Home / Allianz Australia / Determination 933375

Determination 933375

Partial denial of flood claim for mould damage relying on exclusion for mould and atmospheric conditions

FirmAllianz Australia
Decided2023-07-11
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

Complainants claimed for flood damage including mould in their home; the insurer partially denied the claim citing the mould and atmospheric conditions exclusion. AFCA found the mould was caused by the flood and required the insurer to arrange a scope of works and remediate or cash settle with a 20% uplift.

The complainants showed on the balance of probabilities that the mould resulted from the flood, an insured event, so the insurer could not rely on the mould exclusion.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimrepair or rectify

Related

All Allianz Australia determinations · Find similar determinations

Text of the determination

Determination Case number 933375 Financial firm Allianz Australia Insurance Limited Determination | Case number: 933375 Page 1 of 7 Case number: 933375 10 July 2023 1 Determination overview 1.1 Complaint This complaint relates to a claim by the complainants under their home and contents insurance policy held with the financial firm (insurer), for damage to the insured property caused by flood. The insurer partially accepted the claim but says that the cause of the remaining damage is excluded from cover under the terms of the policy. 1.2 Issues and key findings Is the insurer entitled to deny the balance of the complainants’ claim? No. Given the exchanged material the insurer is not entitled to deny the balance of the complainants’ claim. Incorrect settlement advice from the insurer Yes, the insurer provided incorrect settlement advice. However, there is no evidence that the complainants acted to their detriment based upon this advice. No further action, save for taking steps to ensure it does not happen in another complaint, is required by the insurer. Why is the outcome fair? The outcome is fair as the insurer is required to consider the exchanged material and the terms and conditions of the policy to determine its obligations to the complainants, regarding the claim. 1.3 Determination This determination is in favour of the complainants. The insurer is required to comply with the provisions of this determination. Determination | Case number: 933375 Page 2 of 7 2 Reasons for determination There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address all issues. This complaint has been determined based on what is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous decisions where applicable. While the parties have raised numerous issues in their submissions, for the purposes of this determination commentary has been restricted to those issues considered directly relevant to the outcome only. 2.1 Is the insurer en titled to deny the complainants’ claim? Coverage of the policy The complainants’ home and contents insurance policy provides cover for loss or damage to building or contents caused by the insured events, listed in the policy documentation, if they occur during the period of insurance. The coverage provided by the policy is subject to conditions, limitations, and exclusions. This means that not all loss and damage is automatically covered. Rather, only loss and damage caused by an insured event, during the period of insurance and subject to the conditions, limitations and exclusions, is covered. The full details of the policy coverage, conditions, limitations, and exclusions are contained within the Product Disclosure Statement (PDS) and Certificate of Insurance (COI). I am satisfied that the PDS and COI have been provided to the complainants. Therefore, the insurer is entitled to rely upon the terms of the policy, including its conditions, limitations, and exclusions, to determine its obligations to the complainants. Insured events includ e “Flood” (page 23 of the PDS) and “Storm” (page 26 of the PDS). It is accepted insurance law that the complainants carry the initial onus to establish, on the balance of probabilities (that is, more likely than not), a loss which is covered by the terms and conditions of the policy. Once the complainants have established a loss which is covered under the policy, the onus transfers to the insurer to establish the application of a condition, limitation or exclusion upon which it seeks to rely, to limit its obligations regarding the claim, or to deny the claim. Circumstances of the loss and claim The complainants lodged their claim with the insurer on 6 April 2022, advising that a flood event on 27 February 2002, caused damage to the property. The insurer records that the complainants say that flood water entered the property, damaging the boundary fence, causing a crack to the external render of the house, resulting in internal mould growth and power loss for six days (the complainants say eight to nine days). Determination | Case number: 933375 Page 3 of 7 I understand that the damage to the crack in the external render is no longer in dispute. However, the insurer’s buil ding solutions group (JL), confirmed that damage to the rear fence was caused by the flood event, when the fence was submerged in water to one meter. The insurer is to attend to the damage to the rear fence, under the terms and conditions of the policy, if it has not already done so. The complainants say that due to flood waters in February 2022, the house was evacuated and inaccessible for 11 days. During that period the house was neither cleaned, ventilated or dehumidified and the absence of power meant no air conditioning or fans to dry the home. The fridge did not work, and food was lost. Further, the complainants say that because of the extreme weather events in February 2022, there was a prolonged period of very high humidity levels from both the rain and the evaporating floodwater. The insurer says that the cause of the damage internally at the property was atmospheric conditions, including high humidity, which is excluded from coverage under the policy. The insurer relies upon policy exclusions, at page 15 to 16 of the PDS, which detail; What types of loss and damage are excluded. Your policy does not cover loss or damage from the following situations. …. Any loss or damage that is predominantly caused by or arises from: • wear and tear, gradual dete rioration, or fading, • rust, corrosion, oxidisation, mould, mildew or atmospheric conditions, unless it is a direct result of an insured event, • earth or soil movement including landslide, subsidence, erosion or heave, unless it is a direct result of an insured event, …. The insurer also relies upon the policy exclusion for the insured event of Flood, which at page 23 of the PDS, is detailed as; Not covered ….  Loss or damage that is predominately caused by or arises from: o …. o Wear and tear, or gradual deterioration. As stated, the insurer carries the onus to establish the application of an exclusion upon which it seeks to rely to deny the complainants’ claim. Reports At the insurer’s request, JL attended onsite on 7 June 2022, and provided a report dated 13 June 2022, which includes several photographs. Determination | Case number: 933375 Page 4 of 7 JL advised that water from the recent flood event entered the garden at the lower rear of the property, rising to a level of approximately one meter up the rear fence. JL advised that recent damp weather and high humidity caused spotting from condensation, although the complainants are said to have advised JL that there is no evidence to show water had entered the house from the flood or otherwise. In conclusion, JL says that any spotting in the house is due to the recent damp weather and very high humidity, with no flood or storm water entering the house. At the insurer’ s request, restoration company RE, inspected the property on 24 June 2022, and provided a report which includes numerous photographs. RE advised that it attended on site; ….to ascertain the damages to the property for the claimed mould damage . (sic) Further, RE advised that the complainants said the rising damp during the storm has caused high moisture levels and the mould had started to develop. Within its report, RE listed the resulting damage as;  Damage to the entire property,  Water Category 3, and  Water Class 2. While onsite RE advised that it;  Cleaned the son’s bedroom, but more time was needed to finish the job, and  Treated the affected areas with the antimicrobial solution. RE recommended;  Further attendance,  Remediation of affected areas, and  Contents to be relocated prior to cleaning. At the request of the complainants, mould inspection specialists EC, attended onsite on 2 December 2022 and provided a report dated 13 December 2022, which includes numerous photographs, many of which show the presence of mould in the house. EC reported of widespread mould growth in multiple areas of the house after the flood event. Within his report, EC advised;  There were no concerns with the indoor dry bulb temperature, dew point temperature, relative humidity and absolute humidity on the day of the assessment.  All moisture content, wood moisture equivalent and relative moisture content levels in the walls, floors, windowsills, ceiling, and carpet tack strips were within normal tolerances and were not of concern.  The assessment of the property did not detect any plumbing leaks or waterproof membrane issues.  Mould with visible mycelium growth was identified on the air conditioner ceiling vents, on the ceiling in (the son’s) bedroom and the dining area, on the underside of several window frames and on the top of (the son’s) bedroom ceiling fan.  Suspected mould growth or staining from past mould growth was noted on the deck couches lining, (the son’s) bedroom block -out curtain and the sides of the outdoor louvers. Determination | Case number: 933375 Page 5 of 7  Suspected mould growth was noted on the master bedroom fabric wallpaper and on the bathroom window frame. EC confirmed that during the extreme rain event in February 2022, there was a prolonged period of very high humidity levels both from the rain and from evaporating floodwater. In my view this is significant. On the day of inspection, as detailed above, EC found no concerns with the measured temperatures or moisture content levels. However, EC confirms that;  It is very important that the surfaces of materials in the indoor environment at not at or below the dew point temperature (the temperature to which air must be cooled to become saturated with water vapor) otherwise condensation and moisture will occur on these surfaces and create a potentially ideal environment for mould to grow,  At times of higher internal relative humidity and prolonged periods of wet weather, the risk of condensation would increase even further,  During prolonged periods of rainfall and or water ingress, mould growth and dust mite activity may increase due to prolonged raised levels of relative humidity,  A wood moisture equivalent level above 18% would be considered damp and is of concern as it is high enough to support mould growth, and  Elevated moisture content levels can contribute to elevated levels of humidity, which in addition to increasing the risk of fungal growth, could also increase dust mite activity. Given that EC says there was a prolonged period of very high humidity during the extreme rain event in February 2022, it follows that there was an increased likelihood of condensation and thus, resultant mould. Finally, based on the reported history of widespread mould growth in the house and the visible mould growth noted on several surfaces, EC recommended professional mould remediation of the property and contents. Conclusion The coverage provided by the policy is for loss or damage caused by flood. The PDS does not say that the flood must enter the home to cause the damage. Given the description of water rising to one meter at the rear fence, I am satisfied that there was a flood. There is no evidence that the home was subject to spotting or mould, prior to the February 2022, significant weather event. The complainants were evacuated and there was no power at the home and the home was vacant for several days. As a result, there was no air conditioning or fans and windows and doors remained in their, presumably, closed position. In my view, the report from EC is thorough, logical, compelling and its conclusions supported by detailed analysis and photographs. Based on all the exchanged material, I am satisfied that the complainants have meet their onus to show that the development of spotting and mould was caused by the February 2022, flood, an insured event under the policy. Determination | Case number: 933375 Page 6 of 7 Given that the mould was caused by an insured event, flood, consistent with the AFCA approach, the insurer cannot rely upon the policy exclusion for mould to deny the complainants’ claim. Within 14 days of the acceptance of this determination by the complainants, the insurer is to arrange a scope of works and actionable quotation from a suitably qualified expert to complete remediation as recommended by EC. At its discretion, the insurer may arrange for the remediation or cash settle the complainants based upon the actionable quotation and in accordance with the terms and conditions of the policy. If the insurer cash settles the claim, it is to add a 20% uplift to the actionable quotation, to account for contingencies. The insurer is also to have due regard to its obligations under the policy for food in the fridge and emergency accommodation. 2.2 Incorrect settlement advice from the insurer? The exchanged material confirms that on 1 August 2022, the insurer sent the complainants a cash settlement fact sheet offering amounts for damage to the building and contents. The insurer then contacted the complainants on 8 August 2022, to advise that the offer was sent in error and the partial denial of the claim remained and that the insurer would not raise the money referred to in the offer. There is no evidence that the complainants acted to their detriment, based on the 1 August 2022, correspondence. In the circumstances I am not satisfied that the insurer is required to take any further action, save for taking steps to ensure that the error does not occur on another claim. 2.3 Why is the outcome fair? The outcome is fair as the insurer is required to consider the exchanged material to determine its obligations to the complainant, under the terms and conditions of the policy, regarding the claim. Determination | Case number: 933375 Page 7 of 7 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.