Whether damage should be covered under one claim, whether the insurer delayed repairs, and whether the $6,292 settlement offer for outstanding repairs should be increased to $50,000

FirmIAG
Decided2023-07-24
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$50,000
SourceAFCA PDF

Summary

The complainant said the insurer should have covered leak damage under one claim, caused delays, and should pay $50,000 for outstanding repairs. AFCA found in favour of the insurer and required no further action.

The damage arose from at least four separate leaks, delays were due to the complainant not replacing the copper piping, and the evidence did not show the $6,292 offer was insufficient for covered repairs.

Issues

Subjects and remedies

broker or intermediaryhome or building damagethird party authorityno remedy

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination Case number 928554 Financial firm Insurance Australia Limited Determination | Case number: 928554 Page 2 of 6 Case number: 928554 24 July 2023 1 Determination overview 1.1 Complaint The complainant held a home insurance policy with the financial firm (the insurer). In August 2020, the insured property was damaged by a leak from its copper piping. Over the next two years, the copper piping developed more leaks which caused more damage. The insurer has repaired some of the damage, but the property needs further repairs. The insurer says it will cover the damage caused by the leaking water, but the complainant is responsible for replacing the copper piping. The complainant does not dispute this. The complainant says the insurer:  opened four claims for damage caused by leaks, but should have covered all the damage under one claim  caused unreasonable delays in repairing the property  should pay $50,000 for outstanding repairs. The insurer has offered to settle the claims by paying $6,292 for outstanding repairs. 1.2 Issues and key findings Should the insurer cover all damage under one claim? No. The claimed damage was caused by at least four separate leaks, which occurred at different times and in different places. It is fair for the insurer to cover the damage under four separate claims. Did the insurer cause unreasonable delays? No. The copper piping in the house needs to be completely replaced. The complainant has known this since August 2020, but he has not replaced the copper piping. This is the reason the property has not been repaired. This is not the insurer’s fault. Is the insurer required to increase its settlement offer? No. The available information does not show the insurer’s offer is insufficient to pay for all outstanding repairs covered under the policy. 1.3 Determination This determination is in favour of the insurer. The insurer is not required to take any further action in relation to this complaint. Determination | Case number: 928554 Page 3 of 6 2 Reasons for determination 2.1 Should the insurer cover all damage under one claim? Insurer opened four claims On 25 August 2020, the complainant’s tenant said the ceiling in the main bathroom collapsed. On 18 October 2020, the complainant’s insurance broker lodged a claim for the damage. The complainant says he told his broker about the incident in August 2020, and did not realise the broker did not lodge a claim until October 2020. The damage was caused by a burst copper pipe joint. Over the next two years, the copper piping in the house developed more leaks and caused more damage. The insurer opened four claims relating to the damage. The complainant says he only ever lodged one claim, and the insurer should cover all the damage under one claim. Claims relate to four separate events The insurer appointed a loss adjuster, who reviewed the claims and inspected the property on 5 April 2022. The loss adjuster said the property had been damaged by at least four separate events:  August 2020: burst copper pipe joint above main bathroom ceiling  January 2021: burst pipe behind en suite shower  October 2021: leak under en suite vanity  April 2022: overflow from en suite floor waste. The complainant says the leaks all occurred ‘around the same time’. However, he agrees the leaks occurred in different places. The claims opened by the insurer all relate to leaks from copper pipes. However, there were at least four separate leaks, and they occurred at different times and in different places. In my view, it is fair for the insurer to cover the damage caused by the leaks under four separate claims. Complainant says insurer did not renew policy The policy expired on 31 August 2022. The complainant says the insurer refused to renew the policy because of the high number of claims made under the policy. He says this would not have happened if the insurer had covered all the damage under one claim. Under AFCA Rule C.1.4, AFCA cannot consider a complaint about a refusal to provide insurance, unless the complaint is that:  the decision was made indiscriminately, maliciously, or on the basis of incorrect information  the complainant was misinformed about the insurance cover  the insurer refused to provide medical indemnity insurance. The available information does not show the insurer refused to renew the policy indiscriminately, maliciously, or on the basis of incorrect information. In this determination, I have not considered whether the insurer was entitled to refuse to renew the policy. Determination | Case number: 928554 Page 4 of 6 2.2 Did the insurer cause unreasonable delays? Complainant has not replaced copper piping On 25 August 202 0, the complainant’s plumber (PS) attended the property. PS said the bathroom ceiling had collapsed because of water leaking from a copper pipe. PS said all of the copper piping in the house should be replaced with PEX (plastic) piping. On 5 December 2020 and 6 December 2020, the complainant says PS replaced copper piping with PEX piping. PS said they replaced all the copper piping in the house. On 21 January 2021, the insurer discovered a leaking copper pipe at the house. The complainant admits PS did not replace all the copper piping. On 13 April 2021, PS sent another plumber (AP), who replaced more piping. On or about 4 April 2022, the insurer’s plumber (BC) attended the property and discovered a leaking copper pipe. BC said the house had some new pipes, but also had some of the old copper pipes. BC said the copper piping had green spotting throughout, and should be completely replaced. BC told the complainant about its findings in April 2022. However, the complainant has not replaced the remaining copper piping. Complainant is responsible for replacing copper piping The insurer says it will cover damage caused by water leaking from pipes, but the complainant is responsible for replacing the pipes. The complainant does not dispute this. The complainant is not claiming for the cost of replacing the copper piping in the house. From August 2020, the complainant knew all copper piping in the house should be replaced. He says he paid to have copper piping replaced in December 2020 and, when he realised the work was not completed, he arranged further pipe replacements in April 2021. The work was still not completed, but he says he could not have known this until BC told him in April 2022. He has not explained why he did not take any further action after April 2022. Insurer has not caused delays The complainant says the insurer has delayed the repair of the property by:  failing to detect leaks when it inspected the property  failing to complete repairs in a timely manner  failing to clean dust and mould from the property  appointing different staff members to manage the claims. The property was damaged in August 2020, and still has not been fully repaired. This is because the complainant has not replaced the copper piping in the house. This is not the insurer’s fau lt. The insurer has not done anything to prevent the complainant from replacing the copper piping. The complainant says the property was damaged by the burst pipe in August 2020, and was further damaged because the insurer mishandled the claim. I do not agree. The property was further damaged because the copper piping developed new leaks. This would not have happened if the complainant replaced the copper piping. The available information does not show the insurer caused damage to the property, or otherwise delayed repairs to the property. Determination | Case number: 928554 Page 5 of 6 2.3 Is the insurer required to increase its settlement offer? Insurer has offered $6,292 for outstanding repairs The insurer says:  its builder has done repairs at a cost of $40,047.65  it has paid the complainant $5,769.86 for further repairs  it has offered to settle the claims by paying an additional $6,292 for further repairs. The complainant has asked the insurer to settle the claims by paying an additional $50,000. Insurer not required to accept complainant’s quote The compl ainant has provided a builder’s quote dated 4 October 2022 totalling $22,671. The builder’s quote covers the following work to the en suite:  demolition  plumbing and electrical works (not costed)  tiling labour  installation of a new vanity and cabinetry  replacement of flooring. The loss adjuster’s report of 3 June 2022 says the insurer repaired the en suite (except for the tiling) in August 2021. The insurer has offered to pay the complainant $5,100 for the cost of en suite tiling (this is included in the insurer’s offer of $6,292 to settle the claims). The loss adjuster said there had been further leaks in the en suite since August 2021, but did not say what damage this had caused. A restorer appointed by the insurer inspected the property on 6 April 2022. The restorer said the leaks in the en suite had destroyed carpet in an adjoining bedroom, but did not report any other damage. A quote from the complainant’s plumber (AP) dated 7 December 2021 says walls, vanities, and floors need to be removed in order to replace ‘old leaking pipework’. The insurer says the complainant is responsible for the cost of replacing pipework. The complainant does not dispute this. The available information does not show the insurer is liable for any damage to the en suite, other than damage it has already repaired and damage it has offered to pay for. Insurer not required to increase offer The complainan t’s builder’s quote totals $22,671. The complainant says he is also claiming the cost of the following work, which is not included in the builder’s quote:  supplying tiles for the en suite  removing and replacing a wall in the main bathroom  replacing mouldy insulation in the ceiling  cleaning dust and mould from the entire house. The complainant has not provided quotes for any of this work. The available information does not show this work is necessary to repair damage covered under the policy. The available i nformation does not show the insurer’s offer is insufficient to pay for all outstanding repairs covered under the policy. Therefore, the insurer is not required to increase its settlement offer. Determination | Case number: 928554 Page 6 of 6 3 Supporting information 3.1 The AFCA process AFCA’s approach is b ased on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. I have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, I have restricted this determination to the issues that are relevant to the outcome. Complainant represented by family member or friend The complainant was represented by a family member or friend. In this determination, statements by the complainant’s representative are treated as if they were made by the complainant.