Home / Westpac / Determination 931792

Determination 931792

Bank delayed issuing loan offer and misled complainants that the lapsed loan was available

FirmWestpac
Decided2023-08-31
ProductCredit · Home loan
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$4,000
Amount claimed—
SourceAFCA PDF

Summary

Complainants said the bank delayed issuing a construction loan offer and misled them that it was still available after it lapsed, causing building cost increases and delays. AFCA found the bank delayed and misled them and ordered $4,000 non-financial loss, but rejected the claim for increased building costs and delays.

The bank's delay and misleading conduct caused stress and inconvenience, but the builder's inability to obtain insurance, not the bank's conduct, caused the cost increases and delays.

Issues

Subjects and remedies

broker or intermediaryhome or building damagepay non financial loss

Related

All Westpac determinations · Find similar determinations

Text of the determination

Determination Case number 931792 Financial firm St George Bank Determination | Case number: 931792 Page 2 of 9 Case number: 931792 14 August 2023 1 Determination overview 1.1 Complaint In 2021, the complainants applied, through their broker, for a loan with the financial firm (bank) to finance the construction of a residential investment home on vacant land. The bank approved the loan (loan 1) and generated a letter of offer on 17 November 2021 which the complainants signed in February 2022. By time they signed, however, the loan 1 offer had lapsed, and in June 2022, the bank reassessed and reapproved the construction finance (loan 2). The complainants signed and accepted loan 2 in June 2022. The complainants say:  the bank delayed sending them the loan 1 offer,  when they signed accepting the offer, they did not know the offer had lapsed as the bank did not tell them,  until May 2022 the bank misled them to believe loan 1 was in place and would be available to fund the construction, and  because of the bank‟s conduct, the builder sought to cancel the building contract, this forced them to agree to a building contract variation increasing building costs by approximately $80,000, construction was delayed by twelve months resulting in lost rental income and they suffered significant stress and inconvenience. 1.2 Issues and key findings Did the bank mislead the complainants? Yes. The bank misled the complainants to believe loan 1 was in place and would be available to drawdown when it was not. The loan 1 loan approval expired or lapsed sometime between December 2021 and February 2022, but the bank failed to inform the complainants of this until May 2022. Is the bank liable to pay the complainants compensation? The bank should pay the complainants non-financial loss compensation of $4,000 for the stress, upset and inconvenience caused by the bank‟s delay and misleading conduct. The bank is not required to pay any additional compensation as its conduct did not cause the increased construction costs and building delays. Why is the outcome fair? The bank‟s conduct caused the complainants stress, upset and inconvenience over several months and it is fair the bank pays them non-financial loss compensation. It would not, however, be fair to require the bank to compensate the complainants for construction cost increases and delays when the a vailable information does not establish the bank‟s conduct was the cause of these. 1.3 Determination This determination is substantially in favour of the complainants save for I have not awarded the compensations they were seeking. The bank should pay them total compensation of $4,000. Determination | Case number: 931792 Page 3 of 9 2 Reasons for determination 2.1 Did the bank mislead the complainants? Yes. The bank misled the complainants to believe loan 1 was in place and would be available to drawdown when it was not. The loan 1 loan approval expired or lapsed sometime between December 2021 and February 2022, but the bank failed to inform the complainants of this until May 2022. The bank delayed making the loan 1 offer documents available to the complainants The bank approved loan 1 and generated a digital “Residential Loan Agreement offer‟ (offer) on 17 November 2021. On the available information, the complainants (or their broker) followed up the offer documents with the bank several times, including on 30 November, 4, 7 and 8 December 2021, 7 January 2022 (when the broker applied for a loan 1 pricing reduction), and again on 8 February 2022. During the complaint, the bank provided the complainants and AFCA with some inconsistent information about whether the offer had been mailed or emailed, to who, when it did this, and whether when emailed the offer was sent to a valid email address. Ultimately, however, the bank acknowledged it could not establish it properly issued the loan offer to the complainants or their broker until 8 February 2022 when it says it emailed the offer to the branch for printing. This was an unreasonable delay and poor service. The loan 1 offer expired The offer included the following clause: … to accept the Loan Offer, please sign, date and return to us at our address given under “Contact Details” within 14 days o f the date of the letter enclosing it … If we receive your acceptance after this time, your acceptanc e will only be effective where this is consistent with us complying with our responsible lending obligations … The bank says the offer is required to be signed and returned within 14 days of the offer date, which in this case was 1 December 2021. The bank also says its offer must be accepted within 90 days of being issued, from the issuing date on 17 November 2021 which would be 15 February 2022. The complainant came into the branch to sign the offer on 22 February 2022. The bank has provided an internal email dated 24 February 2022 which says the loan documents are not acceptable as they are expired. Based on the available information, I accept loan 1 had at least expired on or about 15 February 2022 and it seems its availability was subject to the bank‟s discretion between 1 December 2021 and 15 February 2022. Determination | Case number: 931792 Page 4 of 9 The complainants are not responsible for the loan 1 expiry The complainants signed the offer documents on 22 February 2022 at the branch, after it had expired, despite them being on notice it was available from 8 February 2022. I do not accept, however, that it would be reasonable to hold the complainants responsible for the loan expiring before they signed accepting it. There is no information to show that at any time on or before 22 February 2022, the bank warned the complainants the loan had expired or was at risk of expiry and that time was of the essence to sign. Further, it had been the bank who had originally, delayed making the documents available and the complainants had regularly followed them up over the prior three months. And I note that the building approvals had not yet issued. The bank misled the complainants the loan was available The complainants finalised the building approvals in May 2022. They have supplied a notice of commencement of building work which they signed on 13 May 2022 and which nominated a building commencement date of on or about 17 May 2022. To commence building, however, under the building contract (Clause 4.1(d)), the builder also required written notice from the complainants‟ bank showing the amount of finance approved and confirming building works may commence. After 13 May 2022, therefore, the complainants sought this notice from the bank. Following the request, t he bank‟s notes indicate it was attempting to arrange the notice, but it appears that it was not until 26 May 2022 that the bank properly realised the it could not do so because the loan was not in place. Further, in the period up to 23 May 2022, the bank‟s note s show it was consistently informing the complainants that the loan was in „approved status‟ . It did not tell the complainants that the offer had expired or may have expired and that the complainants would need to reapply for the finance. The bank says: If [the complainant] had called our cont act centre then I would not expect that our front line call centre staff would have understood that the [loan 1] contracts had expired as they would not have had that information, so to that extent we would agree it was more likely than not that he was not informed they had expired. Our records do indicate that we did notify his broker and his broker being his agent should have informed [the complainant], this is the generally accepted method by which information between the bank and the borrower is exchanged with broker introduced applications. The bank is referring to its internal email dated 24 February 2022 mentioned above, which had identified the offer documents had expired and could not be accepted. The complainants say the bank did not inform the broker. The bank has not provided documentation which establishes the broker was on notice loan 1 had expired on or about 24 February 2022 or before 26 May 2022. The available information shows that the bank told the complainant that the loan had expired on or about 26 May 2022. I accept the complainants would reasonably have understood from the information the bank was supplying until 26 May 2022, that loan 1 was available to be drawn to fund the building works. I am satisfied the bank misled the complainants. Determination | Case number: 931792 Page 5 of 9 2.2 Is the bank liable to pay the complainants compensation? The bank should pay the complainants non-financial loss compensation of $4,000 for the stress, upset and inconvenience caused by the bank‟s delay and misleading conduct. The bank is not required to pay any additional compensation as its conduct did not cause the increased construction costs and building delays. The bank approved loan 2 in June 2022 The bank approved the fresh application for loan 2 on or about 6 June 2022. After initially issuing loan documents with a typographical error, the bank issued further loan documents on 7 June 2022 which its notes say it sent to the branch on 8 June 2022 (a Wednesday) by internal mail. It is not clear from the available information how long the internal mail took or when the bank informed the complainants the documents were available. The complainants signed the documents on 15 June 2022. On 23 June 2022, the bank issued the commencement notice satisfying clause 4.1 (d) of the building contract. The builder could not secure insurance The complainants have provided an email they received from their builder on 20 June 2022 saying: As you may be aware that building industry is going through one of the toughest time at the moment. This is also impacting [builder]. We are not able to get HBCF [ The Home Building Compensation Fund NSW] Insurance your project at this stage and cannot guarantee how long it will take. Without HBCF Insuranc e, we cannot commence on construction. I regret to say that we have no choice but to cancel your project. We will review the cost incurred for this project to date and refund any excess amount. Kindly email me your bank details. We will also provide you wit h a letter that will allow you to built with someone else. Once again, my sincere apologies for any inconvenience caused . [sic] The Home Building Compensation Fund in NSW (HBCF) provides insurance for residential building projects over $20,000. A builder is required to obtain this cover before they commence work. This is also a bank pre-requisite before the loan can be drawn. Subsequently, the complainants say they sought quotes from other builders which were significantly higher, and they negotiated with their original builder ultimately agreeing on an increase in the contract price by $50,000 plus another $30,000 for variations. The complainants say there have since been other building delays which mean the building is still now only 50% complete. The complainants say, but for the bank‟s conduct, they would have finished the building 12 months earlier and under the original contract price terms. The bank’s conduct did not cause the complainants ’ financial loss For the reasons set out above, I accept that the bank delayed, misled the complainants about the status of the loan and provided poor service. Determination | Case number: 931792 Page 6 of 9 Further, I accept that if the bank had provided the loan 1 documents earlier or had notified the complainant in a reasonable timeframe the loan had expired, the complainants could have had a loan in place on or about 17 May 2022 (the building commencement date on the notice), albeit subject to builder insurance. However, I do not accept that the bank‟s conduct led to the failure of the builder to commence work and to the delays the complainants have experienced. The builder‟s email dated 20 June 2022 above shows that the builder was not in a position to commence building regardless of the status of the complainants‟ loan . The complainants have not provided any information to show that if the builder had received the bank‟s commencement letter earlier (sometime between 13 May and 20 June 2022), rather than three days after the builder‟s email, the builder would have been able to secure the insurance and commence building. In support of their claim, the complainants say the builder commenced a project for a friend in April 2022. However, the earliest commencement date for the complainants was 17 May 2022 and they have not provided any information to show the builder could have commenced on or after this. The complainants have also submitted a letter from their builder dated 15 June 2023 to AFCA saying: This is to advise you that the price on the signed tender and contract dated 24/09/2021 had validity till June 2022. Since, we did not receive the commencement letter from the bank prior to June 2022, [the builder] increased the contract price upon review of this project. Should you have any questions then please do not hesitate to contact me. The complainants have not, however, provided any information to show that the above formed a specific term of the contract or that the builder had any such right. Nor have they provided any contemporaneous evidence that the builder exercised that right in June 2022. I also note that this letter is inconsistent with the email of 20 June 2022 when the builder advised its failure to obtain insurance was the reason it needed to cancel the contract and made its offer to refund some costs. The available information shows the builder could not commence building between 17 May and 23 June 2022, because he did not have insurance; not because he did not have the bank commencement letter. T here is no information available to me to show the bank‟s poor conduct in relation to the loan caused the complainants to breach their building contract leading to the losses they are claiming. The bank is not, the refore, liable for the complainants‟ claims for increased building costs and delays. The bank should pay the complainants non-financial loss compensation AFCA has the power to award compensation for loss and damage caused by a financial firm‟s error or breach. Any award of compensation is subject to our compensation caps (which are available in our Rules at www.afca.org.au ). AFCA has no power to award punitive damages and generally will not award compensation for a co mplainant‟s time spent pursuing a complaint. Determination | Case number: 931792 Page 7 of 9 Non-financial loss compensation is compensation for unusual stress, inconvenience and/or loss of enjoyment and upset caused by a financial firm‟s breach or error. We will only award compensation for non-financial loss if the available information shows the complainant suffered unusual stress, inconvenience and/or upset above what we would expect a reasonable person to bear when dealing with an unexpected error. The bank caused both complainants unnecessary stress, upset and inconvenience when the complainants needed to repeatedly follow up the loan 1 documents, had to deal with the shock of realising in late May 2022 that loan 1 was not in place, and lodge a new application. The bank should pay the complainants non-financial loss compensation of $2,000 each for this (a total of $4,000) to their nominated account within seven days of their acceptance of this determination. I also appreciate that the complainants have suffered very significant stress, upset and inconvenience because their building has been delayed and the costs rose substantially. However, the bank is not responsible for this, so it is not liable to further compensate the complainants. 2.3 Why is the outcome fair? It is fair the bank pays the complainants non-financial loss compensation I am required to assess the bank‟s conduct based on what is fair in all the circumstances, having regard to factors such as legal principles, good industry practice, codes of practice and previous decisions (which are not binding). Given the bank‟s conduct set out above, it is fair that the bank pays the complainant s non- financial loss compensation for the unnecessary stress, upset and inconvenience it has caused. It would not, however, be fair to require the bank to pay for construction cost increases and delays and the stress, upset and inconvenience associated with this, when the available information does not establish the bank‟s conduct was the cause. Determination | Case number: 931792 Page 8 of 9 3 Supporting information 3.1 The AFCA process AFCA’s a pproach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 Timeline of key events Date Details 24 Sep 2021 Date of build ing contract for an agreed pric e of $546,275 9 Oct 2021 The complainants paid balance of 5% deposit ($22,313.75) to builder 16 Nov 2021 The bank approved loan 1 17 Nov 2021 Date on loan 1 Loan offer documents 8 Feb 2022 The bank sent the loan 1 documents to the branch 22 Feb 2022 The c omplainants signed loan 1 documents Determination | Case number: 931792 Page 9 of 9 13 May 2022 The complainants signed the Notice of Commencement of Building Works with a nominated building commencement date of 17 May 2022 26 May 2022 The bank identified loan 1 had expired/lapsed 28 May 2022 The complainants submitted loan application 2 3 Jun 2022 The b ank re - approved loan application 2 8 Jun 2022 The bank sent loan contract 2 to branch 15 Jun 2022 The co mplainants signed and accepted loan contract 2 20 Jun 2022 B uilder email to complainants re insuranc e and decision to end contract. 23 Jun 2022 The bank issued the authority to commence construction letter 27 Aug 2022 The builder issued the complainants with a co ntract variation

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.