be our recommendation that an additional allowance for sealing the stains
be allowed for and form a part of the repair work compensation to be offered to the
complainants
As the accidental damage under item (v) forms a part of the above areas, we
would recommend the builder provides suitable compensation to cover the costs
of repairs, so the complainants can undertake repairs in conjunction with the
above works.
The insurer’s proposed settlement is: -
Builder to provide a liability SOW for gapping to internal walls and ceilings
(insurer obligation) – Unable to be warranted – Cash Settlement (CS) Only
Builder to provide a liability SOW for stain sealing and painting to ceiling and
walls (Insurer obligation) – Unable to be warranted - CS Only
Builder to provide liability SOW for hallway ceiling repair (builder obligation) –
Unable to be warranted - CS Only.
Determination | Case number: 948431 Page 7 of 12
Patio/Alfresco and rear eves
i. Lap joins on central poly carb sheeting incorrect orientation
ii. Missing fixings/screws
iii. Apron flashing/sealing between alfresco and roof sheet termination missing
iv. Alfresco to rafter bracket penetration through fascia not sealed
v. Timber framed alfresco side wall not in line with dwelling brick wall
vi. Holes in rear metal fascia from repair to reinstate fascia to rafter ends (filled with putty
and covered with metal plate)
vii. Penetration through eave sheets for hold down rod misplaced and patched poorly
viii. Texture paint to above laundry door damaged during eave replacement
ix. Staining to new eave sheets.
The insurer’s conclusion (after reviewing all reports) is:
The alfresco timber/metal structure has not been impacted by the claimed event
and all reports indicate the damage was superficial and isolated to the corrugated
polycarbonate and metal roof sheeting
We note the alfresco roof pitch would appear less than 3-5 degrees, and
trapezoidal sheeting (Spandek) would be a more suitable replacement in this
instance
We note the timber battens attached to the metal purlins would not meet current
AS 1170.2 Structural Design Actions-Wind Actions
Due to the construction type and the lack of spacing between the alfresco roof
sheet height and main roof sheet termination height, it would be unlikely a change
in pitch or an increase in batten size would be suited to the current timber/metal
structure
Due to the builder being unable to warrant the repair methodology, we would
recommend the complainants be suitably compensated to replace the alfresco
sheeting with Spandek in place of corrugated sheeting
The metal fascia to the alfresco section leading towards the laundry should be
replaced until the nearest termination or join to eliminate the holes installed to
screw attach to the fascia to the rafter ends
Damage to the FC eave sheeting as a result of hold down misplacement should be
repaired by the builder while undertaking the metal fascia replacement
Damage to the wall as consequential damage of the eave lining repair should have
the texture coating reinstated
Due to concerns with underlying and multiple pre-existing coatings on the external
wall the builder would be unable to warrant the repairs and we recommend the
customer is suitably compensated for the repair works.
The insurer’s proposed settlement is: -
o Builder to provide a liability SOW for alfresco roof sheeting as Spandek
(insurer obligation) – Unable to be warranted - CS Only
o Builder to provide liability SOW for apron flashing (insurer obligation) – Unable
to be warranted - CS Only
o Builder to replace metal fascia to alfresco section to nearest termination point
(insurer obligation)- Builder Proceed
o Builder to replace rear eave FC sheeting (builder obligation) - Builder Proceed
Determination | Case number: 948431 Page 8 of 12
o Builder to provide liability SOW to prepare and install texture coating (insurer
obligation) – Unable to be warranted - CS Only.
Garage storage room
i. Water ingress though lower brick course and concrete slab junction
ii. Brick mortar join to third course up from FFL has spalled.
The insurer’s conclusion (after reviewing all reports) is: -
The horizontal cracking to the brickwork mortar joins should be repaired under
the claimed event. The engineer has recommended a suitable repair method
to remove mortar to a depth of 60mm to the internal wall side and install an
epoxy repair mortar
Due to underlying foundation settlement acting on the repair, the builder will be
unable to warrant the repair against further influence from the pre-existing
condition, we recommend the complainant is suitably compensated for the
repair works.
The insurer’s proposed settlement is: -
Builder to provide a liability SOW for mortar repair to garage storage room
(insurer obligation) – Unable to be warranted - CS Only.
Roof structures and finishes
Ridge struts not perpendicular to ridge
Sarking eave termination detail differs to engineer ’s drawings, l ap joins tapped,
however section noted as not overlapping
New gable barge flashing to metal fascia junction at gable ends uneven, gaps and
warped
Gable barge flashing ridge junction covered with decretive flower detail
Gable barge flashing around vent pipe detail poor
Gable barge flashing and fascia junction to front elevation near antenna skew
Flume to ridge over living/kitchen, base of rear flue plate folded down with potential to
direct water to under ridge flashing-lower flume attachment plate coverage past roof
penetration not enough
Confirm HWS bracket fixings sealed correctly
Waxy/oil/substance allowing dust to attach to metal roof surface
Tiedown attachment to wall, was originally installed incorrectly (to brick course), has
now been installed to concrete slab edge as required
Periodic roof maintenance to include tensioning of roof screws
Metal angle installed across the eave section of metal roofing not reinstated to new
roof structure
Damage to left elevation rear metal fascia from impact (Customer has advised gate
may have impacted when dislodged during event).
The insurer’s conclusion s (after reviewing all reports) is:-
The builder should rectify the sarking lap join above the manhole with a
suitable method supplied by the manufacturer
Determination | Case number: 948431 Page 9 of 12
Gable barge flashings require design and replacement to prevent oil canning,
reduce exposure of fixings and secure the down turn to the end rafter or
suitable metal/timber roof structural component
The original flume should be replaced and ensure the design is in line with
NCC Volume 2 2019 Part 3.5.1.7 section (a) iv and design considerations
under HB 39-2015 Section 8.6
The builder should undertake works to seal the fixings between the HWS
bracket underside and the roof sheeting to weatherproof the roof structure
The contaminated section of roof sheeting requires cleaning by the builder to
reduce the attraction and collection of dust on the roof sheets near the HWS
An assessor be appointed to determine coverage on the reported impact
damage, if the damage is accepted under the event, the metal fascia should
be replaced to the nearest junction/termination point.
The insurer’s proposed settlement is:
Builder to undertake rectification works to sarking join above manhole (builder
obligation)
Builder to design and install suitable gable flashings (builder obligation). (This
will require customer to complete last item Metal Gable replacement prior to
being undertaken by builder)
Builder to supply and install new flume (insurer obligation) - Builder Proceed
Builder to complete sealing of the HWS bracket (builder obligation) - Builder
Proceed
Builder to lean metal roof sheeting around HWS (builder obligation) - Builder
Proceed
Builder to provide liability SOW for metal gable fascia replacement for
assessor review (insurer obligation) - Unable to be warranted - CS Only.
I note the complainants raised additional concerns following receipt of the insurer’s report
dated 15 August 2022. These concerns appear to have been addressed in a second Building
Coordinator Report from the insurer dated 5 October 2022.
After reviewing all of these documents, together with the balance of the evidence available, I
am satisfied the items listed for cash settlement can be paid to the complainants, plus a 20%
uplift/contingency. This is reasonable given the breakdown in the relationship between the
complainants and the insurer’s appointed service providers.
Insurer has not addressed issues about repairs to roof and materials used
The complainants say water damage has occurred to the roof eaves since the repairs were
completed by WB. They say this is due to poor workmanship and that Bradfords Polyair (high
grade insulation) was not used, despite the insurer saying it was.
The complainant says they spoke to a consultant from Bradfords who said it was not their
product (as it has an identification mark on it) and what was installed was done poorly. The
complainants sought answers from the insurer and its builder about this issue, but the
information made available does not show these questions were answered properly.
Determination | Case number: 948431 Page 10 of 12
Should the complainant provide written advice from Bradfords that its product has not been
used in these repairs, the insurer is to complete the repairs again, provide proof of the correct
product used, and guarantee the repairs.
Complainants ’ other concerns not supported by expert opinion
As set out above, the complainants have raised numerous issues relating to the quality of
repairs completed and have refused the cash settlement offer by the insurer. The
complainants say the insurer should be compelled to complete the works.
It is clear from the extensive correspondence provided that the relationship between the
complainants and the insurer and its service providers has deteriorated.
However, I note the complainants have not provided any expert reports or opinion to support
their claims that the repairs are of poor quality, or to refute the conclusions of the insurer set
out above, or the insurer’s proposed resolutions. The arguments made by the complainants,
in the absence of supporting evidence, does not assist their cause.
2.2 Should the insurer pay non-financial loss compensation?
Non-financial compensation is warranted
Under the AFCA rules, non-financial loss compensation (capped at $5,400) may be awarded
in circumstances where a complainant has suffered an unusual degree or extent of physical
inconvenience, time taken to resolve the situation or interference with their expectation of
enjoyment or peace of mind.
AFCA takes a conservative approach to compensation for non-financial loss. It is not awarded
when a person suffers the normal degree of inconvenience when a problem occurs.
Moreover, non-financial loss is not intended to be a punishment for any wrongdoing on the
part of the insurer.
I accept the complainants in this matter have suffered an unusual degree of physical
inconvenience and interference with their expectation of enjoyment and peace of mind.
For instance, ongoing disputes about the quality of works completed, and about the way
forward in this claim, have no doubt taken a toll on the complainants.
The complainants have also alleged the insurer deliberately withheld reports and information,
that service providers were incompetent, colluded with the insurer, and lied and falsified
information about the repairs and materials used.
The insurer acknowledges not all reports and requested correspondence were provided to the
complainants in a timely manner. However, the information made available does not show
any of the information not provided was relevant to its decisions on liability or proposed
settlement.
In all the circumstances, I am not satisfied the insurer has conspired to withhold information
or has been dishonest. However, on numerous occasions the insurer failed to respond to
reasonable queries from the complainants in a timely manner, if at all.
The insurer has not managed the complaint well. On numerous occasions it was asked for
information and responses which were not provided, in full or at all.
Determination | Case number: 948431 Page 11 of 12
All of these factors have interfered with the complainants’ expectation of enjoyment and their
peace of mind. It follows the insurer should pay the complainants, jointly, $3,000 in non-
financial loss compensation.
2.3 Claim should be resolved in this way
Insurer’s offer of ca sh settlement must include uplift/contingency
Within 14 days notice that the complainants accept this determination, the insurer must:-
Pay to the complainants a cash settlement for all listed works and rectifications set out
in section 2.1 above that have been listed for cash settlement, plus a 20%
uplift/contingency on top of this to factor in the risk of the works passing to the
complainants and the likely possibility that further works may be required; and
Provide to the complainants clear and precise details setting out how the total sum of
such cash settlement has been calculated; and
Pay to the complainants, jointly, the sum of $3,000 in non-financial loss compensation.
In addition, and within 14 days of the complainants establishing that the incorrect product was
used during repairs to the roof, the insurer must arrange to rectify such works using the
correct products as soon as possible.
Given the issues that now exists between the parties, and the claim delays that have already
occurred, I emphasize that time is of the essence regarding all remaining works and
rectifications to be completed by the insurer.
Finally, I note the complainants have raised concerns about premium increases in several
recent emails. These concerns do not form part of this complaint. The complainants should
direct any concerns they have regarding premium increases directly to the insurer. The
insurer can then address those concerns via the usual processes. If the complainants then
remained dissatisfied with the insurer ’s response, they may be entitled to lodge another
complaint with AFCA.
2.4 Why is the outcome fair?
The outcome is fair because the insurer is entitled to choose how it settles claims. In this
instance, there have also been numerous issues between the complainants and the insurer
and its service providers and a cash settlement for the majority of the repairs (aside from the
roof repairs) is appropriate.
Determination | Case number: 948431 Page 12 of 12
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:-
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:-
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.