Determination 926806

Alleged delay by mortgage manager in processing loan application causing settlement delay and extra $10,000 cost

FirmMezy Assets Pty Ltd
Decided2023-09-27
ProductCredit · Business lending
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$10,000
SourceAFCA PDF

Summary

An SMSF corporate trustee claimed the mortgage manager delayed its loan application, forcing an extra $10,000 payment to the vendor to extend settlement. AFCA found the firm did not cause the delay and required no compensation.

There was insufficient evidence that the firm's conduct caused the lender's delay or that earlier action would have achieved settlement on 14 June 2022, given third-party steps such as valuation and lender assessment.

Issues

Subjects and remedies

broker or intermediarysmsfthird party authorityno remedy

Related

All Mezy Assets Pty Ltd determinations · Find similar determinations

Text of the determination

Determination Case number 926806 Financial firm Mezy Assets Pty Ltd Determination | Case number: 926806 Page 1 of 5 Case number: 926806 27 September 2023 1 Determination overview 1.1 Complaint The complainant is a corporate trustee of the B super fund, which is a self-managed superannuation fund. The complainant is represented by Ms X, one of its directors. The complainant and A company entered into a bare trust arrangement, in which A company agreed to hold property on trust, with the complainant as the sole beneficiary. In March 2022, A company purchased a commercial property in Queensland (commercial property) with a 90-day settlement, meaning it was scheduled to take place on 14 June 2022. Settlement was delayed by a week and the vendor required payment of an additional $10,000 to extend the settlement date. The complainant, through its broker, applied for finance to the financial firm. The financial firm, as mortgage manager, submitted the complainant’s loan application to a lender, who approved the loan application on 14 June 2022. The complainant says the financial firm caused the delay and would like the financial firm to reimburse it the additional $10,000 the complainant, via A company, had to pay for settlement. An Australian Financial Complaints Authority (AFCA) Senior Dispute Resolution Specialist has provided a preliminary assessment of the issues in dispute that was in favour of the financial firm. The complainant rejected the preliminary assessment. 1.2 Issues and key findings Did the financial firm ’s actions cause settlement to be delayed? No. The financial firm acted reasonably and did not cause the delay in settlement. Why is the outcome fair? Based on the available information, the financial firm acted sufficiently reasonably when it requested information from the complainant’s broker and submitted the loan application and the complainant’s information to the lender. The financial firm also ac ted without unreasonable delay when it passed on the lender’s requests to the complainant’s broker. There is insufficient information to show that the financial firm’s conduct adversely affected the time the lender took to assess the complainant’s loan app lication. Accordingly, it would not be fair to compel the financial firm to pay the complainant the $10,000 as sought. 1.3 Determination This determination is in favour of the financial firm. The financial firm is not required to compensate the complainant. Determination | Case number: 926806 Page 2 of 5 2 Reasons for determination 2.1 Did the financial firm’s actions cause settlement to be delayed? No. The financial firm acted reasonably and did not cause the delay in settlement. The complainant applied for a loan On 9 February 2022, before A company purchased the commercial property, the complainant as trustee of the B super fund submitted a loan application with the financial firm to purchase a property in NSW (application). The application is described in its header as a ‘SMSF Loan Application Form’ and it provides:  the applicant is the B Super Fund  the asset is a property in NSW with a purchase price of $735,000 (which is not the property that is eventually purchased, being a property in Queensland)  the SMSF trustee is the complainant  the property trustee is the A company  Ms X and Mr B are the fund members. There is no information submitted as to why A company subsequently purchased the Queensland commercial property in March 2022 when it listed a property in NSW in the application. But nothing turns on that question. It just indicates that the application gave rise to discussions between the parties, and during those discussions some details of the application were changed. There is nothing unusual in those events. A company and the complainant entered into a bare trust arrangement Earlier, on 30 June 2021, A company and the complainant entered into a deed settling a bare trust arrangement (bare trust deed) where:  A company is the holding trustee  the beneficiary is the complainant  A company and the complainant settle the Bare Trust referred to as the A Trust  A company acts as the custodian of the asset referred to in Schedule One for the sole and exclusive benefit of the complainant  Schedule One does not list any property as an asset  A company has not and will not provide any of the purchase monies  the real purchaser is the complainant. A company purchased the commercial property On 16 March 2022, A company as trustee for the A Trust entered into a contract of sale (contract of sale) to purchase the commercial property for $700,000. The contract of sale states that the settlement date was to be 90 days from the contract date (which was 16 March 2022). Settlement of the loan was delayed Settlement of the contract of sale took place on 21 June 2022. Based on the available information, the following events took place in the lead up to that settlement: Determination | Case number: 926806 Page 3 of 5  between 9 February 2022 and 22 March 2022, the financial firm and the complainant’s broker corresponded regularly regarding the information the financial firm required  on 16 March 2022, A company entered into the contract of sale  on 5 April 2022, the financial firm sent the application to the lender for conditional approval  on 7 April 2022, the lender requested further information, which the financial firm advised the complainant’s broker on the same day  on 14 April 2022, the lender issued a conditional approval, subject to a valuation report and additional information. There were public holidays for Easter and ANZAC day that followed  o n 26 April 2022, the financial firm sent an email to the complainant’s broker requesting more information  on 3 May 2022, the financial firm reviewed further information received from the complainant’s broker and sent it to the lender.  between 4 and 13 May 2022, the financial firm and the lender corresponded about ordering a valuation.  on 9 May 2022, the lender advised the financial firm that they were experiencing a high amount of valuation requests from all of their broker groups which was causing delays in other parts of the process (i.e. data loading) and asked the financial firm to order a valuation and obtain quotes. The financial firm advised that it was unable to order valuations and asked the lender to order a valuation as per the normal process.  on 12 May 2022, the financial firm asked the lender again to order the valuation. Subsequently on 13 May 2022, the financial firm ordered a valuation but the valuer cancelled on 17 May 2022 due to no capacity. A second valuer was allocated on that day.  on 21 May 2022, the second valuer inspected the commercial property  on 31 May 2022, the financial firm received the valuation report  on 1 June 2022, the financial firm sent the valuation report to the lender  on 9 June 2022, the financial firm passed on to the complainant’s broker four further questions from the lender, and the financial firm and the broker emailed about those questions during this day  on 10 June 2022 (Friday), the lender requested further information after reviewing the valuation (an email on this date indicates the valuer was concerned the purchase was not on an arms-length basis, and so the lender sought information about it). The financial firm and the complainant’s broker corresponded about further information the lender required. The lender also called Ms X and Mr L to complete the customer interview as part of the approval process.  o n 13 June 2022, the complainant’s broker advised the financial firm to proceed with 70% LVR at $455,000  on 14 June 2022, when settlement was due to take place, the lender issued a formal approval  o n the same day, the complainant’s lawyer, who was also acting on behalf of A company in the purchase of the commercial property , called the vendor’s solicitor and asked to reschedule settlement to 21 June 2022. The vendor agreed, subject to A company increasing the purchase price by $10,000.  on 16 June 202 2, the complainant’s solicitor emailed the executed loan documents to the financial firm and advised the ‘anticipated settlement’ date was 21 June 2022.  on 21 June 2022, settlement was effected and the vendor received an additional $10,000. The financial firm did not cause the delay in settlement Based on the available information, the financial firm’s actions in progressing the application were not unreasonable. There are some emails from the complainant’s broker to the financial Determination | Case number: 926806 Page 4 of 5 firm providing copies of trust deeds and other information in the days shortly prior to the scheduled settlement date, and noting that the documents had been provided two months earlier. So it appears the financial firm’s record keeping and document tracking could have been more diligent. However, with seven parties involved in the transaction from the purchaser side, being:  the complainant, as borrower  the bare trustee (A company), as purchaser  the complainant’s broker  the complainant’s solicitors  the financial firm  the lender  the lender’s solicitors, it appears there were many emails and much material circulating in the week prior to the scheduled settlement. In addition, the need for a commercial valuation (the underlying property was a retail shop) in the weeks prior to settlement added to the delay. The complainant did highlight to its own broker (which was not the financial firm) the importance of achieving the scheduled settlement date, such as in an email on 9 June 2022, when the complainant wrote: …our solicitor has informed that the vendor does not agree to extend the settlement date which is 14 June. This will trigger penalty interests to be accumulated and worse still could be deal cancelled. Unfortunately we will hold the bank/valuer accountable for delaying the process by sending the wrong invoices and not recognising documents sent ages ago. While it is possible the financial firm could have been more diligent in pursuing the settlement and tracking documentation provided to it, there is insufficient information to show the financial firm’s actions were the cause of a delay in the lender being able to approve the loan and issue documentation. There is an indication that the financial firm did follow up the relevant parties when it was appropriate to do so and passed on information to the complainant’s broker and to the lender without unreasonable delay. In addition, there is insufficient information to show that had the financial firm acted differently, settlement would have taken place on 14 June 2022. This is because there were various other actions that were required to be taken by third parties, such as the lender and the valuer. There is also no information to show the lender would have approved the application any earlier, had it received a valuation report earlier. 2.2 Why is the outcome fair? Based on the available information, the financial firm acted sufficiently reasonably when it requested information from the complainant’s broker and submitted the loan application and the complainant’s information to the lender. The financial firm also acted without unreasonable delay when it passed on the lender’s requests to the complainant’s broker. There is insufficient information to show that the financial firm’s conduct adversely affected the time the lender took to assess the complainant’s loan application. Accordingly, it would not be fair to compel the financial firm to pay the complainant the $10,000 as sought. Determination | Case number: 926806 Page 5 of 5 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.