Home / Suncorp Group / Determination 942700
Determination 942700
Claim declined for storm damage to garage wall on basis of ground movement, seepage and defect exclusions
Summary
Complainants' garage wall cracked after a major storm and the insurer declined the claim relying on ground movement, seepage and defect exclusions. AFCA found the storm was the proximate cause, no exclusion applied, and ordered repair or cash settlement with a 20% uplift plus $2,250 toward the engineer's report.
Complainants established a valid storm claim and the insurer failed to prove any exclusion applied under the policy wording.
Issues
- Claim denial primary · upheld
“The panel is not satisfied the insurer has proven a valid exclusion applies to the claimed damage.”
- Claim amount dispute secondary · upheld
“complainants' quote includes work outside insurer's liability; insurer to produce scope of works and actionable quote”
- Inadequate claim investigation secondary · upheld
“insurer repeatedly referred to the garage wall as a retaining wall; not recognised until referred to AFCA”
- Product terms interpretation secondary · upheld
“Added weight of rainwater cannot fairly be considered 'any other earth movement'; seepage must be continuous”
Subjects and remedies
home or building damagenatural disasterpay claimpay compensationrepair or rectify
Text of the determination
Determination
Case number 942700
Financial firm AAI Limited
Determination | Case number: 942700 Page 1 of 8
Case number: 942700 18 December 2023
1 Determination overview
1.1 Complaint
The complainants lodged a claim on their home and contents insurance policy after the
southern wall of their garage cracked following a storm on 27 February 2022.
The insurer declined the claim and says the damage is not attributable to a single storm or
insured event. It says the damage is ongoing and the result of gradual deterioration, ground
movement, and building defects, all of which are excluded from cover.
The complainants disagree with the insurer‟s application of the exclusions and say the storm
is the cause of damage. They are seeking cover for the cost of repairing the wall.
1.2 Issues and key findings
Have the complainants established a claim within the terms of the policy?
Yes. The complainants have established a valid claim under the terms of the policy.
Is the insurer entitled to decline the claim?
No. The panel is not satisfied the damage was caused by earth movement or seepage of
water as defined in the policy or that the garage wall was defective when it was built.
How should the claim be settled?
The insurer is to either complete repairs or cash settle the claim based upon an actionable
quotation. If the insurer chooses to cash settle the claim, it must add a 20% uplift to the
actionable quote to allow for the transfer of risk and any contingencies.
Why is the outcome fair?
The outcome is fair in all the circumstances as the damage was caused by the storm and the
insurer has not shown an exclusion applies to allow it to decline the claim.
1.3 Determination
This determination is in favour of the complainants. Within 14 days of notification of the
complainants accepting this determination the insurer is to:
appoint a structural engineer and builder to prepare a scope of works (SOW) and
actionable quote to complete the repairs to the garage wall.
on receipt of the SOW and actionable quote the insurer is to either appoint the builder to
complete the repairs or cash settle the claim based on the actionable quote
if cash settled the insurer is to increase the actionable quote by 20% to allow for possible
contingencies
Determination | Case number: 942700 Page 2 of 8
2 Reasons for determination
2.1 Have the complainants established a claim within the terms
of the policy?
Yes. The complainants have established a valid claim with the terms of the policy.
Complainants must show a valid claim
It is established insurance law that an insured has the initial onus to prove on the balance of
probabilities (that is more likely than not) that the loss or damage claimed falls within the
terms of the policy. This is commonly called a prima facie or valid claim.
The complainants home and contents policy is an insured events policy providing cover for a
series of insured events including storm. Cover is subject to various conditions and
exclusions.
Circumstances of loss.
The complainants‟ property is in Queensland and was subject to the Catastrophe 221 storm
event that occurred on 27 February 2022. The severe storm discharged substantial rainwater
and rainwater run-off. This is not disputed.
The complainants supplied an historic record of major rain events, sourced from the Bureau
of Meteorology. According to the records, rainfall measured during this storm was more than
1000 mm; the highest of any major rain event recorded by Alderley station. The panel is
satisfied this information confirms the insured property experienced an exceptional and
unusual amount of rainfall.
The complainants say significant rainfall during the storm added extra weight to the soil
against the garage wall. They say the added weight overloaded the wall and caused it to
crack. The complainants maintain that there was no evidence of the wall cracking prior to the
event. They had purchased to property in July 2021. A pre-purchase inspection report from
BP confirms that while there were signs of efflorescence to an internal wall there was no
structural damage present.
The complainants, both engineers, provided their own report including commentary and pre-
event photographs of the wall. The photographs confirm that at the time of the pre-purchase
inspection in May 2021 there was no cracking to the wall.
To support their position the complainants appointed engineer AE to assess the damage and
comment on the contributing factors. With respect to the cause of the damage, AE concluded:
The crack visible on the southern wall is consistent with wall movement, which
may be attributed to one or both of the following reasons:
a) A change in earth pressure on the retained side of the wall due to external
factors (e.g. saturated due to prolonged wetting).
b) Differential ground movement in the form of subsidence, which can be caused
by changes in ground moisture levels or sub-soil erosion.
Determination | Case number: 942700 Page 3 of 8
Insurer says damage occurred over time
The insurer says the damage was not caused by a storm. Rather, it says the storm only
exacerbated the underlying condition of the wall.
The insurer says efflorescence indicates the damage has been occurring over a long period
of time. The insurer‟s experts say efflorescence indicates hydrostatic pressure had built up
behind the wall over time.
To support its position, the insurer engaged builder (A) and engineer (KM) to inspect and
report on the cause of the damage.
Builder A concluded the crack was likely present for a period of time and is not related to the
storm. Builder A said the efflorescence present shows water seepage through the wall. In this
regard, engineer KM disagrees with builder A. They conclude the storm did contribute to the
loss but was not the sole contributing factor.
They concluded the crack:
…could not be solely attri buted to the February 2022 storm event. The movement
of this wall would have occurred over the life of the structure with the storm event
exacerbating the damage observed.
During the 2022 February storm event, the soil behind the retaining wall would
have become saturated and added horizontal water pressure in combination with
the earth pressure on the retaining wall.
The complainants have expressed concern over KM‟s qualifications. Having reviewed the
available material, the Panel is satisfied KM‟s report was reviewed by a member of the
Registered Professional Engineers of Queensland (RPEQ) and is therefore appropriate to
consider.
Available information on balance, shows proximate cause of damage was the
storm event
The panel is not satisfied the evidence shows damage to the retaining wall occurred over
time. Rather the information shows, the damage on balance was caused by a single event.
The panel has reviewed the photographs supplied by the complainants of the wall before the
storm and the pictures provided in the expert reports. Although the complainants‟ images are
somewhat blurry, the panel is satisfied the photos show a significant increase in efflorescence
following the storm.
The panel accepts that efflorescence is caused by water pressure against the wall. The
significant increase indicates the storm caused a much higher pressure behind the wall during
the storm. The panel is satisfied there was an exceptional and unusual amount of rainfall
preceding the damage to the garage wall. Because the wall successfully retained earth from
its construction in 1975, it is reasonable to conclude this historic storm was the dominant
cause of collapse.
Both parties‟ engineers agree the rain would have added weight to the soil behind the wall.
The amount of rain was unusually high and would have contributed significant weight against
Determination | Case number: 942700 Page 4 of 8
the wall. While KM opines the movement of the wall would have occurred over the life of the
structure, they say:
This method of brickwork retaining wall construction is non-ductile and would not
provide progressive collapse like a standard retaining wall with steel
reinforcement would (e.g. a reinforced concrete or blockwork retaining wall) as the
steel progressively yields during failure.
Complainants have established claim falls within terms of policy
Because the failure was sudden and there is no information to show the wall moved prior to
the storm, the panel is persuaded the damage did not occur over time.
The panel is satisfied the information provided shows the complainants established a valid
claim. Because the complainants established a valid claim, the onus shifts to the insurer to
show an exclusion applies.
2.2 Is the insurer entitled to decline the claim?
No. The panel is not satisfied the damage was caused by earth movement or seepage of
water as defined in the policy or that the garage wall was defective when it was built.
Onus shifts to insurer to show it is entitled to deny valid claim
Once the complainant establishes a valid claim under the terms of the policy, the onus shifts
to the insurer to establish a condition or exclusion applies if it is to refuse the claim.
Insurer liable for claim
The insurer says exclusions for loss caused by ground movement, seepage of water and
building defects apply. The panel has considered each of these exclusions as defined in the
policy and does not agree the exclusions apply.
The exclusion for ground movement is provided on page 27 of the Product Disclosure
Statement (PDS).
Things we don‟t cover
Loss or damage to, or caused by, connected with or arising from, or liability
caused by, connected with or arising from:
Ground movement
erosion, vibration subsidence, landslip, mudslide, collapse, shrinkage or any other
earth movement, but we will cover landslide or subsidence that is specifically
covered under the following insured events:
- …
- „Storm‟ page 41;…
The write back for landslide and subsidence which occurs following a storm event is not
relevant to the complaint. This is because neither party has argued landslide or subsidence
has contributed to the damage.
Determination | Case number: 942700 Page 5 of 8
The earth movement exclusion does not align with the description of how the experts say the
loss occurred. The experts say the crack formed when the storm added water weight behind
the wall, causing it to fail. Therefore, the panel is satisfied the insurer has not shown erosion,
vibration subsidence, landslip, mudslide, collapse, shrinkage or any other earth movement
has contributed to the damage. Further, the panel is not satisfied the added weight of
rainwater can fairly be considered „any other earth movement‟.
The PDS provides the following definition for seepage of water on page 29:
Seepage of water
water seeping or running:
‒ through the earth (hydrostatic water seepage);
‒ down the sides of earth or earth fill that is up against the building;
‒ down the sides or underneath swimming pools or spas or underground tanks;
‒ against or through retaining walls;
‒ from agricultural or overflow pipes.
In the context of the policy and common understanding, for water to be considered seeping or
running, the movement must be continuous. The Macquarie dictionary defines seep as:
Verb 1. To pass gradually, as liquid through a porous substance; ooze.
The storm contributing water to the soil was sudden and not gradual, and therefore the
seeping water exclusion would not apply in this case.
KM says the wall likely had design defects. They do not consider a wall of its kind sufficient to
retain the two meters of earth. To show the wall is defective by way of design or
workmanship, the insurer would need to show its construction did not comply with the
relevant building code. The insurer has not done so.
Further the panel notes the insurer has repeatedly referred to the garage wall as a “retaining
wall”. It is not a retaining wall as defined within the terms of the policy. This was not
recognised by the insurer until the matter was referred to AFCA. The wall may not have been
a suitable design for a retaining wall, but it was suitable for a garage wall.
Further, the wall stood for over 40 years without failure until a historic storm occurred. This
does not suggest any defect in design or workmanship. The panel is not satisfied the
exclusion for defects, faults and workmanship applies.
Therefore, having regard to the policy wording the panel is not satisfied the insurer has
proven a valid exclusion applies to the claimed damage. Because the insurer has not proven
the claim is excluded, it is required to cover the claim in accordance with the policy terms.
2.3 How should the claim be settled?
The insurer is to either complete repairs or cash settle the claim based upon an actionable
quotation. If the insurer chooses to cash settle the complainants, it must add a 20% uplift to
the actionable quotation to allow for the transfer of risk and any contingencies.
Determination | Case number: 942700 Page 6 of 8
The complainants say the wall must be rebuilt
The complainants seek a full rebuild of the garage. They say the wall is not repairable due to
the nature of the damage, and it is not possible to replace only the damaged section. They
say the wall must be removed and replaced, and the roof of the garage cannot remain
standing during rectification.
The crack in the wall is not repairable and due to physical, structural limitations is
not possible to replace “only” the damaged section of the wall. The entire
damaged wall needs to be removed and replaced. It is not possible for the other
walls or the roof of the garage wall to remain standing during this works for safety
reasons.
The policy says the insurer will either authorise repairs or rebuilt the damage to a building.
Page 78 of the PDS says:
Repairing or rebuilding damaged parts
We will only repair or rebuild the parts that are damaged where the damage is
covered by your policy. Apart from the limited circumstances where we will repair
or rebuild undamaged parts (see „When we will pay extra in relation to
undamaged parts‟ pa ge 79) this policy does not cover you to replace undamaged
parts, such as when:
[…]
an external wall is damaged we will replace the damaged parts of the wall, not
undamaged areas of the wall or other sides of the building.
Page 79 of the PDS explains that the only circumstances the insurer will cover undamaged
parts of the building is when it is unable to match materials such as floor tiles, wall paper,
paint, wall coverings or floor coverings. The panel is satisfied it is fair that this is not
applicab le in the complainants‟ circumstances given it involves an external wall.
The complainants’ quote includes work outside of the insurer’s liability
The complainants provided a quote for demolition and construction of a blockwork wall to
replace the damaged wall. Builder S provided a quote for $108,800 not including GST for the
following scope of works:
removal stacking and reinstallation of the entire roof structure
demolition of brick walls and provision of a reinforced concrete block retaining wall to the
Southern and Western Walls including a new reinforced concrete footing and waterproof
membrane
demolition of brick walls and provision of a concrete block only wall to the Northern wall
painting of all external walls upon completion
reinstatement of the concrete path above the Southern wall
removal and reinstatement of the existing pool fence to enable the walls construction
Determination | Case number: 942700 Page 7 of 8
works area will be left clean and tidy
removal of works generated spoil, waste and rubbish.
The complainants‟ position is that repairs require the demolition of the undamaged walls.
They have not provided evidence in support of this. Based on the available information, the
insurer‟s liability is limited to the cracked southern garage wall. The panel agrees the entire
southern wall must be demolished and rebuilt, however, evidence has not been provided
showing the other walls of the garage must be rebuilt. The complainants submit the other
walls and roof of the garage cannot remain standing during the rectification.
The scope of works therefore includes items that may fall out side of the insurer‟s liability. The
insurer is not liable for rebuilding the undamaged western walls, and because the original
walls were not painted, painting the walls.
The insurer is to produce a scope of works
It is fair that within 14 days of notification of the complainants accepting this determination the
insurer must:
appoint a structural engineer and builder to prepare a scope of works (SOW) and
actionable quote to complete the repairs to the garage wall.
on receipt of the SOW and actionable quote the insurer is to either appoint the builder to
complete the repairs or cash settle the claim based on the actionable quote
if cash settled the insurer is to increase the actionable quote by 20% to allow for possible
contingencies
2.4 Should the insurer contribute to the complainant’s
professional costs?
Yes. The insurer should pay the complainants $2,250 as contribution to the costs of the report
from AE.
AFCA can determine an insurer contributes to professional costs incurred
Under AFCA rule D.5 the panel can determine an insurer contributes up to $5,000 to
professional costs necessarily incurred by a complainant in the course of the complaint.
The panel is of the opinion the report was necessarily obtained to address the issues raised
by the insurer and assisted resolving the complaint. The complainants‟ engineer‟s report
assisted investigation of the damage.
It is fair in the circumstances that the insurer reimburses the complainant for the cost of AE ‟s
report being $2,250, upon provision of the paid invoice.
2.5 Why is the outcome fair?
The complainants have shown the proximate cause of garage wall damage was the storm.
The insurer has not shown a valid exclusion applies, and therefore must cover the claim.
Given the issues in dispute and the weight of available evidence, it would not be fair for the
insurer to deny the claim. Despite this, the available information does not support that the
available scope of works would be fair resolution of the claim. Further investigation of the
insurer‟s liability is warranted, and the insurer may then opt to either organise repair of the
damage or cash settle with a suitable allowance for any contingencies.
Determination | Case number: 942700 Page 8 of 8
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what s fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel
includes:
an ombudsman
a member with significant experience in consumer and small business advocacy
a member with extensive experience in the insurance industry.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.