Adequacy of cash settlement offer for storm water damage repairs, interest and non-financial loss for claim handling delays
Text of the determination
Determination
Case number 942412
Financial firm Defence Service Homes Insurance Scheme
Determination | Case number: 942412 Page 1 of 7
Case number: 942412 5 September 2023
1 Determination overview
1.1 Complaint
The complainant represents his parents, RA and RJ, who hold home building insurance with
the financial firm (insurer). In this determination the complainant, RA and RJ will be referred
to as ‘the complainant’ unless context requires otherwise.
On 2 March 2022, the complainant lodged a claim following water ingress during a storm on
28 February 2022. The insurer has agreed to cover the cost of repairing a bedroom ceiling
and the study ceiling and walls. It has offered a $15,000 cash settlement, based on quotes
from builder TB, plus allowances for contingencies and temporary accommodation (TA).
The complainant says the insurer’s cash settlement offer is inadequate to cover the cost of
claim related repairs. He seeks a cash settlement of around $40,000 based on a quote from
builder TD, plus TA. In addition, because of the insurer’s poor claim handling and delays, he
seeks interest and non-financial loss compensation.
1.2 Issues and key findings
Is the insurer required to pay more as a cash settlement?
No. T he insurer’s offer reasonably allows for the cost of claim related repairs, contingencies
and TA. The insurer has also said that if mould is found in the walls and is directly related to
the water ingress, it will treat that as separate and in addition to the cash settlement offer.
Is the complainant entitled to interest?
No. The insurer has on balance not unreasonably withheld payment of the cash settlement.
Is non-financial loss compensation payable?
Yes. The insurer contributed to some of the delays experienced, which has caused the
complainant stress and inconvenience. The insurer is to pay $500 in compensation.
Why is the outcome fair?
The insurer’s offer reasonably allows for the cost of claim related repairs, contingencies and
TA. It has also said it will separately cover mould found in the walls that is directly related to
the water ingress. It would not be fair to require the insurer to pay more for the claim. It is fair
that the insurer pays $500 in compensation as it contributed to the delays experienced.
1.3 Determination
This determination is substantially in favour of the insurer.
Within 14 days of RA and RJ accepting this determination, the insurer is to pay them:
$15,000 as a cash settlement
$500 (in total) in non-financial loss compensation.
The insurer is also to assess any subsequent mould claim in accordance with its offer.
Determination | Case number: 942412 Page 2 of 7
2 Reasons for determination
The parties provided several submissions to AFCA. While this determination does not refer to
each submission, I have taken them all into account in reaching my decision.
2.1 Is the insurer required to pay more as a cash settlement?
No. The insurer’s offer reasonably allows for the cost of claim related repairs, contingencies
and TA. The insurer has also said that if mould is found in the walls and is directly related to
the water ingress, it will treat that as separate and in addition to the cash settlement offer.
Insurer has offered a cash settlement
On 2 March 2022, the complainant lodged a claim on his home building insurance after his
home sustained damage during a storm on 28 February 2022. He also lodged a claim on his
contents insurance, which was issued by another financial firm. The contents claim is not the
subject of this determination.
On 3 March 2022, the insurer appointed TB to attend to make safe repairs and to assess the
damage resulting from the storm. The insurer and TB say that TB repeatedly tried to contact
the complainant from 3 March 2022 but was only able to do so on 11 April 2022.
On 22 April 2022, TB attended to make safe repairs. Those repairs were limited to electrical
work as water was reported to have dripped out of light fittings in a bedroom and the study.
No other hazards or breaches to structural integrity were observed. Photos were taken, some
of which showed a small hole in the study ceiling. This was deemed unrelated to the claim.
At TB’s request, roofer NL inspected the home’s roof on 5 May 2022. NL concluded that the
water ingress into the bedroom had been caused by an overflow of the valleys due to debris
build- up. The water ingress into the study was caused by the roof’s pitch being non -
complainant, leading to water pooling and entry between sheet lap joins.
NL included in its report a photo of the study ceiling, showing the hole had become much
larger. NL noted under the photo, ‘ Insured has removed section of ceiling lining in rear
bedroom due to being soaked with water ’.
After receiving NL’s commentary, TB provided its report to the insurer on 7 July 2022. TB said
the resultant damage to the bedroom and study ceiling was caused by the storm. TB said TA
would not be needed as the home was liveable and would continue to be so during repairs.
TB provided a scope of works (SOW) for claim related repairs, totalling $3,917.58. It included
an allowance for asbestos testing and removal and disposal of damaged sheeting/linings.
TB also submitted a mud map depicting the area of damage. It locates the damaged study
ceiling, watermarks on the partial wall between the bedroom and the study and to a small
section of the bedroom wall. It also identifies damaged carpet in the middle section between
the rooms (on both sides of the partial wall) and stretching into the hall.
In a letter dated 13 July 2022, the insurer told the complainant that subject to the terms of the
product disclosure statement (PDS), it would cover the bedroom and study ceiling damage,
but not damage to external paintwork. The latter is not in dispute.
The complainant informed the insurer he intended to obtain from his own builder a SOW for
the claim related repairs . He provided TD’s SOW to the insurer on 13 September 2022. That
Determination | Case number: 942412 Page 3 of 7
SOW referred to removal of asbestos ceilings and walls. TD had assumed the material was
asbestos given the age of that section of the home.
The parties agreed that the insurer would obtain an asbestos report. TB’s asbestos specialist
inspected the home on 27 October 2022 to collect samples of the ceiling material. On 2
November 2022, TB reported that testing had confirmed the presence of asbestos. A photo
was taken of the hole in the study ceiling, showing its edges had been taped over.
The insurer obtained an updated SOW from TB, which allowed for removal and replacement
of the water affected asbestos walls and ceilings (approximately 22sqm). TB increased its
quote for claim related repairs to $10,156.81. On 10 November 2022, the insurer offered to
pay the complainant that amount as a cash settlement.
On 2 December 2022, the insurer received a report from hygienist HS. Sample testing only
showed asbestos materials in the bedroom and study ceilings, but no asbestos contamination
elsewhere in the home. Noting the large hole in the study ceiling, HS recommended make
safe by way of containment of the damaged ceiling and specialist cleaning of the two rooms.
On the same day, the insurer provided HS’s report to the complainant and offered to:
arrange for the bedroom/study to be sealed and for asbestos removal to occur
as a precautionary measure, arrange TA for the period the asbestos removal would take
(estimated by TB to be approximately one week).
The complainant responded saying he agreed to the rooms’ sealing off and to the provision of
a week’s TA. However, he stated that no other work could be undertaken until the extent and
cost of claim related repairs was resolved (he had by that stage lodged a formal complaint
about those matters with the insurer).
On 5 December 2022, the insurer offered to cash settle the claim for $10,156.81 plus the cost
of a week’s TA. The offer was made in the insurer’s stage one i nternal dispute resolution
(IDR) review response. The complainant did not accept the offer.
On 12 December 2022, the insurer provided its stage two IDR review response. It said:
there was no evidence of asbestos contamination in April 2022, when TB completed make
safe repairs
the asbestos issue was first raised by TD in its SOW provided on 13 September 2022
the complainant was responsible for disturbing the asbestos study ceiling by increasing the
size of the pre-existing small hole
‘any rectification or cl ean-up/testing of asbestos could have [been] transferred to be the
responsibility of the policyholder’
The cash settlement offer remained unchanged
While it was unlikely the wall cavity was mould affected, it was willing to check via an
endoscopic camera
If the check showed walls needed to be replaced, the SOW for claim related repairs would
be updated.
On 16 December 2022, the insurer offered $15,000 as a cash settlement ‘that encompasses
the approved scope of works, seven days accommodation and contingenc ies’. The insurer
also said that if mould was found in the walls and was directly related to the water ingress, it
would be ‘considered separate and in addition to this offer’.
Complainant says the insurer’s offer is inadequate
The complainant says the ins urer’s cash settlement offer is manifestly inadequate.
Determination | Case number: 942412 Page 4 of 7
According to the complainant, there was an extensive delay by the insurer following TB’s
initial attendance at the property. He says:
During this time my father … was required to make a larger hole in the ceiling to
dry out the area and to release any further pooling of water. The smell to the area
was what I could only describe as putrid due to mould forming in the carpet, water
seepage from the walls and the roof cavity. Due to no contact from [the insurer]
my father and brothers removed the water damaged carpet and placed fans into
the area to dry the area out. This also required making the hole larger in the
ceiling to allow water to escape and to dry that part of the damaged area out.
He relies on TD’s SOW and quote dated 7 September 2022, totalling $48,348.32, but
concedes TD has made a miscalculation. The correct total is $34,901.68. The SOW allows for
asbestos removal - 5sqm for the study ceiling, 16sqm for the bedroom ceiling, and 50sqm of
wall sheeting.
The complainant also refers to an SOW builder CS prepared for the contents insurer on 24
June 2022. CS appears to have mistakenly understood that it was to quote on claim related
building repairs. The amount CS quoted was $27,849.14, a significant amount of which
related to the strip out of asbestos ceilings and walls in the quantities TD repeated in its
SOW.
The complainant has previously offered to accept a cash settlement of $37,000.
Insurer is not required to pay more than it has offered
A cash settlement must be based on a reasonable quote for claim related repairs, actionable
by a retail customer. An uplift is then to be applied to the quoted amount to allow for
contingencies and the loss of the lifetime guarantee that applies to insurer approved repairs.
Based on the provided information, I am not satisfied that it would be reasonable to require
the insurer to pay a cash settlement higher than it has offered. This is because:
by refer ence to the provided photos and TB’s mud map, TB’s updated SOW appears to
best reflect the repairs required to address the water damaged building components
the make safe photos TB took on 22 April 2022 do not show any obvious signs of water
pooling on the study ceiling such that it was necessary to significantly expand the hole in
the ceiling (NL noted the ceiling had been soaked based on what the complainant said)
even if it was necessary, there is no persuasive evidence that the complainant approached
the insurer about the issue before making the hole larger
the insurer has nevertheless agreed to pay the cost of rectifying the study ceiling, and has
a made reasonable allowance for damaged asbestos walls
the extent of asbestos removal/replacement TD and CS have allowed for, on balance,
appears to go beyond what is necessary to address the water damage
I am not satisfied that TD’s SOW may be relied upon as reflecting claim related repairs. It
contains a significant mathematical error. It also includes unnecessary allowances for
carpet replacement (contents, so not the responsibility of the insurer), a temporary toilet
(the home’s toilet is functional) and catastrophe levy (not shown to be applicable)
I am also not satisfied that CS’s SOW may reasonably be rel ied upon given that it was not
obtained by either party. Rather, it was prepared by CS for the contents insurer due to a
misunderstanding. As noted above, it’s asbestos removal allowance appears excessive
While they have not been itemised, I am satisfied t he insurer’s offer makes reasonable
allowances for contingencies and TA. For example, assuming a 25% contingencies uplift
Determination | Case number: 942412 Page 5 of 7
(representing the higher end of what AFCA would typically expect), there would still be
$2,304 available for seven days’ TA
The insurer has made clear that if mould is found in the walls and is directly related to the
water ingress, it will treat that as separate and in addition to the cash settlement offer.
2.2 Is the complainant entitled to interest?
No. The insurer has on balance not unreasonably withheld payment of the cash settlement.
Interest is payable from when the insurer unreasonably withheld the claim
The complainant seeks interest on the cash settlement amount payable, on the basis the
insurer continually delayed assessing the claim.
AFCA may award interest on a payment to be made by a financial firm. In relation to general
insurance complaints, Section 57 of the Insurance Contracts Act, 1984 (Cth) is applied. Under
section 57, interest is payable from the day the insurer unreasonably withheld the principal
amount, until it is paid.
Insurer is not required to pay interest
I am not satisfied that it would be reasonable to require the insurer to pay interest on its cash
settlement payment.
The insurer has not unreasonably withheld payment, given that:
as is apparent from the dates and information set out in section 2.1 above, the insurer did
not unduly delay the claim’s progression
rather, difficulties were experienced in contacting the complainant and time was taken by
the complainant obtaining TD’s SOW. Neither of these matters were due to any failing by
the insurer
the complainant has repeatedly rejected the insurer’s cash settlement offer.
2.3 Is non-financial loss compensation payable?
Yes. The insurer contributed to some of the delays experienced, which has caused the
complainant stress and inconvenience. The insurer is to pay $500 in compensation.
AFCA can award compensation for poor claim handling
Under paragraph D.3 of the AFCA Rules, we may award compensation for non-financial loss
(capped at $5,400) where the insurer’s actions have caused an unusual amount of:
physical inconvenience
time taken to resolve the situation
interference with the complainant’s expectation of enjoyment or peace of mind.
Insurer’s claim hand ling has caused some stress and inconvenience
The complainant says he is seeking compensation for:
the stress and mental angst in dealing with the lack of communication by [the
insurer] for over 7 months, the amount of wasted time to try and bring a resolution
to the claim being acknowledged and finalised, and the endless follow up required
to ensure the safety of my father and any person in the home.
Determination | Case number: 942412 Page 6 of 7
In relation to the safety point, the complainant says the insurer should have advised RA that
the ceilings and walls in the two affected rooms were made from asbestos and should not be
touched.
Based on the exchanged information, I am not satisfied that the insurer failed to communicate
for seven months. To the contrary, it appears that the insurer communicated regularly with the
complainant after the initial difficulty making contact.
I also note that the insurer issued its claim decision just outside the standard four-month
period referred to in the General Insurance Code of Practice. Allowing for the initial contact
problem, that is reasonable.
As noted above, the delay in resolution is mostly due to the complainant rejecting the
insurer’s cash settlement offer.
I am not satisfied that the insurer is responsible for stress due to RA and others potentially
being exposed to asbestos. It has not been shown it was necessary for RA to expand the
hole in the asbestos ceiling. There is also no persuasive evidence that the complainant
approached the insurer about any concerns before the hole was enlarged and driers installed.
Further, any issues related to carpet removal and associated drying activity would be the
responsibility of the contents insurer, not the insurer subject of this complaint.
However, I accept that the insurer could have been more empathetic towards RA and RJ
given their advanced ages. As it was offering a cash settlement, the insurer should also have
allowed a contingencies uplift earlier.
I am satisfied that these matters did contribute to some of the delay experienced, which has
caused the RA and RJ stress and inconvenience. The insurer is to pay them $500 (in total) in
compensation.
2.4 Why is the outcome fair?
The insurer’s offer reasonably allows for th e cost of claim related repairs, contingencies and
TA. It has also said it will separately cover mould found in the walls that is directly related to
the water ingress. It would not be fair to require the insurer to pay more for the claim. It is fair
that the insurer pays $500 in compensation as it contributed to the delays experienced.
Determination | Case number: 942412 Page 7 of 7
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. I have reviewed and considered
all the information the parties have provided.
While the parties have raised several issues in their submissions, I have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.