Home / Suncorp Group / Determination 938848
Determination 938848
Cash settlement amount for storm damage repairs
Summary
Complainants disputed the insurer's cash settlement after storm damage and wanted their builder's $161,700 quote. AFCA upheld the insurer's right to cash settle on its final quote but increased the contingency to 20% and awarded $2,500 for non-financial loss.
The policy lets the insurer choose cash settlement, its final quote was the more persuasive reasonable cost of repair, the contingency was increased to 20%, and claim handling caused undue stress.
Issues
- Claim amount dispute primary · upheld“final scope and quote reasonable but uplift increased from 10% to 20% for contingencies and transfer of risk”
- Poor claim handling secondary · upheld“insurer's claim handling has caused the complainants unnecessary stress and inconvenience”
- Delay secondary · upheld“some delay is the result of the insurer's claim handling; several assessments needed for accurate scope”
- Product terms interpretation secondary · not upheld“Under the policy, the insurer can opt to cash settle the claim. It gave a reasonable explanation for its choice”
Subjects and remedies
home or building damagenatural disasterpay claimpay non financial loss
Related
All Suncorp Group determinations · Find similar determinations
Text of the determination
Determination
Case number 938848
Financial firm AAI Limited
Determination | Case number: 938848 Page 2 of 8
Case number: 938848 6 October 2023
1 Determination overview
1.1 Complaint
The complainants hold a home building and contents insurance policy with the financial firm
(insurer). Following a storm in April 2021, the complainants lodged a claim for damage to the
property. After an initial denial, the insurer accepted the claim and obtained scopes of work
and quotes for repair of the tiled floor and associated works.
The complainants are dissatisfied with the insurer’s offer of a cash settlement of $93,039 and
a contingency payment of 10%. The complainants say the amount is inadequate and want the
insurer to either undertake the repairs or pay their quote of $161,700 and a contingency.
1.2 Issues and key findings
Is the insurer entitled to cash settle the complainants?
Yes. Under the policy, the insurer can opt to cash settle the claim. It gave a reasonable
explanation for its choice of settlement.
Does the proposed cash settlement represent the reasonable cost of repairs?
No. While the insurer’s final scope of work and quote represents the reasonable cost of
repair, it is to increase its cash settlement with a 20% uplift for contingencies and the transfer
of risk.
Are the complainants entitled to compensation for non-financial loss?
Yes. The insurer’s claim handling has caused the complainants unnecessary stress and
inconvenience. It is required to pay them $2,500 in compensation for non-financial loss.
Why is the outcome fair?
The outcome is fair because the exchanged material established the insurer is entitled to
cash settle the claim but increase the uplift. It also is fair that the insurer pays compensation
for the negative impact of its claim handling on the complainants.
1.3 Determination
This determination is partially in favour of the complainants. Within 21 days of the
determination being accepted, the insurer is to:
cash settle the claim based on K’s quote plus a 20% contingency
pay the complainants $2,500 compensation for non-financial loss.
Determination | Case number: 938848 Page 3 of 8
2 Reasons for determination
2.1 Is the insurer entitled to cash settle the complainants?
Yes. The insurer is entitled to cash settle the complainants.
Insurer can choose to repair or cash settle
The policy outlines how the insurer can settle the claim. It will decide if it will repair damage to
the home or pay the complainants what it would cost the insurer for the repair. In making the
choice, the insurer is to be fair and reasonable.
The insurer says it has chosen to offer a cash settlement rather than repair because its
builder identified structural movement at the property and the builder would not warrant the
repairs.
The complainants are concerned a cash settlement could leave them financially exposed if
the quote is inadequate or if unexpected costs arise during the repair, for example, due to
concrete cancer. However, the settlement includes an uplift to allow for unexpected costs
within reason and I have considered whether the insurer’s quote is adequate.
In the circumstances, I am satisfied it is reasonable for the insurer to cash settle the amount it
would cost the insurer for the repair.
2.2 Does the proposed cash settlement represent the
reasonable cost of repairs?
No. While the insurer’s final scope of work and quote represents the reasonable cost of
repair, it is to increase its cash settlement with a 20% uplift for contingencies and the transfer
of risk.
Insurer obtained a new scope of work and quote
The insurer’s initial cash settlement offer ($54,635) in January 2023 was not accepted by the
complainants. They said an assessor told them the cost could be $120,000 and the insurer’s
quote did not include the cost of the kitchen benchtop.
After assessing the complainants’ scope of work and quote, the insurer offered a second cash
settlement ($77,254). The insurer reviewed its initial quotes and determined they were more
in line with industry pricing than the complainants ’ .
However, during the AFCA review, the insurer undertook an additional onsite assessment.
The insurer’s final scope of work and quote is based on K’s onsite assessment in September
2023. It comprised:
tiled floor 150 square metres and associated work $68,877
kitchen benchtop, splashback and kickers $24,161
uplift for contingency 10% $9,309.
The insurer also offered the complainants and their pet dog four weeks of temporary
accommodation whilst repairs are being completed, although costs were to be discussed
before approval.
The complainants have rejected the insurer’s new quote.
Determination | Case number: 938848 Page 4 of 8
Insurer says its cash settlement is fair and reasonable
The insurer reported its cash settlement is based on a quote that is actionable, fair and
reasonable.
In the report dated 6 September 2023, K confirmed its pricing was in line with allowed rates at
the time of estimation. It confirmed it would reattend to add a contingency as removing tiles
may reveal other problems which have not been scoped.
The complainants disagree the insurer’s cash settlement is fair and reasonable and prefer
their builder’s quote.
Complainants have not shown their preferred quote is fair and reasonable
The complainants initially provided a scope of work and quote from indepe ndent builder ‘B’ for
$161,700. On request, they provided a more itemised quote in July 2023, although I note it is
not as detailed as K’s . The complainants had discussed obtaining a second separate quote
but decided to pursue settlement based on B’s quote.
In contrast to K’s quote, B included:
tiled floor 217 square metres and associated work $151,580
kitchen benchtop and skirting boards; no mention of splashback $10,120
no uplift for contingency.
The complainants were asked to comment on differences between the scopes of work and
quotes. They advised:
B is a qualified builder and the quote is not excessive
the difference in square metres is likely because the insurer missed something, for
example, tiles going to the windowsill or in the kitchen
B told them the larger area of tiles and subsequent cost is to allow for factory wastage
and/or contingency.
The insurer’s assessor rejected B’s quote because:
the cost is ‘unrealistic’ in its overall cost
allowance for the tiling work was $605 per square metre for removal of existing tiles and
bedding plus laying new
the tiled floor area is over K’s SOW.
In comparing the rationales for the quotes, I am satisfied the insurer has provided a detailed
explanation to substantiate its costing. It confirmed it used current pricing, assessed the area
to be tiled and was actionable. I note K issued three quotes with significant differences in
scope and pricing. While the number of attempts is arguably grounds to question the validity
of the last quote, in this case the quotes each represent reasonable variation in scope. In
addition, the pricing per metre for the tiled work is consistent.
However, the complainants’ quote in July 2023, has since expired and lacks an explanation
for the difference in area or a detailed breakdown of pricing.
Given the marked difference in price per square metre for the tiled work, it is reasonable to
expect B to provide information to substantiate its costing. The explanation of additional area
to account for wastage/contingency is less persuasive.
B’s quote is also missing work associated with the tile repair, which indicates less accuracy
overall in its assessment. In saying that, I acknowledge B’s quote assisted in establishing that
K’s initial scope of work and associated quote was not fair and reasonable.
Determination | Case number: 938848 Page 5 of 8
Ultimately, I am satisfied the final scope of work and quote from the insurer is more
persuasive. I accept after the recent assessment the insurer has shown, on balance, its quote
is fair and reasonable.
Cash settlement to be based on K’s final scope of work and quote
Given the issues with the complainants’ scope of work and quote, I accept there is sufficient
cause to determine a fair cash settlement based on K’s final quote.
The insurer is to cash sett le the claim based on K’s quote plus a 20% contingency. This is to
address that the risks of the work passing to the complainants and the likely possibility that
there may be variations required during the works , as noted in K’s commentary . No interest is
payable on the final amount given the claim should be settled on current rates.
The insurer’s offer of four weeks’ temporary accommodation is fair and reasonable. It is to
assess the complainants’ claim for temporary accommodation under t he terms of the policy.
2.3 Are the complainants entitled to compensation for non-
financial loss?
Yes. The insurer’s claim handling has caused the complainants unnecessary stress and
inconvenience. It is required to pay them $2,500 in compensation for non-financial loss.
AFCA has a conservative approach to compensation
AFCA can compensate a complainant for non-financial loss (capped at $5,400 under the
Complaint Resolution Scheme Rules). AFCA may decide a financial firm should compensate
a complainant for such a loss only where there has been an unusual amount of:
physical inconvenience;
time taken to resolve a situation; or
interference with the complainant’s expectation of enjoyment or peace of mind.
Overall, AFCA expects complainants to be moderately robust and bear the normal degree of
inconvenience in dealing with a claim.
The insurer did not handle the claim reasonably overall
I note determination 823282 was delivered by AFCA in the insurer’s favour in December
2021, in relation to a related claim. The complainants lodged the claim for storm damage only
in May 2022 and I have considered the insurer’s claim handling from that date.
In my view, some delay is the result of the insurer’s c laim handling. For example, it took
several assessments for K to determine an accurate scope of work and fair quote. In the call
notes on 5 December 2022, the insurer acknowledged an error in its earlier advice to the
complainants about cover and ultimately accepted cover on 17 January 2023. There was also
some confusion and miscommunication between the insurer’s agent and the insurer about
damage to the ceiling which was not being claimed.
In addition, had the insurer provided more details about the quote the complainants were to
obtain, they could have avoided having to get a second quote from B and the delay between
April and July 2023. I also note the insurer made its decision on the cash settlement four
weeks after receiving B’s quote.
Determination | Case number: 938848 Page 6 of 8
I am satisfied the complainants have suffered an unusual degree of stress and inconvenience
because of the insurer’s handling of the claim.
2.4 Why is the outcome fair?
The outcome is fair because the insurer’s scope of work and quote represents the reasonable
cost of repair. However, the 10% uplift should be increased to 20%, being a fairer allowance
for contingencies and the transfer of risk in the circumstances.
Determination | Case number: 938848 Page 7 of 8
3 Supporting information
3.1 Policy wording
Page 92
How we settle your claim
We choose how we settle home claims
If we agree to pay a claim for loss, theft or damage to your home, we will decide if
we will:
• repair damage to your home;
• rebuild your home;
• pay you what it would cost us to repair or rebuild your home;
• pay you the home sum insured shown on your certificate;
• give you a voucher, store credit or stored value card for the amount it would cost
us to repair or rebuild an item.
If we rebuild (or pay you what it would cost us to rebuild), we will rebuild on a ‘new
for old’ basis.
If we repair (or pay you what it would cost us to repair), we will at our option repair
on a ‘new for old’ basis or repair to a similar condition to what your home was in
before the loss or damage occurred.
Unless we tell you otherwise, we will deduct any amounts you owe us from any
amount we owe you.
Determination | Case number: 938848 Page 8 of 8
3.2 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.