Cash settlement amount for flood damage to home, temporary accommodation and non-financial loss
Text of the determination
Determination
Case number 931260
Financial firm Hollard Insurance Partners Limited
Determination | Case number: 931260 Page 1 of 9
Case number: 931260 24 October 2023
1 Determination overview
1.1 Complaint
The complainant holds a home and contents insurance policy underwritten by the financial
firm (insurer). She lodged a claim for damage to her property by a flood on 8 March 2022.
The insurer accepted the claim. However, it says some of the damage was not related to the
flood and it is not liable for this. It obtained a scope of works (SOW) to repair the damage it
accepted as covered and paid this amount with a 20% contingency uplift to the complainant.
The complainant does not accept this. She wants her home rebuilt. She also wants temporary
accommodation until her home is repaired and compensation for non-financial loss.
1.2 Issues and key findings
Is the insurer required to do anything further?
Yes. Whilst the insurer is not required to change its SOW, the obtained quote is out of date.
The parties are required to obtain further repair quotes in accordance with section 2.1 of this
determination. The insurer is to then settle the claim as outlined in that section, including an
allowance for temporary accommodation costs.
Is an award of compensation required?
Yes. The insurer has not handled the matter well and the complainant and her family are
extremely vulnerable. The insurer must pay compensation for non-financial loss of $5,000.
Why is the outcome fair?
The support piers of the home are not in good condition and had significant pre-existing
damage. The insurer is not responsible to repair the piers. However, it is fair that the parties
both obtain new, actionable quotes, based on the complainant addressing the foundations
issue. The insurer is to settle based on the parameters set out below. It is also fair that the
insurer pays significant compensation for its poor handling of the claim.
1.3 Determination
This determination is mostly in favour of the insurer.
Within 14 days of the complainant accepting this determination, the insurer must contact her
to begin the process of implementing it. The insurer and the complainant must obtain new
repair quotes for the repair of the home and the insurer is to use these as a basis for
settlement. This must be done in accordance with the steps set out in section 2.1.
The insurer may then cash settle the complainant as set out in this section, including an
allowance for temporary accommodation, as specified. There is no need to include interest.
The insurer is required to pay the complainant compensation for non-financial loss of $5,000.
Determination | Case number: 931260 Page 2 of 9
2 Reasons for determination
The complainant is represented by a solicitor, MB. For convenience, unless indicated
otherwise, reference to „the complainant‟ will include both.
2.1 Is the insurer’s offer for the building damage fair?
Yes. Whilst the insurer is not required to change its SOW, the obtained quote is out of date.
The parties are required to obtain further repair quotes in accordance with section 2.1 of this
determination. The insurer is to then settle the claim as outlined in that section, including an
allowance for temporary accommodation costs.
Complainant seeks cover for building damage and temporary accommodation
The complainant‟s home was initially constructed in or around 1890, with renovations and
additions (including in 2017) added thereafter. It was flooded as part of a major inundation
event on 8 March 2022. The home was inundated about 500mm above floor level.
The insurer acknowledges there was extensive damage to the home, which requires repair. It
says some of this damage pre-dated the claim event and is not covered by the policy. The
insurer says this damage was due to a combination of construction defects, poor
workmanship, deterioration and wear and tear.
Whilst agreeing to cover the loss, the insurer limited its cover to only the damage it considers
was caused by the flood event. The insurer‟s nominated repairer (AJ) considers the repairs
cannot be warranted. The insurer therefore offered a cash settlement of $247,792.47 based
on AJ‟s repair quote and a 20% contingency uplift ($49,558.49). This meant a final settlement
offer of $297,350.96. The insurer paid this amount to the complainant on 30 March 2023.
The insurer also arranged temporary accommodation for the complainant and her family,
pending the resolution of the claim.
The complainant is unhappy with the settlement and does not accept it. She considers the
offer is not sufficient to address the damage. She wants to have the home repaired and the
temporary accommodation extended until this is complete.
Loss caused by flood is covered subject to policy terms and conditions
The terms of the policy include the Certificate of Insurance (COI) and the Product Disclosure
Statement (PDS). There is no dispute the insurer sent these documents to the complainant.
Further, there is no dispute the home was significantly inundated and the claimed loss (flood)
is covered under the terms of the policy.
The insurer partially accepted the claim for building damage but says it can limit this cover as
much of the claimed damage pre-dated or was not related to the flood event. The
complainant denies this.
Given there is obvious flood damage throughout the home, I am satisfied the onus rests with
the insurer to explain why some of this damage should not be covered.
Insurer must exercise policy discretion to cash settle fairly
Under the terms of the policy, the insurer says it will decide whether to:
Determination | Case number: 931260 Page 3 of 9
repair or rebuild the lost or damaged part of your building ;
replace your building ;
… ; or
pay you the amount we determine to be the reasonable cost or repairing or
rebuilding the lost or damaged part of your building up to the sum insured
stated on your [COI] .
In this case, the insurer has opted to cash settle the claim. The discretion to settle by way of a
cash settlement is not absolute. It must be exercised fairly. As the purpose of the policy is to
insure the building and contents, it is always preferable that damage to the building is
repaired, unless it is not viable to do so.
Where a claim is settled by way of a cash settlement, the insurer is required to pay the
reasonable cost to repair the damage to the property. The cash settlement should be
sufficient to ensure that the complainant is able to engage her own contractors to complete
the claim-related repairs.
Engineer says renovations to home not compliant with building code
The insurer engaged a consulting engineer, SC to review the damage. SC attended the home
on 23 June 2022, confirming there was extensive flood damage. It also identified significant
pre-existing damage and maintenance issues.
SC wrote that the rear pergola was converted into a bedroom and bathroom in 2017. The
converted bathroom area ‟ s ceiling was 1.8m. SC says this is less than the 2.1m height
required under the Building Code of Australia (BCA) at the time. It considers the conversion of
the rear extension into a bedroom/bathroom was not compliant with requirements of the BCA.
Further, SC found:
the footing system consists of a combination of sandstone piers with loose bricks propping
up the floor framing
the home was founded on „loose – very loose silty sand material ‟
the flooding of this sandy material does „not have a significant influence on the footings‟,
unless there is erosion, which can undermine them and cause subsidence
no influence from the flood on these footings was found
the sandy material was „ poorly graded, and typically experiences long-term subsidence as
a result of long-term consolidation and settlement of the foundation material ‟ .
SC ‟s report concludes the home is repairable as it only requires „non - structural repairs‟. Any
footing movement is „ consistent with long-term consolidation and subsidence of the footing
system ‟ . It provided a SOW for repairs related to the flood damage.
Based on this SOW, the insurer sought repair tenders. It received three quotes from local
builders:
AJ quoted for $247,792.47
SH quoted $438,275.50, and
MC quoted $161,283.98.
The insurer decided to settle the claim based on the AJ quote. This was on the basis the
quote was more competitive. It says the SH quote includes repair/upgrade to the rear
extension and the policy does not cover costs associated with the defects.
Determination | Case number: 931260 Page 4 of 9
Noting SH also did not individually itemise its costings, I am not satisfied this quote should be
preferred. MC did not visit the home. None of the repairers were prepared to warrant the work
(or undertake it ). However, AJ‟s quote was used by the insurer as a basis for settlement.
Complainant says insurer’s cash settlement offer is inadequate
The complainant says that the insurer‟s cash settlement was inadequate . She believes the AJ
quote is not a reasonable assessment of the cost of repairing the claimed damage.
The complainant provided a report dated 24 March 2023 from consulting engineer CS. CS
attended the property on 24 January 2023, concluding:
I confirm the existing dwelling structure was never repairable and that the best
solution, was always to “knock - down and rebuild”.
CS says the footings were incorrectly described by SC as „concrete pad footing‟, which is not
correct. There are no pads and no sandstone piers. It is best described as an „ unstable
fo undation system‟, which is due to the „passage of flood waters‟ through the property. CS
also notes SC did not address the drop in the flooring after the event, which it acknowledges
was one of the complainant‟s concerns.
As the home was inundated 500mm above floor level (and about 500mm above ground level,
due to the piers), this doubles the pressure load from the flood on the home. CS disagrees
with SC‟s view that flooding would not typically impact this type of footing. It considers the
level of flooding caused:
differential settlement and has then affected the bearers, joists, walls and roof, all
of which are no longer stable.
Once the flooring, wall and ceiling linings are removed „the timber structure will become
completely unstable‟ and could collapse . Structural certification of the building would need to
be confirmed before any repair work could be undertaken. This is not in the SOW.
The complainant later provided a quote from CR for $1,149,500.00 to rebuild the home.
Evidence of long-term footing movement which SC says is not flood related
SC reviewed the CS report. It considers there is:
clear evidence of long-term deterioration and historic replacement of original
sandstone footings with loosely stacked brickwork,
This sandstone portion of the pad footing was about 75mm below natural ground level. SC
says there was no collapse of the footings observed at the time of inspection. There is no
evidence they were affected by the flood.
The footings are unstable due to the „original defective construction‟ of the footing system and
prior repairs, not the flood. I accept the photos show an unstable and apparently imprecise
use of bricks to support the piers under the home. It does not look stable.
SC notes there were no cracking or movement-related cracks in the home. I accept this would
likely be expected if there was foundation movement from the flood event.
Determination | Case number: 931260 Page 5 of 9
SC challenges CS‟s findings about the pressure brought to bear by the water flow. It says
there is no evidence the foundations were affected. Any difference in the floor levels is due to
long-term settlement and consolidation of the footings. This is a pre-existing defect.
CS maintained its view. Given the extent of damage and the flood, CS considers there is no
other reasonable alternative other than to rebuild the home.
Exchanged material does not show insurer is liable to replace the footings
The insurer cites two major reasons it cannot repair the home:
problems with the footings which it says are not related to the flood event
renovations in 2017 not being conducted in accordance with the building code, leaving the
ceiling spaces in some rooms too low.
The respective engineers disagree over the state of the footings.
Photos from under the home show the piers have been supported in some areas using bricks.
When this work was conducted is not known, however it clearly pre-dated the flood event.
I acknowledge this method has been successful, if unorthodox. The photos inside the home
(after the flood event) show no persuasive evidence of significant footing movement. Such
movement would reasonably be expected to cause issues with the flooring and cracks in the
walls. These are not evident.
AJ undertook a thorough examination of the home and the damage when it was preparing a
repair quote. It noted the issues with the foundations and agreed with CS that these:
are consistent with long-term subsidence as a result of long-term consolidation
and settlement of the foundation material.
AJ also confirmed:
The existing footing system is consistent with the combination of a sandstone pier
with loose bricks installed and propping of the existing floor framing structure.
There was no flood related lateral movement, floatation or dislodged bricks
observed at the time of our inspection.
Based on this, I accept any footing movement, on balance, pre-dated the flood event.
Whilst this may have been exacerbated by the flood event, I am satisfied it can be primarily
attributed to the unusual nature of the footing system. I am not persuaded the severity of the
flooding event was the dominant or effective cause of any issues.
The complainant and CS highlight issues accepted by the insurer at a nearby property as
evidence that the home requires a rebuild. Each claim and the damage to each home must
be considered on merit. I am not satisfied that because another home requires a rebuild, that
the situation is automatically replicable to the complainant‟s home.
On balance, I not satisfied the evidence is persuasive that the flood caused damage to the
footings which requires their replacement. I acknowledge the footings likely should be
replaced. However, I consider this is more due to the haphazard nature of their construction
and maintenance, rather than the claimed event.
Given this, I accept the insurer is not liable to rebuild the entire home.
Determination | Case number: 931260 Page 6 of 9
Whilst I have not considered the issue with the ceiling heights, I note CS did not detail the
exact BCA areas which were not complied with. I am also not convinced by this evidence that
any such breach is necessarily an impediment to repairing the home.
Unfair to rely on quotes obtained as a basis for settlement
I acknowledge none of the insurer‟s repairers have quoted with the intention of completing the
work at the complainant‟s property. There is no actionable quote which has been prepared on
behalf of the insurer.
I accept this is largely due to the footings and their likely unsuitability for a rebuild. This does
not mean the insurer is liable for the footings. As noted above, there is no persuasive
evidence they were damaged by the event. To the extent they were, this is due to the manner
of their construction and maintenance.
I also accept this might be due to concerns over the viability of the structure once it is
stripped. This was noted by CS.
The repair of the home will be extensive and almost total. I dismissed consideration of the MC
quote (too low), the CR quote (too expensive) and SH quote (it did not itemise the individual
costings). Therefore, I consider the best analysis of the required damage is likely the
(unactionable) AJ quote. However, I note this quote was compiled on 9 September 2022.
I accept the home has likely deteriorated further since this quote was prepared. The costs to
repair it have likely increased. To this end, I consider the fairest way to resolve this matter is
to get additional repair quotes to use as a basis for settlement.
Parties to work cooperatively to arrange new quotes to settle the claim
The parties must each engage an independent builder to prepare up-to-date quotes to repair
the home. The insurer may use AJ again, if it chooses. Each builder must visit the site and
prepare a new quote. The repair quotes must be itemised and costed, based on the SC
SOW.
The quotes obtained and considered must be actionable on the basis that the complainant
agrees to independently address and repair the issues with the footings. This will include
ensuring they are commensurate with current building standards.
The insurer is to cash settle the claim based on the average of the two quotations with a 25%
contingency uplift, less the amount it has already paid to the complainant. This is on the basis
the average of the two quotes does not exceed the building sum insured applicable at the
time of the loss.
The contingency uplift serves to address the transfer of risk passing to the complainant to
complete the work. It will also compensate her for the loss of the lifetime guarantee and
caters to the possibility there may likely be variations required during the works.
An allowance must also be made for further mould treatment and asbestos removal at the
property if it proves necessary.
Given any cash settlement will be based on an up-to-date estimates with a contingency uplift,
I am satisfied there is no need to award interest.
Insurer to extend te mporary accommodation to cater for repair work
There is no dis pute that until the repairs are completed the complainant‟s home remains
uninhabitable.
Determination | Case number: 931260 Page 7 of 9
Whilst the insurer has already paid more than the policy limit for temporary accommodation,
this is due to the delays involved in reviewing and determining the extent of the loss.
I am satisfied the insurer should continue to provide cover for temporary accommodation until
it is ready to settle the claim.
As part of the quoting process, each repairer is to estimate a fair repair period to undertake
the necessary claim related repair work. Once it is ready to propose settlement, the insurer is
to:
average the amount of the respective time estimates and use this as a basis for calculating
an extended period applicable for temporary accommodation
allow an additional 12 weeks for the time it will reasonably take to permit the repairer to
commit to the work
further allow additional time for mould treatment and/or asbestos removal timeframes,
should it extend the repair delay
add a 15% contingency to this estimate to account for any additional and reasonable
delays which may occur.
2.2 Is an award of compensation required?
Yes. The insurer has not handled the matter well and the complainant and her family are
extremely vulnerable. The insurer must pay compensation for non-financial loss of $5,000.
AFCA can award compensation for non-financial loss
Under our Rules, AFCA can award up to $5,400 compensation for non-financial loss. This
must relate to poor claims handling or other actions of the insurer which cause an unusual
degree of stress, delay, or inconvenience.
We expect complainants to be moderately robust, and we will not award compensation for the
ordinary degree of inconvenience involved in making a claim.
Insurer is to pay compensation for non-financial loss of $5,000
The insurer acknowledges there were significant delays with the claim and communication
issues with the complainant. It offered to pay compensation for non-financial loss of $2,000
on 8 December 2022.
I accept the complainant was extremely vulnerable, with two dependent children, including
one with significant personal challenges. The complainant detailed numerous instances
where her correspondence to the insurer went unanswered.
The insurer also contacted her bank about a mortgage payout unnecessarily. It did not obtain
an actionable quote to repair the home or adequately explore options to assist the
complainant, noting her vulnerable state.
I consider these issues considerably and significantly upset the complainant over and above
the trauma of the damage caused to her home. I accept she suffered an unusual degree of
stress, delay and inconvenience in the handling of this matter.
Whilst the insurer apologised for not handling the matter as well as it should have, I am not
satisfied it has adequately acknowledged or accounted for its failures. I am further concerned
about the significant impact this has had on the complainant.
Determination | Case number: 931260 Page 8 of 9
To this end, I consider a substantial compensatory payment for non-financial loss is
warranted. I am satisfied the insurer should pay $5,000 to the complainant.
2.3 Why is the outcome fair?
The support piers of the home are not in good condition and had significant pre-existing
damage. The insurer is not responsible to repair the piers. However, it is fair that the parties
both obtain new, actionable quotes, based on the complainant addressing the foundations
issue. The insurer is to settle based on the parameters set out above. It is also fair that the
insurer pays significant compensation for its poor handling of the claim.
Determination | Case number: 931260 Page 9 of 9
3 Supporting information
3.1 The AFCA processes
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.