Home / Suncorp Group / Determination 941668

Determination 941668

Partial decline of storm/flood claim (footings, roof, solar panels, loss of rent) and claim delays

FirmSuncorp Group
Decided2024-01-08
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$5,400
Amount claimed—
SourceAFCA PDF

Summary

The complainant's home building claim after February 2022 heavy rains was partly declined for footings, roof, solar panels and loss of rent. AFCA upheld the declines but found unreasonable delay and ordered $5,400 non-financial loss plus reimbursement of storage and water delivery costs.

The complainant did not establish an insured event caused the footings, roof or solar damage and loss of rent cover did not apply, but the insurer unreasonably delayed mould remediation and the water tank replacement.

Issues

Subjects and remedies

home or building damagemental healthnatural disasterpay compensationpay non financial loss

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 941668 Financial firm AAI Limited Determination | Case number: 941668 Page 2 of 13 Case number: 941668 28 November 2023 1 Determination overview 1.1 Complaint The complainant holds home building insurance with the financial firm (the insurer). On or about 18 March 2022 she lodged a claim for damage to her property following heavy rains in February 2022. The insurer partially accepted the claim. However, it declined cover for the footings, roof repairs of the main house, the solar panels, and loss of rent. The complainant wants the insurer to accept the claim for the solar panels, the footings and roof repairs of the main house. She also wants the insurer to pay her for loss of rent and the balance of the sum insured remaining for temporary accommodation costs. She also says the insurer delayed the conduct of the claim and wants the insurer to pay her $5,400 as compensation for non-financial loss. 1.2 Issues and key findings Is the insurer required to accept the damage to the house footings? No. The insurer is entitled to decline this aspect of the claim because there is insufficient information showing an insured event caused damage to the footings of the house. Is the insurer required to accept the damage to the roof? No. The insurer is entitled to decline the claim for roof repairs. This is because the information shows the roof requires replacement due to its age and wear and tear which existed prior to the rains in February 2022. Is the insurer required to accept the damage to the solar panels? No. The insurer is entitled to decline the claim for the solar panels because the damage is due to gradual deterioration not the storm event. Has the insurer caused delays on the claim? Yes. The insurer unreasonably delayed the mould remediation and the hygienist clearance certificate and the replacement of the second water tank. Is the insurer required to pay the balance of the sum insured for accommodation costs? No. The information does not show the complainant has incurred additional accommodation costs. However, the insurer is to settle any additional necessary accommodation costs during the repairs to the granny flat flooring. Determination | Case number: 941668 Page 3 of 13 Is the insurer required to pay for loss of rent? No. The insurer is entitled to decline the claim for loss of rent because the complainant did not have cover. This is because the property is not an investment property and had been lived in by the complainant. Is the insurer required to pay compensation for non-financial loss? Yes. The insurer is required to pay $5,400 as compensation for non-financial loss. Why is the outcome fair? The outcome is fair in all the circumstances because it considers the insurer’s o bligations according to the terms and conditions of the policy. It would not be fair to require the insurer to pay the costs of the replacement of the roof, footings, solar panels, and loss of rent when the information shows the damage is not covered under the policy. However, it is fair for the insurer to compensate the complainant for its delays on the claim. 1.3 Determination This determination is substantially in favour of the insurer. Within 14 days of receipt of the complainant’s acceptance of this determination , the insurer must pay the complainant $5,400 as compensation in non-financial loss. Within 14 days of receipt from the complainant of evidence of invoice and payment, reimburse the complainant for storage costs and water delivery costs she has incurred as set out in section 2.4 of this determination. Determination | Case number: 941668 Page 4 of 13 2 Reasons for determination 2.1 Is the insurer required to accept the damage to the house footings? No. The insurer is entitled to decline this aspect of the claim because there is insufficient information showing an insured event caused damage to the footings of the house. Complainant has initial onus to establish loss covered by terms of policy It is accepted insurance law that the complainant carries the initial onus to establish, on the balance of probabilities (that is, more likely than not), a loss which is covered by the terms and conditions of the policy. Only if the complainant can do this, will the onus shift to the insurer to show, on balance, it is entitled to decline cover in line with the policy wording or otherwise. The policy is an ‘insured events’ policy. This means not all loss and damage i s automatically covered. Rather, only loss or damage caused by one or more of the insured events, and not subject to exclusions, is covered. Flood is an insured event. Storm is also an insured event. The product disclosure statement (PDS) includes specific exclusions under both the flood and storm insured events for loss or damage caused by erosion, vibration, subsidence, landslip, landslide, mudslide, collapse, shrinkage or any other earth movement, unless the landslide or subsidence occurred within 72 hours of, and directly because of, flood or storm. Complainant says event caused damage to house footings The complainant lodged a claim on or about 18 March 2022 for damage to the external structures on her property. The property consists of main house, granny flat, quarters and shed and stables. The original main house is reported to be between 70 to 100 years old (various reports quote different ranges) and had been relocated and refurbished on the current property (Roof contractor CR report dated 6 July 2022). The complainant purchased the property in 2009. She says following the heavy rains the foundations of her house became unstable due to the dam water run-off. She admits the flood waters have not entered her house. The insurer partially accepted the claim. However, the insurer says the event has not caused damage to the footings of the house. Parties provided reports on the damage The complainant provided an invoice report from a roofer RT dated 31 May 2022 which says the following: The roof, gutters and facia are majorly damaged due to the house sinking so much due to major water from flooding. I have noticed that the front verandah roof is warping. This will be a complete re-roof which will include new roof, new facia, new soffits, new guttering. This will be hard to complete as the house has sunk and warped so much due land movement from floods. Every ceiling within the house has black mold along with all walls and window frames making this house unlivable. In my personal opinion this house will need to be rebuilt. [sic] Determination | Case number: 941668 Page 5 of 13 The insurer provided a roof report from a roofer (CR) dated 6 July 2022. CR says:  the house is 80 to 100 years of age, has been relocated from another area to the present location and been refurbished  the roof to the main section of the house is in poor condition and approximately 50 years of age  a newer renovated section is in fair condition and approximately 10 years  it recommended a full roof replacement  flooding of the property has seemed to affect the footings of the building, and having some effect of twisting of the roof trusses  recommended a qualified builder to certify structural integrity of the overall building, footings and trusses. Neither roof specialist explained how they formed the view that the footings of the house had been affected by the event by examination of the footings. The insurer’s assessor (MM) inspected the property on or about 6 June 2022. MM says:  the main house had no evidence of storm runoff or flood damage internally  he inspected the subfloor and found no damage or staining to the yellow tongue or timber sub-frame  reviewing cabinetry and furniture pieces, he found no swelling or damage that can be attributed to the event  there was mould evident to the bathroom and porch FC sheet ceiling however no water staining was evident and poor ventilation is the likely cause. The insurer’s engineer (MC) inspected the property on or about 19 June 2022. MC states:  the property has three dwelling structures being the main house, the quarters, the granny flat, and also has a stable among other rural outbuildings  the house footings are piers on concrete footings  water has not entered the older timber structures but did enter the granny flat  there were no notable deflections or undulation on the floor of the house  the house veranda was generally sound but had some localised weathering of the floor near the left outer edge to the left – likely from leaking gutters above  along the left veranda, the roof beam has sagged, gutters at front left have corroded and spill directly to the ground beside the veranda  guttering is missing along left of the entry roof and the support post is close to a supporting stump  there was no notable deflection of the floor at this point suggesting the issue is with the veranda post or supporting timbers and this was not caused by storm water run-off. On 31 January 2023 the insurer’s assessor (B) attended the property. He says:  the rafters to the old part of the house had been cut through and then aligned and secured with a hardwood cleat to one side with four coach bolts securing the cleat to the rafter  most of the rafters at that location have sagged due to the insufficient cleating of the cut rafters  he questioned if the house had been relocated to the current property and the complainant advised it was and this was the reason the rafters were cut for the transportation of the house. Insufficient information showing damage to footings from insured event Having considered the available information, the panel does not accept the complainant has satisfied her initial onus to show a flood, or any other insured event covered under the policy, Determination | Case number: 941668 Page 6 of 13 caused damage to the footings of the house. This is because the information shows, on balance:  the house footings are piers on concrete  the flood water did not enter the sub-floor of the property as there are no stained markings or damage to the timber frame, which is supported by photos  the flood waters did not enter the house itself which was admitted by the complainant  the floors of the house are unaffected  the roof specialists have not provided any information showing they examined the footings of the house and explained how they formed their view the house is sinking because of the flood event based on an examination of the footings  the insufficient cleating of the cut rafters as part of the relocation of the house to the current property explains the condition of the sagging of the roof. The panel is satisfied it is fair for the insurer to decline cover for the damage to the footings. 2.2 Is the insurer required to accept the damage to the roof? No. The insurer is entitled to decline the claim for roof repairs. This is because the information shows the roof requires replacement due to its age and wear and tear which existed prior to the rains in February 2022. Dispute regarding damage to the roof The complainant arranged for her own roof report from RT which states the roof needs replacement. The complainant says the insurer should pay for roof repairs to the main house. The insurer says it will not accept cover for the roof because the damage is due to wear, tear, gradual deterioration and maintenance issues. The policy excludes loss or damage caused by wear and tear and gradual deterioration. The insurer also refers to sections of the PDS regarding keeping the home well maintained and in good condition. Roof damage, on balance, not due to any insured event The CR roof specialist report dated 6 July 2022 says there are two roofs on the main house: a new roof as part of an extension and there is an old main roof. CR roof specialist recommended a full roof replacement with insulation anti condensation blanket installed under all new roofing. CR records that the house is 80-100 years of age, had been relocated from another area to the present location and the:  main old roof of the house is 30-40 years of age, is in poor condition and has no roof insulation blanket  a newer section of the roof where there is an extension is 10-15 years old and is in fair condition with insulation blanket. CR provides photos of the old main roof that show:  older roof sheeting approximately 50 years of age  chimney flashings, which it says are old existing chimney flashings in poor condition  existing ridge junction laps and joints that it describes as being in poor condition. The insurer’s as sessor (B) attended the property on or about 31 January 2023 and says the rafters of the roof were cut as part of the relocation of the house from another property to the current property. He notes most of the rafters have sagged due to the insufficient cleating of the cut rafters. Determination | Case number: 941668 Page 7 of 13 RT has not provided photos nor evidence supporting his conclusions that the house had sunk. As discussed above, there is insufficient information to show the house footings or the house sank due to the event. This is because there is no evidence the house footings were subject to any flooding. The panel is satisfied the information shows the main roof was old and in poor condition requiring replacement before the storm event, due to gradual deterioration and lack of maintenance. There is insufficient information showing the storm event was the proximate cause for the poor condition of the main roof. Insurer entitled to decline the claim for roof repairs Having considered the available information, the panel does not accept the complainant has satisfied her initial onus to show an insured event covered under the policy caused damage to the roof. Rather, the information shows the damage is due to gradual deterioration and maintenance issues. The insurer is entitled to decline the claim for roof repairs. 2.3 Is the insurer required to accept the damage to the solar panels? No. The insurer is entitled to decline the claim for the solar panels because the damage is due to gradual deterioration not the storm event. Complainant wants the insurer to accept claim for replacement of solar panels The complainant wants the insurer to accept the claim for replacement of the solar panels. She says the panels are cracked underneath and need to be replaced. Co mplainant’s electrical report says the panels have deteriorated over time The complainant has provided her own electrical report by JT electrician who inspected the solar panels on 3 May 2023. The report explains the reasons for the replacement of the solar panel which includes the following: The system appears to have been installed correctly under relevant regulations. In the process of removing the panels from the roof, it was noticed that the backing material of the panels has deteriorated significantly, to the extent that it poses a major risk to ingress of water and dust into the PV Cell. Large cracks appear in all the removed solar panels backing sheets due to inferior manufacturing materials and their constant exposure to thermal cycling. The pan els were operational but are now deemed ‘unsafe’ to reinstall. Insurer is entitled to decline cover for damage to solar panels The panel is satisfied it is fair for the insurer to decline cover for damage to the solar panels. This is because there is no information showing the solar panels were damaged by the storm event. Determination | Case number: 941668 Page 8 of 13 The information provided the complainant ’s electrician confirms the solar panels needed replacement because of inferior manufacturing materials and their constant exposure to thermal cycling. This confirms the damage is gradual deterioration and not storm specific damage. The PDS excludes cover for wear and tear and gradual deterioration. 2.4 Has the insurer caused delays on the claim? Yes. The insurer unreasonably delayed the mould remediation and the hygienist clearance certificate and the replacement of the second water tank. Insurer unreasonably delayed mould remediation and hygienist report On 11 May 2022 the complainant notified the insurer of the house having mould. She says she and the residents needed temporary accommodation. The insurer obtained reports that show the presence of mould, including:  assessor report dated 6 June 2022 confirming mould present on the property and temporary accommodation required  engineer report dated 5 August 2022 says there is black mould on the property and this needs to be remediated immediately. The information on the file, including the in surer’s claim notes show:  on or about 12 May 2022 the insurer arranged A building services to arrange remediation of the mould  on 21 June 2022 the insurer and complainant discussed that remediation would occur on 15 July 2022  on 18 July 2022 the complainant rings to say mould remediation has not occurred  on 13 October 2022 the complainant called the insurer to say the mould remediation crew came a few days ago and appeared to do some work, that she does not know what is going on and if they are coming back  on 25 October 2022 the notes state that mould remediation completed, however the notes after this time show the insurer trying to obtain confirmation that it had been completed  on 20 December 2022 the complainant called the insurer about the mould remediation and she will arrange it herself due to the delays in arranging, and the complainant advised she is not happy with the delay in booking the mould remediation  on 20 January 2023 the complainant called and emailed an invoice of mould remediation in the granny flat and says she wants the insurer to arrange it, and also requests the hygienist be arranged as part of a dual assessment  on 2 February 2023 the complainant contacted the insurer to advise the mould remediation had been completed, the complainant requested the insurer provide a hygienist to confirm the granny flat would be habitable, and the Insurer requested A builder to make the arrangements for reattendance by a hygienist  on 3 February 2023 A builder confirmed they had appointed a hygienist to confirm the property was habitable  on 16 February 2023 O hygienist attended and provided a report dated 13 March 2023 about the house and granny flat. The report stated the granny flat was suitable for occupation, but that the owners may consider painting the ceiling with mould resistant paint to minimise potential for ongoing environmental mould growth. The insurer agreed to complete this painting in the granny flat.  on or about 14 April 2023, the insurer had arranged the painting of the granny flat so that it was habitable for the complainant to move into. Determination | Case number: 941668 Page 9 of 13 The panel is satisfied there was an unreasonable delay by the insurer by several months to arrange mould remediation and the hygienist report from the date it was first reported. The insurer has not adequately explained the cause of this delay. The complainant did not have contents cover and had to pay storage costs while mould remediation occurred. It is acknowledged the insurer compensated the complainant’s storage costs for the amount of $710 on or about 16 September 2022 as a gesture of good will. Due to the insurer’s unreasonable delays, the pan el considers it fair for the insurer to reimburse any additional storage costs incurred by the complainant from September 2022 to 14 April 2023 subject to the complainant providing invoices and confirmation of payment. The insurer is required to make this payment outside of the terms and conditions of the policy because of unreasonable delay in arranging the mould remediation and clearance certificate. Insurer unreasonably delayed the second water tank replacement The complainant notified the insurer that the second water tank had been swept away as part of the claim and this was urgent. The insurer advised it would arrange a make safe and get an assessor report. The make safe did not include the replacement of the second water tank. The e ngineer’s report dated 5 August 2022 includes:  the water tank had been impacted by the storm water run-off  tank water represents the only supply of drinking water at the property, and water has already been bought in by tanker  onsite tanks should be reinstated at the earliest opportunity to avoid further cost and inconvenience. The insurer did not replace the second water tank until 28 May 2023. The panel is satisfied this was an unreasonable delay that could have been avoided. As the insurer did not replace the second water tank earlier, the complainant was required to order water delivery by a tanker incurring additional cost. The complainant says she had 18 horses on the property for which she needed to ensure water was available. The insurer has compensated the complainant for tanker delivery of water for the amount of $410 outside the terms of the policy. The panel is satisfied it is fair for the insurer to reimburse any further water deliveries the complainant had to arrange since then to the date the second tank was replaced, subject to the complainant providing evidence of invoice and payment. The insurer is required to pay this outside of the terms of the policy due to its unreasonable delay. 2.5 Is the insurer required to pay the balance of the sum insured for accommodation costs? No. The information does not show the complainant has incurred additional accommodation costs. However, the insurer is to settle any additional necessary accommodation costs during the repairs to the granny flat flooring. Complainant says insurer should have arranged a pet friendly cabin The complainant says the insurer did not arrange appropriate accommodation. She required to be at the property as she has horses and other pets to care for. Determination | Case number: 941668 Page 10 of 13 In May 2023, the complainant provided AFCA a quote for a pet-friendly cabin available in her area which could be transported to the property and leased on the following terms:  Rental per week $1,000 per week  $2,500 site set up fee and removal/extraction inclusive of power connect, water connection, disposal of septic/sewerage waste and end of term cleaning  $2,400 for transport of the cabin to and away from the property The complainant says this was the appropriate accommodation which should have been arranged for her by the insurer. Policy covers temporary accommodation if insured event causes damage The policy provides temporary accommodation costs where the insured event has caused damage to the house to the extent it cannot be lived in. Temporary accommodation costs will be provided for the period it takes to repair the house so that it can be lived in again. The standard of the accommodation will be:  a maximum of 4 weeks in short-term accommodation  a residential accommodation similar standard to the policyowners home eg. if the policyowner has a 3 bedroom residential house then the insurer will arrange for a 3 bedroom house. The maximum the insurer will pay for temporary accommodation costs is 10% of the sum insured. The building sum insured amount at the time of the insured event was $643,000. Insurer says it paid temporary accommodation The insurer says it paid for temporary accommodation from 15 May 2022 to 20 December 2022. It says it also paid to make the granny flat on site habitable for the complainant during claim-related repairs to the main dwelling. It says it is not liable for further temporary accommodation costs whilst the complainant undertakes maintenance repairs. Provision of a caravan was not unreasonable in the circumstances The information shows that in May 2022 the complainant requested on site accommodation at the property and this included the option of a caravan. The insurer also offered the complainant the option of her arranging a mobile home or caravan for which she would be reimbursed. The claims notes show the insurer’s accommodation provider stated the provision of a caravan was subject to availability. The complainant did not offer the insurer the quote for an on-site pet friendly cabin until May 2023. The panel is not satisfied that the insurer’s actions for arranging a caravan in May 2022 as opposed to a pet friendly cabin in the circumstances were unreasonable. Had the complainant arranged the quote in May 2022 and the on-site pet friendly cabin been available, it would have been open for the insurer to reimburse the complainant for the costs at that time. Future temporary accommodation costs to be settled The insurer accepts its trades damaged the floorboards in the granny flat. It says the complainant may require temporary accommodation for two days while these repairs take place. The insurer is liable to cover any necessary temporary accommodation costs during these repairs if required. Determination | Case number: 941668 Page 11 of 13 Insurer not required to pay any further temporary accommodation costs The complainant says she was living from 22 December 2022 in a tent because the house and the granny flat were unliveable. The complainant was entitled under the policy for temporary accommodation equivalent to the accommodation she had been living in. A tent or converted shed is not the equivalent of where she lived. However, whilst the complainant wants the remainder of the sum insured for temporary accommodation paid to her, the information does not show she incurred further temporary accommodation costs. Whilst the panel accepts there were delays on the claim, the panel considers this is more appropriately dealt with under the non-financial loss aspect of the complaint below. In the event the complainant has incurred temporary accommodation costs not already settled, the complainant is to provide evidence of these costs to the insurer for reimbursement. If the complainant has not incurred any further costs, the insurer is not liable for any further costs. 2.6 Is the insurer required to accept for claim of loss of rent? No. The insurer is entitled to decline the claim for loss of rent because the complainant did not have cover. This is because the property is not an investment property and had been lived in by the complainant. The complainant is claiming loss of rent The complainant is claiming $37,200 for loss of rent as follows:  rent from G who had a verbal agreement to stay and paid $500 per fortnight for the granny flat and she provided a bank statement to support her claim  rent from R who paid $600 per week for the house and provided an unsigned tenancy agreement and a bank statement in support. Loss of rent not covered in the circumstances The policy schedule records the complainant had building cover only and the following disclosure was made:  the home is home owner occupied  the home is not used for business. The policy provides at page 63 cover for loss of rent on condition the property is an investment property which is rented on a permanent basis and the policy owner does not live at the property. The complainant acknowledges the property was not an investment property and she was living at the property. Based on this the insurer is not required to accept the compla inant’s claim for loss of rent. 2.7 Is the insurer required to pay compensation for non- financial loss? Yes. The insurer is required to pay the complainant $5,400 as compensation for non-financial loss. Determination | Case number: 941668 Page 12 of 13 AFCA can award compensation for non-financial loss Under our Rules, AFCA may award compensation for non-financial loss where there has been an unusual amount of:  physical inconvenience  time taken to resolve the situation  interference with the complainants’ expectation of enjoyment or peace of mind. AFCA takes a conservative approach to compensation and expects complainants to bear a normal degree of inconvenience during a claim or when a problem occurs. The complainant raised several concerns with the insurer’s claims handling and delays , including over 14 months of the house not being habitable. She detailed the effect these had on her mental health. Insurer is required to pay $5,400 as compensation for non-financial loss The panel acknowledges the insurer paid the complainant $1,000 as compensation for delay in the assessment of the claim and being one week without accommodation. However, the insurer’s payment of compensation does not impact AFCA’s jurisdiction to award the maximum amount for compensation. The panel is satisfied the insurer’s actions impacted on the complainant’s essential living requirements and affected the complainant’s mental health negatively over a long period. Having regard to all the circumstances, the panel is satisfied it is fair for the insurer to pay the complainant $5,400 as compensation for non-financial loss. This is because the panel is satisfied the complainant suffered an unusual degree of interference to her peace of mind and inconvenience because:  the insurer unreasonably delayed the mould remediation in the granny flat and house and the clearance certificate from a hygienist  the insurer unreasonably delayed the reinstallation of the second water tank which was necessary for the property as it relied on rainwater  the insurer caused the complainant to be living in temporary accommodation longer than what was necessary, which included living in a tent, which was not to an acceptable standard. 2.8 Why is the outcome fair? The outcome is fair in all the circumstances because it considers the insurer’s obligations according to the terms and conditions of the policy. It would not be fair to require the insurer to pay the costs of the replacement of the roof, footings, solar panels, and loss of rent when the information shows the damage is not covered under the policy. However, it is fair for the insurer to compensate the complainant for its delays on the claim. Determination | Case number: 941668 Page 13 of 13 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. A panel determined this matter Due to the nature of this complaint, we referred it to a panel for determination. The panel includes:  an ombudsman  a member with significant experience in consumer and small business advocacy  a member with extensive experience in the insurance industry.