Home / Suncorp Group / Determination 934389

Determination 934389

Dispute over the cash settlement amount for accepted flood claim, comparing insurer's and complainants' builders' repair quotes

FirmSuncorp Group
Decided2023-09-11
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$429,324
Non-financial loss—
Amount claimed$619,558
SourceAFCA PDF

Summary

Complainants claimed $619,558.44 for flood repairs after rejecting the insurer's builder; the insurer offered $390,294.72. AFCA found the insurer's builder's quote more reliable but ordered a 10% contingency, totalling $429,324.19, plus security system replacement if testing shows it is needed.

Under the policy, when the insured declines the insurer's repair offer the insurer pays its assessed builder's quote, and a 10% contingency was fair given likely variations for omitted items.

Issues

Subjects and remedies

home or building damagenatural disasterpay claim

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 934389 Financial firm AAI Limited Determination | Case number: 934389 Page 1 of 10 Case number: 934389 31 August 2023 1 Determination overview 1.1 Complaint The complainants hold a home and contents insurance policy with the financial firm (the insurer). They lodged a claim for flood damage. The insurer accepted the claim. The insurer offered to have its builder repair the damage. The complainants rejected this offer. They said they did n ot have confidence in the insurer’s builder. The parties agree the insurer will settle the claim by paying the cost of repairs. The parties disagree on the cost of repairs. Both parties appointed builders who provided multiple quotes for repairs. The insur er’s builder’s first quote was $111,655.85, but their latest quote is $388,318.72. The insurer has offered to settle the claim by paying $390,294.72 ($388,318.72, plus $1,975 added by the insurer’s assessor). The complainants’ builder’s first quote was $ 389,959.89, but their latest quote is $619,558.44. The complainants want the insurer to settle the claim by paying $619,558.44. 1.2 Issues and key findings Which builder’s quotes are more reliable ? The insurer’s builder greatly increased their quote. This is because the insurer agreed to cover more, and asked its builder to add more work to its quote. The complainants’ builder greatly increased their quote . There is no satisfactory explanation for the increase. Extra work was added to the quote, but the extra work was not enough to explain the increase in costs. For these and other reasons, the panel finds the insurer’s builder’s quotes more reliable than the complainants’ builder’s quotes. Is the insurer required to increase its settlement offer? The complainants have identified several items omitted from the insurer’s builder’s quotes, and the insurer has not explained the omissions. It is likely that if the insurer’s builder started repairs, it would charge for variations (extra work not included in its quote). It is fair for the insurer to pay a 10% contingency for potential variations. 1.3 Determination This determination is mostly in favour of the insurer. Within 14 days of being informed of the complainants ’ acceptance of this determination, the insurer must pay the complainants $429,324.19, being the amount of its assessed builder’s quote ( $390,294.72), plus a 10% contingency for potential variations ($39,029.47). If testing of the security system shows it needs to be replaced because of the flood, the insurer must pay the cost of replacing the security system. Determination | Case number: 934389 Page 2 of 10 2 Reasons for determination 2.1 Which builder’s quotes are more reliable ? Insurer accepted claim for flood damage The complainants lodged the claim on 27 February 2022. They said the ground floor of their home had been inundated by about a metre of water. The insurer appointed a builder (ARC), who inspected the home on 14 March 2022. ARC said the entire ground floor of the home had been flooded by water from a nearby creek. The complainants’ policy includes flood cover. The insurer accepted the claim. Claim must be cash-settled The policy says the insurer will settle a claim for building damage by appointing a builder to repair the damage or by paying the cost of repairs. The complainants have consistently said they want the insurer to pay a cash settlement instead of arranging repairs. The insurer’s notes show the complainants asked about getting a cash settlement from 28 April 2022, two months after the claim was lodged. The insurer offered to appoint ARC to repair the home. The complainants rejected this offer. They say they do not have confidence in ARC, and do not want them to repair the home. As the complainants will not allow the insurer to repair the home, the only way the insurer can settle the claim is by paying a cash settlement. Increase in insurer’s builder’s quote explained ARC provided repair quotes with the following totals and dates:  $111,655.85 (30 March 2022)  $200,638.17 (13 September 2022)  $181,707.64 (31 October 2022)  $378,566.07 (1 December 2022)  $382,677.32 (15 January 2023)  $388,319.72 (14 March 2023). The insurer is offering to settle the claim for building damage by paying $390,294.72 (ARC’s quote of $388,318.72, plus $1,975 for additional insulation). ARC’s quotes changed because the insurer agreed to cover more damage as part of the claim, and asked ARC to add more repairs to its scope of works. (The decrease between 13 September 2022 and 31 October 2022 was because the insurer said the external pavers were not covered, and asked ARC to remove these from its scope of works.) The most significant change was in ARC’s quote of 1 December 2022, which was $196,858.43 higher than their previous quote. It included a lot of work that was not in their previous quotes, including:  $54,915 to replace cedar doors in the lounge, office, dining room, and kitchen  $17,860 to replace cedar sash windows in the lounge and kitchen  $2,940 to paint weatherboards in the garage  $32,030 to replace tiles throughout the ground floor and on the front patio (previous quotes only included the cost of replacing tiles in the bathroom and laundry). Determination | Case number: 934389 Page 3 of 10 The above figures add up to $107,745. This does not include the builder’s mark -up (15%), GST (10%), or the increased cost of insurance (about $30,000). When these are added, the above figures add up to $166,297.43. There were also some smaller items added. This explains the difference between ARC’s estimate of 1 December 2022 and their previous quotes. Increase in complainants’ builder’s quote not fully explained The complainants appointed a builder (J). J provided repair quotes with the following totals and dates:  $389,959.89 (8 October 2022)  $619,145.90 (28 December 2022)  $625,590 (3 April 2023)  $619,558.44 (22 April 2023). J’s first quote listed the wo rk to be done, but did not list the cost of each work item. The second quote listed the cost of repairing each room, but did not list the cost of each work item within the room. The third quote was fully itemised, but contained significant errors. The fourth quote is a corrected version of the third quote. J’s second quote was $229,186.01 higher than their first quote. It includes the following work, which was not included in their first quote:  $74,673 to replace cedar doors and windows, instead of just sanding and varnishing them (the quote also included uncosted items to replace doors in each room)  $19,500 to replace tiles on the front veranda  $4,500 (according to J’s later quotes) to remove lead paint from the garage  mould rectification and painting of the front veranda eaves (uncosted, and not included in J’s later quotes) . The above figures add up to $98,673. This includes the builder’s mark -up (not specified), but not GST (10%). With GST, the above figures add up to $108,540.30. The complainants say J’s second quote was higher than their first quote because it included extra work. The panel is not satisfied with this explanation. The extra work included in the second quote does not appear to explain the higher cost. Complainants’ quote more specific on materials The policy says the insurer will repair damaged property ‘to the same type, standard and specification (but not brand) as when new ’. The complainants say the home was built using high-quality materials. They say they worry the materials used by ARC to repair the home would not be of the same standard. The materials with the greatest effect on the cost of repairs appear to be the timber and tiles. Both builders’ quotes specify types of timber to be used: cedar and cherry. There does not appear to be any disagreement about how much of these materials will be used, or where they will be used. Neither builders’ quotes specify the types of tiles to be used. ARC’s quotes include additional labour costs because ‘the tiles have a dec orative pattern and also the tiles are not a standard tile and are no longer available’. J’s quotes including tiling ‘ to match existing, including borders and the feature rizzone in entrance. ’ Determination | Case number: 934389 Page 4 of 10 J’s third and fourth quotes include detail that is not included in ARC’s quotes. For example:  both builders’ quotes include two pak kitchen cabinetry, but J also specifies ‘ stone and laminate b ench tops’  ARC does not specify the type of cabinetry and benchtops being replaced in the laundry; J specifies cabinetry and bench tops with Tasmanian oak edging  J specifies the model of toilet to be installed in the bathroom. Both quotes use reasonable labour rates The complainants say ARC’s quotes use an unrealistically low labour rate of $35 per hour. This is incorrect. Most o f the labour in ARC’s quotes is $60 per hour; plumbing and electrical work is $90 per hour. Most of the labour in J ’s quote s is $65 to $85 per hour; plumbing is $90 per hour and electrical work is $110 per hour. The panel believes both builders’ quotes use reasonable labour rates. Insurer’s quote more reliable on supervision The complainants say ARC’s quotes do not allow enough supervision. ARC’s quotes allow $3,000 for 40 hours of supervision at $75 per hour. J’s first and second quotes do not specify any allowance for supervision. J’s third quote allows $20,400 for 24 days of supervision at $85 per day. The insurer says this is a typo; 24 days at $85 per day is $2,040. The complainants say the actual cost of supervision is $16,320, being 24 days of supervision at eight hours a day (192 hours) at $85 per hour. J’s fourth quote allows $16,320 for supervision, but does not say how this is calculated. The panel finds ARC’s quotes more reliable than J’s quotes on the issue of supervision. Insurer’s quote not aff ected by error in measurement ARC’s quotes say the garage is 6m x 6m x 2.4m. The complainants say the garage is actually 10m x 8m x 2.7m (as stated on J’s quote s ), and this has a ‘ huge impact ’ on the cost of repairs. The insurer says this has no impact on the cost of repairs. ARC’s latest quote allows for the painting of 107m 2 of external garage weatherboards. J’s latest quote does not state the area of weatherboards to be repainted. Neither quote includes any other measurement of length or area in the garage. The measurement of the garage does not appear to have affected the quotes. The complainants say ARC incorrectly measured other rooms. However, the measurements for the other rooms are similar in both quotes. The available information does not show ARC’s quotes are affected by any error in measurement. Insurer not required to pay for security system before testing J’s quote s includ e $15,000 (excluding builder’s margin and GST) to replace the security system if it is found to be faulty. ARC’s quotes include the cost of testing the security system. Determination | Case number: 934389 Page 5 of 10 The security system has not been tested since the flood. The complainants say it will need to be replaced because part of it was underwater during the flood. However, no testing has been done to confirm this. The insurer says it will consider paying for the security system after it is tested. The panel considers this reasonable. Insurer’s quote is actionable AFCA gives more weight to actionable quotes (i.e. quotes prepared by someone who is willing and able to perform the quoted work for the quoted price). AFCA generally considers these more reliable than quotes prepared by someone who will not perform the work. The insurer has consistently said ARC is willing and able to repair the home, and it is willing to authorise and guarantee ARC’s repairs. The complainants say, during a meeting on 28 November 2022, ARC said they did not want to repair the home. However, the insurer says ARC is still willing to repair the home. The com plainants say they are concerned ARC’s repairs would not restore the home to the same standard as when it was new. However, the available information does not establish this. The complainants’ email of 13 March 2023 said J was ‘ no longer able to engage in our repairs and restoration of our home ’. The complainants have not appointed another builder. Insurer’s estimate more reliable overall J’s latest quote include some detail that is not included in ARC’s latest quote. Despite this, the panel finds ARC’s quote more reliable. This is because:  ARC’s quote was actionable  ARC’s quote was more reliable on the issue of supervision  all of ARC’s quotes were itemised. J’s earlier quotes were not itemised, which makes them difficult to assess  J greatly increased their quote between 8 October 2022 and 28 December 2022, and the increase was not explained by the extra work added to the quote. ARC also greatly increased their quote, but the increases were explained. For the above reasons, the panel believes it is fair to us e ARC’s latest quote as the basis for settlement of the claim. 2.2 Is the insurer required to increase its settlement offer? Insurer’s offer is consistent with policy terms The cover provided by the policy is set out in the product disclosure statement. Relevant policy terms are quoted in section 3.2 of this determination. The policy says the insurer will settle a claim for building damage as follows:  if possible, the insurer will appoint a builder to repair the damage  if the insurer offers to repair the damage, but the complainants do not accept the offer, the insurer will pay the amount of an assessed quote by the insurer’s builder (the policy notes this may be less than the amount that would be charged by the complainants’ builder ) Determination | Case number: 934389 Page 6 of 10  if it is not possible for the insurer to appoint a builder to repair the damage, the insurer will ask the complainants to appoint a builder, then pay the amount of an assessed quote by the complainants’ builder. The insurer appointed a builder and offered to repair the damage. The complainants rejected the offer. Therefore, under the policy terms, the insurer is entitled to settle the claim by paying $390,294.72 (ARC’s quote of $388,318.72, plus $1,975 added by the insurer’s assessor). The available informatio n does not show the insurer’s builder cannot repair the damage. Therefore, under the policy terms, the insurer is not required to settle the claim by paying the amount quoted by the complainants’ builder. Fair to base settlement on insurer’s builder’s quot e The insurer’s offer is consistent with the policy terms. It is also fair to the complainants. The insurer offered to have ARC repair the home. If ARC’s repairs were successful, the damaged parts of the home would be restored to new condition. If ARC’s re pairs were defective (as the complainants feared), the complainants could have had them rectified at the insurer’s expense. If there was information showing ARC’s repairs would not meet the standard required by the policy, it would be fair for the complainants to refuse to allow ARC to attempt repairs, and it would be unfair for the insurer to pay a cash settlement based on ARC’s quote. However, the available information does not show ARC’s repairs would not have restored the damaged parts of the home to new condition. It was fair for the insurer to offer to have ARC repair the home. As the complainants did not allow ARC to repair the home, it is fair for the insurer to pay a cash settlement based on ARC’s quote. Insurer must pay contingency for potential variations The complainants say ARC’s quote omits items that are necessary to repair the flood damage, including:  replacement of the newel post, balustrades, and handrail on the flight of stairs  labour to replace panelling, skirting, doors, and architraves (only material cost included)  replacement of kickboards in the laundry  grinding of the concrete slab to prepare for tiling  painting of 18 external wooden pillars (only nine included). The insurer has not responded to these points. If ARC started repairing the flood damage, and found this required work not included in its quote, it could submit a variation for the extra work to the insurer. If the variation was justified, the insurer would have to pay the cost of the extra work. The damage is extensive. Both parties’ builders made significant amendments to their scopes of work. The complainants have nominated items they say are wrongly omitted from ARC’s quote, and the insurer has not responded. For these reasons, the panel considers it likely there would be a variation during repairs. The panel believes it is fair for the insurer to pay a settlement based on ARC’s assessed quote totalling $390,294.72, plus a contingency for potential variations. The panel considers a fair contingency would be 10% of the assessed quote, which is $39,029.47. These amounts total $429,324.19. Determination | Case number: 934389 Page 7 of 10 Outcome is fair in the circumstances The insurer offered to repair the damage, and the complainants did not accept the offer. The policy clearly says that in these circumstances, the insurer will only pay the amount of an assessed quote by its builder, even if the complainants’ builder would charge more. The complainants chose not to have the insurer repair the damage. It would not be fair to require the insurer to pay money outside the p olicy terms because of the complainants’ choice. The panel believes the insurer should pay a 10% contingency for potential variations. This is fair to the insurer, because it would have to pay for any justified variations if its builder repaired the damage. The panel is satisfied this determination provides the fairest possible outcome, based on the available information. Determination | Case number: 934389 Page 8 of 10 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. A panel determined this matter Due to the nature of this complaint, we referred it to a panel for determination. The panel includes:  an ombudsman  a member with extensive experience in consumer and small business advocacy  a member with extensive experience in insurance. One complainant represented both complainants In this determination, statements by one complainant are treated as if they were made jointly by both complainants. 3.2 Relevant policy terms Product Disclosure Statement Making a claim (pages 87 – 98 ) How we settle home claims We will aim to use a member of our builder supplier network to repair or rebuild the damage to the home. Sometimes this is not always possibl e e.g. if there is pre - existing damage. This will determine how the home claim will be settled. When a member from our supplier network can complete the repair or rebuild When your claim for loss or damage to the home is covered, we will engage a builder from our supplier net work to prepare a scope of works and provide a quote on the cost to repair or rebuild the home on a ‘new for old’ basis. Once the scope of works and quote is provided to us, we will arrange for it to be assessed. This will involve reviewing the quote to make sure that the quote is appropriat e and reasonable for the scope of works. This includes a consideration of the appropr iateness of materials, repair method, labour Determination | Case number: 934389 Page 9 of 10 and mat erial costs and overall cost. If the amount of the assessed quote to repair or rebuild is less than the home sum insured, we will off er yo u the choice to have the home re paired or rebuilt (bas ed on the re commendation of our builder).   If the amount of the assessed quote to repair or rebuild is equal to or more than the home sum insured, the damage will not be repaired or rebuilt.  If you accept the o ff er  If you choose to not accept the offer  You will be paid the home sum insured The builder we engage will complete the repair or rebuild on a ‘new for old’ basis. You will be paid the amount of the assessed quot e to repair or rebuild on a ‘new for old’ basis. Note: this amount may be less than what it would cost you to arrange the repairs or rebuild wit h your own builder. We are able to secure supplier discounts from within our supplier network. When a member of our supplier network is unable to complete the repair or rebuild When your claim for loss or damage to the home is covered and a member of our supplier network is unable to complete the repair or rebuild, we will ask you to engage a builder to provide a scope of works and provide a quote on the cost to repair or rebuild your home on a ‘ne w for old’ basis. Once the scope of works and quote is provided to us, we will arrange for it to be assessed. This will involve reviewing the quote to determine it is appropriate and reasonable for the scope of works. This includes a consideration of the a ppropriateness of materials, repair method, labour and ma terial costs and overall cost eff ectiveness. If the quote is appropriate and reasonable for the scope of works, we will then pay you the assessed amount. If it is not, the quote may be adjusted. This may include adjusting the scope of works or the quote. We will then pay you the adjusted amount of the quote. … ‘New for old’ means: New materials, new items We rebuild, replace or repair with new items or new mat erials that are reasonably and readily available at the time of replacement or repair from Australian suppliers. New for old, regardless of age We rebuild, replace or repair new for old regardless of age, with no allowance for depreciation. … Same type, standard and specification a s when new We replace or repair to the same type, standard and s pecification (but not brand) as when new. If the same is not reas onably available from an Australian supplier, we replace or repair with replace or repair with items or mat erials of a similar type, standar d and specification when new. We can Determination | Case number: 934389 Page 10 of 10 replace with a di ff erent brand. …