Insurer's contractors allegedly damaged shower waterproof membrane during repairs; insurer refused further repairs

FirmQBE
Decided2023-06-29
ProductGeneral Insurance · Strata
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

After insurer-arranged repairs to a sewage-damaged apartment, the complainant found water damage to new floorboards and blamed the contractors for damaging the shower membrane. AFCA found the evidence did not show the contractors caused it and decided in favour of the insurer.

On the balance of probabilities, expert reports from the insurer's construction expert and engineer were more compelling than the complainant's cause-and-effect theory, so the insurer was not responsible under the Code for further repairs.

Issues

Subjects and remedies

home or building damageno remedy

Related

All QBE determinations · Find similar determinations

Text of the determination

Determination Case number 927806 Financial firm QBE Insurance (Australia) Limited Determination | Case number: 927806 Page 1 of 5 Case number: 927806 29 June 2023 1 Determination overview 1.1 Complaint The complainant is a beneficiary under a residential strata insurance policy underwritten by the financial firm (insurer). The insurer arranged repairs to the complainant’s apartment after it was damaged by a sewerage leak. A month after the repair work had been completed, the complainant noticed water damage to the newly laid floor boards. The complainant says the new damage occurred because the insurer’s contractors damaged the waterproof membrane in her ensuite shower when they removed and replaced the original floor boards. She wants the insurer to repair the damage to the shower and the affected boards. The insurer says the new damage was not caused by the work done by its contractors. It says the damage is maintenance related and is not the insurer’s responsibility. 1.2 Issues and key findings Is the insurer responsible for further repairs? No. The available information does not establish the insurer’s contractors damaged the shower membrane, shower tiles or the new floor boards. The insurer is not responsible for further repairs because of the work of its contractors. Why is the outcome fair? I sympathise with the complainant who is understandably distressed and upset to have moved back in to her home after three months of renovations only to notice fresh damage to her newly laid floors. However, the available information does not establish the work done by the insurer’s contractors caused the new damage. In the circumstances it would not be fair to hold the insurer liable for further repairs. 1.3 Determination This determination is in favour of the insurer. The insurer is not obliged to take any further action in relation to the claim or this complaint. Determination | Case number: 927806 Page 2 of 5 2 Reasons for determination 2.1 Is the insurer responsible for further repairs? No. The available informa tion does not establish the insurer’s contractors damaged the shower membrane, shower tiles or the new floor boards. The insurer is not responsible for further repairs because of the work of its contractors. Circumstances of the claim In February 2022, th e complainant’s apartment was extensively damaged following a leak from sewerage pipes in her apartment building. She moved out of the apartment for three months while repairs to her apartment were completed. Approximately one month after her return home she noticed water damage to her newly laid flooring outside the master bedroom ensuite. The complainant says the renovation involved removal of the skirting and floor boards in the master bedroom. She says water is escaping because the ensuite shower waterproofing was damaged during the renovation work. She says there is damage to the door frame in the same location which shows there has been trauma to the area. The insurer is responsible for repairers under the Code The General Insurance Code of Practice (Code) deals with authorised repairers. The relevant part of the Code is set out in section 3.2 of this determination. It provides that if an insurer has selected and directly authorised a rep airer to repair an insured’s damaged property, the insurer will accept responsibility for the quality of the work. The parties disagree on the cause of the damage After the complainant lodged her claim, she asked the body corporate ’s plumber (BP) to inspect the damage. BP visited the apartment on 12 August 2022. Its invoice sets out its findings as follows: inspect shower in ensuite of unit [number] found there is evidence of waterproofing failure possibly caused by recent works disturbing waterproof membrane as there was no evidence of leaking prior to works or any evidence of water leaking under the flooring when it was removed The insurer engaged a construction expert (NC) to assess and report on the cause of the damage to the new flooring. NC inspected the apartment on 19 September 2022. It later provided a report which summarised its findings as follows:  a flood test of the shower floor showed water could be seen entering gaps between the floor and wall tiles, and not resurfacing. This was confirmed with dye  an initial thermal inspection showed water damage but no moisture. A thermal inspection after tests were conducted showed new moisture tracking under the tiles from the shower towards the ensuite doorway  test results suggest that the water damage to the floorboards at the ensuite doorway is a result of water entering gaps between the floor and wall tiles in the shower. NC has provided photographs of the results of the thermal testing which show the path the water was travelling after the tests. Determination | Case number: 927806 Page 3 of 5 T he insurer denied the complainant’s claim following NC’s report. When the complainant lodged a complaint about this decision, the insurer suggested an engineer (IE) be appointed to inspect the damage. IE inspected the complainant’s apartment on 13 January 2023. In its 9 February 2023 report IE said:  there was evidence of moisture staining within the main bedroom’s timber flooring adjacent to the ensuite bathroom  an inspection of the ensuite bathroom revealed evidence of minor gaps within the grout/sealant near the doorway and within the shower as well as moisture related damage to the door’s architrave  given the pattern of damage to the recently replaced timber flooring, it is most likely that the source of moisture damage is leakage from the tiled shower  the previously completed testing suggests there is a deficien cy in the shower’s waterproofing and/or the grout/sealants, that is allowing water to escape  given the restoration and repair works did not include works in the ensuite, it is unlikely that the restoration and subsequent repair works contributed to the deficienc ies in the shower’s waterproofing or the grout/sealants  reports from February 2022 show high levels of moisture recorded within the lower section of the main bedroom’s wall adjacent to the ensuite shower. These photos also suggest there may have been some slight darkening or staining at the join between the two floorboards located next to the bathroom’s doorway  given the ensuite is some distance from the reported sewer pipe leakage, it did not believe the most recent high reading was related to the sewer pipe leakage  it did not believe the reported d amage to the bathroom’s waterpro ofing nor the staining/damage to the replaced timber floorboards in the main bedroom had occurred because of the restoration or rectification works undertaken. The complainant maintains the damage was caused by contractors The complainant agrees with IE, in so far as it says that deficiencies in the shower membrane caused the new water damage. However, she maintains the damage was caused by the insurer’s contractors because:  the insurer admits their contractors damaged the door frame which abuts the shower screen frame  the insurer admits there was no water damage on the floor or wall when they repaired the floor and replaced the skirting  there was no leak present before the insurer’s contractors completed repairs . Based on ‘cause and effect’, the repairs caused damage to the water proofing when the floor planks were being removed  she has been told the relevant contractor had difficulty removing the floor boards from the concrete  the obvious inference is that the contractors caused damage which caused a leak post renovation. The complainant has not provided any further expert reports about the cause of the damage. The available information does not show the insurer is responsible When presented with different claims and opinions, AFCA will consider each account and report, together with any supporting material, to try to form a view about what is more likely than not to have occurred. Determination | Case number: 927806 Page 4 of 5 I have carefully reviewed the complainant’s account of what has happened, the views expressed by BP, NC and IE and the submissions made by both parties. I have also reviewed the available photographs. Having undertaken this exercise, I am satisfied the available information does not show the damage to the ensuite shower was caused by the insurer’s repair work. I have reached this view because:  even acc epting the insurer’s contractors caused damage to the door frame (which I note the insurer has agreed to rectify), the available information does not show how the contractors ’ work damaged t he shower’s waterproof membrane or tiles  the available information suggests the original floorboards were laid up to a metal frame in the walls which included a metal bar along the cement floor. There is no evidence to show that the contractor’ s work breached the frame area, the plasterboard and then the waterproof membrane and tiles on the other side of the metal frame. Without more, I do not think the damage to the door frame (which is separate from the shower area) shows the repair work compromised the shower membrane  there was moisture detected in the master bedroom wall in February 2022 although no leak was detected  I am not persuaded that the contractor ’s difficulty removing the boards from their concrete base shows his work breached the metal frame, plasterboard and tiles of the adjoining ensuite  at best, BP says damage by the contractors is ‘possible’. There is no other expert opinion which supports the view that the contractors caused the damage  I find the views expressed by the insurer’s appointed construction expert and engineer more compelling than the ‘cause and effect’ theory put forward by the complainant. The insurer is not responsible for further repairs The available information does not show the insurer’s contractors are responsible for the new damage to the newly laid floor. I am satisfied the insurer is not required to carry out further repairs. 2.2 Why is the outcome fair? I sympathise with the complainant who is understandably distressed and upset to have moved back in to her home after three months of renovations only to notice fresh damage to her newly laid floors. However, the available information does not establish the work done by the insurer’s contractors caused the new damage. In the circumstances it would not be fair to hold the insurer liable for further repairs. Determination | Case number: 927806 Page 5 of 5 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the relevant legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). Each party has had the opportunity to address any issues raised and all relevant information has been exchanged between the parties. I have reviewed and considered all relevant information the parties have provided. While the parties have raised several issues in their submissions, I have kept commentary in this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 Relevant parts of the Code Page 29 - Use of repairers 86. If we have selected and directly authorised a repairer to repair your damaged property, then we will accept responsibility for the quality o f their work and the materials they use. Complaints about the repairer’s conduct, timeliness, quality of work or the materials they use will be handled under our Complaints process.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.