Home / Suncorp Group / Determination 941209

Determination 941209

Complainant sought reimbursement of $7,495 roof maintenance repairs, waiver of second excess and removal of second claim record after two water ingress events

FirmSuncorp Group
Decided2023-07-20
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$7,495
SourceAFCA PDF

Summary

The complainant claimed reimbursement of roof maintenance repairs after two water ingress events and disputed two claims and excesses. AFCA found for the insurer, as maintenance was the complainant's responsibility and two claims were applicable; the insurer had already waived the second excess.

Maintenance repairs were required regardless of the insured events, the complainant did not show detrimental reliance on the insurer's error, and the two separate events justified two claims.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 941209 Financial firm AAI Limited Determination | Case number: 941209 Page 1 of 4 Case number: 941209 20 July 2023 1 Determination overview 1.1 Complaint The complainant lodged two claims with the financial firm (insurer) under his home insurance policy. They are for water damage sustained to the property following two water ingress events. The insurer accepted the claims for the resultant damage, however, required the complainant to undertake maintenance repairs prior to rectifying the damage. Following the initial claim, the complainant incurred $7,495 in maintenance-related repairs to the roof. The complainant is dissatisfied with the insurer’s handling of the claim and says:  the maintenance related issues the insurer identified following the initial claim were incorrect  he has completed unnecessary repairs and incurred preventable costs due to the insurer’s incorrect assessment following the initial claim  two claims should not be recorded on his insurance policy  he is not liable for two policy excesses. The complainant is seeking reimbursement for the maintenance repairs to the roof, waiving of the second excess and the removal of the second claim from his records. 1.2 Issues and key findings Is the insurer liable for the maintenance related repairs? No. The complainant is required to undertake these repairs even in the absence of an insurable loss. I accept two claims are applicable given the two ingress events occurred on two separate occasions. Why is the outcome fair? The exchanged evidence shows the roof required maintenance repairs. It is not the insurer’s obligation to establish the extent of the maintenance related repairs required to mitigate further losses. 1.3 Determination This determination is in favour of the insurer. The insurer is not liable for the maintenance related repairs and it is appropriate the insurer records two claims. The insurer agreed to waive the excess for the second claim. Determination | Case number: 941209 Page 2 of 4 2 Reasons for determination The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. I have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, I have restricted this determination to the issues that are relevant to the outcome. 2.1 Is the insurer liable for the maintenance related repairs? Maintenance repairs to the roof were required prior to the internal repairs The following relevant facts are not in dispute:  the complainant lodged two claims for storm-related damage  the insurer has agreed to cover the internal water damage following the two events  the insurer has declined to cover any maintenance-related repairs  this damage to the roof was not caused by an insured event. The exchanged evidence shows that the maintenance-related repairs to the roof following the initial claim was completed by the complainant’s repairer (KW). These repairs include  re-lay, re-bed and re-point top ridge and hips.  supply sand, cement and tiles to replace non-functional tiles.  chipped tiles considered functional are not included.  quote includes the use of flexible pointing and excludes any roof plumbing. The complainant’s main argument is that he incurred these costs unnecessarily as the insurer has incorrectly identified the source of the water entry. Evidence shows numerous water entry points The insurer does not dispute the insurer’s repairer (DA) has incorrectly identified the holes in the sarking as the cause of the water ingress during the assessment of the initial claim. However, the ongoing investigation into causation has identified other water entry points. I note these entry points were identified prior to the second loss such as the cracked tiles. The insurer says that further water ingress has occurred due to the inadequate maintenance repairs completed by the complainant’s repaire r KW. The complainant disagrees. The complainant says the maintenance work was limited to the replacing of the ridge capping and pointing (even though this was not the water ingress source) which was not poor workmanship. I find this is inconsistent with the invoice for the works the complainant is claiming for. KW included repairs to the broken tiles. The insurer contends the complainant has not suffered a loss due to DA’s incorrect findings as the complainant is liable for the maintenance repairs regardless of the outcome of this claim. The insurer’s repairer (HR) says the water ingress in t he second claim is due to the vent pipe penetration and cracks to the pointing above the ridge. A roofer (RD) says the broken and poorly repaired tile is causing the water ingress. RD notes several broken tiles and missing valley cuts and breaks. Determination | Case number: 941209 Page 3 of 4 I accept HR and RD findings are consistent in that one of the entry points is through the cracks and chips in the tiles. I note DA identified this issue prior to KW conducting his repairs. It appears that KW has inadequately rectified these issues. I am not satisfied this water ingress is due to any error or wrongdoing from the insurer. I accept an additional source of water ingress (ventilation pipe penetration) was identified following the second loss, however, the insurer agreed to cover the resultant damage. T he complainant has not relied on the insurer’s error to his detriment The complainant says the insurer has overlooked the ventilation pipe penetration as the source of the leak. The complainant contends had the insurer addressed this issue in the first claim, the second loss would not have occurred and arguably a second claim would not be required. I disagree. The complainant has not provided any evidence to show what step(s) he has taken to address the ventilation penetration concerns. Even if I were to accept that the insurer has mistakenly identified the source of the water ingress, I am not satisfied the complainant has shown he has relied on this error to his detriment. This is because the complainant is required to undertake any maintena nce-related repairs to the property to mitigate further damage in any event. I accept these maintenance repairs are inevitable to prevent further damage. I consider the complainant has the onus in establishing the extent of the maintenance-related issues to his property. I do not accept that the insurer is liable to establish the full extent of the maintenance required for a property. However, it is reasonable to expect an insurer to bring any identified issues to the insured’s attention during the claim. I acknowledge the complainant’s position that he incurred substantial costs to rectify issues with the roof, only to discover two months later that these repairs are arguably inadequate, causing further damage. I consider the insurer’s position to be fair and reasonable given it agreed to cover the resultant damage following the second event. There is no compelling information that the noted defects in the roof structure did not require repairs at some point in time even in the absence of the two losses. I accept the two incidents are two separate claims for the purposes of the policy and two excesses are normally applicable. I acknowledge the inconvenience caused to the complainant because of two consecutive losses, however, I am not satisfied this inconve nience is due to the insurer’s conduct. I accept the insurer has engaged several experts to assist the complainant in addressing the cause of the water entry. The insurer has waived the applicable policy excess of $1,000 for the second claim. Considering my findings above, I am satisfied this is reasonable in the circumstances. 2.2 Why is the outcome fair? The exchanged evidence shows the roof required maintenance repairs. It is not the insurer’s obligation to establish the extent of the maintenance related repairs required to mitigate further losses. Determination | Case number: 941209 Page 4 of 4 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.