Cash settlement amounts for Persian rug and building repairs, and non-financial loss for claim handling

FirmSuncorp Group
Decided2024-01-23
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$9,900
Non-financial loss$1,000
Amount claimed$89,935
SourceAFCA PDF

Summary

After a burst pipe damaged her home, the complainant disputed the insurer's cash settlements for building repairs and a Persian rug lost by the insurer's restorer. AFCA raised the rug settlement to $9,900, awarded $1,000 non-financial loss, and left the building settlement unchanged.

The rug was lost or made unrepairable by the insurer's restorer, so the guarantee of repairs applied without the $2,000 cap, while the building settlement was based on a reasonable scope and contingency.

Issues

Subjects and remedies

home or building damagepay claimpay non financial loss

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 941373 Financial firm AAI Limited Determination | Case number: 941373 Page 1 of 9 Case number: 941373 22 January 2023 1 Determination overview 1.1 Complaint In June 2021, the complainant‟s home was damaged by water escaping from a burst pipe behind the shower wall and she claimed under her home building and contents policy on 4 July 2021. Following disagreements between the parties over a number of elements of the claim, the complainant requested, and the insurer made, a cash settlement offer on 5 September 2022. The complainant disputes the cash settlement amounts offered for building repairs and a Persian rug. In addition, the complainant is seeking further compensation for the stress and inconvenience caused due to the way the insurer handled the claim for the damaged Persian rug. 1.2 Issues and key findings Is the insurer required to increase the cash settlement for the Persian rug? Yes, the cash settlement amount for the rug should be increased to $9,900. Is the insurer required to increase the amount for building repairs? No . The insurer‟s building repair cash settlement was based on a reasonable scope of works and quote and included a fair contingency. Therefore, the insurer is not required to increase the cash settlement offer for the building repairs. Is the complainant entitled to compensation for non-financial loss? Yes, the handling of the rug element of the claim was so delayed and confused it is fair that the insurer pay $1,000 to the complainant in non-financial loss compensation. Why is the outcome fair? This outcome is fair because the rug was most likely lost or rendered unrepairable as a result of the actions of the insurer‟s agents and the handling of the claim caused unusual levels of stress to the complainant . On the building claim the insurer‟s cash settlement was based on a reasonable scope of works and quote. 1.3 Determination This determination is partly in favour of the complainant. Within 14 days of receiving notice that the complainant has accepted this determination the insurer must pay to the complainant:  $9,900 in cash settlement for her Persian rug under the guarantee of the quality of repairs provision in the policy; and  $1,000 for non-financial loss compensation for the manner in which the Persian rug element of the claim was handled. Determination | Case number: 941373 Page 2 of 9 2 Reasons for determination After initially raising questions about causation, the insurer accepted the claim. It organised trades to complete mould remediation and provide a quote for damage from the insured event. However, there were ongoing delays and disagreements between the parties including on matters that were eventually resolved and are not the subject of this determination. Eventually the complainant asked the insurer to cash settle the remainder of the claim. On 5 September 2022, the insurer offered the complainant a cash settlement of $46,349.29 for the building repair, $7,060.41 for removal and storage of contents, a 20% uplift for unforeseen costs ($10,682.80) and $5,907.50 as ex gratia payment recognising the complainant‟s claim exper ience for the building claim had not been to its standards. That cash settlement was paid to the claimant on 6 September 2022. During this time a separate claim was lodged for damage or loss caused to a Persian rug. The insurer eventually accepted the claim and offered a cash settlement amount of $1,859 which it says is in line with the terms and conditions of the policy. Whilst initially broader, the dispute before AFCA has been reduced to the questions about the Persian rug settlement amount, the appropriate amount for building repairs and the concerns over the stress caused by the handling of the rug claim. 2.1 Is the insurer required to increase the cash settlement for the Persian rug? Yes, the cash settlement amount for the rug should be increased to $9,900 The policy provides limited cover for rugs The policy provides cover for rugs subject to limitations. Unless a particular value is specified when cover is arranged the applicable limit for a hand knotted rug is $2000 per rug. As at the date of the water damage event, a different value had not been specified. This is reflected in the certificate of insurance. After the date of the water damage event and whilst this dispute was ongoing the complainant approached the insurer and did get a specified value included on the policy for the rug. This was initially done on 28 April 2022 for $20,000 and subsequently, on 7 August 2022, it was increased to $25,000. Complainant says the policy limit should not apply The complainant is seeking for the insurer to pay $20,000 for the cost of replacing the damaged Persian rug. She says the Persian rug was a specified item under the policy with a sum insured of $25,000. She also says the insurer initially denied picking up the Persian rug from the property and later admitted it did, only to advise that it cannot locate it and that it was lost in storage. Eventually the Persian rug was located however was deemed non-restorable and disposed of. Determination | Case number: 941373 Page 3 of 9 The complainant says in this case the policy is not relevant as it was not an insured event which caused the loss but rather the loss of the rug in storage. Therefore, the insurer needs to reimburse the value of the Persian rug as it failed to meet its duty of care. The complainant says she initially did not remember the price of the Persian rug when lodging the claim as it was purchased 11 years prior. On 6 July 2023, she was able to provide evidence that the Persian rug was purchased in 2012 for $7,256.14. She argues that the worth of the Persian rug will be far greater than its purchased price as such items appreciate in value over the years. She has also provided evidence that she could get an equivalent replacement rug made for $9900. Insurer says the cash settlement offer for the rug is adequate The insurer highlights the damage to the Persian rug was caused by an escape of liquid event which occurred on 9 June 2021 and that the policy relevant at the time limits the insurer‟s liability for damage to a rug to a maximum of $2,000 unless specified. The insurer says the Persian rug was collected to assess for water damage from the escape of liquid event and later confirmed the rug was non-restorable. Therefore, it is only liable to pay the maximum sum of $2,000 for a rug as per the policy limit for an unspecified item. The insurer says it found a similar replacement rug for a cost of $1,859 based on its research. Therefore, it says the cash settlement offer of $1,859 for the claimed rug is adequate and it is not liable to increase the settlement amount to match the rug‟s purchased price. The question to be determined in relation to the rug If the rug was damaged by the escaped water event in June 2021 to such a degree that it was not repairable it is clear that the policy limit applies and the insurer should pay the replacement cost up to the policy cap of $2000. The insurer puts the replacement cost at $1859. Whilst this might leave the complainant out of pocket, the policy limit is clear and the complainant had not at the time of the event taken steps to specify a value for the rug. On the other hand, if the rug was taken for treatment and either treatment was delayed for so long that the rug became unrepairable, or the rug was lost by the restorers, then the claimant is entitled to be compensated under the term of the policy that guarantees the quality of repairs. In that circumstance the policy cap would not apply. The evidence about what happened to the rug There is quite a deal of uncertainty as to what happened to the rug. One contributing factor to this has been that the claimant has generally referred to the rug as „the blue rug‟ whilst the restorer generally re ferred to it as „the black and gold rug‟. For convenience and without expressing a view as to which is more accurate, I will refer to it as the blue rug. Whilst the story has changed over time it is now clear the parties agree that:  Initially two other rugs (both red in colour) were collected from the home for mould treatment in September or October 2021;  The blue rug was not initially taken because it was too large for the van;  Subsequently, possibly a few days later, the blue rug was collected and taken to the insurer‟s restorer;  The two red rugs, both restored, were returned to the complainant In February 2022; and  On 1 March 2022 the complainant contacted the insurer with concerns the rug the subject of the claim had not been returned to her. Determination | Case number: 941373 Page 4 of 9 When the concerns were raised about the non-return of the rug, the insurer investigated with its restorer and the mould assessor that transported the other rugs. It concluded that the blue rug had never been collected from the complainant‟s home and denied liab ility. It maintained that position through the insurer ‟ s internal dispute resolution process (August 2022) and in its initial response to the current dispute process (January 2023). However, after the complainant provided a photograph of the rug at the restorer ‟s premises, a photogra ph that had been sent by text message to her by the restorer in April 2022, the insurer again made inquiries of the restorer in April 2023. The response from the restorer on 17 April 2023 was that they had had the rug, that it had been unrepairable, and that they had advised the complainant of this in late April 2022. Further, they had asked her if she wanted the rug back and she had said „no‟, as she had made a claim for it with the insurer. They then disposed of the rug. In response to this the complainant maintains that when she contacted the restorer they advised that they had already disposed of the rug and that she had not said she did not want it back and at that stage she had not made a claim for it. Analysis of the evidence on the rug Thus there are two conflicting versions of events. In terms of the claimant‟s position it is not to her credit that she for many months she refrained from providing the photo of the rug at the restorer‟s which establishes it had been taken there, even though she was conscious that the insurer maintained that it had not been collected from her home. However, the evidence for the insurer‟s version of events and in particular that of their restorer, is weak. It involves the restorer maintaining they had disposed of the rug on the complainant ‟ s approval. They did so without contacting the insurer who had engaged them and in circumstances where, on their own account, the complainant had advised she was claiming for the rug from the insurer. They communicated none of this to the insurer. When it was subsequently raised with them, they denied for almost 12 months that they had ever had the rug. They appear to have no written records of their handling of the rug including of the phone call with the complainant in April 2022. They too failed to advise the insurer about the photo. The insurer refers to a rug restoration report dated 30 August 2021, which lists the rug as unrepairable. However, whilst there is a document headed “Restoration Report” the date of 30 August 2021 is included only as „Date of Claim‟ and the d ocument provides no information as to what the damage to the rug was or why it was unrepairable. It is unclear when the document was generated, and it cannot be relied upon as evidence that the rug was unrepairable as at August 2021. The two red rugs were returned to the complainant in February 2022. There is no evidence of their return being reported to the insurer by the restorer, at which time one might have expected some reference to how the third rug was being dealt with. In addition, the complainant maintains that the blue rug was located further away from the site of the leak than were the red rugs and has provided a floorplan setting this out. She says it had no water damage and just needed treatment for potential mould. The early on-site report of the insurer‟s remediation expert tends to support this. In their report dated 14 September 2021 they found that one of the red rugs had “Condition 2” mould with signs of settle d spores. They recommended cleaning and restoration of the two red rugs. The reported mould levels on all other soft samples tested were low and consistent with normal levels. Whilst we don‟t know if the blue rug was tested, one would expect that if, it showed any sign of water damage Determination | Case number: 941373 Page 5 of 9 or mould, it would have been tested. That would even more be the case if the damage or mould was sufficient that it was at risk of being unrepairable. The two red rugs were successfully restored. One would have expected that a rug located further from the leak would also be able to be restored. I acknowledge that the evidence on this issue is incomplete, however, on the balance of probabilities I think it more likely that the initial impacts of the event on the blue rug were repairable but that either:  because the rug was overlooked at the restorer ‟ s premises from September 2021 until April 2022, it became unrepairable; or  it was lost or disposed of by the restorer without proper approval being obtained. Because the cause of the loss was the actions of the insurer‟s restorer, the insurer is liable to compensate the complainant for the rug under the policy guarantee of the quality of repairs. What amount should the insurer pay in compensation for the rug I have already noted above that in circumstances where the liability arises under the guarantee of the quality of repairs, the $2000 cap for rugs does not operate. Equally, the specified values for the rug, which the complainant arranged in April and August 2022, are not determinative. This is not a claim for an insured event under the policy. The amount of compensation should be the cost to replace the rug with one of similar quality. The assessment of that amount is made more difficult by the fact the we no longer have the rug but only photos of it. The specified value of $25,000 under the current policy provides an indication of the value the complainant puts on the rug but she is not qualified to assess its value and there is no evidence as to how she arrived at that figure. The other information available is the original purchase price of $7,256 in 2012, the quote the complainant has provided of $9900 for getting a replacement rug made, the insurer‟s r esearch based figure of $1859 and the figure noted on the „Restoration Report” of $2500. Each of those figures is open to question. The original purchase price related to the rug 12 years ago. It may have accrued in value or depreciated since that time. The figure of $9900 for a replacement was obtained by the complainant from a supplier who may have some expertise but did not have access to the rug being replaced. The insurer‟s research based figure appears to be based on internet searches by a non-expert and based only on a photo of the blue rug. The replacement cost included by the rug restorer on the document headed „Restoration Report‟ has the benefit of coming from a rug restorer whom you would expect to have expertise and originally had access to the rug. However as noted above it is not clear when the document was generated and given the history that the restorer thought they had never had the rug until their position change in April 2023, it seems more likely it was generated recently. By that time, they no longer had the rug, the technician who originally dealt with the rug had left the business and it was clear that there was an argument that the restorer had mishandled the rug. Balancing these factors, I consider the original purchase price must be a baseline. Because the restorer disposed of the rug it is not possible to get expert evidence as to whether the value of the rug had increased. Thus to the extent there is doubt as to whether it has appreciated or depreciated in value, the benefit of that doubt should go to the complainant. On that basis the appropriate figure is that provided by the complainant‟s rug supplier that the rug can be replaced for $9900. That is the amount that the insurer should pay in cash Determination | Case number: 941373 Page 6 of 9 settlement. No additional excess is payable because the liability does not arise under a new claim on the policy. 2.2 Is the insurer required to increase the amount for building repairs? No. The insurer‟s building repair cash settlement was based on a reasonable scope of work s and quote and included a fair contingency. Complainant says the insurer’s cash settlement offer for building repairs is inadequate The complainant is seeking the insurer pay an additional amount for the building repairs based on her own quote from her chosen builder for $69,935. She says the difference in cost between her quote and the insurer‟s quote is primarily due to the insurer‟s quote showing low labour costs which she says is questionable given the labour rates should be similar as the construction industry is regulated. The complainant in her response to AFCA on 2 May 2023, listed out items which she says should be covered by the insurer and that these items were either not accounted for in the insurer‟s quote or were under-priced. She also says that the fact it took insurer nine attempts to assess all the repairs required listed in the scope of work shows that the insurer‟s process to deliver a complete scope of works with fair pricing is unreliable. The evidence indicates the insurer’s offer for building repairs is reasonable The Insurer says it has correctly assessed its liability towards the building repairs based on the scope of works prepared by its builder. That quote dated 23 May 2022 for the insured repairs is for $46,349. The insurer has also provided a 20% contingency allowance of $10,682 to allow for transfer of risk and unforeseen costs and $7,060 for storage of contents. The insurer argues the complainant‟s quote is excessive and identifies the following issues:  the allowance for carpentry and flooring is excessive for the nature of the works required;  the allowance for demolition is excessive as most of the demolition has been completed; and  it includes allowance for disconnection of shower plumbing, however these works are already completed. The complainant has not provided any reasons to contest the argument that her quote contains repairs of areas that were not damaged by the insured event and contains allowances for work that has already been completed by the insurer engaged trades. I acknowledge the process of getting a satisfactory scope of work took time however, information shows the insurer agreed to all the concerns raised by the complainant and arranged multiple onsite assessments to address the complainant‟s concern s. I do not consider organising multiple assessments caused a loss to the complainant rather it was to her benefit as the issues she pointed out were addressed. I have also considered the complainant‟s position that the insurer should pay additional costs due to the current increase in prices in the building industry. However, the insurer already Determination | Case number: 941373 Page 7 of 9 factored in 20% uplift for any unforeseen increase in costs to the cash settlement offered and paid it to the complainant on 6 September 2022. I also note the insurer has always maintained that the claim was cash settled at the complainant‟s request and that the insurer‟s builder has always advised that it was willing to complete the building repairs for the price quoted. On the balance of the evidence , I am satisfied the insurer‟s cash settlement offer for building repairs is reasonable. Accordingly, the insurer is not required to increase the cash settlement offer for building repairs. 2.3 Is the complainant entitled to compensation for non- financial loss? Yes, the handling of the rug element of the claim was so delayed and confused it is fair that the insurer pay $1,000 to the complainant in non-financial loss compensation. AFCA can award compensation for poor claim handling AFCA may award compensation for non- financial loss where the insurer‟s actions have caused an unusual amount of:  physical inconvenience  time taken to resolve the situation  interference with the complainant‟s expec tation of enjoyment or peace of mind. Information shows insurer has mishandled the claim The insurer acknowledges the complainant‟s dissatisfaction regarding the service provided during the claims process and the delays with settlement of the rug. However, the insurer maintains it is not required to compensate the customer for non-financial loss as it has not acted inappropriately, nor unnecessarily delayed the claim. The available information shows the Persian rug in dispute was collected from the complain ant‟s property for restoration in or about September 2021, was not returned with the other rugs and, due primarily to confusion between the insurer and its agents and an apparent lack of record keeping, its whereabouts remained unclear and contested until April 2023. Whilst the claimant could have helped things by forwarding to the insurer a copy of the photo the restorer had sent to her in April 2022, this might equally have been done by the restorer. The delay and confusion lead to unnecessary stress for the complainant with the insurer confronting her with, amongst other things, challenges as to whether she could prove ownership of the rug – a rug that the insurer‟s agents had collected from her house and not returned. I am satisfied that this caused well beyond the normal expected levels of stress arising from making a claim and it is fair that the insurer should pay the claimant $1000 in non-financial compensation. 2.4 Why is the outcome fair? The outcome is fair because:  The loss of the rug being, on balance, attributable to the actions or the insurer‟s agents, the policy cap does not apply and the available evidence supports a fair replacement value being $9900; Determination | Case number: 941373 Page 8 of 9  On the evidence, the insurer‟s cash settlement offer for building repairs is adequate and included appropriate amounts for contingency; and  It is fair that the insurer should compensate the complainant for the stress and inconvenience it has unreasonably caused while handling the claim for damage to the Persian rug. Determination | Case number: 941373 Page 9 of 9 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.