Home / Youi / Determination 939655

Determination 939655

Insurer accepted then declined escape of water claim relying on shower base leak exclusion; temporary accommodation and delay

FirmYoui
Decided2023-08-10
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded—
Non-financial loss$4,000
Amount claimed—
SourceAFCA PDF

Summary

The insurer accepted then declined an escape of water claim, relying on a shower base leak exclusion. AFCA found the exclusion not established and ordered the claim paid via expert scope, reimbursement of reasonable costs of modifying and moving to the second home, interest, and $4,000 non-financial loss.

The insurer bore the onus of proving the exclusion, and the leak from the shower rose connection is not a shower base, recess or cubicle; the insurer also failed to assist with suitable temporary accommodation.

Issues

Subjects and remedies

disabilityhealth or medicalhome or building damagepay claimpay compensationpay interestpay non financial lossrepair or rectify

Related

All Youi determinations · Find similar determinations

Text of the determination

Determination Case number 939655 Financial firm Youi Pty Ltd Determination | Case number: 939655 Page 1 of 12 Case number: 939655 17 July 2023 1 Determination overview 1.1 Complaint The complainant holds a building and contents insurance policy with the financial firm (insurer). Following an escape of water event, the insurer accepted the complainant‟s claim. However, after further testing it later retracted its acceptance of the claim. The complainant says the insurer should not have declined the claim and is seeking coverage for her damaged home and for temporary accommodation. 1.2 Issues and key findings Is the insurer’s assessment of its liability under the claim fair ? No. The insurer is required to comply with the provisions of this determination. Is the insurer obligated to pay temporary accommodation? Yes. The insurer is to make payment in accordance with this determination. Should the complainant be awarded compensation? Yes. The insurer is to pay the complainant $4,000 in non-financial loss compensation. Why is the outcome fair? This outcome is fair because the complainant has established a valid claim and the insurer has not established the application of its exclusion. The insurer failed to provide adequate assistance regarding suitable temporary accommodation, and therefore it should pay the costs associated with the temporary accommodation. Finally, it is fair the insurer pays non-financial loss compensation to account for the emotional stresses the complainant experienced. 1.3 Determination This determination is substantially in favour of the complainant. The insurer is required to comply with the provisions of this determination. Determination | Case number: 939655 Page 2 of 12 2 Reasons for determination 2.1 Is the insurer’s assessment of its liability under the claim fair? No. The insurer is required to comply with the provisions of this determination. The complainant lodged two claims with the insurer (one ending in 334 and another in 998). This complaint will only consider the damage claimed under 334, for the following reasons: The complainant originally discussed with AFCA the issues with her son‟s bedroom and the bathroom (334). The complainant later advised that the kitchen damage occurred because of the insurer‟s trades leaving open the windows and that there were concerns with the roof (998). I acknowledge the difficult situation the complainant is currently in. However, as the claims to all areas cannot be considered without a proper investigation/opportunity to submit new information, it is unfair to group all the claims together. In fairness, the complainant should be allowed an opportunity to consider her position regarding the kitchen and the roof, submitting her own reports or quotes should she wish to. This determination is limited to considering the building damage stemming from the bathroom and her son‟s bedroom , temporary accommodation and the insurer‟s claim management. The policy covers insured events, with limited accidental damage coverage The insurer provided the complainant with the relevant policy documentation including the product disclosure statement (PDS) and certificate of insurance (COI). I accept the insurer is entitled to rely on the policy provisions to assess its liability under the claim. The policy covers the insured property against loss or damage caused by one or more of the listed insured e vents, including „Escaping Water‟ . The policy also covers accidental damage. However, the coverage for accidental damage is only for contents items. The cover provided by the policy is subject to the conditions, limitations and exclusions specified in the PDS. The complainant has established a claimable loss The insurer partially accepted the complainant ‟s claim for escape of water. The acceptance by the insurer extends to the carpets, hot water system and remediation works. The insurer is still waiting on a cash settlement form to be signed by the complainant. With respect to the main issues in contention, the insurer says:  damage is due to escaping water from a shower base, which is excluded under the policy  the quotes for damage to the building are excessive and include areas not established as being damaged directly by the water  the complainant never sent in receipts/invoices for temporary accommodation costs. At page 15 the PDS, it details: What is not covered? Loss or damage which was: • caused by water escaping: Determination | Case number: 939655 Page 3 of 12 - from a leak in a shower base, recess or cubicle; The insurer seeks to rely upon this exclusion to deny the complainant‟s claim. Parties provided quotes for reinstatement works The insurer offered to reinstate the damage to the home its trades did, the cost of the works it already completed and the carpet. The quote submitted for reinstatement works was for a total $7,784.89 and include the following:  HWS cupboard  bedroom  linen cupboard  WIR to main bed  hallway  hot water system The complainant says the insurer‟s offer is an „insult‟ and it would not be near enough to reinstate the property to what it was before the ins urer‟s trades entered her home. The complainant submitted a quote from WC. This quote was divided into two parts: bathroom repairs and additional repairs. The total quote was $56,100 and includes:  the bathroom repairs because of leaking shower rose, demolishing the existing bathroom  supply and installing the villa board sheeting, waterproofing, tile bed, wall/floor tiles, tap ware, vanity, towel rails, bath, toilet, shower screen  painting  plumbing  additional repairs because of the leaking shower rose, such as remove and replace the damaged bottom wall plate, re-sheeting removed plasterboard, supply and installing the new skirting/architraves, shelving, carpet to hallway and hot water system. Complainant says the insurer should cover all damage stemming from the escaping water event There was a dispute regarding the carpet, but the insurer has agreed to the complainant‟ s quotation of $15,200.10. The carpet is no longer in dispute, although the complainant says that the furniture removal was not covering electrical items. The complainant says the claim should not have been denied because the shower base passed the leak test, and every other leak test passed other than where the shower rose joins the wall. The complainant says the insurer ripped up her home, forced her to live elsewhere and then change its position and declined the claim. Simply because there was a second report, the complainant says the first report should not be ignored. She questioned why the insurer ripped up her home and then declined the claim. The complainant‟s home is isolated, and she says should not have to pay extra because the insurer caused further damage, only to decline the claim later. The insurer’s reports The insurer appointed CC to conduct a leak detection test on 11 May 2022. CC noted that the water damage was from the leaking shower rose connection. CC says the threaded connection did not have enough tape installed and the wall penetration was not Determination | Case number: 939655 Page 4 of 12 sealed causing some of the water to leak back into the wall. Water has pooled inside the wall and spread to the adjacent rooms. CC provided photographs accompanying this report, and one item shows red dye on the shower base with the comment: „shower flood test – test passed; no dye water leaked into the water damaged areas. Flood test 30 minutes, no signs of leakage‟. Another photograph from CC shows the cut hole in the wall to confirm the water leak from the shower rose connection. The photograph shows dampness and mould. Another photograph shows the assessor‟s hand and the caption below reads „There was excessive water leaking from the shower rose wall connection‟. A second leak detection report, from MC, was submitted by the insurer once it was determined there was further water damage. The complainant was living in a different location with one of her sons and she was not present at the time. This second leak detection was conducted by MC on 31 October 2022. MC says:  there was water ingress around the bathroom  at the time of inspection, the timberwork was dry and there were no roof leaks or plumbing leaks  after turning on the shower for around 10 minutes, the water ingress appeared to be occurring from a failed waterproof membrane  water was seeping through the bottom plates  the Villaboard sheets are porous in nature and draws water through its fibres in a vertical fashion, giving the appearance of a water leak from the ceiling space  the sagging cornice has not been caused by water ingress. MC submitted photographs accompanying the report, showing water seeping through the bottom plates. The photographs from MC also show the back of the bathroom damaged and damp. However, MC provides no comment on the shower rose and whether it contributed to the damage. Nor does he provide a photograph of the failed waterproof membrane. CC‟s report is dated 11 May 2022. MC‟s report is dated 31 October 2022. The insurer‟s Notice of Response (NOR) is dated 6 January 2023. There is no indication that the insurer provided MC a copy of CC‟s report for comment. I am satisfied that the insurer‟s decision to deny the claim is based upon MC‟s report to the exclusion of CC‟s report and its findings. Apart from relying upon the MC report, the insurer does not explain why it no longer relies upon CC‟s report or the findings therein. The complainant remains unclear why the second leak detection was done, especially considering the first report from CC shows the shower passed the leak test and damage was visibly up the shower rose. She says since the claim was initially accepted, the insurer should be liable to accept the scope of works and fix the damage. The complainant says the shower base was waterproofed about six years ago. The complainant has provided a video of the bathroom area. This video appears to show water is coming from the shower base when the shower is turned on. However, the complainant is neither an expert, nor does she carry the onus to establish that an exclusion does not apply. Determination | Case number: 939655 Page 5 of 12 As stated, the insurer carries the onus to show that an exclusion applies to allow it to deny the complainant‟s claim. While the insurer argues the video supports its position, it has not sought an opinion from either MC or CC. In my view the insurer should have done so. CC‟s report is clear on at least two points:  there is a leak from the shower rose connection and  a flood test of the shower for 30 minutes, showed no signs of leakage. CC‟s report includes helpful photographs to support his position regarding both the leak from the shower rose and no leak following the 30-minute flood test of the shower. While MC‟s report also includes photographs , they are not of the so called, failed waterproof membrane. MC says that the water ingress had being happening for a long time. CC conducted his leak detection test approximately six months prior to MC. This to me suggests that the water ingress and likely the damage wa s occurring, prior to CC‟s test, which is, as CC observed. Having carefully considered both reports, I prefer the view of CC that the leak of water is from the shower rose connection. The policy exclusion applies to water leaking from a: ….shower base, recess or cubical… The policy does not define any of these three items. In my view, the shower rose connection is not a shower base; is not a shower recess and is not a shower cubical. The shower rose connection is an appliance within the shower recess or shower cubical. The result is that the insurer has not established the application of its policy exclusion, to deny the complainant‟s claim. The insurer is to pay the complainant’s claim for the damage under the terms and conditions of the policy Based on the exchanged material I am satisfied that the insurer is required to pay claim number ###334, under the terms and conditions of the policy. Unfortunately, I do not believe that there is sufficient information upon which to decide regarding the limit of the insurer‟s liability to the complainant, under the claim. The complainant has provided a quotation, but it includes the hot water service, which I understand the insurer has settled separately. The quotation also includes the vanity, towel rails, bath, toilet and melamine shelving which the complainant has not yet established were damaged by the escaping water event. In my view it is fair that upon acceptance of this determination by the complainant, the insurer arranges for the attendance of an appropriately qualified expert to prepare a scope of works and actionable quotation for repairs to the damage caused by the escaping liquid event. The insurer is then, at its discretion, to complete repairs or cash settle the complainant based upon the actionable quotation. If the insurer chooses to cash settle the complainant, it is to add 20% to the actionable quotation to allow for the transfer of risk and any contingencies. Determination | Case number: 939655 Page 6 of 12 The parties are encouraged to work together to achieve a satisfactory outcome. In addition, the insurer is to pay the complainant‟s reasonable costs incurred of moving herself and the family from the primary home (see below for reference to the primary home) to the second home (see below for reference to the second home). The complainant is to provide details and evidence of the reasonable costs incurred. If, when the rectification work at the primary home is completed, the complainant choses to return to the primary home, the i nsurer is to pay the complainant‟s reasonable costs incurred of moving herself and her family to the primary home. The complainant is to provide details and evidence of the reasonable costs incurred. 2.2 Is the insurer obligated to pay temporary accommodation? Yes. The insurer is to make payment in accordance with this determination. The policy covers temporary accommodation, subject to terms and conditions The PDS states at page 18: 2. Temporary Accommodation: Insured Events What is covered? Buildings Where the premises is owner-occupied, the actual cost you incur for your suitable temporary accommodation for a period of up to 12 months, while your buildings are being repaired or rebuilt, if you cannot live at the premises after an insured event for which a claim is accepted under your buildings policy and we agree that temporary accommodation is required. The most we will pay for each claim is 12% of the building sum insured , which includes up to:  4 weeks in suitable emergency or short-term accommodation;  28 weeks in suitable residential accommodation at a similar standard to your home; and  The reasonable and necessary costs for:  Redirection of mail from the insured premises for up to 12 months;  Utility connection costs at the temporary accommodation residence; and  Relocation of your contents to and from the temporary accommodation residence if you have contents cover under this policy . We will also pay up to $250 per month for pet accommodation, up to a limit of $3,000, for each claim. Determination | Case number: 939655 Page 7 of 12 Suitable accommodation will be assessed based on factors including number of household members , proximity to the insured property , parking requirements and availability. The relevant building sum insured is $936,000. Thus, under the policy, the maximum amount of temporary accommodation payable over 12 months, if applicable, would be $112,320. The complainant’s position The exchanged material confirms that the insurer encouraged the complainant and her family to move out of the home, due to its damaged condition. As such, I am satisfied that the policy requirement, „that you cannot live at the premises‟, has been satisfied. The policy list of factors to be considered when assessing suitable accommodation is not an exhaustive list. In my view, it includes a consideration of the reasonable needs and requirements of the complainant‟s family including her son‟s medical condition and resultant needs. The complainant says it was impossible to find suitable alternative accommodation given her son‟s special needs and i t is not in dispute that the complainant experienced significant difficulties in locating suitable temporary accommodation. The complainant says the insurer did not consider her son‟s disabilities when it told her to move out of her home and as a result she had to move into a house she had previously purchased (the second house). That second house had to be renovated to make it accessible for her son. The complainant confirmed that she bought the second house to renovate and use as an investment. It was not purchased to move in to. It was only when she could not locate suitable temporary accommodation, that she moved into the second house. It is clear to me that given the son‟s special needs, the renovations required to make the second house suitable, were extensive. The complainant says that she had a ceiling hoist, wheelchair lift and accessible bathroom installed, together with numerous structural changes. The complainant says the insurer offered her $9,900 per month for temporary accommodation. The complainant says she did not send, to the insurer, any receipts regarding the renovations because she did not want only those items to be settled. She would like the insurer to cover the $9,900 per month it said she would be entitled to, despite her having to come up with her own solution for suitable temporary accommodation. The financial and personal difficulty the complainant experienced when being told she had to move while remediation of her home was taking place is clear. However, the policy coverage regarding temporary accommodation is for: …. the actual cost you incur for your suitable temporary accommodation…. The insurer says that as the complainant cannot provide evidence of payments for temporary accommodation, the policy coverage does not apply. The insurer says that there is no financial prejudice to the complainant as she was able to move into the second home that she already owned. The claim was lodged on 29 March 2022 and the insurer‟s notes record that the complainant told the insurer, on 21 April 2022, that she did not require temporary accommodation , “at this stage” . Determination | Case number: 939655 Page 8 of 12 The complainant advised that she was living temporarily back in the primary home for about six weeks, while the second home was undergoing repairs. She moved back to the second home in May of 2023, and currently remains there as the remediation works required to her primary home have not been completed. The insurer‟s cla im notes record that on 20 July 2022, the insurer told the complainant that it could not proceed with the restoration until she had vacated the primary home. The complainant advised that she had been in Sydney for a while and was not living at the primary home. It was during this exchange that the insurer advised the complainant that she should seek her own temporary accommodation and the policy had an allowance of “$9+” per month , to work with. The notes record that the insurer requested the complainant to send through payments for reimbursement, “if they source something”. It is clear to me from these notes that the insurer not only encouraged the complainant to move to temporary accommodation, but also, effectively left the complainant to her own devices. While I accept that the complainant‟s circumstances are complicated, and that the complainant is in the best position to understand the needs of her family, I am satisfied that the insurer could have and should have done more regarding the question of suitable temporary accommodation. Insurer required to contribute to the costs incurred by the complainant to support her son It is not in dispute the complainant‟s son is unwell and required constant care. It is also not in dispute the insurer at least encouraged the complainant to move out of her primary home to ensure her family‟s safety. However, I do not accept that because the complainant was unable to provide invoices for temporary accommodation she should not be reimbursed for the costs incurred to ensure her home was safe and secure for her son. The insurer should pay the first four weeks of emergency temporary accommodation, this is to cover the fact the complainant had to plan and move her and her son into the second home, regardless of the fact she owned the second home. I regard this as irrelevant because the complainant still had to move her son and the insurer was aware of his special needs. Further, I acknowledge the insurer initially offered the complainant assistance to locate accommodation, but she refused. Also, based on the email correspondence submitted to AFCA, the complainant did not share with the insurer, until after moving in to the second home that she owned, renovated and modified the second home. The complainant made the choice to move into the second home, but I accept that she had few if any options and the insurer largely left her to her own devices. While the insurer is not solely responsible for finding suitable temporary accommodation, as I have said, the insurer should and could have done more. In the circumstances of this claim and complaint, I am satisfied it is fair and reasonable that the insurer is to pay the reasonable costs incurred by the complainant to make the second home accessible for her son (such as a ceiling hoist, lift, ramp, special bathroom, extra power points and battery backup system and anything else she needed to modify the home for her son‟s special needs ). Determination | Case number: 939655 Page 9 of 12 The complainant is to submit invoices/receipts to show what changes were made to the second home and the insurer is to cover the reasonable cost of the changes. If the parties cannot agree on the reasonable costs, they may refer this complaint back to AFCA for further determination. In addition, the insurer is to pay interest on the amount to be paid for the changes, in accordance with the Insurance Contracts Act 1984, from the date the complainant paid the amount, until it is reimbursed by the insurer. I have considered whether the insurer should pay temporary accommodation costs while the repairs at the primary home are being completed. Given the complainant has moved to the second home and noting my determination regarding the insurer paying the reasonable cost of changes to the second home, I do not believe it would be either fair or reasonable for the insurer to pay temporary accommodation costs during the period of repair at the primary home. 2.3 Should the complainant be awarded compensation? Yes. The insurer is to pay the complainant $4,000 in non-financial loss compensation. Circumstances of the claim The complainant lodged her claim on 29 March 2022. The claim lodgement noted that her son‟s wardrobe was wet, and she was unsure where it was coming from. She noticed mould on the wall and says it was possible that rainwater entered from the ceiling. The complainant advised the insurer that her son is on life support. On 5 April 2022 a make safe for the roof was requested, including a leak detection test. On 21 April 2022, the complainant said she did not require temporary accommodation at that time. On 15 June 2022, the insurer noted that a second claim should be lodged for the roof damage, and a building consultant may need to attend a site visit. On 5 July 2022, a cash settlement was proposed, the estimate was $2,500, plus a possible 15% for lack of warranty because the insurer was not completing the works and extensive mould throughout the property. The complainant was to lodge a separate claim for the roof leaks. The final figure was $3,194.36, less excess. On 20 July 2022, the insurer contacted the complainant and advised the area was not to be lived in while restoration was going to be completed and advised the complainant there is an allowance of $9,000+ for temporary accommodation. The complainant was asked to send in confirmation of the accommodation and she would be reimbursed for it. The complainant asked about the carpet and the insurer advised it would be reviewed once restoration is complete. On 8 September 2022, email to JL stated that R had stripped out a large area and noted extensive damage. The causation still needed to be established. The complainant confirmed she was not living at the property and her eldest son is in a different area of the house. The complainant was informed of the further damage. The complainant advised the insurer that the bathroom where initial leak was detected has not been used since early-May and the bathroom was updated around 5 years ago. Determination | Case number: 939655 Page 10 of 12 On 20 September 2022, the insurer notified the complainant that the containment barrier was taken down, windows open and equipment was turned off. The containment barrier was required to be in place and the complainant was asked to call back. On 14 October 2022, the parties discussed the complaint and the complainant was upset that the repairs were taking too long. The insurer advised the remediation works were done, but the repair works she needs to do must be complete before any other works take place. On 9 November 2022, the complainant was advised works had stopped because further mould was located. A roofer and plumber were requested to re- attend the site. The insurer‟s assessor reviewed the complaint and advised the original claim (ending in 334) for escaping water was incorrectly assessed. The new information suggested the cause of the original leak, mould and subsequent damage was due to a failed shower recess and water-proofing, which is a policy exclusion. This claim was now being denied. The insurer acknowledged that areas of the home still needed completion and it would arrange a cash settlement to reinstate the strip-out. A remediator would be appointed to complete further mould remediation and the insurer wanted the receipts/invoices for temporary accommodation. On 13 December 2022, the complainant was given an update on the storm claim (ending in 998). JL was to re-attend to review the damage and provide a scope. The cash settlement for this claim is separate to the escape of water claim. The complainant also contacted the insurer and advised she and her son moved into a separate home because it had to be modified to accommodate her son‟s disabilities. On 15 December 2022, regarding the roof, there was confirmed hail damage. A separate claim would need to be lodged for the hail damage to the whirly birds. Regarding claim ending in 334, a scope of works for the bathroom damage was to be submitted by JL. Regarding claim ending in 998, there was kitchen damage. This is consistent with moisture and there was no evidence of leaking occurring. It is hard to determine the exact cause of swelling in the kitchen cabinetry; it is unrelated to the previous claims because the areas are around 20m apart. On 19 December 2022, the complainant lodged an AFCA complaint. Complainant says the insurer should not have accepted the claim and decline it later The complainant says when the insurer originally accepted the claim, she expected works would only take a few weeks. She says that because she had to move into the second home, she lost potential income. Although there is no evidence of the second home being used as an investment before she and her son moved in, I accept the complainant had no choice but to move in to the second home. I also accept she had to modify the second home to suit her son‟s needs and make the second home more accessible. AFCA Rules allows for an award of non-financial loss The Rules (Rule D 3.3) allow for an award of up to $5,400 for non-financial loss compensation, if the insurer caused the complainant to suffer an unusual degree or extent of inconvenience, delay or interference. AFCA takes a conservative approach when considering any award of compensation. Determination | Case number: 939655 Page 11 of 12 Insurer to pay compensation for stress and inconvenience I have considered all the exchanged material. I note:  the insurer accepted the claim but later denied it, and in my view denied it incorrectly,  the insurer failed to provide the complainant with adequate assistance regarding suitable temporary accommodation,  t he process of repairs was unreasonable slow, at least in part because the insurer‟s builder was unresponsive, and  t he complainant‟s family are particularly vuln erable. I accept the complainant experienced an undue level of stress, inconvenience and delays over the life of the claim. Accordingly, the insurer is to pay the complainant $4,000 in non-financial loss within 14 days of receiving notice of the complainant‟s acceptance of this determination . 2.4 Why is the outcome fair? This outcome is fair because the complainant has established a valid claim and the insurer has not established the application of its exclusion. The insurer failed to provide adequate assistance regarding suitable temporary accommodation, and therefore it should pay the costs associated with the temporary accommodation. Finally, it is fair the insurer pays non-financial loss compensation to account for the emotional stresses the complainant experienced. Determination | Case number: 939655 Page 12 of 12 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.