Bank delayed issuing loan offer and misled complainants that the lapsed loan was available
Text of the determination
Determination
Case number 931792
Financial firm St George Bank
Determination | Case number: 931792 Page 2 of 9
Case number: 931792 14 August 2023
1 Determination overview
1.1 Complaint
In 2021, the complainants applied, through their broker, for a loan with the financial firm
(bank) to finance the construction of a residential investment home on vacant land. The bank
approved the loan (loan 1) and generated a letter of offer on 17 November 2021 which the
complainants signed in February 2022. By time they signed, however, the loan 1 offer had
lapsed, and in June 2022, the bank reassessed and reapproved the construction finance
(loan 2). The complainants signed and accepted loan 2 in June 2022. The complainants say:
the bank delayed sending them the loan 1 offer,
when they signed accepting the offer, they did not know the offer had lapsed as the bank
did not tell them,
until May 2022 the bank misled them to believe loan 1 was in place and would be available
to fund the construction, and
because of the bank‟s conduct, the builder sought to cancel the building contract, this
forced them to agree to a building contract variation increasing building costs by
approximately $80,000, construction was delayed by twelve months resulting in lost rental
income and they suffered significant stress and inconvenience.
1.2 Issues and key findings
Did the bank mislead the complainants?
Yes. The bank misled the complainants to believe loan 1 was in place and would be available
to drawdown when it was not. The loan 1 loan approval expired or lapsed sometime between
December 2021 and February 2022, but the bank failed to inform the complainants of this
until May 2022.
Is the bank liable to pay the complainants compensation?
The bank should pay the complainants non-financial loss compensation of $4,000 for the
stress, upset and inconvenience caused by the bank‟s delay and misleading conduct. The
bank is not required to pay any additional compensation as its conduct did not cause the
increased construction costs and building delays.
Why is the outcome fair?
The bank‟s conduct caused the complainants stress, upset and inconvenience over several
months and it is fair the bank pays them non-financial loss compensation. It would not,
however, be fair to require the bank to compensate the complainants for construction cost
increases and delays when the a vailable information does not establish the bank‟s conduct
was the cause of these.
1.3 Determination
This determination is substantially in favour of the complainants save for I have not awarded
the compensations they were seeking. The bank should pay them total compensation of
$4,000.
Determination | Case number: 931792 Page 3 of 9
2 Reasons for determination
2.1 Did the bank mislead the complainants?
Yes. The bank misled the complainants to believe loan 1 was in place and would be available
to drawdown when it was not. The loan 1 loan approval expired or lapsed sometime between
December 2021 and February 2022, but the bank failed to inform the complainants of this
until May 2022.
The bank delayed making the loan 1 offer documents available to the
complainants
The bank approved loan 1 and generated a digital “Residential Loan Agreement offer‟ (offer)
on 17 November 2021.
On the available information, the complainants (or their broker) followed up the offer
documents with the bank several times, including on 30 November, 4, 7 and 8 December
2021, 7 January 2022 (when the broker applied for a loan 1 pricing reduction), and again on 8
February 2022.
During the complaint, the bank provided the complainants and AFCA with some inconsistent
information about whether the offer had been mailed or emailed, to who, when it did this, and
whether when emailed the offer was sent to a valid email address.
Ultimately, however, the bank acknowledged it could not establish it properly issued the loan
offer to the complainants or their broker until 8 February 2022 when it says it emailed the offer
to the branch for printing. This was an unreasonable delay and poor service.
The loan 1 offer expired
The offer included the following clause:
… to accept the Loan Offer, please sign, date and return to us at our address given under
“Contact Details” within 14 days o f the date of the letter enclosing it …
If we receive your acceptance after this time, your acceptanc e will only be effective where
this is consistent with us complying with our responsible lending obligations …
The bank says the offer is required to be signed and returned within 14 days of the offer date,
which in this case was 1 December 2021.
The bank also says its offer must be accepted within 90 days of being issued, from the
issuing date on 17 November 2021 which would be 15 February 2022.
The complainant came into the branch to sign the offer on 22 February 2022. The bank has
provided an internal email dated 24 February 2022 which says the loan documents are not
acceptable as they are expired.
Based on the available information, I accept loan 1 had at least expired on or about 15
February 2022 and it seems its availability was subject to the bank‟s discretion between 1
December 2021 and 15 February 2022.
Determination | Case number: 931792 Page 4 of 9
The complainants are not responsible for the loan 1 expiry
The complainants signed the offer documents on 22 February 2022 at the branch, after it had
expired, despite them being on notice it was available from 8 February 2022.
I do not accept, however, that it would be reasonable to hold the complainants responsible for
the loan expiring before they signed accepting it.
There is no information to show that at any time on or before 22 February 2022, the bank
warned the complainants the loan had expired or was at risk of expiry and that time was of
the essence to sign. Further, it had been the bank who had originally, delayed making the
documents available and the complainants had regularly followed them up over the prior
three months. And I note that the building approvals had not yet issued.
The bank misled the complainants the loan was available
The complainants finalised the building approvals in May 2022. They have supplied a notice
of commencement of building work which they signed on 13 May 2022 and which nominated
a building commencement date of on or about 17 May 2022.
To commence building, however, under the building contract (Clause 4.1(d)), the builder also
required written notice from the complainants‟ bank showing the amount of finance approved
and confirming building works may commence. After 13 May 2022, therefore, the
complainants sought this notice from the bank.
Following the request, t he bank‟s notes indicate it was attempting to arrange the notice, but it
appears that it was not until 26 May 2022 that the bank properly realised the it could not do so
because the loan was not in place.
Further, in the period up to 23 May 2022, the bank‟s note s show it was consistently informing
the complainants that the loan was in „approved status‟ . It did not tell the complainants that
the offer had expired or may have expired and that the complainants would need to reapply
for the finance.
The bank says:
If [the complainant] had called our cont act centre then I would not expect that our front line
call centre staff would have understood that the [loan 1] contracts had expired as they
would not have had that information, so to that extent we would agree it was more likely
than not that he was not informed they had expired. Our records do indicate that we did
notify his broker and his broker being his agent should have informed [the complainant],
this is the generally accepted method by which information between the bank and the
borrower is exchanged with broker introduced applications.
The bank is referring to its internal email dated 24 February 2022 mentioned above, which
had identified the offer documents had expired and could not be accepted. The complainants
say the bank did not inform the broker.
The bank has not provided documentation which establishes the broker was on notice loan 1
had expired on or about 24 February 2022 or before 26 May 2022. The available information
shows that the bank told the complainant that the loan had expired on or about 26 May 2022.
I accept the complainants would reasonably have understood from the information the bank
was supplying until 26 May 2022, that loan 1 was available to be drawn to fund the building
works. I am satisfied the bank misled the complainants.
Determination | Case number: 931792 Page 5 of 9
2.2 Is the bank liable to pay the complainants compensation?
The bank should pay the complainants non-financial loss compensation of $4,000 for the
stress, upset and inconvenience caused by the bank‟s delay and misleading conduct. The
bank is not required to pay any additional compensation as its conduct did not cause the
increased construction costs and building delays.
The bank approved loan 2 in June 2022
The bank approved the fresh application for loan 2 on or about 6 June 2022. After initially
issuing loan documents with a typographical error, the bank issued further loan documents on
7 June 2022 which its notes say it sent to the branch on 8 June 2022 (a Wednesday) by
internal mail. It is not clear from the available information how long the internal mail took or
when the bank informed the complainants the documents were available. The complainants
signed the documents on 15 June 2022.
On 23 June 2022, the bank issued the commencement notice satisfying clause 4.1 (d) of the
building contract.
The builder could not secure insurance
The complainants have provided an email they received from their builder on 20 June 2022
saying:
As you may be aware that building industry is going through one of the toughest time at
the moment. This is also impacting [builder]. We are not able to get HBCF [ The Home
Building Compensation Fund NSW] Insurance your project at this stage and cannot
guarantee how long it will take.
Without HBCF Insuranc e, we cannot commence on construction. I regret to say that we
have no choice but to cancel your project. We will review the cost incurred for this project
to date and refund any excess amount. Kindly email me your bank details.
We will also provide you wit h a letter that will allow you to built with someone else.
Once again, my sincere apologies for any inconvenience caused . [sic]
The Home Building Compensation Fund in NSW (HBCF) provides insurance for residential
building projects over $20,000. A builder is required to obtain this cover before they
commence work. This is also a bank pre-requisite before the loan can be drawn.
Subsequently, the complainants say they sought quotes from other builders which were
significantly higher, and they negotiated with their original builder ultimately agreeing on an
increase in the contract price by $50,000 plus another $30,000 for variations. The
complainants say there have since been other building delays which mean the building is still
now only 50% complete.
The complainants say, but for the bank‟s conduct, they would have finished the building 12
months earlier and under the original contract price terms.
The bank’s conduct did not cause the complainants ’ financial loss
For the reasons set out above, I accept that the bank delayed, misled the complainants about
the status of the loan and provided poor service.
Determination | Case number: 931792 Page 6 of 9
Further, I accept that if the bank had provided the loan 1 documents earlier or had notified the
complainant in a reasonable timeframe the loan had expired, the complainants could have
had a loan in place on or about 17 May 2022 (the building commencement date on the
notice), albeit subject to builder insurance.
However, I do not accept that the bank‟s conduct led to the failure of the builder to commence
work and to the delays the complainants have experienced.
The builder‟s email dated 20 June 2022 above shows that the builder was not in a position to
commence building regardless of the status of the complainants‟ loan . The complainants
have not provided any information to show that if the builder had received the bank‟s
commencement letter earlier (sometime between 13 May and 20 June 2022), rather than
three days after the builder‟s email, the builder would have been able to secure the insurance
and commence building.
In support of their claim, the complainants say the builder commenced a project for a friend in
April 2022. However, the earliest commencement date for the complainants was 17 May 2022
and they have not provided any information to show the builder could have commenced on or
after this.
The complainants have also submitted a letter from their builder dated 15 June 2023 to AFCA
saying:
This is to advise you that the price on the signed tender and contract dated 24/09/2021
had validity till June 2022. Since, we did not receive the commencement letter from the
bank prior to June 2022, [the builder] increased the contract price upon review of this
project.
Should you have any questions then please do not hesitate to contact me.
The complainants have not, however, provided any information to show that the above
formed a specific term of the contract or that the builder had any such right. Nor have they
provided any contemporaneous evidence that the builder exercised that right in June 2022. I
also note that this letter is inconsistent with the email of 20 June 2022 when the builder
advised its failure to obtain insurance was the reason it needed to cancel the contract and
made its offer to refund some costs.
The available information shows the builder could not commence building between 17 May
and 23 June 2022, because he did not have insurance; not because he did not have the bank
commencement letter. T here is no information available to me to show the bank‟s poor
conduct in relation to the loan caused the complainants to breach their building contract
leading to the losses they are claiming.
The bank is not, the refore, liable for the complainants‟ claims for increased building costs and
delays.
The bank should pay the complainants non-financial loss compensation
AFCA has the power to award compensation for loss and damage caused by a financial firm‟s
error or breach. Any award of compensation is subject to our compensation caps (which are
available in our Rules at www.afca.org.au ). AFCA has no power to award punitive damages
and generally will not award compensation for a co mplainant‟s time spent pursuing a
complaint.
Determination | Case number: 931792 Page 7 of 9
Non-financial loss compensation is compensation for unusual stress, inconvenience and/or
loss of enjoyment and upset caused by a financial firm‟s breach or error. We will only award
compensation for non-financial loss if the available information shows the complainant
suffered unusual stress, inconvenience and/or upset above what we would expect a
reasonable person to bear when dealing with an unexpected error.
The bank caused both complainants unnecessary stress, upset and inconvenience when the
complainants needed to repeatedly follow up the loan 1 documents, had to deal with the
shock of realising in late May 2022 that loan 1 was not in place, and lodge a new application.
The bank should pay the complainants non-financial loss compensation of $2,000 each for
this (a total of $4,000) to their nominated account within seven days of their acceptance of
this determination.
I also appreciate that the complainants have suffered very significant stress, upset and
inconvenience because their building has been delayed and the costs rose substantially.
However, the bank is not responsible for this, so it is not liable to further compensate the
complainants.
2.3 Why is the outcome fair?
It is fair the bank pays the complainants non-financial loss compensation
I am required to assess the bank‟s conduct based on what is fair in all the circumstances,
having regard to factors such as legal principles, good industry practice, codes of practice
and previous decisions (which are not binding).
Given the bank‟s conduct set out above, it is fair that the bank pays the complainant s non-
financial loss compensation for the unnecessary stress, upset and inconvenience it has
caused.
It would not, however, be fair to require the bank to pay for construction cost increases and
delays and the stress, upset and inconvenience associated with this, when the available
information does not establish the bank‟s conduct was the cause.
Determination | Case number: 931792 Page 8 of 9
3 Supporting information
3.1 The AFCA process
AFCA’s a pproach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
3.2 Timeline of key events
Date Details
24 Sep 2021 Date of build ing contract for an agreed pric e of $546,275
9 Oct 2021 The complainants paid balance of 5% deposit ($22,313.75) to builder
16 Nov 2021 The bank approved loan 1
17 Nov 2021 Date on loan 1 Loan offer documents
8 Feb 2022 The bank sent the loan 1 documents to the branch
22 Feb 2022 The c omplainants signed loan 1 documents
Determination | Case number: 931792 Page 9 of 9
13 May 2022 The complainants signed the Notice of Commencement of Building Works
with a nominated building commencement date of 17 May 2022
26 May 2022 The bank identified loan 1 had expired/lapsed
28 May 2022 The complainants submitted loan application 2
3 Jun 2022 The b ank re - approved loan application 2
8 Jun 2022 The bank sent loan contract 2 to branch
15 Jun 2022 The co mplainants signed and accepted loan contract 2
20 Jun 2022 B uilder email to complainants re insuranc e and decision to end contract.
23 Jun 2022 The bank issued the authority to commence construction letter
27 Aug 2022 The builder issued the complainants with a co ntract variation