Home / Bendigo and Adelaide Bank / Determination 927414
Determination 927414
Alleged unreasonable delay in completing mortgagee sale of properties and continued charging of interest, fees and costs after taking possession
Summary
The complainant said the bank unreasonably delayed settlement of mortgagee sales of two properties and wrongly kept charging interest, fees and costs. AFCA found in favour of the bank and ordered no compensation.
The delay was caused by matters outside the bank's reasonable control, and the loan terms entitled the bank to keep charging interest, fees and enforcement costs until repaid.
Issues
- Delay primary · not upheld
“The delays were due to matters outside the bank's reasonable control. The bank did not unreasonably delay completing the sale of the properties.”
- Debt collection or enforcement secondary · not upheld
“Bank not required to wait or rectify defects before exercising its rights as mortgagee; decision to sell previously determined.”
- Incorrect fees or charges secondary · not upheld
“The bank can charge interest and fees on the loan until the amount it is owed is paid in full.”
- Misleading conduct secondary · not upheld
“I find the bank did not mislead or provided incorrect information to the complainant or her solicitor.”
- Poor communication secondary · not upheld
“The information does not show the bank failed to respond to the complainant's solicitor.”
Subjects and remedies
home or building damagethird party authorityno remedy
Text of the determination
Determination
Case number 927414
Financial firm Bendigo and Adelaide Bank Limited
Determination | Case number: 927414 Page 1 of 12
Case number: 927414 18 September 2023
1 Determination overview
1.1 Complaint
The complainant and her ex-husband obtained a loan from the financial firm (the bank). The
loan was secured by a mortgage over a property.
In early 2020, the bank took possession of the property as mortgagee. At the time, two
houses were constructed on the property but the plan of subdivision had not been approved
by the local council or registered at the Land Registry. The bank sold each house with
settlement of each sale subject to the approval and registration of the plan of subdivision.
The bank had to engage various parties (including the builder) to obtain certain compliance
certificates that the local council and titles office required to approve and register the plan of
subdivision. Certain works, including stormwater drainage works, also need to be completed.
When all the works and compliance certificates were obtained, the plan of subdivision was
approved and registered. Settlement of the sale of the two properties (properties) created by
the subdivision were then completed.
The complainant says the bank:
unreasonably delayed completing the sale of the properties
should refund the additional interest she had to pay on the loan because of the bank‟s
delay
continued to charge her interest, fees and costs after taking possession of the properties.
1.2 Issues and key findings
Did the bank unreasonably delay completing the sale of the properties?
Although it took a substantial amount of time to register the plan of subdivision and complete
the sale of the properties, this was not caused by the bank acting unreasonably. Completing
the necessary works and registering the plan of subdivision was complex and time
consuming. The delays were due to matters outside the bank‟s reasonable control. The
bank did not unreasonably delay completing the sale of the properties.
Is the bank entitled to charge interest, fees and costs after taking possession of
the properties?
The bank can charge interest and fees on the loan until the amount it is owed is paid in full.
The loan terms also allow the bank to charge or pass-on its enforcement costs.
Why is the outcome fair?
The outcome is fair because although it took time to complete the sale of the properties, this
was caused by matters outside the bank‟s reasonable con trol. The bank is also entitled to
continue to charge interest, fees and costs after taking possession of the properties.
As the bank has not breached a duty or obligation owed to the complainant and has acted in
accordance with the agreed loan terms, it would not be fair to make the bank compensate the
complainant.
Determination | Case number: 927414 Page 2 of 12
1.3 Determination
This determination is favour of the bank.
The bank is not required to pay any compensation to the complainant.
Determination | Case number: 927414 Page 3 of 12
2 Reasons for determination
2.1 Did the bank unreasonably delayed settlement of the
properties?
Although it took a substantial amount of time to register the plan of subdivision and complete
the sale of the properties, this was not caused by the bank acting unreasonably. Completing
the necessary works and registering the plan of subdivision was complex and time
consuming. The delays were due to matters outside the bank‟s reasonable control. The
bank did not unreasonably delay completing the sale of the properties.
The complainant says the bank unreasonably delayed completing the sales
The complainant says the bank unreasonably delayed completing the sale of the properties.
In support of her position, the complainant points to the fact that the bank sold the properties
in August and September 2020 but did not complete the sales until mid-May 2023.
Settlement was delayed due to matters outside the bank’s control
After considering all the information, I find the bank did not unreasonably delay completing
the sale of each property. Instead, I find the delay was caused by several matters outside the
bank‟s reasonable control.
From the information available to AFCA, a timeline of events can be created. The timeline is
set out in section 3.2. The timeline contains what I find took place regarding the registration
of the plan of subdivision and completion/settlement of the property sales.
Below is an overview of that timeline. It is the combination of the circumstances described
below and in the timeline that caused the delay. The delay was not caused by the bank
acting unreasonably.
An overview of what took place
When the bank sold the properties as mortgagee in possession, the plan of subdivision had
not been approved by the local council or registered at the Land Registry. To register the
plan of subdivision, significant works needed to be completed, those works inspected (and in
some cases rectified), and then certified as complete. This was necessary so that certain
compliance certificates could be issued. The works included works to stormwater drainage
and plumbing. An occupancy permit was also required.
Despite the bank and its agent‟s reasonable attempts, those engaged to carry out and inspect
the required works sometimes delayed, were hard to contact or did not respond. To keep
things moving forward the bank had to appoint new parties to step in and carry out some of
the work or the required inspection which added time.
The builder who constructed the homes on the properties was also unhappy about not being
paid the final instalment under the building contract and was in dispute with the complainant
and her ex-partner. The dispute was not finalised until September 2021. A copy of the
orders made by the tribunal that heard the dispute were not provided to the bank until
February 2022, and the orders did not a ssist dealing with the builder‟s claim that it was owed
a final instalment of $184,000.
The bank then negotiated directly with the builder for a reduced amount of $150,140.67 but
doing so took time. A deed documenting the terms of agreement also needed to be prepared
Determination | Case number: 927414 Page 4 of 12
and negotiated with builder‟s solicitor. The deed between the builder and bank was finalised
in July 2022. The bank then paid the builder the agreed amount, and the builder released
certain compliance certificates that were necessary to obtain an occupancy permit.
The occupancy permit was necessary to register the plan of subdivision, but it was not issued
until 22 August 2022.
Registering the plan of subdivision was then further delayed because the Land Registry
required the bank and the registered proprietors to sign a document – a section 88B
instrument. However, when the bank contacted the complainant and asked her to sign the
document as one of the registered proprietors, the complainant refused. This meant the bank
had to investigate alternatives on how the document could be signed on behalf of the
registered proprietors which caused further delays. After consulting its solicitor and Land
Registry, Land Registry accepted the document could be signed using powers provided to the
bank under its mortgage.
A caveat was also lodged on the property by the complainant‟s solicitor for unpaid legal fees
which the bank had to deal with. The bank had to obtain a letter of consent to the subdivision
from the caveator before the plan of subdivision could be registered.
The plan of subdivision was finally registered by Land Registry on or around 19 April 2023
with settlement of the sales completed by 16 May 2023.
Although the time to register the plan of subdivision and complete the sales was longer than
what the parties may have initially expected, I find the delay was due to matters outside the
bank‟s reasonable control, not by the bank acting unreasonably.
A determination has already been made on when the bank decided to sell the
properties
The complainant says the bank should have negotiated with the builder before selling the
properties because it sold the properties before the plan of subdivision was registered.
However, there has already been a determination issued by AFCA in case 759584 that found
the bank was not required to wait or rectify defects before exercising its rights as mortgagee.
That is, deciding to sell the properties before the plan of subdivision was approved and
registered.
The information does not show the bank failed t o respond to the complainant’s
solicitor
The complainant says her solicitor would often contact the bank‟s solicitor and be ignored,
which increased her own legal costs. However, this is not support by the information the
parties have provided. If the complainant has an issue about the legal costs her solicitor has
charged her, the complainant can raise this directly with her solicitor, and if not satisfied with
the response, with the Office of the NSW Legal Services Commissioner.
The bank’s estimates to payout the loan that were not misleading
The complainant says the bank provided incorrect and misleading information when it
provided payout estimates for the loans. The complainant says the bank represented the
estimates would not change by thousands of dollars, but this is what occurred.
I have been provided with copies of the emails between the parties regarding the payout
estimates. It is clear from these that the bank said the estimates provided as at 28 October
2022:
Determination | Case number: 927414 Page 5 of 12
excluded interest to settlement
that there would be settlement adjustments to take into account.
The complainant‟s solicitor then asked the bank to clarify the estimated figures as they “…do
not potentially include hundreds of thousands of dollars worth of builders’ fees and council
costs. Please confirm this is or is not the case as the information provided thus far has been
most vague. ”
The bank‟s solicitor responded saying:
I am further instructed the figures provided on 31 October 2022, albeit an
estimate, include all major costs and a „small‟ buffer for unexpected costs.
The figures do not include settlement adjustments and interest from 28 October
2022 to settlement date.
My client does not expect figures will change by hundreds of thousands.
The bank‟s estimates and the final pa yout amounts did not vary by hundreds of thousands.
Having considered all the information, I find the bank did not mislead or provided incorrect
information to the complainant or her solicitor.
2.2 Is the bank entitled to charge interest, fees and costs after
taking possession of the properties?
The bank can charge interest and fees on the loan until the amount it is owed is paid in full.
The loan terms also allow the bank to charge or pass-on its enforcement costs.
The bank can charge interest, fees and costs after taking possession of the
properties
The complainant says the bank should not charge interest, fees and costs after it took
possession of the properties.
However, the bank‟s entitlement to do so is set in the terms and conditions of the loan which
the complainant agreed to when she signed the loan contract. Relevantly, those terms
provide the bank is entitled to:
charge interest and fees until the amount owing is paid (see clause 5 and 7)
recover the costs it incurs in enforcing and selling its security (see clause 21).
2.3 Why is the outcome fair?
The outcome is fair in all the circumstances
The outcome is fair because although it took time to complete the sale of the properties, this
was caused by matters outside the bank‟s reasonable control. The bank is also entitled to
continue to charge interest, fees and costs after taking possession of the properties.
As the bank has not breached a duty or obligation owed to the complainant and has acted in
accordance with the agreed loan terms, it would not be fair to make the bank compensate the
complainant.
Determination | Case number: 927414 Page 6 of 12
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
3.2 Timeline of events
Date & Record Description
5 Aug 2020 Cont ract of sale for property one is signed. Settlement is subject to registration
of the plan of subdivision.
24 Sep 2020 Cont ract of sale for property two is signed. Settlement is subject to registration of
the plan of subdivision.
21 Oct 2020 The bank‟s solicitor advises they have experienced delays with the surveyor
25 Nov 2020 The bank‟s solicitors advises all documents to support subdivision has been
Determination | Case number: 927414 Page 7 of 12
provided to the Council
4 Dec 2020 Council inform the bank of additional requirements to obtain subdivision
approval.
21 Dec 2020 The bank‟s solicitor advises the property presenter the bank requires a Final
Identification Survey f rom the surveyor to finalise the subdivision
15 Jan 2021 Identification Survey inspection is booked for this date
27 Jan 2021 Identification Survey inspection takes place
29 Jan 2021 Identification Survey received from the surveyor. Additional documents from the
surveyor are needed
Feb 2021 The Property presenter makes multiple attempts are made to reach the surveyor
throughout early to mid - February 2021 to gain an update on documents for
subdivision
19 Feb 2021 The Property presenter cont acts the surveyor again requesting further
documents required for subdivision as a matter of urgency
The Bank‟s solicitors advised they are liaising with the Council regarding
stormwat er plans required for subdivision
22 Feb 2021 The Property presenter advises the Bank‟s solicitor the surveyor has responded
to the many requests for additional documents with “Everything other than the
storm water plan you already have”.
Mar 2021 The Bank‟s solicitor engaged the servic es of an engineering consu ltant to provide
a Hydraulic/Stormwater Engineer Certificate for the stormwater drainage
8 Apr 2021 The Bank is made aware of inc omplet e drainage works, which need to be
finalised before the Engineer can provide a Hydraulic Engineers Certificate
28 Apr 2021 The current surveyor is viewed as unresponsive. Bank‟s solicitor contacts a new
surveyor for assistance in obtaining the Occupancy Certificat e needed for the
subdivision
7 May 2021 A plumber and engineer attend the property to finalise the Hydraulic/Stormwater
Engineer Certificate. However, the certific ate was not approved on this day and
it eventuates that further visits are necessary
12 May 2021 The new survey or responds to the Bank‟s solicitors to advise of costs prior to
their inspect ion
23 Jun 2021 The Bank‟s solicitor advises the final inspection was satisfactory and all that
remains now is for the pool fencing to be reins pected.
21 Jul 2021 Bank‟s solicitor provides updat e to the Bank that two certificates are actually still
required by Council to progress with subdivision – the Certificate of Occupancy
Determination | Case number: 927414 Page 8 of 12
and Hydraulic/Stormwater Engineer Certificate.
Bank is advised of issues with pool complia nce and that there are various
stormwat er rectification works to be completed, which the engineer and plumber
are to work on
5 Aug 2021 Plumber is yet to finish the stormwater rectification works. Bank‟s solicitor notes
the property is in the local government area affected by the COVID - 19 lockdowns
20 Aug 2021 Bank‟s solicitor advises that due to lack of res ponse from the plumber, they had
reached out to another plumber and received a quote of $15,279 to complete the
stormwat er rectification works. The Bank‟s requests a second quote
23 Aug 2021 The Bank‟s solicitor advises that the new plumber had spoken to the Council as it
had come to light that the stormwater rectification work would be more
complicated than originally thought, hence the large quotation. The Bank‟s
solicitor arranges a second quot e.
3 Sep 2021 A second quote of $13,500. 00 for stormwat er rectification works is received and
approved by the Bank
13 Sep 2021 The Property presenter advises the stormwater rectification works should be
completed in two weeks.
29 Sep 2021 The Property presenter advises the new plumber has informed them the works
would now be completed mid next week due to a slight hold up in receiving
materials.
20 Oct 2021 After the Bank requested an updat e on stormwater rectific ation work, the
Property presenter advises the plumber has confirmed the works will be
completed by the “end of this week or latest Monday next week.”
22 Oct 2021 The plumber advises rectification work has been completed
26 Oct 2021 The Property presenter advises they are trying to arrange the engineer to inspect
the completed stormwater rectification work
2 Nov 2021 The Property presenter advises they were having trouble cont racting the
engineer to book an inspection of the stormwater rectification work. However,
inspection now booked for 4 November 2021
9 Nov 2021 Engineer‟s onsite inspection identified furt her r ectification works are required.
Quote from plumber is $32,050. Property pres enter asks the engineer to review
the quote and confirm the scope of work is in fact required for compliance
certificate to be issued.
11 Nov 2021 Engineer confirms if the scope of works are carried out, a complianc e certificate
can be issued for the stormwater works.
Plumber indicates he would be able to push to have work completed before
Christmas
17 Dec 2021 The Property Presenter advises that further rectification work has been
Determination | Case number: 927414 Page 9 of 12
completed.
The Bank‟s solicitor advises they would contact the engineer and surveyor to
obtain relevant certificates.
12 Jan 2022 The Bank follow up as no updates received from engineer or surveyor
21 Jan 2022 The Bank further follow up as no updat es from engineer or surveyor.
31 Jan 2022 Bank solicitor advises they have not been able to reach the surveyor but
engineer has just advised they had just returned to work after Chr istmas/New
Year holidays
2 Feb 2022 Bank receives engineer‟s compliance certificate. Bank still trying to contact
surveyor
7 Feb 2022 Surveyor advises the Bank‟s solicitor that there were a number of items the
original builder has not yet provided, which he will need prior to issuing an
occupancy certificat e
9 Feb 2022 Bank instructs its solicitor to contact the builder and request a copy of the
compliance certificates required to obtain the occupancy certificate.
15 Feb 2022 Email response from the builder stating he held all the required certificat es but
will not release them unless he is paid $184,000 for previous completed work.
The Bank‟s solicitor responds to the builder requesting a breakdown of fees
claimed.
18 Feb 20 22
Cont act notes
The builder provided a breakdown of costs
23 Feb 2022 The Bank receives a copy of the NCAT orders dated 14 September 2021 in the
dispute between the builder and complainant. The bank requests their solicitor
review the orders and provide guidance on whether the builder is owed money
25 Feb 2022 The Bank provides a copy of the NCAT orders to its property agent (PS) and
advis es their solicitor in reviewing, but asks PS to reach out to the builder for a
meeting
2 Mar 2022 Bank‟s p roperty agent schedules meeting with the builder for 17 March 2022.
4 - 8 Mar 2022 Bank receives advice from its solicitor on the NCAT orders whic h includes advice
that the orders do not say the builder is not entitled to be paid for works
performed
16 Mar 2022 After considering solicitors advice, the bank opts to negotiate with the builder to
obtain the compliance certificat es required for the plan of subdivision
17 Mar 2022 Bank‟s agent met with the builder and advised that the builder is not willing t o
negotiate the final progress payment amount.
Determination | Case number: 927414 Page 10 of 12
22 Mar 2022 The advice received form the Bank‟s solicitor is that the builder should be paid
the final progress payment less the cost of any rectification works.
29 Mar 2022 Bank offers to pay builder $125,715.00 in return for compliance certificates
30 Mar 2022 The builder requests further information on rectification work
8 Apr 2022 Requested information/documents provided to the builder.
18 Apr 2022 The builder agrees to deduct a total of $24,859.33 from the final progress
payment amount for the rectification works, leaving a final payment of
$159,140.67.
20 Apr 2022 Bank offers to pay builder $150,140.67
21 Apr 2022 The builder accepts the Bank‟s offer.
The Bank instructs its solicitor to prepare a Deed of Agreement so that payment
could be made to the builder in return for the compliance certificates.
23 May 2022 Deed of Agreement sent to the builder to be signed.
27 May 2022 The builder advises he has referred the Deed of Agreement to his solicitor for
review prior to signing.
7 Jun 2022 Bank‟s agent requests updat e from builder about signing the Deed of Agreement
8 Jun 2022 Builder advises his solicitor will request some amendments to the Deed of
Agreement
15 Jun to 15 Jul
2022
Bank negotiates amendments to terms of Deed of Agreement
18 Jul 2022 Bank receives the signed Deed of Agreement
20 Jul 2022 Builder advises all the required certificates have been lodged via the NSW
Planning Port al to the nominated survey or in order to obtain final occupancy
certificate.
Bank‟s agent informs the bank that the surveyor will need to inspect the
properties as three months has elapsed since the previous inspection
22 Jul 2022 The surveyor re - inspects the properties and finds the rainwater tank is non -
compliant as it is too close to the pool fence.
Bank finds solution is to install non - climbable screening
Determination | Case number: 927414 Page 11 of 12
22 Jul to 22 Aug
2022
A contractor is engaged to quote and carry out w orks to make rainwater tank and
pool compliant. Contractor and surveyor speak about the work that is required.
Bank approves quote and works are performed and inspected.
24 Aug 2022 Bank receives the Certificate of Occupancy for lodgement with the Plan of
Subdivision
29 Aug 2022 Bank receives advice from the local council listing additional 13 requirements
before the Plan of Subdivision can be approved. Requirements include an
administration sheet, section 88B instrument, updated survey/linen pla n, updated
services letter, new Plan of Subdivision certificate of currency
Sep and Oct
2022
Bank attends to satisfying additional council requirements for approval of the
Plan of Subdivision with assistance from the builder. There is a delay because a
new Certificate of Currency for the Plan of Subdivision is required from the
surveyor and the surveyor proves diffic ult to contact/reach
Early Nov 2022 Surveyor responds. Inspects site and issues new certific ate of currency for Plan
of Subdivision
21 Nov 2022 Plan of Subdivision approved by council
22 Nov 2022 Bank instructs surveyor to lodge Plan of Subdivision with Land Registry
12 Dec 2022 Surveyor advises Bank that the borrowers and the Bank will need to sign a notice
referred to the section 88B instrument to register the plan of subdivision with
Land Registry.
20 Dec 2022 Complainant declines to sign the s88B instrument to register the plan of
subdivision
20 Dec to 2022
10 Jan 2023
Bank investigate how to progress Plan of Subdivision if complainant does not
sign s88B instrument which include inquiries with Land Registry
10 Jan 2023 Land Registry inform the Bank it will accept the s88B instrument being signed by
the Bank under powers given to the Bank under its mortgage
20 Jan 2023 Pl an of Subdivision lodged with Land Registry
8 Feb 2023
Bank‟s Letter
Bank notified by Land Registry that it requires written consent to the Plan of
Subd i vision from the complainant‟s solicitor who has lodged a caveat on the
property for unpaid legal fees
9 Feb to 11 April
2023
Bank contacts caveator to obtain caveator‟s consent t o the Plan of Subdivision
including follow - ups on the caveator
12 Apr 2023 Bank receives caveator‟s written cons ent to the registration of the Plan of
Determination | Case number: 927414 Page 12 of 12
Bank‟s Letter Subdivision which the Bank‟s solicitors provide to the Surveyor so that it can be
provided to Land Registry
19 Apr 2023 Plan of Subdivision registered
12 May 2023 Settlement of the first property is c ompleted.
15 May 2023 Settlement of the second property is completed.