Dispute over whether insurer must repair building with like-for-like materials after defective contractor repairs

FirmAIG Australia Limited
Decided2024-04-05
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

A family trust's commercial building was damaged by the insurer's contractor, and the insurer's builder used non-matching materials in the rectification. AFCA found for the complainant and required the insurer to appoint builders to complete like-for-like repairs, including Durra Panel and plywood.

The insurer is liable in negligence and under the General Insurance Code guarantee to restore the building as closely as reasonably possible to its prior condition, and the complainant did not waive that right by signing the builder's contract.

Issues

Subjects and remedies

elderly or capacityhome or building damagesmall businessreassess claimrepair or rectify

Related

All AIG Australia Limited determinations · Find similar determinations

Text of the determination

Determination Case number 935872 Financial firm AIG Australia Limited Determination | Case number: 935872 Page 2 of 12 Case number: 935872 4 April 2024 1 Determination overview 1.1 Complaint The complainant (a family trust) held a business insurance policy with the financial firm (the insurer). The policy insured a commercial building. The complainant lodged a claim for broken glass. The insurer appointed a contractor to repair the glass. The contractor‟s work was defe ctive, and damaged other areas of the building. The insurer appointed a builder to rectify the defects and repair the damage. The insurer‟s builder used building materials that did not match the materials being replaced. The complainant wants the building repaired with matching materials. The insurer says:  the complainant is not entitled to „like for like‟ repairs; it is only entitled to repairs that are compliant with relevant building codes and „fit for purpose‟  the complainant signed a contract with the insurer‟s builder to allow it to start work. The non-matching materials were specified in the contract. By signing this contract, the complainant waived its right to have the building repaired with matching materials. 1.2 Issues and key findings Is the complai nant entitled to ‘like for like’ repairs ? Yes. The complainant is entitled to „like for like‟ repairs. This includes:  the replacement of damaged Stramit ceiling panels with new Durra Panel ceiling panels (the closest available equivalent)  the replacement of damaged plywood with new plywood. Did the complainant waive its right to ‘like for like’ repairs ? No. The complainant did not know, and could not reasonably have been expected to know, that the building materials specified in the contract were inappropriate. The complainant did not agree to defective repairs, or waive its right to non-defective repairs. How should this complaint be settled? The insurer should settle the complaint by appointing a builder or builders to rectify the defective repairs. Why is the outcome fair? The complainant is legally entitled to „like for like‟ repairs, and the insurer promised it would arrange this. It is fair to require the insurer to fulfil this promise. 1.3 Determination This determination is in favour of the complainant. The insurer must settle this complaint as set out in section 2.3 of this determination. Determination | Case number: 935872 Page 3 of 12 2 Reasons for determination 2.1 Is the complainant entitled to ‘like for like’ repairs ? Yes. The complainant is entitled to „like for like‟ repairs. This includes:  the replacement of damaged Stramit ceiling panels with new Durra Panel ceiling panels (the closest available equivalent)  the replacement of damaged plywood with new plywood. Insurer authorised rectification work with non-matching materials In December 2019, the complainant discovered broken glass at its commercial property during an end-of-lease inspection. The complainant lodged a claim for the damage. The insurer accepted the claim and appointed a glass repairer (G) to repair the damage. In December 2021, G completed repairs. During the repairs, G disconnected a storm water pipe and did not reconnect it. As a result, a significant amount of water entered the building during a storm on 7 January 2022, causing water damage. In July 2022, the insurer agreed t o rectify G‟s repairs and repair the water damage. The insurer appointed a builder (J) to perform this work. On 29 August 2022, the complainant signed a building contract with J. The insurer says J‟s repairs are about 85% complete. The complainant has not allowed J to finish the repairs because of a dispute over building materials. The complainant says J replaced damaged building materials with new materials that do not match the original materials. The insurer does not dispute this, but says the complainant is not entitled to have the building repaired with materials that match the original materials. Insurer promised ‘like for like’ repairs Before signing the building contract, the complainant expressed concerns that J might use inferior building materials. On 29 August 2022, the insurer‟s loss adjuster emailed the complainant saying: If you are concerned about the materials … not being confirmed to you yet, you can write at the bottom of the contact the following. „Subject to materials being confirmed by [J] and agreed to by [the complainant]”. On 6 October 2022 , the insurer‟s loss adjuster emailed the complainant saying: [J is] aware they must install compliant materials and they will do as all codes require in that regard. That includes … sound check plaster where it was installed before. Again if you had timber skirts they will be supplied and fitted in timber not MDF. On 7 October 2022, the insurer‟s loss adjuster emailed the complainant saying: [J] will replace any damaged materials which cannot be repaired with either matching materials to what are there now ( for example, no MDF if timber was there before). Where any materials are no longer available, [J] will replace with the nearest equivalent and as required to meet the current building codes. Determination | Case number: 935872 Page 4 of 12 The loss adjuster‟s emails show it repeatedly promised the building would be repaired with „like for like‟ materials (i.e. materials that matched the existing materials, or their nearest available equivalents). However, a short time later, the insurer told the complainant it was not entitled to have the building repaired with „like for like‟ materials. On 12 December 2022, the insurer emailed the complainant saying: I reiterate again … the notion you‟re entitled to “like for like” materials and is not one you can insist upon … you are entitled to have the building reinstated but only to a standard which meets all of the compliance and fit for purpose markers. Complainant entitled to ‘like for like’ repairs The parties agree that the insurer is liable for the cost of repairing the damage caused by G‟s faulty repairs. However, the parties disagree about the standard to which the building must be repaired. The complainant says it is entitled to have the building restored to the condition it was in before it was damaged. The insurer says it is only required to carry out repairs that are compliant with relevant building codes and „fit for purpose‟. The damage was caused by the negligence of the insurer‟s contractor. The insurer is liable for this damage in negligence. I referred the insurer to Gates v City Mutual Life Assurance Society Ltd [1986] HCA 3, which says the common law remedy for torts (including negligence) is to place the wronged party in the position they would have been in if the wrong had not occurred. In this case, this would mean restoring the building to the condition it was in before the damage. The insurer referred to Bellgrove v Eldridge [1954] HCA 36, which says the remedy for a building defect is „the reasonable cost of rectifying the… defect so far as that is possible‟, as long as rectifying the defect is „a reasonable course to adopt‟. The insurer notes that repairing the building will not restore it to the exact condition it was in before the damage, because the materials used in the repair will be newer than the materials being replaced. I agree that it would not be possible to restore the building‟s prior condition exactly. Therefore, the appropriate remedy in negligence is the cost to restore the building‟s prior condition as closely as reasonably possible. In addition to being liable for the damage in negligence, the insurer is liable under the General Insurance Code of Practice. The Code (to which the insurer subscribes) says an insurer must guarantee repairs if it „selected and directly authorised a repairer‟. The insurer selected and directly authorised G, so it must guarantee G‟s repairs. In my view, this means it must pay the cost of restoring the building to the condition it would have been in if G‟s repairs were done correctly. If G‟s repairs were done correctly, the water damage would not have occurred. For the above reasons, the insurer is liable for the cost of restoring the building, as closely as reasonably possible, to the condition it was in before the damage. It is not sufficient for the insurer to restore the building to a condition that is compliant with relevant building codes. If the building previously exceeded the minimum standards required by the building codes, repairs that merely meet the minimum standards would leave it in a worse condition than it was in before it was damaged. This would not discharge the insurer‟s liability in negligence, and would not fulfil the insurer‟s guarantee on repairs. Determination | Case number: 935872 Page 5 of 12 The insurer cannot discharge its liability by repairing the building with materials that are inferior to the materials being replaced, even if the inferior building materials are compliant with all relevant building codes. The complainant is entitled to „like for like‟ repairs: repairs using matching materials, or their nearest available equivalents. Repairs should have used Durra Panel J replaced damaged Stramit ceiling panels with Soundchek ceiling panels. The Stramit panels are 60mm thick, and made of compressed straw. The Soundchek panels are 13mm thick, and made of plasterboard. J says it „ relied on contractor supplier resources ‟ to choose appropriate building materials. However, the ceiling panels used by J are radically different to the original ceiling panels. The original panels are more than four times as thick, and made of a completely different material. It appears J made little or no attempt to match the new panels to the ones being replaced. The complainant objected to the replacement of Stramit with Soundchek. The insurer said Stramit was obsolete. However, the complainant did its own research and found Stramit is still being manufactured, albeit under a new name: Durra Panel. There may be differences betwee n the Stramit used in the construction of the complainant‟s building and the Durra Panel manufactured today. However, the insurer has not identified any differences. The insurer admits Durra Panel appears to be „ still made in the same fashion ‟ as Stramit. The available information indicates Durra Panel is the available material that most closely matches the damaged material. Restoring the building, as closely as reasonably possible, to the condition it was in before the damage, requires the installation of Durra Panel. The insurer says Soundchek is compliant with relevant building regulations. However, for the reasons set out above, this does not mean it is sufficient to discharge the insurer‟s liability. Repairing building with Durra Panel is reasonable The insurer refers to Bellgrove v Eldridge [1954] HCA 36, which says the cost of rectifying defects is only recoverable if rectifying the defects is „ a reasonable course to adopt ‟. The insurer says repairing the complainant‟s building with Durra Panel would not be a reasonable course to adopt. It says Soundchek is compliant with relevant building regulations, and suitable for the type of building. It says replacing Soundchek with Durra Panel would cost over $100,000, and would not provide any benefit that would justify the cost. The complainant says Durra Panel is superior to Soundchek, because:  it provides better sound insulation  it provides better temperature insulation  it is fire-resistant  it allows easier access to the building‟s wiring and plumbing, because it is strong enough for workers to walk or crawl on  it matches the ceiling panels in the rest of the building. The insurer admits Durra Panel provides better sound insulation than Soundchek. It has not commented on the other ways the complainant says Durra Panel is superior to Soundchek. It admits Durra Panel is „ a better product ‟. Determination | Case number: 935872 Page 6 of 12 The insurer says the sound insulation issue could be resolved by installing a layer of insulation, which would be much cheaper than replacing the panels. However, the complainant says there are several other ways Durra Panel is superior to Soundchek. The insurer has not proposed any solution to these issues. The available information indicates repairing the building with Soundchek has left the building in worse condition than if it was repaired with Durra Panel. The available information indicates the only way to rectify this is to remove any remaining damaged Stramit, and any newly installed Soundchek, and replace it with Durra Panel. In my view, repairing the building with Durra Panel is a reasonable course to adopt. Complainant entitled to have building repaired with Durra Panel The use of Soundchek did not discharge the insurer‟s liability. It broke the insurer‟s promise to repair the building with matching materials, or their nearest available equivalents. In the circumstances, it constitutes a defect. The complainant is entitled to have the damaged Stramit replaced with new Durra Panel. Complainant entitled to have building repaired with plywood The insurer‟s loss adjuster promised the complainant J would not replace timber with MDF (medium-density fibreboard). J broke this promise, and replaced plywood with MDF. The insurer says the use of MDF is compliant with relevant building regulations. For the reasons set out above, this does not justify changing the building material. In the circumstances, the replacement of plywood with MDF constitutes a defect. The complainant is entitled to have the damaged plywood replaced with new plywood. 2.2 Did the complainant waive its right to ‘like for like’ repairs ? No. The complainant did not know, and could not reasonably have been expected to know, that the building materials specified in the contract were inappropriate. The complainant did not agree to defective repairs, or waive its right to non-defective repairs. Not fair to conclude complainant waived right On 29 August 2022, the complainant signed a building contract with J. The contract specified the installation of „ soundchek plasterboard ‟ to the ceilings, and the installation of „ MDF timber panelling and trims ‟ . By signing this contract, the insurer says the complainant waived any right it may have had to have the building repaired with Durra Panel and plywood. An insurer‟s builder will typically prepare a contract setting out what repairs will be done. The customer will have to sign this contract before the builder starts repairs. In most cases, the customer will not have any building expertise, and will not know whether the builder has chosen inappropriate methods or materials. Unless they appoint another builder, they must rely on the builder‟s professional judgment. If an insurer‟s builder chooses inappropriate methods or materials, the insurer should compensate its customer for any loss they suffer as a result. In most cases, it would be unfair for the insurer to say the customer agreed to the inappropriate repairs by signing the building contract. This would likely only be fair if the customer knew, or should have known, the repairs were inappropriate. Determination | Case number: 935872 Page 7 of 12 The complainant says it only signed the contract because the insurer said J would not use any building materials wit hout the complainant‟s approval. The insurer has not refuted this, and it is consistent with the loss adjuster‟s email of 29 August 2022. J prepared the contract specifying the use of Soundchek and MDF. By doing so, J implied these were appropriate materials to use in repairing the building. To the extent the complainant agreed to the use of these materials, it relied on J‟s representation that they were appropriate. The complainant did not know, and could not reasonably have been expected to know, that the materials specified in the contract were inappropriate. It would be unfair to conclude that, by signing the contract, the complainant agreed to the defective repairs, and waived its right to non-defective repairs. Doctrine of election does not apply The legal doctrine of election applies when a party chooses between inconsistent rights. For example, if a seller fails to deliver goods, the buyer may insist on delivery of the goods or demand a refund. The buyer is not entitled to receive both the goods and the refund. The insurer says the right to have the building repaired with Durra Panel is inconsistent with the right to have the building repaired with Soundchek. It says, by signing the contract, the complainant elected to have the building repaired with Soundchek, and waived its right to have the building repaired with Durra Panel. A party can only choose between inconsistent rights if they have knowledge of the circumstances giving rise to those rights. When the complainant signed the contract, it did not know the materials specified in the contract were unsuitable. It did not know more suitable materials were available, and it had the right to have its building repaired with those materials instead. The complainant did not know it had the right to have its building repaired with more suitable materials. Therefore, it cannot have elected to waive this right. Doctrine of estoppel does not apply The legal doctrine of estoppel applies when:  one party makes a representation (i.e. the party says or implies something)  a second party relies on the representation  the second party would suffer a detriment if the first party was allowed to resile from its representation (i.e. the second party would suffer a loss if the first party broke its promise). In the circumst ances described above, a court may say the first party is „estopped‟ (prohibited) from breaking its promise. Estoppel does not mean a party can never change its mind. Estoppel will only require a party to fulfil a promise if breaking the promise would be unconscionable. The insurer says estoppel applies in this case, because:  the complainant made a representation that it was willing to have the building repaired with Soundchek  the insurer relied on that representation, and repaired the building with Soundchek  if the complainant is allowed to change its mind, the insurer will suffer detriment (because it will have to pay the cost of replacing the Soundchek with Durra Panel). Determination | Case number: 935872 Page 8 of 12 The complainant signed the contract specifying the use of inappropriate building materials. However, at the same time, it told the insurer it wanted to approve any building materials before they were used in the repairs. To the extent it agreed to the use of inappropriate materials , it relied on J‟s representation that the materials were appropriate. The complainant never said or implied that it would accept J‟s repairs even if they turned out to be defective. When the complainant discovered J‟s repairs were defective, it demanded the insurer rectify the defects. This was not unconscionable. Estoppel does not require the complainant to accept defective repairs. 2.3 How should this complaint be settled? The insurer should settle the complaint by appointing a builder or builders to rectify the defective repairs. Insurer is able to arrange rectification work The insurer says it is not willing to appoint a builder to install Durra Panel. The complainant says it wants the insurer‟s builders to complete the repairs. It does not want the insurer to cash-settle the claim. It says its directors are elderly and in poor health. They do not believe they could handle the work of contacting builders, arranging inspections, and obtaining quotes. J said installing Durra Panel would likely require removing roof sheets. It said this would be a „major concern‟ because old roofs are often poorly maintained. However, the complainant provided an email from Durra Panel ‟s manufacturer saying it could be installed from the underside without removing the roof. The insurer has not provided any information to refute this. Even if roof sheets had to be removed, there is no evidence the building has any maintenance issues that would prevent this. The complainant obtained a quote to install new Durra Panel ceilings from a builder (LB). The insurer says LB is not on its building panel, so it would not authorise repairs by LB. However, it has not given any reason why it could not authorise J, or another builder on its panel, to install Durra Panel ceilings. The available information indicates the insurer could arrange and guarantee rectification work. Not fair for insurer to cash-settle claim AFCA generally considers that if an insurer starts repairs, it should finish them. It is unsatisfactory to abandon repair work and leave the insured responsible for finishing it. An insurer may be left with no other option if it cannot complete the repairs. However, in this case, the insurer has not shown it cannot complete the repairs. In my view, it would not be fair for the insurer to leave repairs unfinished and pay the complainant the cost of completing repairs. This is because:  the insurer is able to complete and guarantee the work  the required work includes rectifying defective work by the insurer‟s builders . It would be difficult for the complainant to appoint a builder to complete and guarantee this work  the complainant would be responsible for appointing and managing a builder, which would be more difficult for the complainant than it would be for the insurer  the complainant would lose the insurer‟s guarantee on repairs. Determination | Case number: 935872 Page 9 of 12 The insurer must appoint a suitably qualified expert or experts to complete the rectification of its defective repairs. This includes:  rectification of G‟s defective repairs  repair of the water damage caused by G‟s defective repairs  replacement of all damaged Stramit with new Durra Panel  replacement of all damaged plywood with new plywood. Insurer may only cash-settle if it is impossible to complete repairs The parties will need to work together to allow the insurer to complete repairs. Depending on both parties‟ conduct, their relationship may deteriorate to the extent that it becomes impossible for them to work together, and the insurer will not be able to complete repairs. If it becomes impossible for the insurer to complete repairs, the insurer may settle the complaint by paying the cost of the outstanding repairs. The insurer may not do this unless it has made every reasonable attempt to complete the repairs. If the insurer claims it is impossible for it to complete repairs, and the complainant alleges otherwise, the complainant may lodge another AFCA complaint. If it becomes impossible for the insurer to complete repairs, and the insurer cash-settles the claim, it must pay the complainant an amount that will allow it to complete all outstanding repairs. It must also pay the complainant an amount that fairly compensates it for the disadvantages that come with a cash settlement, including the loss of the insurer‟s guarantee, and the difficulty it will face appointing builders to rectify the insurer‟s faulty repair s. If the parties cannot agree on a fair settlement sum, the complainant may lodge another AFCA complaint. Insurer may impose reasonable conditions to complete repairs While J was carrying out repairs, the complainant‟s directors entered the worksite after hours to take photographs of the work in progress. The insurer‟s loss adjuster said this was a breach of Worksafe rules. The loss adjuster said the complainant and its building surveyor could inspect the work once it was complete. The insurer says it also offered to allow a supervised site inspection once a week, but the complainant did not accept this. If the insurer appoints a builder to complete the work, the complainant must follow any reasonable instructions given to maintain the safety of the worksite. This includes staying off the worksite when the builder considers it unsafe. If the complainant does not follow reasonable instructions given to maintain the safety of the worksite, the insurer may stop repairs and settle the complaint by paying the cost of the outstanding repairs. Insurer not required to obtain building permit The complainant has asked the insurer to obtain a building permit. The complainant emailed the Victorian Building Authority (VBA) and asked whether a building permit was required. The VBA replied and said they could not answer this question. The VBA said a building permit would be required for some kinds of work, such as:  changing the floor area or height of the building  adversely affecting the structural soundness of the building  adversely affecting the safety of the building. Determination | Case number: 935872 Page 10 of 12 The insurer says the work does not fall into any of these categories. It says no building permit is required. The available information does not show a building permit is required. Therefore, the insurer is not required to obtain a building permit. Insurer not required to repair lintel The complainant says there is a crack in the lintel (beam) above the window that was replaced. The insurer says the crack in the lintel is appears to be where two pieces were welded together during construction. It says the lintel was not damaged by its builders. The available information does not show the insurer‟s builders caused the crack in the lintel. Therefore, the insurer does not need to arrange repairs to the lintel. Insurer must assess other claimed damage The complainant says the insurer‟s builders damaged the following items by „moving scaffold frames and other building materials‟ and „working without protection‟:  marble at the entrance  foyer on ground floor  concrete stairs  dancing room on ground floor. The complainant has provided photographs of the damage. The insurer has not responded to the allegation that its builders caused the damage. The insurer must assess the above damage and determine whether it was caused by its builders. If the damage was caused by the insurer‟s builders, the insurer must repair the damage. 2.4 Why is the outcome fair? The complainant is legally entitled to „like for like‟ repairs, and the insurer promised it would arrange this. It is fair to require the insurer to fulfil this promise. Determination | Case number: 935872 Page 11 of 12 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. I have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, I have restricted this determination to the issues that are relevant to the outcome. 3.2 Relevant law Gates v City Mutual Life Assurance Society Ltd [1986] HCA 3 M, W AND D JJ. In contract, damages are awarded with the object of placing the plaintiff in the position in which he would have been had the contract been performed — he is entitled to damages for loss of bargain (expectation loss) and damage suffered, including expenditure incurred, in reliance on the contract (reliance loss). In tort, on the other hand, damages are awarded with the object of placing the plaintiff in the position in which he would have been had the tort not been committed (similar to reliance loss). Bellgrove v Eldridge [1954] HCA 36 D C.J., W AND T JJ. Departures from the plans and specifications forming part of a contract for the erection of a building may result in the completion of a building which, whilst differing in some particulars from that contracted for, is no less valuable. For instance, particular rooms in such a building may be finished in one colour instead of quite a different colour as specified. Is the owner in these circumstances without a remedy? In our opinion he is not; he is entitled to the reasonable cost of rectifying the departure or defect so far as that is possible … The qualification, however, to which this rule is subject is that, not only must the work undertaken be necessary to produce conformity [with the contract], but that also, it must be a reasonable course to adopt. No one would doubt that where pursuant to a building contract calling for the erection of a house with cement rendered external walls of second-hand bricks, the builder has constructed the walls of new bricks of first quality the owner would not be entitled to the cost of Determination | Case number: 935872 Page 12 of 12 demolishing the walls and re-erecting them in second-hand bricks. In such circumstances the work of demolition and re-erection would be quite unreasonable or it would, to use a term current in the United States, constitute "economic waste".