Settlement amount for building repairs after leaking pipe damage, plus temporary accommodation and expert report costs
Text of the determination
Determination
Case number 942569
Financial firm AAI Limited
Determination | Case number: 942569 Page 1 of 10
Case number: 942569 14 December 2023
1 Determination overview
1.1 Complaint
The complainant held a landlord insurance policy with the financial firm (insurer) for her rental
property. The property was tenanted. The tenant moved out when large cracks were noticed
in the internal walls.
The complainant initially was unable to establish the cause of the problem. A broken pipe was
later found to be discharging liquid and the complainant made a claim with the insurer around
March 2019 for damage to the building and loss of rent.
The insurer accepted the building claim. A dispute arose about the extent of damage caused
by the leaking pipe. The insurer declined the claim for loss of rent relying on its policy
conditions.
Subsequently, a complaint was lodged with AFCA (case number 712690). Under this
complaint, AFCA determined the insurer was required to re-calculate the settlement offer for
the building repairs and make payments, including rental loss for 26 weeks.
The insurer made further assessments and offered the complainant $164,109.21 (including
$2,000 non-financial loss) in resolution of the claim. The complainant is dissatisfied with the
insurer’s settlement offer and asks the insurer to pay $446,951 for building repairs and
$38,475.50 towards temporary accommodation, storage and removalist costs. The
complainant also wants the insurer to pay for her expert fees.
1.2 Issues and key findings
Should the insurer increase its offer for building repairs?
Yes. The insurer should increase its offer as detailed in section 2.1 of this determination to
factor the gaps in the scope of works.
Should the insurer cover the costs relating to temporary accommodation,
storage and contents removal?
No. The insurer’s settlement includes an allowance for furniture removal and storage.
Temporary accommodation is not payable given the property was not the complainant’s place
of residence and the previous determination provided loss of rent.
Is the complainant entitled to recover the costs of dealing with the complaint?
Yes. The complainant has shown it is fair the insurer contributes to the report fees. The
insurer is required to pay $5,000 in this regard.
Should the insurer pay non-financial loss?
Yes. There were aspec ts of the insurer’s claims handling that was unreasonable. This would
have caused an unusual degree of stress and inconvenience. The insurer has offered to pay
$2,000 in non-financial loss for this. This is fair in all the circumstances.
Determination | Case number: 942569 Page 2 of 10
1.3 Determination
This determination is partially in favour of the complainant.
Within 21 days of the insurer receiving notice the complainant accepts the determination, the
insurer is required to pay the complainant the following:
$192,077.59 for the building repairs plus interest as set out in section 2.1
$5,000 for the report fees
$2,000 for non-financial loss compensation.
Determination | Case number: 942569 Page 3 of 10
2 Reasons for determination
2.1 Should the insurer increase its offer for building repairs?
Previous AFCA determination
The previous Determination said the following about how the claim was to be settled:
The parties dispute the fair settlement amount that is consistent with this determination.
Insurer says its cash settlement offer is sufficient
The insurer has offered the complainant $164,109.21 in full and final settlement of the claim
and in consideration of the previous AFCA determination. This offer includes:
> $124,699.39 (Total repair cost $138,989.24 less 50% of the costs relating to the west
wall of $14,289.85)
> 30% contingency of the repair cost totalling $37,409.82
> $2,000 non-financial loss.
The total repair cost was based on a builder A’s SOW and quote. A’s SOW was based on a
SOW done by engineer M.
The insurer says it allowed a 30% contingency in good faith, which is 10% more than the
amount noted under the previous AFCA determination.
Determination | Case number: 942569 Page 4 of 10
Complainant says the insurer’s offer is insufficient
The complainant says the insurer’s offer does not include the full scope of works or actionable
costs based on her discussions with builders and architects. To calculate a more realistic
estimate, the complainant engaged a quantity surveyor (MQ).
MQ estimated the repair cost to be $446,951. In resolution, the complainant asks the insurer
to pay $446,951 for building repairs.
A’s SOW and quote can be used as a starting point
After careful consideration of all the available information, the panel notes the following
regarding both parties quotes and SOW.
The insurer says A’s estimate is actionable. In support of its position, the insurer provided
comments from A which in part says the following:
As discussed, If we were to be engaged in works outside of the insurance
industry, we would look to complete these for the currently forseen and provided
SOW and costing
This indicates the rates provided are market-based and actionable.
The complainant says she was told these rates could not be matched. However, the only
evidence provided in support is from MQ. It is not clear from MQ’s evidence that based on his
research and understanding, the rates and allowances in A’s quote could not be matched by
anyone in the market. For instance, MQ’s evidence is not supported by other contractors
confirming the rates and al lowances in A’s quote as not being reflective of the market.
Instead, MQ’s evidence appears to be an opinion of a reasonable value of the cost to rectify
the property in accordance with the previous AFCA determination. However, there are several
concerns w ith MQ’s estimate.
MQ has quoted a significant sum. The sum quoted exceeds the sum insured applicable at the
time ($393,900). This is despite the fact the works do not require a complete demolishing and
rebuilding of the home.
The panel acknowledges the cost of materials and trade has increased largely since the
policy was issued in 2018. However, this is still a significant sum for works that are not meant
to fully replace the building.
There are also various costings that are large which has not been verified by contractors. For
example, MQ quoted $37,000 for the architect to design a new kitchen, bathroom and
laundry. On the face of it, that seems excessive. Other rates and allowances quotes are
larger than A’s. For instance, electrician rates have been quoted at around $170 per hour
compared to $55. As stated previously, the panel does not accept MQ’s evidence shows A’s
rates and allowance for the agreed parts of the SOW are unreasonable.
Therefore, based on the available information, the panel accepts A’s scope o f works and
estimate can be used as the starting point for calculating the insurer’s liability .
Adjustments to be made in the insurer’s settlement
The complainant says A’s SOW excludes several items. In support, she provided a further
report fr om MQ who reviewed A’s latest SOW.
Determination | Case number: 942569 Page 5 of 10
For completeness, each area has been carefully examined and the panel agrees some items
need to be included in A’s estimate.
Outhouse Laundry/toilet
MQ says A’s quotes does not make allowance for concreting, sarking and insulation.
However, the updated quote from A includes these items. While MQ refer to higher rates, this
is not supported with actionable quote(s) from service providers.
Bathroom
MQ says A’s quote provides a low rate for sarking, insulation and roofing costs. The
difference between MQ and A for this item is $305 plus builder’s margin and GST. MQ’s
position is not supported with actionable quote(s) from service providers. The panel does not
accept MQ has shown A’s rates are unreas onable.
Kitchen
MQ says A’s quote does not include costs to install a smoke detector. The estimated amount
to supply and install the smoke detector is $120 plus builder’s margin and GST .
The insurer says it is not requirement under the current building codes to include this item.
The insurer has not provided satisfactory evidence to show this is not required in the
circumstances. Considering the damage relates to the reinstatement of the kitchen, the panel
considers it reasonable a smoke alarm there be included. It is therefore fair to include this
item plus an additional 30% for contingency.
MQ also says A’s quote excludes the costs of sarking and insulation and roofing. While A’s
quote includes the roofing (flashing, barge, gutters), the insurer does not explain if A’s
estimate also covers the costs relating to sarking and insulation. Therefore, it is fair the
insurer includes these costs b ased on MQ’s estimate of $1,015 plus builder’s margin, GST
and 30% contingency.
Electrical upgrades
MQ says the current electrical switchboard should be updated to current standards. The
insurer says the complainant has not shown this is a requirement and, in their opinion, it is not
a regulation. MQ disagrees and says it is required as per current regulations.
Given the nature and extent of damage, and the age of the home, the panel accepts it is
plausible this upgrade is likely required to complete the electrical works and provide the
relevant warranty. It is fair the insurer includes this cost based o n MQ’s estimate of $680 plus
builder’s margin and GST with an additional 30% for contingency.
Stormwater pipe and CCTV plumbing
MQ’s quote includes cost s to complete CCTV plumbing and tapping into the existing storm
water and sewer pipes. To this, the insurer says such costs are not related to the previous
AFCA determination. MQ disagrees and says these works are necessary to connect the new
portion of the property to the storm water connections and ensure there are no further
movements.
It is unclear why additional stormwater pipes, pits and modifications to the existing framework
are necessary to do the claim related works. In particular, MQ’s SOW includes installi ng 12lm
of PVC pipes along with a pit. Whilst MQ refers to AS/NZ 3500.3, the relevant standard has
not been included. Neither has an explanation been provided to show why these works are
necessary to comply with that standard.
Determination | Case number: 942569 Page 6 of 10
The insurer’s SOW says it can connect the fittings to the existing framework. This appears
plausible. Therefore, the panel does not accept these works are required.
Landscaping
MQ’s quote includes cost for minor reinstatement and making good the existing landscaping.
Further, it includes costs to reinstate the timber fence and gate as well as the cost to
excavate site. To this, the insurer says this damage is not related to the claimed event. MQ
disagrees and submits these costs relate to reinstating the landscaping (surrounding the area
of works) to its original state.
It is likely these areas will be damaged during the required repairs. The policy does have a
limit of $1,000 for trees, shrubs, plants, hedges or garden beds. Neither the complainant nor
MQ has provided any reason as to why this limit would not apply regarding the ‘Minor
reinstatement and make good to existing soft Landscaping’. Therefore, those works should be
capped at $1,000.
This limit would not apply to the timber fence or gate. Neither would it apply for the excavation
of the site. Therefore, the panel considers it fair that they be included in full. The total cost for
the remaining items is $3,1 90 plus builder’s margin, GST and a 30% contingency.
Hallway
MQ says various preliminary costings for this item was not set out in A’s SOW. The panel
disagrees. A’s SOW did not separate the hallway from the other items when setting out the
preliminaries. In reviewing the preliminaries, the various items in MQ’s quote appear to be
included in A’s SOW . Therefore, the panel does not accept further additional costings are
required.
MQ says A’s SOW does not include the item for disconnecting all structural connections to
brickwork. The panel cannot see this has been included in A’s SOW for the hallway. There is
nothing to refute MQ’s evidence. Therefore, t his should be included. The cost is $2,080 plus
builder’s margin, GST and 30% contingency.
MQ also says A’s SOW does not include scaffolding and rigid board insulation to the
brickworks. The panel notes scaffolding has been included in A’s preliminaries. This
presumably would include the hallway. The panel cannot see the rigid board insulation being
included. This should be added at $1,705 plus builder’s margin, GST and 30% contingency.
Preliminaries and architectural fees
MQ’s overall cost estimate for the preliminari es (equipment hire , engineering, architect’s fees)
are much higher than A’s estimate. For example, A allows approximately $5,000 for design
and engineering. In contrast, MQ estimates the architect’s fees alone at $37,000. This
amount is significant and not substantiated from any architect.
Therefore, the panel maintains that A’s rates are reasonable to be used as a starting point.
Having said that, the panel notes the following.
A has allowed only $3,000 for the architect. The architect is required to redesign the laundry,
bathroom and kitchen. These are essential items with several moving parts. It is part of an
older home which would likely require various factors to consider. Therefore, this seems low.
The panel considers a fairer allowance to be $10,000 (inclusive of builder’s margin, GST and
contingency).
Determination | Case number: 942569 Page 7 of 10
On the other items that are included in both MQ’s and A’s SOWs , the panel accepts it is
reasonable to rely on A’s rates for the reasons previously articulated.
MQ says a town planning permit would be required. The insurer’s building co -ordinator
disagreed. MQ provided a link to the VBA website confirming this. However, the website does
not clarify when a town planner would be required for renovations. Despite this, the panel
notes there is a substantial amount of work being undertaken. This includes designing three
essential areas. In this regard, the panel considers it likely this may be necessary. Therefore
this cost of $3,500 plus builder’s margin, GST and 30% contingency should be added.
MQ included six monthly builder’s clean. The insurer’s building co -ordinator said this is not
required as the contractors would be required to clean up after themselves. Further, the panel
notes A has included at least one builder’s clean. The panel prefers A’s costi ng in this regard
as it is unlikely a builder’s clean would be required every month .
MQ included contractor’s all risk insurance. The insurer says this is provided to the builder
and is a cost borne by the builder. MQ says builders pass this cost. The panel does not agree
with MQ that this is a specific item that is always billed as a separate item to customers. A’s
SOW indicates otherwise. This is not to be included.
There is a large discrepancy for site supervision. MQ allowed $31,752 plus builder’s margi n,
GST and contingency. This, on the face of it, is excessive. A has allowed for 81 hours. This
appears sufficient and is preferred.
MQ says demolition has not been included. However, demolition allowances have been
included for the specific areas in A’s SOW. It is not clear why this should also included in the
preliminaries as yet another item. The panel does not accept this should be added.
Claim should be settled in this manner
In calculating the additional amounts that were based on MQ’s costing, the panel considers it
fair to use MQ’s builder’s margin of 25% plus GST and 30% contingency. This means the
insurer should pay an additional $29,968.38 towards the building repairs based on the
following amounts explained above:
Item Amount
Smoke detector $ 2 14.50
Kitchen sarking/insulation $1, 814.31
Electrical switchboard $ 1, 215 . 5 0
Soft Landscaping (subject to policy limit) $1,000
Landscaping (excluding soft landscaping) $5,702.13
Disconnect structural connections $3,718
Rigid board insulation $3,047.69
Determination | Case number: 942569 Page 8 of 10
Town planner $6,256.25
Architect $7,000
The insurer should also pay interest on this additional amount. Interest is to be calculated
pursuant to section 57 of the Insurance Contracts Act 1984. Interest is payable from 24
November 2022, being about one month after MQ’s report setting out these costings, until
payment is made.
The panel considers it fair to apply interest in this way because:
the additional amounts are based on MQ’s figures which were issued on 24 October 2022
an allowance of one month for the figures to be considered and assessed by the insurer
the amounts were likely out of date after about a month
2.2 Should the insurer cover the costs relating to temporary
accommodation, storage and contents removal?
Complainant says insurer is liable for these costs
The complainant says she will incur additional costs during the repairs such as:
> Removalist’s costs for the contents.
> Temporary accommodation during the repairs.
> Temporary storage for the contents.
A’s SOW includes furniture removal and storage. Therefore, the panel does not accept an
additional allowance is required.
This property was not used as the complainant’s residence. It was an investment property
that was tenanted. As a result, the complainant was settled for loss of rent in the previous
determination. Given this, the panel does not accept there is any basis to include temporary
accommodation.
2.3 Is the complainant entitled to recover the costs of dealing
with the complaint?
Complainant seeks cover for the report fees
The complainant says she engaged MQ to identify the gaps in A’s scope of works and
estimates. She asks the insurer to cover the costs incurred for the report fees ($7,252.35) as
this was a necessary to obtain a realistic and detailed assessment.
It is fair the insurer pays $5,000 for the report fees
Under Rule D.5, AFCA may decide a financial firm contribute to the professional costs
incurred by a complainant in the course of a complaint. These costs can be awarded if the
complainant needed an expert to understand or establish their claim. These costs are
normally capped at $5,000 unless exceptional circumstances apply.
The available information demonstrates A’s estimates have been altered due to the gaps
identified by MQ. Therefore, MQ’s reports assiste d in the complaint. The panel considers it
reasonable for the insurer to contribute to the fees incurred.
Determination | Case number: 942569 Page 9 of 10
However, the panel does not accept exceptional circumstances apply. This is because the
insurer’s settlement was mainly supported compared to MQ. In s uch circumstances, the panel
does not accept it is fair for the insurer to contribute more than the $5,000 normally allowed
for professional costs.
2.4 Should the insurer pay non-financial loss?
Compensation is awarded conservatively
Under the AFCA Rules, we may award compensation (capped at $5,400) for non-financial
loss. This is where a complainant has suffered an unusual degree or extent of physical
inconvenience, time taken to resolve the situation or interference with their expectation of
enjoyment or pea ce of mind due to the insurer’s conduct.
We take a conservative approach to compensation for non-financial loss. It is not awarded
when a person suffers the normal degree of inconvenience when a problem occurs.
Insurer ’s offer to pay $2,000 in non-financial loss is reasonable
It is clear the process involved following the previous determination has been protracted.
Also, the complainant had to produce expert evidence again to dispute the insurer’s works
which resulted in a greater settlement.
This process likely caused an unusual degree of stress and inconvenience on an already very
protracted claim.
However, part of the delay was the complainant seeking a remedy that was mainly
unsubstantiated. In such regard, the inconvenience and stress associated with the progress
after the previous determination was not all caused by the insurer.
The insurer offered to pay $2,000. The panel accepts this is reasonable and consistent with
AFCA’s approach. Therefore, it is fair the insurer pays the complainant $2,000 in non-
financial loss as offered.
2.5 Why is the outcome fair?
It is fair the insurer’s cash settlement is increased to reflect the costs applicable to the
complainant to carry out the repairs accepted under the claim. As the reports from the
complainant’s expert assisted in making adjustments to the scope of works, it is fair the
insurer contributes to the report fees. Overall, the insurer has taken an unusual length of time
to resolve the issues surrounding the scope of works. This caused unnecessary
inconvenience and stress. It is fair the insurer pays non-financial loss compensation.
Determination | Case number: 942569 Page 10 of 10
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel
includes:
an ombudsman
a member with significant experience in consumer and small business advocacy
a member with extensive experience in the insurance industry.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.