Cash settlement offer for flood damage to building and contents, and delays in assessment

FirmIAG
Decided2023-06-09
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$255,152
Non-financial loss$4,000
Amount claimed$489,000
SourceAFCA PDF

Summary

The insurer accepted a flood claim and offered a cash settlement of $223,934.17 for building repairs, which the complainant rejected, seeking a total loss payment plus contents. AFCA partly upheld the complaint, increasing the building settlement, requiring a mould remediation quote, upholding the contents condition and awarding $4,000 non-financial loss.

The SOW was reliable but a 25% contingency uplift was fair given building cost increases and insurer delays, while the contents claim was unproven without a list of damaged items.

Issues

Subjects and remedies

home or building damagenatural disastertheft or burglarypay claimpay non financial lossreassess claim

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination Case number 927016 Financial firm Insurance Australia Limited Determination | Case number: 927016 Page 1 of 5 Case number: 927016 7 June 2023 1 Determination overview 1.1 Complaint The complainant holds a home and contents insurance policy with the insurer and lodged a claim after the property was inundated by flood on 25 February 2022. The insurer accepted the claim. On 22 November 2022 it offered a cash settlement of $223,934.17 for building repairs based on a scope of works (SOW) from its builder plus contents subject to being supplied a list of contents items claimed. The complainant rejected the offer and says that due to the delays the property has sustained further damage. He seeks payment of the sum insured or a total rebuild plus contents. 1.2 Issues and key findings Is the insurers offer to settle the building repairs fair? No. The insurer must increase the offer based on the SOW to $255,152.47 to allow for a 25% contingency fee. The insurer must also obtain an actionable quote for the mould remediation which can be cash settled based on the actionable quote plus a 20% uplift for contingencies. Is the insurers offer to settle the contents claim fair? Yes. It is fair for the insurer to withhold payment of the contents claim until the complainant provides a list of damaged contents for review. Is the complainant entitled to compensation for non-financial loss? Yes. The delays have caused the complainant an unusual degree of inconvenience and time taken to resolve the situation. Compensation of $4,000 for non-financial loss is fair. Why is the outcome fair? While I accept the SOW can be relied on, the outcome is fair due to the significant increase in building and labour costs and delays in the assessment of the claim. It is fair for the insurer to request a list of damaged contents be provided as no supporting documents have been provided by the complainant. 1.3 Determination This determination is partially in favour of the complainant. Within 14 days of the complainant’s acceptance of this determination the insurer must:  pay the complainant $255,152.47 in settlement of the claim for building damage  arrange for an actionable quote to complete the mould remediation. The insurer may then cash settle the mould remediation based on the actionable quote plus a 20% uplift.  pay the complainant $4,000 compensation for non-financial loss The insurer may otherwise withhold any payment for damaged contents until the complainant provide a list of damaged items for the insurer to review and assess. Determination | Case number: 927016 Page 2 of 5 2 Reasons for determination 2.1 Is the insurers offer to settle the building repairs fair? No. The insurer must increase the offer based on the SOW to $255,152.47 to allow for a 25% contingency fee. The insurer must also obtain an actionable quote for the mould remediation which can be cash settled based on the actionable quote plus a 20% uplift for contingencies. Complainant has valid claim within terms of the policy The complainant held a home and contents insurance policy with the insurer and the policy provides cover for loss and damage arising from insured events including flood subject to the terms and conditions set out in the product disclosure statement (PDS). The property was flood damaged on 25 February 2022. The complainant lodged a claim for the damage to the property. The insurer reviewed and accepted the claim. On 22 November 2022 the insurer, relying on its builder’ s scope of works (SOW), offered a cash settlement of $223,934.17 and requested the complainant provide a list of the damaged contents. The complainant rejected the insurer’s cash settlement offer and did not submit a list of damaged contents to the insurer for review. The complainant says the insurer delay in providing an outcome on the claim has led to further damage and vandalism on the property. He seeks a total loss payment on the property ($419,000) plus $70,000 for damaged and stolen contents. Insurer delayed assessment of damage before offering a cash settlement The insurer appointed a builder (ABC) to assess the damage and provide a scope of works for repairs on the damage. ABC reported on 27 March 2022 that the damages were consistent with the flood event and recommended acceptance of the claim. The SOW and quote of $178,099.75 was provided to the insurer on 9 April 2022. The SOW noted that if the engaged restoration company is unable to supply a PRV (Post Remediation Verification) Certificate, it will need to engage with an independent party to supply a PRV Certificate prior to any rebuilding. This may include additional restoration works. The photographs accompanying the ABC assessment, indicate the property was undergoing renovations prior to the flood. No substantial contents are observed, the walls are stripped and there are ladders and paint tins throughout the rooms. The timeline of events provided by the insurer shows the insurer appointed a restoration company “S”. A comedy of errors with the incorrect address being provided delayed S attending the property until 4 May 2022. The report was not received until 11 August 2022. It notes visible mould present in the house. The accompanying photographs again suggest the property was being renovated when flooded and no significant contents are observed. On 7 July 2022, the complainant advised the insurer of further damage to the property because of stealing and vandalism. The complainant believed the condition of the property have worse ned due to the insurer’s delay and therefore requested a cash settlement offer. No evidence of theft or vandalism has been provided by the complainant. The insurer acknowledged there were several months delay in providing an outcome on the claim and appointed ABC to re-attend the property to provide an updated quote and SOW to Determination | Case number: 927016 Page 3 of 5 cover any further damage that may have occurred on the property. The revised SOW was not received until 25 October 2022 and not provided to the complainant until 28 October 2022. No reasonable explanation has been provided for these delays ON 22 November 2022 the insurer offered a cash settlement amount of $223,934.17 (comprising repairs of $204,121.98 as per the SOW plus 10% uplift minus $600 excess). The offer did not address the mould remediation or acknowledge the inconvenience caused by the delays. It is unclear whether ABC reattended the property to reassess the damage when providing the revised SOW. Insurer to increase offer for building damage While the complainant disagrees with the insurer’s scope of works and seeks a total loss payment on the claim for building and contents he has provided no evidence to prove:  the delay in providing a resolution on the claim has resulted in further damage, theft and vandalism  the house is not repairable because it is full of mud, mould and the wiring has been removed  walls have been smashed and items have been stolen on the property The complainant had the opportunity to provide the additional information but has not done so. In these circumstances, I am satisfied it is fair to rely on the revised SOW provide by ABC as it is the only relevant SOW available. ABC assessed the repair cost at $204,121.98. I consider it fair to allow a 25% uplift ($51,030.49) for contingencies due to the significant increase in building and labour costs and the transfer of risk. The insurer must increase the offer based on the SOW to $255,152.47 to allow for a 25% contingency fee. The SOW from ABC does not provide a costing for the mould remediation identified by “S” but notes it is likely to lead to a variation. The insurer must also obtain an actionable quote for the mould remediation which can then be cash settled based on the actionable quote plus a 20% uplift for contingencies. 2.2 Is the insurers offer to settle the contents claim fair? Yes. It is fair for the insurer in this case to withhold payment of the contents claim until the complainant provides a list of damaged contents for review. Complainant has not provided a list of contents Despite request from the insurer and AFCA the complainant has not provided a list of contents he claims were either damaged or stolen during the claims process. As indicated earlier in section 2.1 of this determination, the photographs accompanying the initial assessment by ABC and the report from “S” do not show any damaged conte nts. There is no evidence the contents had been removed or disposed of prior to any assessment of damage. The photographs suggest the house was being renovated at the time of the flood and this may explain the lack of contents. Insurer offer to settle contents claim is fair The policy provided that when making a claim an insured has the responsibility to:  provide any information or assistance required to assess the claim  to not repair or replace items without consent and Determination | Case number: 927016 Page 4 of 5  to provide items such as receipts or photographs as proof of ownership. Failure to meet these responsibilities may result in a reduction of a claim, cancellation of the policy or both. The complainant says he has photographs but has not supplied them.to the insurer. He has not explained the lack of evidence of any contents being present in the house when ABC first conducted an inspection of the damage. In the absence of the complainant’s list of damaged contents, I am not satisfied that the complainant has established a valid claim for the loss of contents. It is fair in the circumstances that the insurer withholds payment of the contents claim until the complainant provides a list of damaged contents for review. The insurer will have the opportunity to assess the contents claim further and determine its attitude to liability. 2.3 Is the complainant entitled to compensation for non- financial loss? Yes. The delays have caused the complainant an unusual degree of inconvenience and time taken to resolve the situation. Compensation of $4,000 for non-financial loss is fair. AFCA can award compensation for non-financial loss Under our Rules, AFCA can award up to $5,400 compensation for non-financial loss. This must relate to poor claims handling or other actions of the insurer which cause an unusual degree of stress, delay, or inconvenience. AFCA takes a conservative approach to compensation for non-financial loss. We expect complainants to be moderately robust, and we will not award compensation for the ordinary degree of inconvenience involved in making a claim. Insurer must pay compensation of $4,000 The insurer delayed assessing the full extent of damage to the complainant’s property. The size of the natural disaster and flood no doubt caused some of the delays but this does not explain the failure to assess the mould remediation, the provision of an incorrect address to “S”, the delays in getting the report from “S” or the delays in getting the revised SOW. I accept the delays would have caused an unusual degree of physical inconvenience and time taken to resolve the situation. This has been complicated by the complainant’s failure to provide information or alternative repair quotations. In accordance with what is fair in all the circumstances, I determine the insurer must pay the complainant $4,000 compensation for non-financial loss. 2.4 Why is the outcome fair? While I accept the SOW can be relied on, the outcome is fair due to the significant increase in building and labour costs and delays in the assessment of the claim. I also accept that it is fair the insurer be provided a list of damaged contents as no supporting documents have been provided by the complainant to prove the loss of contents. Determination | Case number: 927016 Page 5 of 5 3 Supporting information 3.1 The AFCA processes AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.