Claim declined for storm and land slip damage; insurer relied on exclusions for retaining walls, driveways, wear and tear, maintenance and soil movement

FirmAllianz Australia
Decided2023-11-30
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The insurer declined a storm and land slip damage claim at the complainant's Lismore home, relying on exclusions. AFCA found the storm was the proximate cause, required the insurer to scope and repair or cash settle (including the stone retaining wall), and reimburse the expert report cost with interest, but upheld the exclusion for timber retaining walls and the driveway.

The storm was the proximate cause of the damage based on the more persuasive engineering evidence, so exclusions did not apply except for the timber retaining walls and driveway, with the pool retaining wall being necessary to repair covered damage.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay compensationpay interestreassess claimrepair or rectify

Related

All Allianz Australia determinations · Find similar determinations

Text of the determination

Determination Case number 930946 Financial firm Allianz Australia General Insurance Limited Determination | Case number: 930946 Page 1 of 12 Case number: 930946 27 November 2023 1 Determination overview 1.1 Complaint The complainant holds an events-based home and contents insurance policy with the financial firm (insurer). On 9 March 2022 he lodged a claim for damage to his property, including damage to retaining walls and the driveway. This followed a land slip which occurred due to severe storms. The insurer denied the claim on the following bases:-  The policy does not provide cover for damage to retaining walls or driveways  Damage to the property was caused by wear and tear and gradual deterioration, as well as the complainant’s failure to t ake reasonable steps to keep his property well maintained  Damage to the property was caused by soil movement unrelated to an insured event. The complainant disagrees and says the insurer should accept the claim in full. 1.2 Issues and key findings Should the insurer accept the claim? Yes. The evidence demonstrates the proximate cause of the damage to the complainant’s home and property was an insured event. Moreover, the insurer is not entitled to rely upon policy exclusions to deny the claim. Should the damaged retaining walls and driveway be covered? The damage to the complainant’s property and home was caused by an insured event and was much broader and widespread than the damage to the retaining walls and the driveway. The repair and or replacement of the stone retaining wall adjacent to the pool is a fundamental element of the work necessary to repair the claim-related damage to the property. The damage to the timber retaining walls and the driveway is otherwise subject to policy exclusions. Should the complainant be reimbursed for the cost of an expert report? Yes. The insurer is to reimburse to the complainant the cost of an expert report, together with interest on this sum. The expert report helped establish the cause of the damage. Why is the outcome fair? The outcome is fair in all the circumstances because:-  The complainant has established a valid claim for damage to his home and property caused by an insured event  The insurer is not entitled to rely upon policy exclusions to deny the claim, apart from the exclusion related to the timber retaining walls and the driveway Determination | Case number: 930946 Page 2 of 12  The repair and/or reinstatement of the stone retaining wall adjacent to the pool is fundamental to the repair of the storm- related damage to the complainant’s property  The reimbursement of the cost of an expert report obtained by the complainant is appropriate and fair  Throughout this complaint AFCA’s approach has remained objective, consistent with the facts and based on the law. 1.3 Determination This determination is in favour of the complainant. The complaint should be resolved in accordance with section 2.4, below. Determination | Case number: 930946 Page 3 of 12 2 Reasons for determination 2.1 Should the insurer accept the claim? The claim The complainant’s home is loca ted in Lismore, New South Wales. It is a single storey brick structure that sits atop brick stumps. The home has a sheet metal roof. A garage is built upon a concrete slab foundation. There is also a pool on the property, surrounded by a pool fence and gate, which is stabilised by an adjacent stone and masonry retaining wall. The storms and heavy rain which hit parts of south east Queensland and New South Wales in February 2022 are well documented. The weather event ultimately caused catastrophic flooding in parts, including in Lismore. Although the complainant’s home was not flooded (as it is located on land that is slightly elevated and inclined), the complainant described the amount of rain which fell on his property as “biblical”. The complainant says the excessive rainfall caused part of the land on his property to move or “slip” . This, in turn, caused structural damage to the interior and exterior of his home and garage (including a veranda and deck area), as well as structural damage to the pool, the pool fence and gate, and the stone retaining wall. Two timber retaining walls on other parts of the property were also damaged, as were sections of the bitumen driveway. The complainant says his home and property were, generally, in good condition prior to February 2022. He says there were no structural issues affecting the dwelling, the garage, the pool, the retaining walls or the driveway. Parties agree about certain issues Despite the dispute between the parties, they do agree about several issues, including:-  The weather event which affected Lismore and other parts of Queensland and New South Wales in February 2022 was severe. It was categorised as a “ CAT 221 ” catastrophe event by the Insurance Council of Australia  The complainant’s home was constructed in about 2003  The complainant has provided documentation proving his home was constructed in accordance with all applicable building codes. These documents include engineer’s drawings and a “Construction Certificate” issued by Lismore City Council in November 2007  According to a letter from PL, structural engineers, to the Lismore City Council dated 18 December 2001, the subsurface conditions of the complain ant’s property may be summar ised as “highly reactive clay strata”  The complainant’s policy provides a “Quality Care” level of cover for insured events  The complainant’s policy does not provide cover for “Accidental loss or damage”. Complainant has onus to establish valid claim It is established insurance law that the complainant first has the onus to establish the claimed loss is a result of an event covered under the policy. This must be established on the balance of probabilities, meaning that it is more likely than not. This is sometimes called a prima facie valid claim. Determination | Case number: 930946 Page 4 of 12 If the complainant is able to establish a prima facie valid claim, the onus shifts to the insurer to show, on the balance of probabilities, it is entitled to rely on an exclusion under the policy or is otherwise entitled to decline the claim. The policy c overs loss or damage caused by an insured event, being the in cidents listed in the Product Disclosure Statement ( PDS) and the Certificate of Insurance . Page 57 of the P DS defines and “insured event” as: - insured event or event:- ….. a happening which may give rise to a claim within the terms and conditions of this policy. These events include “ storm ” (see p age 26 of the PDS). Storm Covered:-  Loss or damage caused by storm, including cyclone, hail, wind, snow or rain. Moreover, an insured event or incident is generally taken to mean a single event or occurrence (such as a storm), or a series of events or incidents attributable to one source or originating cause (such as several separate storms caused by one weather event). The CAT 221 natural disaster which affected Lismore in February 2022 is one such event. Following the rains of February 2022, the insurer arranged for a representative of AJ, builders, to inspect the complainant’s property on 31 May 2022 and conduct make-safe works. AJ’s report compiled pursuant to that inspection is comprehensive and is support ed by many illustrative photographs. AJ observed and documented a great deal of damage including, but not limited to:-  The concrete slab in the garage had dropped by approximately 10mm and the brickwork on the left side of the garage was cracked  Internal flooring in parts of the dwelling had also dropped by about 10mm  Cracking in internal plasterwork  Cracks in internal floor tiles  Cracks in the floating concrete slab of the external veranda and damage to the timber veranda posts  The concrete slab surrounding the swimming pool had shifted down an embankment, breaking the pool fencing  Damage to the stone retaining wall adjacent to the pool  Damage to an external gate  Cracking and slipping of sections of the external bitumen driveway, with parts of the damaged sections having been washed away. The complainant says that, during the inspection, AJ’s representative told him, “ You can see where the house has gone for a ski ”. Clearly, given the nature and extent of the damage observed by AJ, and the severity of the February 2022 weather event, the complainant has established a prima facie valid claim for storm damage to his home and property. Determination | Case number: 930946 Page 5 of 12 Insurer says policy exclusions apply The insurer also arranged for MO, consulting engineers, to inspect the complainant’s proper ty on 16 June 2022. MO’s report written pursuant to that inspection is dated 1 July 2022 and is thorough and well set out. The report is also accompanied by many helpful photographs. MO opined on page 3 of its report that:- The soil report provided by (the complainant) showed that the site is underlain by reactive soils. Reactive soils are clay soils that, as they wet-up, they swell in volume and when they dry out, they shrink in volume. As a result, some movement should be expected as a result of normal seasonal changes in the moisture content of the soil. MO then concluded:  The cracking to the southern brickwork, the gap between the southern exterior wall and the pathway, movement in the driveway, and the slope in the eastern hallway are consistent with normal long-term reactive soil movements as described above. Additionally, pathways and driveway slabs are non-structural elements that are particularly prone to damage and movement. These movements occur over a long period of time and are not the result of the insured event  The cracking to the brickwork adjacent to the veranda slab on the eastern side of the residence is consistent with the effects of differential movement between the veranda slab and the adjacent brickwork due to concrete shrinkage of the veranda slab. The aged appearance of the cracking indicates that it has occurred prior to the event  The lean to the timber retaining wall east of the residence is consistent with the effects of degradation of the posts due to timber decay. It should be noted that timber decay occurs over a long period of time and as such, the degradation of the timber posts is unrelated to the rain event. The retaining wall appears to be nearing the end of its serviceable life…..  The gap between the concrete paving and the pool coping is consistent with normal long-term ground movements as described above. Typically, concrete paving around pools is constructed without any footings. As such, they are susceptible to movements. As there was a void under the paving slab near the retaining wall, it indicates that there has been washout of the fill material from under the slab, contributing to the movements. Considering the aged appearance of the stepped-up edge of the pool coping and the presence of filler between the concrete paving and coping, the movements have been on-going and have occurred prior to the event  The gap between the slab and the exterior brickwork on the western end of the residence does not indicate any structural distress to the residence. The weathered appearance of the slab edge in the gap indicates that the gap formed prior to the rain event  The rotation of the south-western timber retaining wall is consistent with movement of the posts due to insufficient embedment into the ground and/or long-term timber decay of the posts as described above. The retaining wall appears to have reached the end of its serviceable life….  The cracking to the tiling is consistent with the lack of control joints between the tiles and the walls and between the tiles themselves. Control joints are typically installed to control the differential movements between the tiles and the walls. The fretting to the edges of the cracks indicates that they have formed prior to the event. Determination | Case number: 930946 Page 6 of 12 Following receipt of MO’s report, the insurer denied the cl aim. In its letter dated 1 September 2022, the insurer set out the policy exclusions it relied upon to deny the claim. Most relevantly, these include:-  Storm damage to retaining walls and driveways (see page 26 of the PDS)  Loss or damage caused by, or arising from, a failure by the complainant to take reasonable steps to keep his property well maintained, and structurally sound and secure (see pages 15 and 26 of the PDS)  Loss or damage that is predominantly caused by, or arises from, wear and tear or gradual deterioration (see pages 15 and 26 of the PDS)  Loss or damage that is predominantly caused by, or arises from, earth or soil movement, or settling, expansion or shrinkage, unless it is a direct result of an insured event (see page 15 of the PDS). In sum, the insurer says it is entitled to deny the claim because the damage to the complainant’s home and property was not caused by the CAT 221 event of February 2022. Rather, the damage was either pre-existing, or it was caused by a number of unrelated factors, including wear and tear, natural land movement over time due to highly reactive soils, and a failure by the complainant to adequately maintain his property. The insurer also says that storm damage to retaining walls and driveways is expressly excluded under the terms and conditions of the policy. Proximate cause of damage needs to be analysed Damage can have more than one cause. For instance, in this matter the complainant says the damage to his property was caused by the storm. The insurer maintains the damage was either pre-existing, and/or it was caused by a combination of factors which are all excluded under the terms and conditions of the policy. In deciding whether the policy responds, it is necessary to identify the proximate cause of damage. The proximate cause is not necessarily the first or the last or the sole cause of the loss. It is the effective or dominant or operative cause of the loss. If there are several causes of a loss operating contemporaneously, each must be examined for the qualities of reality, predominance and efficiency as the active, efficient cause that sets a relevant chain of events in action. If one cause would have caused the harm in any case, and the other would not have done so in the absence of the first, the first is the proximate cause. Complainant’s evidence is persuasive Following the insurer’s denial of the claim, the complainant arranged for GE, a civil and structural engineer, to inspect his property on 11 May 2023. GE’s report is dated 22 July 2023. It is comprehensive, logical and is supported by helpful figures and diagrams, together with illustrative photographs. GE observed the following:-  The storm produced localized or flash flooding forcing storm water ingress underside and into the founding soil and over of the ground floor level of the dwelling  The estimated height of water over the ground floor was about 50mm Determination | Case number: 930946 Page 7 of 12  The storm water or flash flooding drained away after 24 hours. However, the saturated condition of the founding soil remained for an estimated four months after February 2022  In regard to the garage and front part of the dwelling, storm water entered through the garage door in the front and the cavities in the brick mortar of the external walls. Storm water also penetrated under the garage slab causing differential settlements and soil swelling in various areas which, in turn, caused defects in the garage slab itself  These movements also produced wall defects above  In the middle and rear areas of the dwelling, storm water entered limited areas only. However, subsequent drying of the foundation soil was severely hindered by the fact the rain was consistent and the humidity of the surrounding air was high  Differential settlement occurred along the external walls of the dwelling. This is a very common effect in soil mechanics  The rear of the dwelling has fill soil on which the footings are supported by concrete piers. The piers were found in firm ground. Though the design and construction are assessed to be stable, the fill may have undergone minor settlements based on the observed land slips in the nearby area  It is also possible that part of the house experienced a translational slip  In regard to the pool area and stone retaining wall, storm water entered into the underside of the pool paving through partly cracked mortar joints in the pool area paving. The volume and steady flow of storm water for a period of several hours flooded the pool underside. This storm water then eroded the soil supporting the tiled area around the pool  The storm water run-off (downslope) under the pool could not exit easily through the stone retaining wall. The consequent increase in water pressure against the stone retaining wall caused a failure of the wall by rotation. This, in turn, caused the failure of the pool supports. GE opined that:-  Retaining walls are only designed for an active or “at rest” earth pressure coefficient of, normally, 0.3. They are not designed for full height water pressure  Total full-height storm water pressure against the stone wall on the complainant’s property may have been in excess of more than 2.5 times the design limit, thereby causing the wall to fail. The wall failed via rotation as the storm water forced an escape route  The failed retaining wall also caused erosion of the soil under the pool. I note GE did not comment on the timber retaining walls or the bitumen driveway. GE concluded:-  The above information concludes without doubt that the shallow footings of the (complainant’s) dwelling….. have undergone plastic settlements as a direct result of the storm event in February 2022  In my opinion, based on the site inspection of the performance of the structure, and the surrounding environmental factors during the storm event in the recent past, the structure does require major repairs in the floor and footings. Determination | Case number: 930946 Page 8 of 12 I have also perused the documentation the complainant lodged with AFCA on 8 November 2022. That documentation includes, amongst other things, a clear history of relevant events, and logical explanations detailing how the damage to his home and property was caused. The complainant’s evidence in this regard also ben efits from many photographs which clearly depict the damage to his home, the damage to the pool area and stone retaining wall, the damage to the driveway and obvious evidence of landslip on his property. Proximate cause of damage is the storm I have considered all available evidence. I am of the opinion the proximate cause of the damage to the complainant’s home and property was the storm. This is because of the following factors:-  AJ is a builder. To the extent that AJ’s report contains conclusions as to c ausation, I am of the opinion such conclusions should not displace the opinions of GE and MO, both of whom are engineers  GE’s report and analysis are more detailed and sophisticated compared to that of MO. GE’s report reveals a very detailed inspection process, together with extensive measurements, explanatory diagrams and illustrative calculations where appropriate. MO’s report lacks these details and nuances  Although MO’s report includes many illustrative photographs, I am not satisfied the appearance of the damage depicted in the photographs entitles MO to draw all of the conclusions it has. For instance, MO concludes that certain damage is not storm related because, for example, cracks in brickwork or concrete foundations appear to be “aged” and, therefore, pre-date the February 2022 weather event. Yet, in my opinion, for the most part, the photographs do not clearly support such conclusions  MO’ s inspection did not involve any destructive investigations or other testing, including testing via excavations. Consequently, MO’s report does not provide a basis upon which to conclude the timber retaining wall posts failed because of decay. In addition, neither AJ or MO appear to have been asked to comment upon the material the complainant lodged with AFCA on 8 November 2022. In particular, the many photographs included in that material which clearly depict damage to the complainant’s home, damage to the pool area and stone retaining wall, and evidence of landslip on the property, are instructive. Finally, I note the complainant says his home and property were, generally, in a good condition prior to the CAT 221 event of February 2022. Moreover, the dwelling was constructed about 20 years ago. I also note the insurer has provided nothing to displace the complainant’s evidence in this regard. Moreover, it has not in any way impeached the complainant ’s credit . Yet, the insurer has not provided any persuasive evidence, or expert opinion from AJ or MO, to explain why, after 20 years of trouble-free existence, the complainan t’s home and property should suddenly develop significant damage and associated defects, coincidentally, shortly after a catastrophic weather event. In all the circumstances, the absence of such evidence on the part of the insurer is significant and manifest. It follows that the insurer should accept the claim and process it in accordance with the terms and conditions of the policy. Determination | Case number: 930946 Page 9 of 12 2.2 Should the damaged retaining walls and driveway be covered? Insurer says damage to retaining walls and driveways is expressly excluded from cover The insurer relies upon policy exclusions to deny the claim insofar as it relates to damage to the stone retaining wall adjacent to the pool, the timber retaining walls and sections of the bitumen driveway on the complainant’s property. Page 26 of the PDS states:- Not covered. • Loss or damage to: – retaining walls, paths, driveways, bridges or landscaping, ….. However, stabilisation of the land supporting the pool clearly is fundamental to ensuring the storm-related repairs to the complaina nt’s home and pool are completed satisfactorily and safely. The retaining wall and driveway exclusions in the policy do not operate in a vacuum. Moreover, the exclusions do not operate by reference to the storm-related repairs to the complainant’s home and pool. Therefo re, the installation of a new, robust retaining wall for the pool area should be considered part and parcel of the necessary costs to repair the complainant ’ s home and pool, including the pool fence and gate. Whilst the insurer may argue that damage to the stone retaining wall, in isolation, is excluded from cover under the terms of the policy, damage to the home and the pool (as well as damage to the pool fence and gate) are covered. Moreover, such coverage must be accepted by the insurer in this matter. In such circumstances, the insurer is required to repair this damage, or pay the costs of doing so. The exchanged information obviously shows such repairs must include a new, robust, reinforced retaining wall which effectively stabilise the area of the complainant’s property surrounding the pool which has been damaged by the CAT 221 event of February 2022 and the storm-related land slip. There is nothing in the policy to say such costs should be excluded when they are to be incurred by reference to repairing the claim-related damage to the property. It follows that, to give proper effect to the policy terms which provide cover for the dwelling and the pool, the insurer should also provide cover for a new, robust retaining wall for the pool. This is consistent with the purpose of the policy which is to indemnify the complainant for loss or damage caused by an insured event. It is also fair and reasonable in all the circumstances. Otherwise, there is insufficient evidence in the exchanged material to establish the repair or replacement of the timber retaining walls and the driveway are a necessary part of the repair of storm-related damage to the house and the property. It follows that cover for the timber retaining walls and the driveway that were damaged by the storm is excluded under the terms and conditions of the policy. Determination | Case number: 930946 Page 10 of 12 2.3 Should the complainant be reimbursed for the cost of expert report? GE report played important role in analysis of claim The complainant paid for GE to inspect his property and report following the insurer’s denial of his claim. GE’s report was instrumental in establishing the proximate cause of the damage to the complainant’s home and property. Accordingly, upon the production of proof of payment by the complainant, the insurer is required to reimburse the complainant for the cost of the report. In addition, the insurer must pay interest to the complainant on the cost of GE’s report in accordance with section 57 of the Insurance Contracts Act 1984 (the Act). 2.4 Complaint should be resolved in this way Insurer can elect to cash-settle Within 21 days of receiving notice the complainant accepts this determination, the insurer must:-  engage an engineer, expert builder, and/or other suitably qualified experts, to draw up a scope of works (SOW) regarding the necessary repairs and associated works to the complainant ’s home, his property and fixtures that have been damaged by the CAT 221 weather event of February 2022  the SOW must include, but is not necessarily to be limited to, provision for repairs and remedial works to the interior and exterior of the complainant’s home and garage, t he pool and its surrounds (including the stone retaining wall)  the SOW should also include any works required to stabilise the earth to the extent that is necessary to repair the claim related damage  upon production of proof of payment by the complainant, reimburse to the complainant the cost of the GE report and pay interest on that sum from the date the report was paid for by the complainant to the date of settlement in accordance with section 57 of the Act. The insurer must also provide to the complainant an explanation, and breakdown, of how the interest has been calculated. Within a further 14-day period of receipt of the SOW, the insurer must obtain at least one actionable quotation based upon the SOW, either by way of a tender process or otherwise. All repairs and remedial works included in the SOW and quotation(s) must also comply with all current and applicable Commonwealth and New South Wales building-related, safety-related and health-related laws, regulations and codes. Within a further seven days of receipt of the associated quotation(s), the insurer must elect to either:  commence the necessary repairs and associated works as soon as possible, or  offer a cash settlement to the complainant comprising a sum equal to the total of the preferred actionable quotation, plus a 15% contingency on top of this to factor in the risk of the works passing to the complainant and the likely possibility that further works may be required. Finally, given the time which has elapsed since the complainant made the claim, I emphasize to the insurer that time is of the essence. Determination | Case number: 930946 Page 11 of 12 2.5 Why is the outcome fair? Policy exclusions do not apply The outcome is fair in all the circumstances because the complainant has established a valid claim for damage to his property caused by an insured event. Moreover, apart from the exclusion related to the timber retaining walls and the driveway, the insurer is not entitled to rely upon policy exclusions to deny the claim. Determination | Case number: 930946 Page 12 of 12 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.