Home / Suncorp Group / Determination 941846
Determination 941846
Dispute over scope and cost of storm damage repairs and cash settlement amount
Summary
Landlord policyholder disputed the insurer's $6,505.95 storm damage assessment against his experts' quotes up to $135,770.39. AFCA required a joint re-inspection by both experts, settlement based on new quotes with a 25% uplift, and payment of the complainant's expert costs up to $5,000.
The insurer's original assessment was inadequate but the complainant's quotes were not accepted in full, so a fair scope must be determined by a joint re-inspection with the insurer covering expert costs.
Issues
- Claim amount dispute primary · upheld
“RB's quote is not a fair or thorough estimate of the damage; re-inspection and new quotes required, cash settlement on average of two quotes plus 25% uplift.”
- Claim denial secondary · not upheld
“I acknowledge not all the damage within the home may be covered; maintenance issues are not covered”
- Inadequate claim investigation secondary · upheld
“insurer's failure to properly and comprehensively ensure a reasonable analysis of the damage in the first instance has delayed this claim”
- Delay secondary · upheld
“failure to properly analyse damage in the first instance has delayed this claim”
Subjects and remedies
home or building damagenatural disasterpay claimpay compensationreassess claim
Text of the determination
Determination
Case number 941846
Financial firm AAI Limited
Determination | Case number: 941846 Page 1 of 6
Case number: 941846 14 February 2024
1 Determination overview
1.1 Complaint
The complainant holds a landlord insurance policy underwritten by the financial firm (insurer).
He lodged a claim for storm damage, which occurred on or about 31 March 2022.
The insurer’s repairer assessed the damage and prepared a repair quote for $6,505.95. It
cited maintenance issues as being a significant contributor to the damage. The complainant
obtained his own expert report to suggest the damage was worth as much as $135,770.39.
To address the discrepancy between the quotes, the insurer proposed a re-inspection of the
home, however the parties could not agree to terms for this.
The complainant now seeks cover for his builder’s quote to repair the damage. He also wants
cover for loss of rent for the duration of the repair period.
1.2 Issues and key findings
How should the matter be resolved?
The parties need to have a re-inspection of the home with the main experts present to resolve
their thoughts on the damage and to prepare quotes to address it. The matter should then be
resolved as detailed in section 2 of this determination.
Why is the outcome fair?
The insurer’s original assessment of the damage did not fairly account for all the damage.
Once it became aware of this, the insurer sought a re-inspection with the relevant experts
present. The complainant refused, however it is fair that this be done wit h the insurer to cover
the complainant’s expert fees. Once the further assessment is done, the parties are to resolve
the matter as outlined in section 2 of this determination.
1.3 Determination
This determination is partially in favour of the complainant.
The parties are to arrange a new inspection of the insured property as outlined in section 2 of
this determination. Based on this, the insurer is to arrange settlement of the claim.
The insurer must also cover the complainant’s proven expert costs (not incl uding the re-
inspection, which the insurer must pay directly) up to a maximum of $5,000.
Determination | Case number: 941846 Page 2 of 6
2 Reasons for determination
2.1 How should the matter be resolved?
The parties need to have a re-inspection of the home with the main experts present to resolve
their thoughts on the damage and to prepare quotes to address it. The matter should then be
resolved as detailed below.
Complainant lodged a claim for storm damage to his investment home
The complainant owns a tenanted rental property, which is a timber weatherboard
construction, with a concrete slab and a metal roof. He purchased the property in 1996.
On or about 31 March 2022, the insured home sustained a loss to which the policy responds.
The issue is the extent of the loss and what a fair price is to repair it.
The complainant’s tenant reports the bottom level of the home was flooded:
The water had flooded the bottom level of the house and was running out the
door. The Kitchen, bathroom, dining room and bedroom were all flooded.
In the time since, I have been cleaning mould off the walls from time to time.
The kitchen and some of the bedrooms were affected by water ingress. The damage mainly
included water damage to the kitchen kickboards, water damage to the fixed seating in the
dining room, internal doors and skirting.
The insurer engaged builder RB to attend the home and assess the damage. RB quoted
$6,505.95 to address the claim-related repairs.
The complainant believes this quote is not representative of his loss. He obtained several
reports and quotes of his own and says the damage is worth more than $100,000.
To resolve the matter, the insurer wants its expert to meet with the complainant’s primary
expert on site and review the damage together. The complainant does not want to do this.
Insurer’s experts found not all the damage was caused by storm
RB assessed the extent and cause of damage for the insurer. It considered the main cause of
the damage was maintenance issues. However, it accepted the resultant water damage in the
kitchen and dining room should be covered.
The insurer agreed to allow RB to complete the necessary claim-related repairs if the
complainant carried out the necessary maintenance work. Amongst the maintenance issues
RB found required attention were:
‘under flashing’ needed to be installed to prevent the overflow of water on the roof
splashing into the eave lining
installation of an additional downpipe was required to prevent overflows
a waterproof membrane should be added to the timber cladding.
This view was based on an inspection by roofer CR and replicated in RB’s report .
Plumber SP also identified some issues with the home, including:
a gap in the weatherboard ceiling allowing water into the lounge
Determination | Case number: 941846 Page 3 of 6
broken tiles and grouting in the shower allowing water to penetrate under the sand and
cement screed
rain entering below the awning flashing and through the bathroom wall cavity
surface and groundwater from neighbouring townhouses.
On 31 August 2022, the insurer offered the complainant the option to address the cited
maintenance issues before RB repaired the home. The insurer informed him that
maintenance work was required to prevent ongoing damage. The insurer told the complainant
it would not cover or be responsible for this work. Alternately, he could accept a cash
settlement for what the insurer considered was covered or obtain his own quote.
Complainant obtained own quotes to address the building damage
The complainant elected to obtain his own quotes to address the damage.
He provided a quote from builder DB dated 25 July 2022. This quote was for $53,994.60.
As the quote was not itemised, the insurer sought greater detail from the complainant.
The complainant later obtained a written report from engineering consultant EB, which
inspected the property on 27 June 2023. EB found:
moisture entered the home because of the storm event
its findings were consistent with RB’s views
an overflow of water on the neighbouring property and the slope of the land meant some of
it flowed into the complainant’s property.
EB suggested the repair work should be conducted as quoted by builder AH. The quote
(supplied by EB) was for $135,770.39 (EB quote). It is not quite clear how EB’s views are
consistent with RB, noting the difference in the repair quotes. Photos of the damage show
there was water entry through the property, with damage to the walls, skirting doors and
floors.
Reviewing EB’s report and quote, the insurer’s internal assessor (TD) agreed:
there are additional damages that have been missed by [RB] during [its]
assessment.
Despite this, TD considered there were some inconsistencies which required further
investigation. This included some internal damage which the assessor believed was not
caused by the storm event. TD recommended a further site attendance. This would enable all
parties to review the true scope of the claimable damage.
The complainant disagrees with TD. He says TD focussed on damage in the bathroom which
was not related to the loss. Further, he disputes TD’s (and RB’s) view that water is
overflowing the gutter and into the eave and running into the kitchen floor. He also disputes
TB’s categorisation of most of the damage.
The complainant obtained a second repair quote from builder AH dated 2 May 2023 for
$114,471 plus a separate warranty estimate fee of $1,350.01. This quote was not individually
itemised. It is not clear if this is meant as a replacement quote for the EB quote or a
comparison quote.
Determination | Case number: 941846 Page 4 of 6
Parties could not come to terms for a further inspection of the damage
Based on TD’s views, the insurer wanted to further inspect the property with the relevant
experts present. The complainant wanted the insurer to guarantee EB’s costs. The insurer
would not commit to covering these costs in their entirety.
Given this, the complainant subsequently refused to agree to the further inspection and the
parties are now at an impasse and unable to resolve the complaint.
The complainant obtained a second report from EB. This notes that TD’s findings contradict
that of RB. EB questions many of TD’s opinions and conclusions.
Kitchen expert RK also attended the home for the complainant and noted the kitchen would
have to be completely replaced. It said it was not salvageable in its current condition.
Not satisfied a decision can be made based on the exchanged information
I am not satisfied a fair estimate of the claim-related damage to the home can be ascertained
from the exchanged information.
I accept the quote from RB is not a fair or thorough estimate of the damage caused to the
home. Similarly, whilst I accept the information provided by EB is useful, I do not accept its
quote should be paid in full. The extreme differences between the quotes is a concern. The
insurer acknowledges the damage is worth more than RB originally suggested, however it
appears it only agreed to this based on EB’s report.
Given this, I am satisfied it is fair that EB’s opinions on the damage be given weight but not to
the extent of paying the entire EB quote (at least without further investigation). I agree the
insurer must be permitted to further review the damage and reconsider (in conjunction with
EB) what a fair settlement should be.
The parties still need to ascertain what is damaged and to what extent this arose from the
storm event (or subsequent ingress or worsening of the problems). I acknowledge not all the
damage within the home may be covered. Further investigation is required.
Fair that a further inspection of the damage is conducted
I consider it is fair that a re-assessment of the damage be done with both RB and EB present.
This will allow them to freely discuss their views and properly examine the cause(s) of the
claimed damage. It is also fair that the insurer covers the costs for both experts to attend.
This is because EB has raised reasonable points about the extent of damage that were
clearly missed by RB (and acknowledged by the insurer). It is best that these two experts be
present to discuss and better address what damage should be covered.
The experts must visit the site on a suitably agreeable date. This can be arranged by the
insurer with the complainant’s assistance. Based on the respective experts’ discussions and
further review, they can each prepare a new quote and/or report to explain their views. The
complainant and a representative of the insurer may also be present.
The quotes obtained must be actionable on the basis that the complainant agrees to
independently address and repair any agreed maintenance-related issues before any repairs
are conducted.
When the quotes are compiled, the insurer may opt to either repair the damage (assuming
any required maintenance work is done first) or cash settle the claim.
Determination | Case number: 941846 Page 5 of 6
If the insurer chooses to cash settle the claim, the settlement amount must:
be based on the average of the two new quotations, and
include a builder’s margin and a 25% contingency uplift.
This is on the basis the average of the two quotes plus the 25% uplift does not exceed the
building sum insured applicable at the time of the loss. The contingency uplift serves to
address the transfer of risk passing to the complainant to complete the work. It will also
compensate him for the loss of the lifetime guarantee and acknowledges there may be
variations required during the work.
An allowance must also be made for mould treatment and asbestos removal at the property if
either of these possibilities prove necessary.
Given any cash settlement will be based on an up-to-date estimates with a contingency uplift,
I am satisfied there is no need to award interest.
Insurer must also cover the complainant’s reasonably incurred costs
I am satisfied the insurer’s failure to properly and comprehensively ensure a reasonable
analysis of the damage in the first instance has delayed this claim. This required the
complainant to obtain his own reports to assess the damage. I accept these reports were
useful and they showed that RB’s original report was not fair or accurate in its assessment of
the damage.
Therefore, I accept the insurer must cover the complainan t’s expert costs (not including the
re-inspection, for which the insurer must pay directly) up to a maximum of $5,000. This is
subject to receiving invoices and/or proof of payments made to the respective experts.
Loss of rent to be assessed as part of the inspection
The complainant seeks loss of rent for the time it will take to repair the damage at the home. I
consider this will be dependent on the further investigations of the two experts.
Loss of rent is payable under the policy to the extent the extent a home sustains damage and
‘cannot be lived in or cannot be re - leased’ for a period.
I am satisfied an estimated time to repair the property (and whether it is livable) should be
included in the experts’ respective reports. The insurer must assess this entitlement as part of
its settlement of the claim.
2.2 Why is the outcome fair?
The insurer’s original assessment of the damage did not fairly account for all the damage.
Once it became aware of this, the insurer sought a re-inspection with the relevant experts
present. The complainant refused, however it is fair that this be done with the insurer to cover
the complainant’s expert fees . Once the further assessment is done, the parties are to resolve
the matter as outlined above.
Determination | Case number: 941846 Page 6 of 6
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.